HomeMy WebLinkAbout820019_POA High Freeboard_20220117PLAN OF ACTION(Poa) FOR HIGH FREEBOARD AT ANIMAL FACILITIES
Facility Number: 82-19 County: Sampson
Facility Name: Kennedy Site
Certified Operator Name:
Brandon Warren Operator Number: 19126
1. Current liquid level(s) in inches as measured from the current liquid level in the lagoon to the
lowest point on the top of the dam for lagoons without spillways; and from the current liquid level
in the lagoon to the bottom of the spillway for lagoons with spillways.
Lagoon 1 Lagoon 2 Lagoon 3 Lagoon 4 Lagoon 5
Lagoon Name/ID: 1
Spillway(Y or N): N
Level(inches): 16
2. Check all applicable items
Liquid level is within the designed structural freeboard elevations of one or more structures.
Five and 30 day Plans of Action are attached. Hydraulic and agronomic balances are
within acceptable ranges.
X Liquid level is within the 25 year 24 hour storm elevations for one or more structures. A
30 day Plan of Action is attached. Agronomic balance is within acceptable range.
Waste is to be pumped and hauled to off site locations. Volume and PAN content of waste
to be pumped and hauled is reflected in section III tables. Included within this plan is a list
of the proposed sites with related facility numbers, number of acres and receiving crop
information. Contact and secure approval from the DWQ prior to transfer of waste to a site
not covered in the facility's CAWMP.
Operation will be partially or fully depopulated.
*Attach a complete schedule with corresponding animal units and dates fro depopulation
*if animals are to be moved to another permitted facility, provide facility number, lagoon
freeboard levels and herd population for the receiving facility
3. Earliest possible date to begin land application of waste: 1/20/2022
I hereby certify that I have reviewed the information listed above and included within the
attached Plan of Action, and to the best of my knowledge and ability, the information is
accurate and correct.
Warren Swine Farms Phone: 910-594-1701
Facility Owner/Manager (print)
Facility Owner/Manager (signature)
Date: 1/17/2022
II. TOTAL POUNDS OF PAN STORED WITHIN STRUCTURAL FREEBOARD AND/OR 25 YR.I24
HR. STORM STORAGE ELEVATIONS IN ALL WASTE STRUCTURES FOR FACILITY
1. Structure ID:
2. Structure ID:
3. Structure ID:
4. Structure ID:
5. Structure ID:
6. Structure ID:
1
n. lines 1 + 2 + 3 + 4 + 5 + 6 =
line m = 1182.1 IbPAN
line m = Ib PAN
line m = Ib PAN
line m = Ib PAN
line m = Ib PAN
line m = Ib PAN
1182.1 lbPAN
III. TOTAL PAN BALANCE REMAINING FOR AVAILABLE CROPS DURING 30 DAY DRAW DOWN
PERIOD. DO NOT LIST FIELDS TO WHICH PAN CANNOT BE APPLIED DURING THIS 30 DAY PERIOD.
o. tract #
p. field #
q. crop
r. acres
s. remaining IRR-
2 PAN balance
(Ib/acre)
t. TOTAL PAN
BALANCE FOR
FIELD (Ibs.)
column r x s
u. application window'
7202
AW1
small grain overseed
54.00
75.00
4050.0
Oct -Mar
5681
IC
small grain overseed
4.72
75.00
354.0
Oct -Mar
5681
1 D
small grain overseed
4.76
75.00
357.0
Oct -Mar
5681
IE
small grain overseed
5.83
75.00
437.3
Oct -Mar
5681
3A
small grain overseed
5.16
75.00
387.0
Oct -Mar
5681
3B
small grain overseed
1.31
75.00
98.3
Oct -Mar
5681
5A
small grain overseed
3.79
41.00
155.4
Oct -Mar
5681
5B
small grain overseed
5.19
45.00
233.E
Oct -Mar
5681
5C
small grain overseed
5.49
46.00
252.5
Oct -Mar
5681
5D
small grain overseed
4.01
57.00
228.E
Oct -Mar
'State current crop ending application date or next crop application beginning date for available
receiving crops during 30 day draw down period.
v. Total PAN available for all fields (sum of column t) =
IV. FACILITY'S PoA OVERALL PAN BALANCE
6553.E Ib. PAN
w. Total PAN to be land applied (line n from section II) = 1182.1 Ib. PAN
PoA (30 Day) 2/21/00
x. Crop's remaining PAN balance (line v from section III) =
y. Overall PAN balance (w - x) =
6553.E Ib. PAN
-5371 Ib. PAN
Line y must show as a deficit. If line y does not show as a deficit, list course of action here including pump and
haul, depopulation, herd reduction, etc. For pump & haul and herd reduction options, recalculate new PAN based
on new information. If new fields are to be included as an option for lowering lagoon level, add these fields to the
PAN balance table and recalculate the overall PAN balance. If animal waste is to be hauled to another permitted
facility, provide information regarding the herd population and lagoon freeboard levels at the receiving facility.
NARRATIVE:
Irrigation onto existing spray fields will continue as weather and field conditions permit. New sample going to lab
next week but would expect it to be much lower due to recent rainfall.
PoA (30 Day) 2/21/00
PoA (30 Day) 2/21/00
PoA (30 Day) 2/21/00
PLAN OF ACTION (PoA) FOR HIGH FREEBOARD AT ANIMAL FACILITIES
30 DAY DRAW DOWN PERIOD
I. TOTAL PAN TO BE LAND APPLIED PER WASTE STRUCTURE
1. Structure Name/Identifier (ID):
1
2. Current liquid volume in 25 yr./24 hr. storm storage & structural freeboard
a. current liquid level according to marker
b. designed 25 yr./24 hr. storm & structural freeboard
c. line b - line a (inches in red zone) =
d. top of dike surface area according to design
(area at below structural freeboard elevation)
e. line c/12 x line d x 7.48 gaIIons/ft'
3. Projected volume of waste liquid produced during draw down period
f. temporary storage period according to structural design
g. volume of waste produced according to structural design
h. current herd #
7040
certified herd #
16.0
19.0
inches
inches
3.0 inches
148836
ft2
278323 gallons
180
232094
7040
actual waste produced = current herd # x line g =
certified herd #
i. volume of wash water according to structural design
j. excess rainfall over evaporation according to design
k. (lines h + i + j) x 7.48 x 30 days/line f=
4. Total PAN to be land applied during draw down period
I. current waste analysis dated
m. ((lines e + k)/1000) x line I =
11/15/2021
REPEAT SECTION I FOR EACH WASTE STRUCTURE ON SITE.
(Click on the next Structure tab shown below)
days
ft3
232094 fti
0
89600
ft3
ft3
401045 gallons
1.74
Ibs/1000 gal.
1182.1 lbs. PAN
PoA (30 Day) 2/21/00
PLAN OF ACTION (PoA) FOR HIGH FREEBOARD AT ANIMAL FACILITIES
30 DAY DRAW DOWN PERIOD
I. TOTAL PAN TO BE LAND APPLIED PER WASTE STRUCTURE
1. Structure Name/Identifier (ID):
2. Current liquid volume in 25 yr./24 hr. storm storage & structural freeboard
a. current liquid level according to marker
b. designed 25 yr./24 hr. storm & structural freeboard
c. line b - line a (inches in red zone) =
d. top of dike surface area according to design
(area at below structural freeboard elevation)
e. line c/12 x line d x 7.48 gallons/fti
3. Projected volume of waste liquid produced during draw down period
f. temporary storage period according to structural design
g. volume of waste produced according to structural design
h. current herd #
certified herd #
inches
inches
inches
ft2
gallons
days
ft3
actual waste produced = current herd # x line g = ft°
certified herd #
i. volume of wash water according to structural design
j. excess rainfall over evaporation according to design
k. (lines h + i + j) x 7.48 x 30 days/line f=
4. Total PAN to be land applied during draw down period
I. current waste analysis dated
m. ((lines e + k)/1000) x line I =
REPEAT SECTION I FOR EACH WASTE STRUCTURE ON SITE.
(Click on the next Structure tab shown below)
ft3
ft3
gallons
Ibs/1000 gal.
0 Ibs. PAN
PoA (30 Day) 2/21/00
PLAN OF ACTION (PoA) FOR HIGH FREEBOARD AT ANIMAL FACILITIES
30 DAY DRAW DOWN PERIOD
I. TOTAL PAN TO BE LAND APPLIED PER WASTE STRUCTURE
1. Structure Name/Identifier (ID):
2. Current liquid volume in 25 yr./24 hr. storm storage & structural freeboard
a. current liquid level according to marker
b. designed 25 yr./24 hr. storm & structural freeboard
c. line b - line a (inches in red zone) =
d. top of dike surface area according to design
(area at below structural freeboard elevation)
e. line c/12 x line d x 7.48 gallons/fti
3. Projected volume of waste liquid produced during draw down period
f. temporary storage period according to structural design
g. volume of waste produced according to structural design
h. current herd #
certified herd #
inches
inches
inches
ft2
gallons
days
ft3
actual waste produced = current herd # x line g = ft°
certified herd #
i. volume of wash water according to structural design
j. excess rainfall over evaporation according to design
k. (lines h + i + j) x 7.48 x 30 days/line f=
4. Total PAN to be land applied during draw down period
I. current waste analysis dated
m. ((lines e + k)/1000) x line I =
REPEAT SECTION I FOR EACH WASTE STRUCTURE ON SITE.
(Click on the next Structure tab shown below)
ft3
ft3
gallons
Ibs/1000 gal.
0 Ibs. PAN
PoA (30 Day) 2/21/00
PLAN OF ACTION (PoA) FOR HIGH FREEBOARD AT ANIMAL FACILITIES
30 DAY DRAW DOWN PERIOD
I. TOTAL PAN TO BE LAND APPLIED PER WASTE STRUCTURE
1. Structure Name/Identifier (ID):
2. Current liquid volume in 25 yr./24 hr. storm storage & structural freeboard
a. current liquid level according to marker
b. designed 25 yr./24 hr. storm & structural freeboard
c. line b - line a (inches in red zone) =
d. top of dike surface area according to design
(area at below structural freeboard elevation)
e. line c/12 x line d x 7.48 gallons/fti
3. Projected volume of waste liquid produced during draw down period
f. temporary storage period according to structural design
g. volume of waste produced according to structural design
h. current herd #
certified herd #
inches
inches
inches
ft2
gallons
days
ft3
actual waste produced = current herd # x line g = ft°
certified herd #
i. volume of wash water according to structural design
j. excess rainfall over evaporation according to design
k. (lines h + i + j) x 7.48 x 30 days/line f=
4. Total PAN to be land applied during draw down period
I. current waste analysis dated
m. ((lines e + k)/1000) x line I =
REPEAT SECTION I FOR EACH WASTE STRUCTURE ON SITE.
(Click on the next Structure tab shown below)
ft3
ft3
gallons
Ibs/1000 gal.
0 Ibs. PAN
PoA (30 Day) 2/21/00
PLAN OF ACTION (PoA) FOR HIGH FREEBOARD AT ANIMAL FACILITIES
30 DAY DRAW DOWN PERIOD
I. TOTAL PAN TO BE LAND APPLIED PER WASTE STRUCTURE
1. Structure Name/Identifier (ID):
2. Current liquid volume in 25 yr./24 hr. storm storage & structural freeboard
a. current liquid level according to marker
b. designed 25 yr./24 hr. storm & structural freeboard
c. line b - line a (inches in red zone) =
d. top of dike surface area according to design
(area at below structural freeboard elevation)
e. line c/12 x line d x 7.48 gallons/fti
3. Projected volume of waste liquid produced during draw down period
f. temporary storage period according to structural design
g. volume of waste produced according to structural design
h. current herd #
certified herd #
inches
inches
inches
ft2
gallons
days
ft3
actual waste produced = current herd # x line g = ft°
certified herd #
i. volume of wash water according to structural design
j. excess rainfall over evaporation according to design
k. (lines h + i + j) x 7.48 x 30 days/line f=
4. Total PAN to be land applied during draw down period
I. current waste analysis dated
m. ((lines e + k)/1000) x line I =
REPEAT SECTION I FOR EACH WASTE STRUCTURE ON SITE.
(Click on the next Structure tab shown below)
ft3
ft3
gallons
Ibs/1000 gal.
0 Ibs. PAN
PoA (30 Day) 2/21/00
PLAN OF ACTION (PoA) FOR HIGH FREEBOARD AT ANIMAL FACILITIES
30 DAY DRAW DOWN PERIOD
I. TOTAL PAN TO BE LAND APPLIED PER WASTE STRUCTURE
1. Structure Name/Identifier (ID):
2. Current liquid volume in 25 yr./24 hr. storm storage & structural freeboard
a. current liquid level according to marker
b. designed 25 yr./24 hr. storm & structural freeboard
c. line b - line a (inches in red zone) =
d. top of dike surface area according to design
(area at below structural freeboard elevation)
e. line c/12 x line d x 7.48 gallons/fti
3. Projected volume of waste liquid produced during draw down period
f. temporary storage period according to structural design
g. volume of waste produced according to structural design
h. current herd #
certified herd #
inches
inches
inches
ft2
gallons
days
ft3
actual waste produced = current herd # x line g = ft°
certified herd #
i. volume of wash water according to structural design
j. excess rainfall over evaporation according to design
k. (lines h + i + j) x 7.48 x 30 days/line f=
4. Total PAN to be land applied during draw down period
I. current waste analysis dated
m. ((lines e + k)/1000) x line I =
REPEAT SECTION I FOR EACH WASTE STRUCTURE ON SITE.
(Click on the next Structure tab shown below)
ft3
ft3
gallons
Ibs/1000 gal.
0 Ibs. PAN
PoA (30 Day) 2/21/00