HomeMy WebLinkAboutSW4211102_O&M Agreement/Plan_20220110Operation & Maintenance Agreement
Project Name:
Project Location:
Store -It -Safe Self -Storage
7660 S NC Hwy 87, Snow Camp, NC 27349-Alamance Co,
maintenance records snail be kept on the following BMP(s). [his maintenance record shall be kept in a login a known set
location. Any deficient BMP elements noted in the inspection will be corrected, repaired, or replaced immediately. These
deficiencies can affect the integrity of structures, safety of the public, and the pollutant removal efficiency of the BMP(s).
The BMP(s) on this project include (check all that apply & corresponding O&M tables wit
Bioretention Cell Quantity:
Dry Detention Basin Quantity,
Grassed Swale Quantity:
Green Roof Quantity:
Infiltration Basin Quantity:
Infiltration Trench Quantity:
Level Spreader/VFS Quantity:
Permeable Pavement Quantity:
Proprietary System Quantity:
Rainwater Harvesting Quantity:
Sand Filter Quantity:
Stormwater Wetland Quantity:
Wet Detention Basin Quantity:
Disconnected Impervious Area Present:
User Defined BMP Present:
Location(s):
Location(s):
Location(s):
Location(s):
Location(s):
Location(s):
Location(s):
Location(s):
Location(s):
Location(s):
Location(s):
Location(s):
Location(s):
Location(s):
Location(s):
1
0
No
Na
UOMMONVO011 lll�+.
I acknowledge and agree by my signature below that I am responsible for the performance of the maintenance procedures listed
for each BMP above, and attached O&M tables. I agree to notify NCDENR of any problems with the system or prior to any
changes to the system or responsible party.
" Responsible Party: Aiken & Charlotte Keppl
Title & Organization:
Street address: 721 Ancient Oaks Dr.
City, state, zip: Holly Springs, NC 27540
Phone number(s): (919) 730-4067
Email: aikenkeoaler0amail.cor
f u I i tl l 1 IA—e
Signature: �'u G�� A' Lj— (� � ,�i�-� Date: f'�z_ l _
1, MG (iiF �4 n Il/tl on re a Notary Public for the Sta of D e-4_- Farb I, IC-
U IC(-rEr:
County of j�/(� )C (� do Nearby certify that A lilts J�eaa )er Char 10
personally appeared before me this _� day of dG-6 and
acknowledge the due execution of the O er #ions and Maintena ce greement .
��tatilttt/lI
Witness mc�a., d4
• C>
o s »
A � . r
soo •`
Seal My commission expires Z
STORM-EZ 1015/2021
Version 1.4 O&M Manual Page 1 of 1
Sand Filter Maintenance Requirements
Important maintenance procedures:
- The drainage area will be carefully managed to reduce the sediment load to the sand filter.
- The sedimentation chamber or forebay will be cleaned out whenever sediment depth exceeds six inches.
- Once a year, sand media will be skimmed.
- The sand filter media will be replaced whenever it fails to function properly after maintenance.
The sand filter shall be inspected quarterly and within 24 hours after every storm event greater than 1.0 inches (or 1.5 inches
if in a Coastal County). Records of operation and maintenance will be kept in a known set location and will be available upon
request.
Inspection activities shall be performed as follows. Any problems that are found shall be repaired immediately.
BMP element:
Potential problem:
How to remediate the problem:
Entire BMP
Trash/debris is present.
Remove the trash/debris.
Adjacent pavement (if
Sediment is present on the
Sweep or vacuum the sediment as soon as possible.
applicable)
pavement surface.
Perimeter of sand filter
Areas of bare soil and/or
Regrade the soil if necessary to remove the gully, and then plant a
erosive gullies have formed.
ground cover and water until it is established. Provide lime and a one-
time fertilizer application.
Vegetation is too short or too
Maintain vegetation at an appropriate height.
long.
Flow diversion structure
The structure is clogged.
Unclog the conveyance and dispose of any sediment offsite.
The structure is damaged.
Make any necessary repairs or replace if damage is too large for
repair.
The inlet device
The pipe is clogged.
Unclog the pipe. Dispose of the sediment off -site.
The pipe is cracked or
Replace the pipe.
otherwise damaged.
Erosion is occurring in the
Regrade the swale if necessary to smooth it over and provide erosion
swale.
control devices such as reinforced turf matting or riprap to avoid future
problems with erosion.
Stone verge is clogged or
Remove sediment and replace with clean stone.
covered in sediment (if
applicable).
Forebay or pretreatment
Sediment has accumulated to
Search for the source of the sediment and remedy the problem if
area
a depth of greater than six
possible. Remove the sediment and stabilize or dispose of it in a
inches.
location where it will not cause impacts to streams or the BMP.
Erosion has occurred.
Provide additional erosion protection such as reinforced turf matting or
riprap if needed to prevent future erosion problems.
Weeds are present.
Remove the weeds, preferably by hand. If a pesticide is used, wipe it
on the plants rather than spraying.
Filter bed and underdrain
Water is ponding on the
Check to see if the collector system is clogged and flush if necessary.
collection system
surface for more than 24
If water still ponds, remove the top few inches of filter bed media and
hours after a storm.
replace. If water still ponds, then consult an expert.
The outlet device
Clogging has occurred.
Clean out the outlet device. Dispose of the sediment off -site.
The outlet device is damaged
Repair or replace the outlet device.
The receiving water
Erosion or other signs of
Contact the local NC Department of Environment and Natural
damage have occurred at the
Resources Regional Office.
outlet.
STORM-EZ 10/5/2021
Version 1.4 O&M Manual Page 1 of 1