County: Craven Project: Duke Energy Staging Area at West New River basin: Neuse
Person financially responsible: DUKE ENERGY PROGRESS LLC -Tim Same, Project #: CRAVE-2020-027
Manager Substation Engineer
Address: 410 SOUTH WILMINGTON ST, Raleigh, NC 27602
1. Project Location: US 70 & NC 43, NEW BERN
Pictures: Yes - Digital
2. Weather and soil conditions: sunny, cool, dry Initial inspection: No
3. Is site currently under notice of violation? No
4. Is the site in compliance with S.P.C.A. and rules? Yes If no, check violations below:
5. Violations:
6. Is the site in compliance with NPDES Permit NCGO10000 Construction Stormwater requirements? Yes
Describe:
7. Has sedimentation damage occurred since last inspection? No If Yes, where? (check all that apply)
Degree of damage:
8. Contact made with (name): No one. Title:
Inspection report: Sent Report Date given/sent: December 01, 2021
9. Corrective action needed:
Permanent ground cover sufficient to restrain erosion has been established. No additional self -monitoring
or self -inspections are required. Project is in compliance and released under the SPCA. Termination of
10. Comments: coverage under the NPDES General Stormwater Permit for Construction Activities (NCG01) must be
requested by the permittee via a Notice of Termination (NOT). The NOT is available at:
httt)s:Hedocs.dea.nc.gov/Forms/NCGO1-Termination. Please note that this correspondence must be
uploaded as part of completing the NOT process.
Reported by: James Edwards Others present: No one.
Date of inspection: November 23, 2021 Time arriving on site: 12:35 PM Time leaving site: 12:45 PM