HomeMy WebLinkAbout20181598 Ver 1_RFI-051 (2)_20220120 REQUEST From:Balfour Beatty
FOR RFI No.: RFI-20001021-051
Contact Person: Robert Mann
INFORMATION Date: 01-18-2022
Contract No. C204177 Critical Path:O Yes ❑ No
Project: Havelock Bypass Project
Subject: In Water Moratorium Time Extension
Specification References:
Drawing References:
Request:
Balfour Beatty would like to request a two-week time extension for the in-water moratorium slated to begin
February 151". 2022. There have been multiple hurdles that have impacted the project schedule for Structures
5/6 including permitting conflicts, Covid related personnel disruptions, and material supply disruptions related
to Covid. BBII has tried to overcome the schedule and material conflicts by implementing a night shift and
working both crews 7 days a week.
The two-week time extension would allow the installation of all necessary production pile, and trestle for
substructure construction to continue without interruption.
Please advise if the request for time extension is acceptable.
Response Required By: ASAP
Reason for Time Constraint: Structure Material Scheduling
Response:
TRANSMISSION TRACKING LOG No. of Pages
Date From To Note
REQUEST From:Balfour Beatty
FOR RFI No.: RFI-20001021-051
Contact Person: Robert Mann
INFORMATION Date: 01-18-2022
Contract No. C204177 Critical Path:O Yes ❑ No
Project: Havelock Bypass Project
Subject: In Water Moratorium Time Extension
Specification References:
Drawing References:
Request:
Balfour Beatty would like to request a two-week time extension for the in-water moratorium slated to begin
February 151". 2022. There have been multiple hurdles that have impacted the project schedule for Structures
5/6 including permitting conflicts, Covid related personnel disruptions, and material supply disruptions related
to Covid. BBII has tried to overcome the schedule and material conflicts by implementing a night shift and
working both crews 7 days a week.
The two-week time extension would allow the installation of all necessary production pile, and trestle for
substructure construction to continue without interruption.
Please advise if the request for time extension is acceptable.
Response Required By: ASAP
Reason for Time Constraint: Structure Material Scheduling
Response: