From: Don Sever, PE <don.sever@summitde.net>
Sent: Friday, September 3, 2021 1:46 PM
To: Cohn, Colleen M
Cc: Norton, April R CIV USARMY CESAW (USA)
Subject: [External] RE: Highland View Subdivision
Attachments: Highland View Revised_Wetland-Impacts 9 3 2021.pdf
CAUTION: External email. Do not click links or open attachments unless you verify. Send all suspicious email as an attachment to
Report Spam.
Colleen,
Thanks for the email. I needed to check on a couple of things before I got back to you. We have concurrently addressing
your review comments and April's comments.
Regarding your comment, Exhibit 3 is showing the existing roadway culvert being replaced. The roadway was built prior
to any buffer rules being in effect. The existing pipe angle skew is 50 degrees. To make the culvert crossing more
perpendicular, we would have to relocate the stream. We didn't think that was a very good solution so we decided to
keep the pipe at its present angle. Reviewing your comment, we are showing the wetland impacts but failed to realize
that the buffer still exists even with this impact. The attached exhibit shows the revision. You mentioned about the
crossing of streams being allowable with mitigation. Is mitigation required in this instance?
On exhibit 5, since the roadway existed prior to the buffer rules, the zone 2 buffer stops where the maintenance ends
for the existing roadway. We have determined that to be approximately 30' from the centerline at this location.
Does this address your questions?
Thanks Don
Don Sever, PE
Senior Project Manager
Tel: 919-322-0115 x3239
Fax: 919-732-6676
DESIGN AND ENGINEERING SERVICES
EEO
Title
v"r
From: Cohn, Colleen M <colleen.cohn@ncdenr.gov>
Sent: Wednesday, September 01, 2021 4:35 PM
1
To: Don Sever, PE <don.sever@summitde.net>
Cc: Norton, April R CIV USARMY CESAW (USA) <April.R.Norton@usace.army.mil>
Subject: Highland View Subdivision
Mr. Sever,
I am reviewing the application for the above reference project, and in order to complete the review process, some
additional information is required:
1. Please provide the Division a copy of your response to the August 30, 2021 email from the U.S. Army Corps of
Engineers requesting additional information. [15A NCAC 02H .0502(c)]
2. The road crossing in Exhibit 3 does not appear to be a perpendicular crossing (between 75 and 105 degrees),
and it is unclear from the plans if there are any buffer impacts at this crossing. Road impacts other than
perpendicular crossings of streams are allowable with mitigation upon authorization. Please provide more detail
about the angle of this crossing and buffer impacts. [15A NCAC 02B .0714(11)]
3. I am having difficulty seeing where Zone 2 of the riparian buffer is located in relation to the proposed
impervious roadway in Exhibit 5. Please provide an updated plan with the edges of Zone 2 and the proposed
roadway clearly defined. [15A NCAC 02B .0611(b)(1)(F)]
Thank you,
Colleen Cohn
Environmental Specialist II
North Carolina Department of Environmental Quality
Division of Water Resources
Raleigh Regional Office
380o Barrett Drive
Raleigh, NC 27609
Office: 919-791-4258
E-mail correspondence to and from this address may be subject to the
North Carolina Public Records Law and may be disclosed to third parties.
2
i
l
LEGEND:
PERMANENT STREAM IMPACT
TEMPORARY STREAM IMPACT
PERMANENT WETLAND IMPACT
TEMPORARY WETLAND IMPACT
MITIGATED WETLAND AREA
PERMANENT ZONE 1 IMPACT
TEMPORARY ZONE 1 IMPACT
PERMANENT ZONE 2 IMPACT
TEMPORARY ZONE 2 IMPACT
STREAM, RIPARIAN BUFFER, AND WETLAND IMPACTS - TOTAL
PERMANENT
SF
AC
STREAM (LF) S-1
56
0.001
RIPARIAN BUFFERZONE1
4519
0.104
RIPARIAN BUFFERZONE2
2189
0.050
WETLAND
19632
0.451
MITIGATED WETLAND
28874
0.663
N ET WETLAND I MPACT
0
0
STREAM, RIPARIAN BUFFER, AND WETLAND IMPACTS - TOTAL
TEMPORARY
SF
AC
STREAM (LF)
20
-
RIPARIAN BUFFERZONE1
2150
0.049
RIPARIAN BUFFER ZONE 2
2248
0.052
WETLAND
25802
0.592
EXHIBIT 1
150
GRAPHIC SCALE
0 75 150 300
600
(IN FEET)
1 inch = 300 ft.
REVISIONS
PROJECT NO.
19-0063
DRAWING NAME:
19-0063_IMPACTS
SHEET NO.
EXH-OVERALL
/ z
If/I11i/� l�j 11.11144*
l \
2y
20 SF I I a
RAL7IIAq // d
WEIIT AIIJD-fMPAC f
�II / I
P RM�tTIVIE
ILI I IMPAC/77II/ �I
II �(III III I
\ II or/
--
(I I (( // _) PERT
E
I Or I/PNAFOREAT 00EXISTI G PAVrEMENT
AL AT
INE
'0
\fr
� lz\v
a
END SIDEWALK AT
PROPERTY LINE
IVIYORARY
,713
ETL D IMPACT
�1 1
06N*tRUCTEI�'WE LANd"
MI (GATED AREA 1,290 SF
\
TEMPORAIRY WETLAND IMPACT
2,986 SIB L \ \V\
\\kl\krfr \fr
Lk
\fr1 H
\fr\
S
STORMWATER
EASEMENT
SCM
(STORMWATER
POND)
STREAM, RIPARIAN BUFFER, AND WETLAND IMPACTS - EXHIBIT 1
PERMANENT
SF
AC
STREAM (LF)
RIPARIAN BUFFER ZONE 1
RIPARIAN BUFFER ZONE 2
WETLAND
12767
0.293
MITIGATED WETLAND
11290
0.259
STREAM, RIPARIAN BUFFER, AND WETLAND IMPACTS - EXHIBIT 9
TEMPORARY
SF
AC
STREAM (LF)
-
RIPARIAN BUFFER ZONE 1
RIPARIAN BUFFERZONE2
WETLAND
6072
0.139
NOTE:
CONTRACTOR IS TO STRIP THE TOP FOOT OF THE
CONSTRUCTED WETLAND AREA AND STOCKPILE IT. THE POND
SHALL BE GRADED ONE FOOT LOWER, THEN THE CONTRACTOR
IS TO BE PLACE THE STRIPPED MATERIAL TO CREATE THE FINAL
GRADES. THE USE OF THE EXISTING MEDIA SHOULD ALLOW FOR
THE REESTABLISHMENT OF THE WETLAND AREA TO ITS
ORIGINAL CONDITION QUICKLY.
LEGEND:
PERMANENT STREAM IMPACT
TEMPORARY STREAM IMPACT
PERMANENT WETLAND IMPACT
TEMPORARY WETLAND IMPACT
MITIGATED WETLAND AREA
PERMANENT ZONE 1 IMPACT
TEMPORARY ZONE 1 IMPACT
PERMANENT ZONE 2 IMPACT
TEMPORARY ZONE 2 IMPACT
GRAPHIC SCALE
25 0 12.5 25 50
100
( IN FEET )
1 inch = 50 ft.
DRAWING NAME.
19-0063_IMPACTS
SHEET NO.
J
2
MITGATED WETLAND
AREA = 2,028 SF
isv Th..771\ Xcis
13,788 SF
TEMPORARY WETLAND IMPACT
3,729 SF
PERMEN ETLAND IMPACT
1,793 SF J
J
STREAM, RIPARIAN BUFFER, AND WETLAND IMPACTS - EXHIBIT 2
PERMANENT
SF
AC
STREAM (LF)
RIPARIAN BUFFER ZONE 1
RIPARIAN BUFFERZONE2
WETLAND
6637
0.152
MITIGATED WETLAND
2028
0.047
STREAM, RIPARIAN BUFFER, AND WETLAND IMPACTS - EXHIBIT 2
TEMPORARY
SF
AC
STREAM (LF)
-
RIPARIAN BUFFER ZONE 1
RIPARIAN BUFFER ZONE 2
WETLAND
18815
0.432
NOTE:
CONTRACTOR IS TO STRIP THE TOP FOOT OF THE
CONSTRUCTED WETLAND AREA AND STOCKPILE IT. THE POND
SHALL BE GRADED ONE FOOT LOWER, THEN THE CONTRACTOR
IS TO BE PLACE THE STRIPPED MATERIAL TO CREATE THE FINAL
GRADES. THE USE OF THE EXISTING MEDIA SHOULD ALLOW FOR
THE REESTABLISHMENT OF THE WETLAND AREA TO ITS
ORIGINAL CONDITION QUICKLY.
GRAPHIC SCALE
25 0 12.5 25 50
100
( IN FEET )
1 inch = 50 ft.
LEGEND:
PERMANENT STREAM IMPACT
TEMPORARY STREAM IMPACT
PERMANENT WETLAND IMPACT
TEMPORARY WETLAND IMPACT
MITIGATED WETLAND AREA
PERMANENT ZONE 1 IMPACT
TEMPORARY ZONE 1 IMPACT
PERMANENT ZONE 2 IMPACT
TEMPORARY ZONE 2 IMPACT
DRAWING NAME.
19-0063_IMPACTS
SHEET NO
J.;
\
8. 9
0\4-
N\A
�1-
ti
6
172 SF
0140 AC
/‘/Sgg,4
16aF
TEMPORARY \-
WETLAND IMPACT
188 SF
\TEMPORARY
ZONE 2
1975 SF
10' BUILDING
/ SETBAfoK -,
\AI a •-z„\^
DJj �r
TF POIC(RY
STREAM IMPACT
MPORARY
1536 SF
TEMPO Y
D IMPAC1
STREAM, RIPARIAN BUFFER, AND WETLAND IMPACTS - EXHIBIT 3
PERMANENT
SF
AC
STREAM (LF) S-1
56
0.001
RIPARIAN BUFFER ZONE 1
4279
RIPARIAN BUFFER ZONE 2
2067
WETLAND W-3
228
0.005
MITIGATED WETLAND
STREAM, RIPARIAN BUFFER, AND WETLAND IMPACTS - EXHIBIT 3
TEMPORARY
SF
AC
STREAM (LF) S-1
20
-
RIPARIAN BUFFER ZONE 1
1536
RIPARIAN BUFFER ZONE 2
1975
WETLAND W-3
915
0.021
LEGEND:
PERMANENT STREAM IMPACT
TEMPORARY STREAM IMPACT
PERMANENT WETLAND IMPACT
TEMPORARY WETLAND IMPACT
MITIGATED WETLAND AREA
PERMANENT ZONE 1 IMPACT
TEMPORARY ZONE 1 IMPACT
PERMANENT ZONE 2 IMPACT
TEMPORARY ZONE 2 IMPACT
GRAPHIC SCALE
25 0 12.5 25 50
100
( IN FEET )
1 inch = 50 ft.
J
m
REVISIONS
STREAM AND WETLAND
IMPACTS - EXHIBIT 3
PROJECT NO.
19-0063
DRAWING NAME:
19-0063_IMPACTS
SHEET NO.
EXH-3
/01
itic5/(7)f\cY1
/,
44scF�I Y �t /
/r)i_P/ /,12/7,0
/7)f(01T/11-
/// l �f 1
J / CO STRUCITUNETL bl
(M")
,L) irf‘l
6° 36' 1"E f /
383.E /
15672—
0.36 AC c
//// /I
YDRIC�501LS�
STREAM, RIPARIAN BUFFER, AND WETLAND IMPACTS- EXHIBIT4
PERMANENT
SF
AC
STREAM (LF)
RIPARIAN BUFFER ZONE 1
RIPARIAN BUFFER ZONE 2
WETLAND
MITIGATED WETLAND
15556
0.357
STREAM, RIPARIAN BUFFER, AND WETLAND IMPACTS - EXHIBIT
TEMPORARY
SF
AC
STREAM (LF)
RIPARIAN BUFFER ZONE 1
RIPARIAN BUFFER ZONE 2
WETLAND
LEGEND:
PERMANENT STREAM IMPACT
TEMPORARY STREAM IMPACT
PERMANENT WETLAND IMPACT
TEMPORARY WETLAND IMPACT
MITIGATED WETLAND AREA
PERMANENT ZONE 1 IMPACT
TEMPORARY ZONE 1 IMPACT
PERMANENT ZONE 2 IMPACT
TEMPORARY ZONE 2 IMPACT
GRAPHIC SCALE
40 0 20 40 80
160
( IN FEET )
1 inch = 80 ft.
DRAWING NAME:
19-0063_IMPACTS
SHEET NO.
/z
,
Afae
, 525�'
ViVhemiiaWISMS Alt-Firr
'100-0:--- ir-Oriv, iv-/IIII.P- ci* _-_,- ___.6-- --......q4----•ems Miiirmaglio...--orwmania
— PERMANENT
ZONE 2 jMPACT
122 SF
TEMPORARY
ZONE 2 IMPACT
130 SF
TEMPORARY - 31.4
ZONE 2 IMPACT ►i f
•
SF
Aline
5p� 12
g1 �
\\
TEMPORARY
ZONE 1 IMPAC-, -- \Z MA C
316 SF �\
TEMPORARYG
, Z9.NE 1JMRAef—
29$ SE
61
23820 SF
/
Nw\
STREAM, RIPARIAN BUFFER, AND WETLAND IMPACTS - EXHIBIT 5
PERMAN ENT
SF
AC
STREAM (LF)
RIPARIAN BUFFERZONE1
240
0.006
RIPARIAN BUFFERZONE2
122
0.003
WETLAND
MITIGATED WETLAND
STREAM, RIPARIAN BUFFER, AND WETLAND IMPACTS - EXHIBIT 5
TEMPORARY
SF
AC
STREAM (LF)
RIPARIAN BUFFER ZONE 1
614
RIPARIAN BUFFER ZONE 2
273
WETLAND
LEGEND:
PERMANENT STREAM IMPACT
TEMPORARY STREAM IMPACT
PERMANENT WETLAND IMPACT
TEMPORARY WETLAND IMPACT
MITIGATED WETLAND AREA
PERMANENT ZONE 1 IMPACT
TEMPORARY ZONE 1 IMPACT
PERMANENT ZONE 2 IMPACT
TEMPORARY ZONE 2 IMPACT
GRAPHIC SCALE
25 0 12.5 25 50
— _
( IN FEET )
1 inch = 50 ft.
100
J
REVISIONS
STREAM AND WETLAND
IMPACTS - EXHIBIT 5
PROJECT NO.
19-0063
DRAWING NAME:
19-0063_IMPACTS
SHEET NO.
EXH-5