HomeMy WebLinkAbout20211813 Ver 1_Email_20211202 Carpenter,Kristi From: Parker, Jerry A Sent: Thursday, December 02, 2021 2:14 PM To: Conchilla, Ryan Subject: FW: [EXTERNAL] FW: B-4805 Rya n, This is the email chain that describes how Duke Power has been instructed to install the utility poles. Let me know if you have any questions. Jerry From: Eason, Patty P<peason@ncdot.gov> Sent:Wednesday, December 1, 2021 2:35 PM To: Parker,Jerry A<japarker3@ncdot.gov> Subject: RE: [EXTERNAL] FW: B-4805 Jerry: Before I send this on to Duke, do you need to run it by Ryan or anyone? I didn't want to risk putting you in a bind if I needed to wait. Thank you! From: Parker,Jerry A<japarker3@ncdot. ov> Sent:Tuesday, November 30, 2021 2:50 PM To: Eason, Patty P<psaan@ncdaategaa_v> Subject: RE: [EXTERNAL] FW: B-4805 Patty, From what I am gathering from the email is that they can auger the hole using a line truck, place the pole in the hole and install pole foam instead of putting back the dirt. The dirt would not be placed in the adjacent wetland or buffer but would be hauled off and disposed of properly. If they could install the poles this way, we should be okay. Jerry From: Eason, Patty P<psaan@ncdaategaa_v> Sent:Tuesday, November 30, 2021 11:40 AM To: Parker,Jerry A<japarker3@ncdot. ov> Subject: FW: [EXTERNAL] FW: B-4805 This is Duke's response to B-4805. Is this acceptable? Thank you! i From: Roberts, Randall K<Ran_d_alI_._Ro.berts( Sent:Tuesday, November 30, 2021 11:00 AM To: Eason, Patty P<pn sc n( ncd_nt:.f >; Daniels, Don T<D ne_Daniels(2_d_uk�..- com> Subject: RE: [EXTERNAL] FW: B-4805 CAUTION. External email. Do not click links or open attachments unless you verify.Send all suspicious email as an attachment to Report Sparn. Patty, We will use a standard auger on the line truck to dig the hole and once the pole is set we will use hydraulic tamps to tamp the hole. I can have them hand dig the hole also, if using the auger is a concern, and I can have them install pole foam in the pole hold, instead of putting dirt back if that is a better option. Thanks, Randy From: Eason, Patty P<pnsaan( ncdaategaa_v> Sent:Tuesday, November 30, 2021 10:47 AM To: Daniels, Don T< on: a_ni21.s.2.4d .Ake_-nn_�_rRy com>; Roberts, Randall K<Ran_d_all.F�c bnrts( d ak - ner com> ...._... Subject: [EXTERNAL] FW: B-4805 Good morning: Can you provide a description of how the pole would be installed? Such as auger, set pole, etc.? I have attached the roadway plan sheet that indicates buffer zone and wet land area that the pole and guy are planned? The guy on northside indicates hand dug in the wetland so that should be sufficient but the pole installation in the buffer just needs some description and I think we will be fine. Thank and have a great, thankful Thanksgiving. From: Parker,Jerry A<japarker3( ncdot. v> Sent:Tuesday, November 23, 2021 2:23 PM To: Eason, Patty P<pnsaan( ncd_nt:.f > Subject: RE: B-4805 Patty, After reviewing the attached drawings and consulting with the USACE Representative, I believe that NCDOT should be okay to proceed with this project provided that the contractor submits a description of how they plan to install the utility poles.The description should specify that any clearing in the wetlands will be by hand only and there should be no removal of vegetation in the buffer. Except for the actual placement of the poles and anchor wires, there should be no bottom disturbing activity in either the wetlands or buffer. Hammering or augering the poles is allowable. Some types of machinery may be okay in the buffer as long as it does not disturb the bottom and does not result in the removal of vegetation. If machinery will be used in the buffer, please specify the type of machinery and where it will enter and exit the buffer. Any disturbance in the buffer should be minimized. Definitely do not cross the stream with any machinery. Also, any poles placed in the buffer should be at least 10 feet from the top of bank. Let me know if you have any questions. 2 Jerry From: Eason, Patty P<psaan( ncdaategaa_v> Sent: Monday, November 22, 2021 6:48 PM To: Parker,Jerry A<jagarker3( ncdot. v> Subject: B-4805 Jerry: This is a bridge replacement project in Rockingham that Tim is letting. The permit shows no permitted sites or impacts but drawing file attached has Duke with two PUEs, one in the buffer zone and one in a wetland area. Are these impacts so small that no permit is needed? I just want to be sure because Tim has let the project and I am trying to get utilities going. Let me know or we can discuss. Thanks. Patty Eason, PE Division Construction Engineer 336-487-0000 it all correspondence;,,lcuirdenc e Cxu aird frurr ffils sondcr is sulcjcc. lu Hie IN C I':"ulc Ic.IRcc;urds I ow aird i°r ay be disclosed lu ffili'd Icartiu;,,, it all correspondence;,,luuirdenc e Cxu aird frurr ffils sondcr is sulcjcc. lu Hie IN C I':"ulc Ic.IRcc;urds I ow aird i°r ay be disclosed lu ffili'd Icartiu;,,, 3