HomeMy WebLinkAbout20071264 Ver 1_401 Application_20070707
WETLAND & ECOLOGICAL CONSULTANTS, LLC
July 20, 200
Mr. Steve Chapin
U.S. Army Corps of Engineers
Asheville Regulatory Field Office
i51 Patton Ave., Room 208
Asheville, North Carolina 288oi
°7-,264 COPY
~~ E~~
Subject: Preconstruction Notification
Nationwide Permit No. i8
Colonial Pipeline Company Exposed Pipe Maintenance
Park Creek Line 1-Pipe Exposure
Rowan County, North Carolina
WEC Project No. o2-o4i9oi-Park Creek
Dear Mr. Chapin:
On behalf of our client, Colonial Pipeline Company (CPC), Wetland & Ecological
Consultants (WEC) respectfully requests authorization for the above referenced project
pursuant to Nationwide Permit (NWP) No. i8 for Minor Discharges, for the required
maintenance of CPC's existing Line i pipeline. The proposed action consists of a minor
discharge of fill required for streambed stabilization needed to protect of an existing
petroleum pipeline located within CPC's maintained right-of--way (ROW). The proposed
activity will require minor disturbance to Park Creek in Rowan County, North Carolina,
at 35° 30.902"Nand 80° 42.445" W (Figure i).
Background
CPC's above referenced maintained ROW, contains two pipelines that transport refined
petroleum: Line 1, 4o-inch diameter; Line 2, 36-inch diameter. At the above referenced
site, bank erosion and streambed degradation has exposed Line i within the stream
channel, significantly reducing the required cover protection level of the pipeline.
(Photograph No. i and 2).
3225 South Cherokee Lane Phone: 770-591-9990
Bldg. Soo Fax: 770-591-9993
Woodstock, Ceorgiu ,3oi8S www.wet-eco.com
PCNNWPNo. i8 July i9, 2ooy
Colonial Pipeline Company -Park Creek WECProject No. o2-o4i9o~
Proposed Activity in Waters of the U.S.
The minor discharge of fill will require disturbance to approximately ~o linear feet of
Park Creek to stabilize the stream bank and protect the existing pipeline. The pipeline
will be protected using pre-cast concrete revetment mats placed into a 45-linear foot
segment of the stream channel (Appendix A). CPC will also place riprap into an
additional 25 linear feet of the stream (i.e., ~o linear feet total) below the ordinary high
water mark. The quantity of this "fill material" (i.e., revetment mat and riprap) below
the plane of the ordinary high water mark will be less than 22 cubic yards.
To minimize sedimentation to the creek during the activity, temporary dams will be
constructed at each end of the work area and the stream flow will be pumped around the
area. The dams will be constructed of sandbags or other suitable material, and the pump
capacity will be able to sufficiently accommodate the stream flow. The pumps will be
installed above the upstream dam with the discharge line routed through the disturbed
area, discharging immediately downstream of the downstream dam (Appendix B).
As an alternative method to using a pump, CPC may use a steel pipe flume to convey the
stream flow through the reach of stream to be disturbed. The flume will be used to
maintain flow to the downstream side of the disturbed area, and the excavation will be
carried out under the flume (Appendix C). Both techniques allow the maintenance to
take place without contact to flowing water (i.e., "in the dry"), thus reducing downstream
sedimentation.
To prevent future erosion of the streambed at this location, and to protect the pipeline
from damage, pre-cast concrete revetment mats will be used to cover and protect the
pipeline while stabilizing the adjacent segments of the streambed as depicted in
Appendix A. The revetment mats will extend approximately 45 linear feet within the
stream channel. The reshaped stream bank will be stabilized with geotextile erosion
control mats, and CPC's Soil Erosion and Sedimentation Control Plan will be
implemented to protect the stream from sedimentation (Appendix D).
Nationwide Permit General Conditions Summary
We have provided the following information to document compliance with the USACE
NWP general conditions. Each condition and subcategory is itemized below.
2
PCNNWPNo. i8 July ~g, 200
Colonial Pipeline Company -Park Creek WECProjectNo. o2-o4i9oi
General Condition i -Navigation
The project site does not occur within navigable waters.
General Condition 2 -Aquatic Life Movements
The discharge of fill activity within the stream will be minimal. The revetment mats
will be "keyed" into the streambed, and will not impede the passage of normal
stream flow or aquatic life.
General Condition ~ -Spawning Areas
Not applicable.
General Condition 4 -Migratory Bird Breeding Areas
Not applicable
General Condition ~ -Shellfish Beds
Not applicable
General Condition 6 -Suitable Material
The concrete revetment mats are pre-cast and hardened before they are placed in
the stream.
General Condition ~ -Water Supply Intakes
The proposed construction does not include a water supply intake.
General Condition 8 -Adverse Effects from Impoundments
Not applicable.
General Condition 9 -Management of Water Flows
During the proposed activity, water flows will be maintained by the use of either a
dam and pump system (Appendix B) or a flume used to convey the flow of the
stream (Appendix C). The concrete revetment mats will be "keyed" in to the
upstream end of the disturbed area to prevent impediment of streamflow (Appendix
A).
General Condition io -Fills Within ioo-Year Floodplains
The project will not result in above grade fill placed within the ioo-year floodplain.
General Condition ii -Equipment
Equipment will be operated from the stream banks.
3
PCNNWPNo. ~8 July i9, 2ooy
Colonial Pipeline Company -Park Creek WECProjectNo. o2-o4i9oi
General Condition 12 -Soil Erosion and Sediment Controls
Best Management Practices and proper erosion and sedimentation controls will be
followed during the maintenance activity (Appendix D).
General Condition i~ -Removal of Temporary Fills
All temporary water flow diversion devices will be removed immediately following
the maintenance activity.
General Condition i4 -Proper Maintenance
The existing pipelines and ROW will continue to be maintained and inspected on a
regular basis to ensure public safety.
General Condition i~ -Wild and Scenic Rivers
The project site is not located in or adjacent to a Wild and Scenic River.
General Condition i6 -Tribal Rights
The project site is not located within or adjacent to an Indian reservation or nation.
General Condition i~ -Endangered Species
No impacts to federally protected species are expected from this project. According
to current North Carolina Natural Heritage Program data, the only federally
protected species listed to occur in Rowan County are the bald eagle (Haliaeetus
leucocephalus) and Schweinitz's sunflower (Helianthus schweinitzit~. At the project
location, neither species were observed at the time of the site visit. Further, this
area does not provide suitable habitat for bald eagles or the sunflower due to the
routine maintenance of the ROW (i.e., mowing).
General Condition i8 -Historic Properties
The proposed activity will be conducted within the existing pipeline ROW, which has
been previously disturbed; thus no archeological resource impacts are probable. No
historic structures were noted within the project area, and no aboveground
structures are proposed for construction. Therefore, the proposed pipeline
protection activity will have no adverse affects to cultural resources in the project
vicinity.
General Condition 1g -Designated Critical Resources Waters
Not applicable.
General Condition 20 -Mitigation
The proposed pipeline protection activities have been designed to avoid and
minimize impacts to jurisdictional waters to the maximum extent practicable. The
stream disturbance of approximately ~o linear feet does not exceed any of the
USACE, Wilmington District, Nationwide Permit Regional Conditions requiring
mitigation [Refer to USACE, Wilmington District Regional Condition 3 (2) below].
However, the proposed stream/bank stabilization completed to maintain and
4
PCNNWPNo. ~8
Colonial Pipeline Company -Park Creek
July i9, 2ooy
WECProjectNo. o2-o4igoi
protect the existing pipelines will result in improved water quality of the stream by
reducing soil/bank erosion, which offsets the minor/temporary disturbance.
General Condition 21 -Water Quality
The activity will be in accordance with the conditions of the DWQ General Certifications
for NWP 3 (WQC N0.3494) and NWP i8 (WQC No. 3402).
General Condition 22 -Costal Zone Management
Not applicable.
General Condition 2~ -Regional and Case-By-Case Conditions
The Wilmington District Final Regional Conditions for Nationwide Permits
i. Waters excluded from the use of NWP during certain timeframes:
i) Waters designated as anadromous fish spawning areas.
Not applicable.
2) Waters within
counties work is
unless approved
Commission.
North Carolina's 25 designated trout
prohibited from October i5 -April i5,
by North Carolina Wildlife Resources
Not applicable.
3) Waters of the U.S. designated as sturgeon spawning areas
work is prohibited from February i -June 30, unless
approved by National Marine Fisheries Service.
Not applicable.
2. Waters subject to additional notification requirements:
i) Waters within i6 North Carolina counties designated to
provide critical habitat for protected species.
Not applicable.
2) Waters designated as "Outstanding Resource Waters"
(ORW), "High Quality Waters" (HQW), "Inland Primary
Nursery Areas" (IPNA), contiguous wetlands, or "Primary
Nursery Areas" (PNA).
Not applicable.
3) Waters in a designated "Area of Environmental Concern"
(AEC) in the 20 coastal counties of eastern North Carolina.
Not applicable.
5
PCNNWPNo. i8 July i9, 200
Colonial Pipeline Company -Park Creek WECProjectNo. o2-o4i9o~
4) Waters on a Barrier Island of North Carolina.
Not applicable.
5) "Mountain or Piedmont Bog" of North Carolina.
Not applicable.
6) Animal Waste Facilities of North Carolina.
Not applicable.
~) Mountain Trout Waters within the 25 designated counties
of North Carolina.
Not applicable.
3. List of Final Corps Regional Modifications and Conditions for All
Nationwide Permits:
1) NWPs may not be used for activities that may result in the loss or
degradation of greater than goo total linear feet of perennial,
intermittent, or ephemeral streams that exhibits important
aquatic function(s). Loss of stream includes the linear feet of
stream bed that is filled, excavated, or flooded by the proposed
activity.
The use of NWP i8 will result in less than 300 linear feet of
disturbance to the streambed.
2) For any NWP that results in impacts more than lso total linear
feet of perennial and/or ephemeral/intermittent stream, the
applicant shall provide a mitigation plan to compensate for the
loss of aquatic function, associated with the proposed activity. For
stream impacts of less than iso linear feet compensatory
mitigation is determined on a case by case basis.
Stream impacts are less than iso linear feet, and the proposed
pipeline protection activity will improve water quality and the
aquatic environment by reducing bank erosion and stream
turbidity.
3) For any NWP that results in a loss of more than iso linear feet of
perennial and/or intermittent/ephemeral stream, the applicant
must comply with NWP General Condition 2'J (PCN).
Not applicable (i.e., less than iso linear feet of stream); however, a
PCN is required for NWP i8 and compliance with NWP General
Condition No. 2~ has been provided by the submission of this
PCN.
4) For all NWPs which allow the use of concrete as a building
material, measures will be taken to prevent live or fresh concrete,
6
PCNNWPNo. ~8
Colonial Pipeline Company -Park Creek
July ig, 200
WECProjectNo. o2-ogl9oi
including bags of uncured concrete from coming into contact with
waters of the state until the concrete has hardened.
The concrete revetment mats that will be used to stabilize the
streambed and protect the pipelines from future exposures are
pre-cast and hardened before they are placed in the stream.
5) For all Nationwide Permits that allow for the use of riprap
material for bank stabilization
i) Filter cloth must be placed underneath the riprap as an
additional requirement of its use in North Carolina waters.
The riprap will be placed on a geotextile fabric in the
stream.
2) The placement of riprap shall be limited to areas depicted
on submitted work plan drawings.
Riprap will be limited to the area indicated on Appendix A.
3) The riprap material shall be clean and free from loose dirt
or any pollutant except in trace quantities that would not
have an adverse environmental effect.
The riprap will be clean/free of dirt.
4) It shall be of a size sufficient to prevent its movement from
the authorized alignment by natural forces under normal
conditions.
The riprap will be of sufficient size to prevent movement
downstream.
5) The riprap material shall consist of clean rock or masonry
material such as, but not limited to, granite, marl, or
broken concrete.
The riprap materials used will consist of clean rock or
masonry material.
6) A waiver from the specifications in this Regional Condition
maybe requested in writing. The waiver will only be issued
if it can be demonstrated that the impacts of complying
with this Regional condition would result in greater
adverse impacts to the aquatic environment.
Not applicable.
6) For all NWPs that involve the construction of culverts, measure
will be included in the construction that will promote the safe
passage of fish and aquatic organisms. The dimension, pattern,
and profile of the stream above and below a pipe or culvert should
7
PCNNWPNo. i8
Colonial Pipeline Company -Park Creek
July 19, 2007
WEC Project No. o2-oqi 9oi
not be modified by widening the stream channel or by reducing
the depth of the stream in connection with the construction
activity. The width, height, and gradient of a prposed opening
should be such as to pass the average historical low flow and
spring flow without adversely altering flow velocity. Spring flow
should be determined from gage data, if available. In absence of
such data, bankfull flow can be used as a comparable level.
Not applicable.
~) Applicants shall notify the NCDENR Shellfish Sanitation Section
prior to dredging in or removing sediment from an area closed to
shell fishing where the effluent maybe released to an area open for
shell fishing or swimming in order to avoid contamination of the
disposal area and allow a temporary shellfish closure to be made.
Any disposal of sand to the beach should occur between November
1 and April 3o when recreational usage is low. Only clean sand
should be used and no dredged sand from closed shell fishing
areas. If beach disposal was to occur at times other than stated
above or if sand from a closed shell fishing area is to be used, a
swim advisory shall be posted, and a press release shall be made.
Not applicable.
8) Adverse impacts to Submerged Aquatic Vegetation are not
authorized by any NWP within any of the 20 costal counties.
Not applicable.
4. Additional Regional Conditions for Specific Nationwide Permits:
NWP i8 may not be used in conjunction with NWP i4 to create
upland.
Not applicable.
North Carolina Division of Water Quality (DWQ) General Certification
Conditions for NWP i8 (GS3,~62) (WQC No. 3402) (DWQ has renewed and
extended the existing General Cerification for a period of six months,
until September ~, aoo~.)
1. Enumerating and Reporting of Impacts:
a. Streams -Impacts to streams shall be measured as length of the
centerline of the normal flow channel. Permanent and/or
temporary stream impacts shall be enumerated on the entire
project for all impacts regardless of which NWPs are used. Stream
relocations and stream bed and/or bank hardening are considered
to be permanent impacts.
This project will cause disturbance to approximately ~o linear feet
of stream within Park Creek during the pipe protection activity to
8
PCNNWPNo. i8
Colonial Pipeline Company -Park Creek
July ig, aoo~
WECProjectNo. 02-o419oi
protect the existing, exposed pipeline to authorized under NWP
i8. Within the ~o-linear foot reach, a section of pre-cast concrete
revetment mats will extend 45 linear feet, with riprap placed on
either side of the revetment mats extending approximately 25
linear feet. This approach will stabilize the stream bank while
protecting the pipeline from future exposure.
b. Wetlands -Impacts to wetlands shall be measured as area.
Permanent and/or temporary wetland impacts shall be
enumerated on the entire project for all impacts regardless of
which NWPs are used.
Not applicable.
c. Lakes and Ponds -Impacts to waters other than streams and
wetlands shall be measured as area.
Not applicable.
d. Total stream impacts greater than or equal to i5o cumulative feet
of stream length for the entire project require written notification
to and approval by the DWQ.
Not Applicable, less than i5o linear feet will be impacted.
e. Impacts to waters of equal to or greater than i/3 of an acre require
written notification to and approval by the DWQ.
Not applicable, the area of the stream impacts is less than i/3 acre.
f. Wetland impacts of greater or equal to i/g of an acre east of I-95
and i/io of an acre west of I-95 require written notification to and
approval by the DWQ. Any impacts to wetlands adjacent to waters
designated as ORW, SA, WS-I, WS-II or Trout or are designated as
North Carolina or National Wild and Scenic River and wetlands
classified as SWL and/or UWL as well as wetlands described in
i5A NCAC 2H.o5o6 (e) require a complete application and written
concurrence from DWQ.
Not applicable.
g. Written notification to DWQ is required for all applications that
propose to use NWP i8. This notification requirement will be
satisfied by providing two copies of the PCN form to DWQ at the
same time that the PCN form is sent to the USACE. A formal
application and fee is not required unless DWQ decides that an
Individual Certification will be required for the project.
Two copies of this PCN submittal will be submitted to DWQ to
satisfy this requirement.
9
PCNNWPNo. i8
Colonial Pipeline Company -Park Creek
July ig, 200
WECProjectNo. o2-o4i9oi
h. Proposed fill or substantial modification for any amount of
wetlands classified in accordance with 15A NCAC 2B.oioi (e) (~)
as Unique Wetlands (UWL) shall require written concurrence
from DWQ.
Not applicable.
2. Impacts to any stream length in the Neuse, Tar-Pamlico or Randleman
River Basins (or any other major river basins with Riparian Area
Protection Rules [Buffer Rules] in effect at the time of application) require
written concurrence under the above referenced Certification.
Park Creek is not located in the Neuse, Tar-Pamlico, or Randleman River
Basins.
3. Irrespective of other application thresholds in the General Certification all
impacts to perennial waters and their associated buffers require written
approval from DWQ.
As specified in the DWQ "Redbook" [15A NCAC o2B.o243 (3)(a)], the
activity is exempt from the riparian buffer protection permitting
requirements.
4. Additional site-specific stormwater management requirements may be
added to this Certification at DWQ's discretion on a case-by-case basis for
projects that have or are anticipated to have impervious cover of greater
than 3o percent.
Not applicable.
5. Compensatory stream mitigation shall be required at a i:i ratio for all
perennial and intermittent stream impacts equal to or exceeding i5o feet
and that require application to DWQ in watersheds classified as ORW,
HQW, Tr, WS-I and WS-II.
Not applicable.
6. In accordance with North Carolina General Statute Section i43-215•3D(e),
any application fora 4oi Water Quality Certification must include the
appropriate fee.
As described above [General Condition 6 -DWQ General Certification
Condition 1(g)], formal application and a fee is not required for the use of
NWP i8.
~. In accordance with 15A NCAC 2H.o5o6(h), compensatory mitigation may
be required for impacts to i5o linear feet or more of stream and/or one
acre or more of wetlands for an entire project.
Not applicable, less than i5o linear feet of stream impacts proposed.
io
PCNNWPNo. i8 July s9, 2007
Colonial Pipeline Company -Park Creek WECProjectNo. o2-ogl9oi
8. For any project involving the re-alignment of streams, a stream relocation
plan must be included with the 4oi application for written DWQ
approval.
Not applicable.
9. Placement of culverts and other structures in waters, streams, and
wetlands must be placed below the elevation of the streambed to allow
low flow passage of water and aquatic life.
The revetment mat will be placed below the streambed elevation as
depicted in Appendix A.
io. Appropriate sediment and erosion control practices which equal or exceed
those outlined in the most recent version of the "North Carolina Sediment
and Erosion Control Planning and Design Manual" or the "North Carolina
Surface Mining Manual" whichever is more appropriate shall be in full
compliance with all specifications governing proper design, installation
and operation and maintenance of such Best Management Practices in
order to assure compliance with the appropriate turbidity water quality
standard.
Best Management Practices and proper erosion and sedimentation
controls will be followed during the maintenance activity (Appendix D).
ii. All sediment and erosion control measures placed in wetlands and waters
shall be removed and the original grade restored within two months after
the Division of Land Resources has released the project.
All erosion control devices (i.e., silt fence and staked hay bales) will be
removed upon the re-establishment of vegetation at the site.
i2. Additional site-specific conditions may be added to projects proposed
under this Certification in order to ensure compliance with all applicable
water quality and effluent standards.
As proposed, this project is incompliance with all applicable water quality
and effluent standards.
13. Measures shall betaken to prevent live or fresh concrete from coming into
contact with waters of the State until the concrete has hardened.
See General Condition 6 - USACE, Wilmington District Regional
Condition 3.3•
i4. If an environmental document is required, this Certification is not valid
until a Finding of No Significant Impact (FONSI) or Record of Decision
(ROD) is issued by the State Clearinghouse.
Not applicable.
ii
PCNNWPNo. i8 July 19, 2007
Colonial Pipeline Company -Park Creek WECProject No. o2-o4i9oi
i5. If this Certification is used to access building sites, all lots owned by the
applicant must be buildable without additional fill beyond that explicitly
allowed under other General Certifications.
Not applicable.
i6. Deed notifications or similar mechanisms shall be placed on all lots with
remaining jurisdictional wetlands and waters or areas within 5o feet of all
streams and ponds.
Not applicable.
i~. When written concurrence is required, the applicant is required to use the
most recent version of the Certification of Completion form to notify
DWQ when all work included in the 401 Certification is completed.
Not applicable, written concurrence from DWQ is not required for this
project.
i8. Concurrence from DWQ that this Certification applies to an individual
project shall expire three years from the date of the cover letter from
DWQ or on the same day as the expiration date of the corresponding
nationwide Permit (i.e., NWP i8).
CPC is required to complete this project before February 24, 2008 in
accordance with U.S. Department of Transportation (USDOT) regulations
for pipeline safety.
General Condition 24 -Use of Multiple Nationwide Permits
Not applicable.
General Condition 2.r, -Transfer of Nationwide Permit Verifications
Not applicable.
General Condition 26 -Compliance Certification
Upon completion of the required maintenance, WEC (as CPC's authorized agent)
will sign and submit the USACE certification letter documenting compliance with
maintenance activities as they are described in this PCN submittal.
General Condition 27 -Pre-Construction Notification
(a) Timing: The prospective permittee must notify the District Engineer with a PCN
as early as possible. The District Engineer must determine if the notification is
complete within 3o days of the date of receipt and as a general rule will request
additional information necessary to make the PCN complete only once.
WEC believes that the contents of this package constitute a complete PCN.
12
PCNNWPNo. i8
Colonial Pipeline Company -Park Creek
July 1g, 2007
WEC Project No. o2-ogi9oi
(b) Contents of the Notification: The following information addresses NWP General
Condition 2~(b):
1) Name, address, and telephone number of the prospective
permittee:
Mr. Jeff Richards
Colonial Pipeline Company
391 Scruggs Road
Ringgold, GA 30736
(706) 891-6658
2) Location of the Proposed Project:
The proposed pipeline protection location is located in Park Creek
Rowan County, North Carolina at 35° 30.902"Nand 80° 42.445"
W (Figure 1).
3) Project description, purpose, effects:
See the "Background" and "Proposed Activities in Waters of the
U.S." sections of this letter.
4) Delineation of affected special aquatic sites, including wetlands:
WEC conducted the field delineation of the project site on June
26, 200. The only feature considered jurisdictional waters on the
subject site is Park Creek a perennial stream. The 200 USACE
Approved Jurisdictional Determination Form is attached as
Appendix E.
5) Mitigation required if the proposed activity will result in the loss of
greater than o.l acre of wetland and PCN required.
Not applicable.
6) Names of federal protected species affected:
Refer to General Condition 17 above.
~) National Register of Historic Places Affected:
Refer to General Condition 18 above.
(c) Form of Notification:
The Wilmington District's PCN form is attached as Appendix F.
General Condition 28 -Single and Complete Project
This project does meet the definition of a single and complete project as defined at 33
CFR 33o.2(i).
13
PCNNWPNo. ~8
Colonial Pipeline Company -Park Creek
Conclusion
July ~9, 200
WECProjectNo. o2-o4i9oi
The pipeline activity proposed in jurisdictional waters of the U.S. and the State of North
Carolina will result in temporary disturbance to approximately ~o linear feet of Park
Creek in Rowan County. During the proposed activity, appropriate erosion and
sedimentation control devices will be used on the entire project site and the proposed
activity is in compliance with Nationwide Permit General Conditions and DWQ
conditions for Section 4oi water quality certification and riparian buffer protection.
Based on this submittal, we respectfully request authorization for the aforementioned
maintenance project pursuant to NWP No. i8. Please contact the undersigned at ~~o-
591-999o if you have any questions regarding this request.
Sincerely,
WETLAND & ECOLOGICAL CONSULTANTS, LL/C~ /~
~_
Shanna Cahill Richard W. Whiteside, Ph.D., C.W.B.
Staff Ecologist Managing Member
Enclosures: Figure i - Site Location Map
Appendix A- Detailed Site Drawings
Appendix B - Typical Dam and Pump Maintenance Dig
Appendix C - Typical Open Cut Dry Flume Maintenance Dig
Appendix D - CPC's Soil Erosion and Sediment Control Plan
Appendix E- Approved Jurisdictional Determination Form
Appendix F - Wilmington District PCN Form
Appendix G- Wilmington District PCN Authorization Letter
Appendix H- Site Photographs (2)
cc: Mr. Jeff Richards, Colonial Pipeline Company
NCDENR, DWQ (2 copies)
i4
2,400 1,200 0 2,400 Feet
Base Map: USGS 7.5-Minute Topographic Quadrangle Enochville, NC, 1993•
Colonial Pipeline Company ~`~ Figure i
Park Creek-Line 1 ~-
WETLAND & ECOLOGICAL Site Location Map
Station 2544+36 CONSULTANTS, LLC
Rowan County, NC Woodstock, Georgia WEC Project No. o2-o4i9oi
APPENDIX A
DETAILED SITE DRAWINGS
w A
w ~^ ~ '`
O ~ ~ N
~ ni ~ . o0
0
`;~
~ ~ ~ o
o p o
~ ~
~ O Z = N
Z ~ ~ a. ~ n
o
v
W
Z H
W
(~~~~ ~ a ~
J ~
O
i ~ z
~ '` I
00
II I ~ N
11 zo
II ~~
~ II
Z ~`
I I '` I I ~ m
II II ~ ~~
II ~I ~ z~ ~~o
I I I I ~~_ ~~ ~~~
II '` II ~~ ~~ ~ ~~W
II o~ az~
I I ~ _ (~~
V VO ~ ~ u
II II ° ~~Q ~2~
II ~ Q~z ~°
~oQ ~~
~~ ~~~
W ~~o
~ ZY =~ W z
W v ~ ~~ W ~Z ~ ~ ~
J ~ W Im ~ Zm W
~N ~? ~ ~
W
~ ~ O
v d' ~-
V b
Z S
o~~
~- ~ _ ~ ~
~ ~ ~9l .~
- ~ ~ v y
m~~~
• 2 ~ ~
W (/) o
m
N ~
0 ~ ~ CI
Q p ..aD
~~ ~~
O ~ °
~ ~,
Z o
~ ~ ~~
U
!4
Z
~ ~ ~ J~~~~o~ d a "~,
r- -
~ -° _
~ ~ ~ - -~
I ~ ~ t;, r` Z
I ' ' ~
I I ' I ~ \
I' ___ _-- __ 2 0
~' ~ $
' y by --------- --
~ vv
I I y V y C7 ~'
' h
m
~~
~~oo ~
W
U
`.b W j
o W ' W Vj ~g~
J Q G
~ I I ~~ ' ~ VOJO ~~
~ ~ ; ~ ~ ~Qz ~o~
o Q~ h
W o~ `~ ~ ~ ~ ~Q o ~Q COQ ~ ~
~ 04o r ~ J Im ~ Im ~~ 0 3~
m a m p H
'~~a W ~3~
3 0~= Z ~~
N V
W
~ ~., o `O ~ ~ W ~
O ~' ~
2 ~ W O~ ~ ~ b
FF
O O 2 ~~ Z~ `~~ ~
2 O ~ h~ O 0'^~
3~''m ~ ~ ~
~a~3~
3WO~W O Q~~N
a Q ~ ~~ ~y s
~~'?im ~ ~ m2~~
p ~i '7 v
2 o i
� N
I �
O m
O
r
^ 1
j AjVAj/\�\A V a
� 3 N
tn
c^o�\
CO)
ado
H � U
Qc Y
k4
g Se
Z
zW
%C U LJ L4 e
co
j
ti
W � N
�?S,
V) o
0
APPENDIX B
TYPICAL DAM AND PUMP MAINTENANCE DIG
PERMANENT ROW
II II
II II
III
I I ~I~
II II
II II
II II
II II
III I
III III
PUMP
SUMP W/INTAKE HOSE -___.
FILTER~SCREEN OR
SUBMERSIBLE PUMP--~~
WATERBDDY
SPOIL CONTAINMENT BERM
(SILT FENCE, HAY BALES
OR OTHER APPLICABLE
MATERIALS)
_= ~ =-.
III
I I II
RETAIN A MIN. 25'
VEGETATIVE BUFFER TO
THE EXTENT POSSIBLE
ENERGY DISSIPATOR/
SCOUR PROTECTION
._.r ____ -'1
FLDW
DAM
MAINTAIN A MINIMUM 25' I
VEGETATIVE BUFFER TO
THE EXTENT POSSIBLE
BACKHOE
FOR STREAM EQUIPMENT
CROSSINGS, SEE NOTE 14
FILTER BAG
RENSpN
xiLLE DATE DRAWN
NIS 01-29-2001 Al5 -
SEE SHEET 2 FOR NOTES
~~ COLONIAL PIPELINE COMPANY
ATW,ffA, GEORCW
TYPICAL DAM AND PUMP
MAINTENANCE DIG
AT WATERBODY LESS THAN 15'
TROW PRQI. N0. DRAWING SNEFf
711F~0.762 COL-000J 1 OF 2
~ I I I
SPOIL I I I ,
~ II
I II
~, ~ I I I
_; ~I I III
`III I I
~~ ~'II II
1. ` ~ j ''~~I I I I
```` TROW ENGINEERING CONSULTANTS INC.
,mo ~c,noraurµ e~w., sort am tuwuac~, a. us. nvoe
Trow ~: c~o~ ~-s..,
DAM AND PUMP CROSSING
THE FOLLOWING IS A SEQUENCE OF CONSTRUCTION AND MITIGATION
MEASURES TO BE FOLLOWED AT ALL "DAM AND PUMP" TYPE CROSSINGS.
SEQUENCE OF ACTMIIES
STEP 1. IMPLEMENT THE TEMPORARY EROSION AND SEDIMENT CONTROLS.
STEP 2. INSTALL DRY STREAM CROSSING MATERIALS.
STEP 3. EXCAVATE TRENCH AND INSPECT OR REPLACE PIPE.
STEP 4. BACKFILL AND RESTORE STREAM BANKS.
STEP 5, REMOVE DAMS.
STEP 6. IMPLEMENT PERMANENT EROSION AND SEDIMENTATION CONTROLS
NOTES:
~• SCHEDULE INSTREAM ACTIVITY FOR LOW FLOW PERIODS AND
FOR THE APPROPRIATE TIMING WINDOW.
2. MARK OUT AND MAINTAIN LIMITS OF AUTHORIZED WORK
AREAS WITH FENCING OR FLAGGING TAPE TO AVOID
UNNECESSARY DISTURBANCE OF VEGETATION. ENSURE
EQUIPMENT OPERATORS WORKING ON THE CROSSING HAVE
BEEN BRIEFED ABOUT THIS PLAN AND THE MEASURES
NEEDED TO PROTECT WATER QUALITY. INSTALL PRE-WORK
SEDIMENT CONTROL MEASURES AS SPECIFlED IN THE PLAN.
ALL NECESSARY EQUIPMENT AND MATERIALS TO BUILD THE
DAMS AND TO PUMP WATER MUST BE ON SfTE OR READILY
AVAILABLE PRIOR TO COMMENCING IN-WATER CONSTRUCTION.
3. CONTRACTOR SHALL SUPPLY, INSTALL AND MAINTAIN SEDIMENT
CONTROL STRUCTURES, AS DEPICTED AND ALONG DOWN GRADIENT
SIDES OF WORK AREAS AND STAGING AREAS SUCH THAT NO
HEAVILY SILT LADEN WATER ENTERS WATERBODY.
a. NO HEAVILY SILT LADEN WATER SHALL BE DISCHARGED DIRECTLY
OR INDIRECTLY INTO THE WATERBODY.
b. EROSION AND SEDIMENT CONTROL STRUCTURE LOCATIONS AS
DEPICTED ARE APPROXIMATE AND MAY BE ADJUSTED AS DIRECTED
BY THE COMPANY INSPECTOR TO ACTUAL SRE CONDITIONS.
c. SILT FENCE OR HAY BALE INSTALLATIONS SHALL INCLUDE
REMOVABLE SECTIONS TO FACILRATE ACCESS DURING
CONSTRUCTION. UTILIZE HAY BALE BARRIERS ONLY IN LIEU
OF A SILT FENCE WHERE FREQUENT ACCESS IS REQUIRED.
d. SEDIMENT LADEN WATER FROM TRENCH DEWATERING SHALL BE
DISCHARGED TO A WELL VEGETATED UPLAND AREA, INTO A HAY
BALE DEWATERING STRUCTURE OR GEOTEXTILE FILTER BAG.
e. SEDIMENT CONTROL STRUCTURES MUST BE IN PLACE AT ALL
TIMES ACROSS THE DISTURBED PORTIONS OF THE RIGHT-OF-WAY
EXCEPT DURING EXCAVATION/INSTALLATION OF THE CROSSING PIPE.
4. TO THE EXTENT POSSIBLE, MAINTAIN A MINIMUM 25 FEET
VEGETATNE BUFFER STRIP BETWEEN DISTURBED AREAS AND THE
WATERBODY. INSTALL AND MAINTAIN A SILT FENCE UPSLOPE
OF THE BUFFER STRIP ON EACH SIDE OF THE WATERBODY.
THE SILT FENCE SHOULD INCORPORATE REMOVABLE `GATES" AS
REQUIRED TO ALLOW ACCESS WHILE MAINTAINING EASE OF
REPLACEMENT FOR OVERNIGHT OR DURING PERIODS OF RAINFALL
5. CONSTRUCT A TEMPORARY SUMP UPSTREAM OF THE DAM AND
LINE WffH ROCKFILL IF A NATURAL POOL DOES NOT EXIST.
INSTALL THE PUMP OR PUMP INTAKE IN THE POOL OR SUMP.
DISCHARGE WATER ONTO AN ENERGY DISSIPATOR DOWNSTREAM
OF THE WORK AREA.
5, EXCAVATED MATERIAL MUST NOT BE STOCKPILED WITHIN 10 FT.
OF THE WATERBODY. THIS MATERIAL MUST BE CONTAINED
WffHIN BERM CONTAINMENT, WITH SECONDARY SILT FENCE
PROTECTION TO PREVENT SATURATED SOIL FROM FLOWING
BACK INTO THE WATERBODY.
7. CHEMICALS, FUELS, LUBRICATING OILS SHALL NOT BE STORED
AND NOR SHALL EQUIPMENT BE REFUELED WITHIN 100 FT. OF THE
WATERBODY. PUMPS ARE TO BE REFUELED AS PER THE SPCC PLANS.
°~" ` 7ROW ENGINEERING CONSULTANTS INC.
s-'~ f]ro YETgPOIn BEM., 91(E ]0p rKwu$[E ~, U51 d]]OE
Prow c~> XB-B«i
MAINTENANCE OF STREAMFLOW
IF THERE IS ANY FLOW IN THE WATERBODY, INSTALL
PUMPS TO MAINTAIN STREAMFLOW AROUND THE ISOLATED
SECTIONS OF CHANNEL. THE PUMP IS TO HAVE 1.5
TO 2 TIMES THE PUMPING CAPACITY OF ANTICIPATED FLOW.
A SECOND STANDBY PUMP OF EQUAL CAPACITY IS TO BE
READILY AVAILABLE AT ALL TIMES. AN ENERGY DISSIPATOR
IS TO BE BUILT TO ACCEPT PUMP DISCHARGE WITHOUT
STREAMBED OR STREAMBANK EROSION. IF THE WORK
IS PROLONGED BEYOND ONE DAY THE AREA NEEDS
TO BE MONITORED OVERNIGHT.
8. IF A REPLACEMENT, PIPE MAKE-UP AREAS ARE TO BE
LOCATED AT LEAST 50 Fi. FROM THE WATER'S EDGE
(WHERE TOPOGRAPHIC CONDTIONS PERMIT) AND SHALL
BE THE MINIMUM AREA NEEDED.
9. DAMS ARE TO BE MADE OF STEEL PLATE, INFLATABLE PLASTIC
DAM, SAND BAGS, COBBLES, WELL GRADED COARSE GRAVEL FlLL,
OR ROCK FILL. DAMS MAY NEED KEYING INTO THE BANKS AND
STREAMBED. ENSURE THAT THE DAM AND VEHICLE CROSSING (IF
NEEDED) ARE LOCATED FAR ENOUGH APART TO ALLOW FOR A WIDE
EXCAVATION. CAP FLUMES USED UNDER VEHICLE CROSSING
DURING DRY CROSSING.
10. DEWATER AREA BETWEEN DAMS IF POSSIBLE. DEWATERING
SHOULD OCCUR IN A STABLE VEGETATNE AREA A MINIMUM OF
50 FT. FROM ANY WATERBODY. THE PUMP DISCHARGE SHOULD
BE DISCHARGED ONTO A STABLE SPILL PAD, FLIER BAG OR
HAY BALE STRUCTURE TO PREVENT LOCALIZED EROSION.
THE DISCHARGE WATER SHOULD ALSO BE FORCED INTO SHEET
FLOW IMMEDIATELY BEYOND THE SPILL PAD BY USING HAY BALES
AND THE NATURAL TOPOGRAPHY. DISCHARGED WATER SHALL NOT
BE ALLOWED TO FLOW INTO ANY WATERBODY OR WETLAND. IF R
IS NOT POSSIBLE TO DEWATER THE EXCAVATION DUE TO SOILS
WRH A HIGH HYDRAULIC CONDUCTIVITY, THE EXCAVATION IS TO BE
CARRIED OUT IN THE STANDING WATER. PUMP ANY DISPLACED WATER
AS DESCRIBED ABOVE TO PREVENT OVERTOPPING OF DAMS.
11. INSPECT/REPAIR PIPELINE AS NEEDED.
12. CONTRACTOR SHALL RESTORE THE STREAM BED AND BANKS TO
APPROXIMATE PRE-CONSTRUCTION CONTOURS, BUT NOT TO
EXCEED 2:1 SLOPE.
a. CONTRACTOR SHALL INSTALL PERMANENT EROSION AND
SEDIMENT CONTROL STRUCTURES AS INDICATED ON A SffE
SPECIFlC BASIS. IN THE ABSENCE OF SITE SPECIFlC INFOR-
MATION, AFLEXIBLE CHANNEL LINER SUCH AS NAG C125 OR
C350 WHICH IS CAPABLE OF WITHSTANDING ANTICIPATED FLOW
SHALL BE INSTALLED. ALTERNATNELY, ROCK RIP-RAP SHALL
BE INSTALLED.
b. ANY MATERALS PLACED IN THE STREAM TO FACILfTATE
CONSTRUCTION SHALL BE REMOVED DURING RESTORATION.
BANKS SHALL BE STABWZED AND TEMPORARY SEDIMENT
BARRIERS INSTALLED AS SOON AS POSSIBLE AFTER IN-STREAM
WORK BUT WfTHiN 24 HOURS OF COMPLETING IN-STREAM WORK.
c. MAINTAIN A SILT FENCE OR HAY BALE BARRIER ALONG
THE WATERBODY UNTIL VEGETATION IS ESTABLISHED IN
ADJACENT DISTURBED AREAS.
13. WHEN THE STREAMBED HAS BEEN RESTORED, THE CREEK BANKS
ARE TO BE CONTOURED TO A STABLE ANGLE AND PROTECTED
WITH EROSION RESISTANT MATERIAL COMPATIBLE WITH FLOW
VELOCITY BETWEEN DAMS (E.G., EROSION CONTROL BLANKETS,
CRIBBING, ROCK RIP-RAP, ETC.). THE DAMS ARE TO BE REMOVED
DOWNSTREAM FIRST. KEEP PUMP RUNNING UNTIL NORMAL FLOW
IS RESUMED. COMPLETE 6ANK TRIMMING AND EROSION PROTECTION.
IF SANDBAGS ARE USED FOR THE DAMS, PLACE AND REMOVE BY
HAND TO AVOID EQUIPMENT BREAKING BAGS.
14. TEMPORAR`( EQUIPMENT CROSSING CAN BE CONSTRUCTED USING ERHER
A FLUME CROSSING OR A TEMPORARY BRIDGE. FOR BRIDGE CROSSING
DETAILS, REFER TO THE TYPICAL RAILCAR BRIDGE CROSSING OR
TYPICAL MAT CROSSING DRAWINGS.
rrrs I oi-ze-zoo4 I us
~~~ COLONIAL PIPELINE COMPANY
ATIANfA, GEORGIA
TYPICAL DAM AND PUMP
MAINTENANCE DIG
AT WATERBODY LESS THAN 15'
Taow rna. ra. orsAw~NC sir
n+~osoaaz ca-ooox z ov z
APPENDIX C
TYPICAL OPEN CUT DRY FLUME MAINTENANCE DIG
SILT FENCE
PERMANENT ROW
TROW ENGINEERING CONSULTANTS INC.
Iwo -Mw". KW.. sort2w TXLWW [ R, M sDos
P„ow. (M) 30-e ,
NIS 101-2B-20041 ALS 1
FOR STREAM EQUIPMENT
CROSSINGS, SEE NOTE 13
r
r
( SEE SHEET 2 FOR NOTES
CD COLONIAL PIPELINE COMPANY
ATLANTA, GEORGIA
TYPICAL OPEN CUT DRY FLUME
MAINTENANCE DIG
AT WATERBODY FROM 15' TO 50'
TROW PROD. "o.1 DRAWMG I SWEET
TWESOOSOJO2 I COL -0001 1 OF 2
<i 11 II
i;
1 11 11
i
I
r
�` ,.,���._ , f,,,� r III � � �
( .
_. ��_�� ,-�__-•_- r_, �,
SANDBAG
PROTECTIONRASOCK NEEDED
15
WATERBODY
j'J
FLOW
-�
-+�1t3
PREFABRICATED ---"
FLUMES
I�
OPTIONAL
I
STEEL PLATE
SPOIL CONTAINMENT BERM
(SILT FENCE, HAY BALES
1
OR OTHER APPLICABLE 1 I
l
MAINTAIN A MINIMUM 25'
MATERIALS)
VEGETATIVE BUFFER TO
N ®I
I i
THE EXTENT POSSIBLE
SILT FENCE
PERMANENT ROW
TROW ENGINEERING CONSULTANTS INC.
Iwo -Mw". KW.. sort2w TXLWW [ R, M sDos
P„ow. (M) 30-e ,
NIS 101-2B-20041 ALS 1
FOR STREAM EQUIPMENT
CROSSINGS, SEE NOTE 13
r
r
( SEE SHEET 2 FOR NOTES
CD COLONIAL PIPELINE COMPANY
ATLANTA, GEORGIA
TYPICAL OPEN CUT DRY FLUME
MAINTENANCE DIG
AT WATERBODY FROM 15' TO 50'
TROW PROD. "o.1 DRAWMG I SWEET
TWESOOSOJO2 I COL -0001 1 OF 2
DRY FLUME MAINTENANCE WORK
THE FOLLOWING IS A SEQUENCE OF CONSTRUCTION AND MITIGATION
MEASURES TO BE FOLLOWED AT ALL 'DRY FLUME' WORK LOCATIONS
SEQUENCE OF ACTMIIES
STEP 1. IMPLEMENT THE TEMPORARY EROSION AND SEDIMENT CONTROLS.
STEP 2. INSTALL DRY STREAM CROSSING MATERIALS.
STEP 3. EXCAVATE TRENCH AND INSPECT/REPAIR AS NECESSARY.
STEP 4. BACKFILL AND RESTORE STREAM BANKS.
STEP 5. REMOVE FLUME CROSSING.
STEP 6. IMPLEMENT PERMANENT EROSION AND SEDIMENTATION CONTROLS.
NOTES:
1. MARK OUT AND MAINTAIN LIMITS OF AUTHORIZED WORK
AREAS WffH FENCING OR FLAGGING TAPE TO AVOID
UNNECESSARY DISTURBANCE OF VEGETATION. ENSURE
EQUIPMENT OPERATORS WORKING ON THE CROSSING HAVE
BEEN BRIEFED ABOUT THIS PLAN AND THE MEASURES
NEEDED TO PROTECT WATER QUALITY.
2. ALL NECESSARY EQUIPMENT AND MATERULLS TO BUILD THE
FLUME MUST BE ON SITE OR READILY AVAILABLE PRIOR
TO COMMENCING IN-WATER WORK.
3. TO THE EXTENT POSSIBLE, MAINTAIN A MINIMUM 25 FT.
VEGETATES BUFFER STRIP BETWEEN DISTURBED AREAS
AND THE WATERBODY. INSTALL AND MAINTAIN A SILT
FENCE OR HAY BALE BARRIER UPSLOPE OF THE BUFFER
STRIP ON EACH SIDE OF THE WATERBODY.
4. CONTRACTOR SHALL SUPPLY, INSTALL AND MAINTAIN SEDIMENT
CONTROL STRUCTURES, AS DEPICTED OR ALONG DOWN GRADIENT
SIDES OF WORK AREAS AND STAGING AREAS SUCH THAT NO
HEAVILY SILT LADEN WATER ENTERS THE WATERBODY.
a. NO HEAVILY SILT LADEN WATER SHALL BE DISCHARGED DIRECTLY
OR INDIRECTLY INTO THE WATERBODY.
b. EROSION AND SEDIMENT CONTROL STRUCTURE LOCATIONS AS
DEPICTED ARE APPROXIMATE AND MAY BE ADJUSTED AS DIRECTED
BY THE COMPANY INSPECTOR TO ACTUAL SfTE CONDITIONS.
c. SILT FENCE OR HAY BALE INSTALLATIONS SHALL INCLUDE
REMOVABLE SECTIONS TO FACILRATE ACCESS DURING
CONSTRUCTION. UTILIZE HAY BALE BARRIERS ONLY IN LIEU
OF A SILT FENCE WHERE FREQUENT ACCESS IS REQUIRED.
d. SEDIMENT LADEN WATER FROM TRENCH DEWATERING SHALL BE
DISCHARGED TO A WELL VEGETATED UPLAND AREA +NTO A HAY
BALE DEWATERING STRUCTURE OR GEOTEXTILE FLIER BAG.
e. SEDIMENT CONTROL STRUCTURES MUST BE IN PLACE AT ALL
TIMES ACROSS THE DISTURBED PORTIONS OF THE RIGHT-OF-WAY
EXCEPT DURING EXCAVATION/REPAIR.
5. FLUME CAPACITY DURING DRY CROSSING SHALL BE SUFFICIENT
TO ACCOMMODATE 1.5 TIMES THE FLOW MEASURED AT THE TIME
OF CONSTRUCTION PROVIDED THAT THE FLUMES WILL BE IN PLACE
NOT MORE THAN 96 HOURS AND NO PRECIPITATION IS FORECAST.
PLU~METHCE ZCIYTY R ODES GNI F~LOWCOR THE OW REASONABLY EXPECTED
TO OCCUR DURING THE INSTALLATION. EXCESS FLUMES REQUIRED FOR
LONGER TERM ACCESS SHALL BE CAPPED DURING DRY CROSSING
PROCEDURES.
6. ENSURE THAT THE DAMS AND EQUIPMENT CROSSING ARE LOCATED
FAR ENOUGH APART TO ACCOMMODATE THE REQUIRED EXCAVATION.
7. PLACE IMPERVIOUS DAMS AT EACH END OF THE FLUME, UPSTREAM
FIRST, THEN DOWNSTREAM. ACCEPTABLE ALTERNATIVES INCLUDE
GRAVEL WffH RIP-RAP PROTECTION, SAND BAGS, STEEL PLATE AND
ROCKFILL. DURING INSTALUTION, INSTALL AN IMPERVIOUS MEMBRANE,
IF NECESSARY, TO LIMR LEAKAGE, DAMS MAY NEED KEYING INTO 13.
THE BANK AND STREAMBED.
TROW ENGINEERING CONSULTANTS INC.
Two ucnarourw, xw., sort xoo iwuwssc[. ti, w~ ~xwe
»~ ~~~ .>u_>w,
B. EXCAVATE AS REQUIRED TO INSPECT OR REPLACE PIPE.
9. EXCAVATED MATERIAL MUST NOT 8E STOCKPILED WTHIN 10 FT.
OF THE WATERBOOY. THIS MATERIAL MUST 8E CONTAINED
WITHIN BERM CONTAINMENT, WITH SECONDARY SILT FENCE
PROTECTION TO PREVENT SATURATED SOIL FROM FLOWING
BACK INTO THE WATERBODY.
10. DEWATERING SHOULD OCCUR IN A STABLE VEGETATED AREA A
MINIMUM OF 50 FT. FROM ANY WATERBODY. THE PUMP
DISCHARGE SHOULD BE DIRECTED ONTO A STABLE SPILL PAD,
FILTER BAG OR HAY BALE STRUCTURE TO PREVENT LOCALIZED
EROSION. THE DISCHARGE WATER SHOULD ALSO BE FORCED
INTO SHEET FLOW IMMEDIATELY BEYOND THE SPILL PAD USING
HAY BALES AND THE NATURAL TOPGRAPHY.
ONGER REQUIRED FOR MN~STRE~AMSAOCTIVIT~Y ORSFOR ROADEACCESS,
AS FOLLOWS:
o. REMOVE THE VEHICLE CROSSING RAMP. BANKS ARE TO BE
EROSTSIONDRESISTAN MATER~tAGL COMPATIBLEEWITH FLOW
CONDITIONS E.G., EROSION CONTROL BLANKETS, CRIBBING,
ROCK RIP- ETC.) TO THE MAXIMUM EXTENT POSSIBLE
BEFORE REMOVING THE DAMS.
b. REMOVE DOWNSTREAM DAM.
c. REMOVE UPSTREAM DAM.
d. REMOVE FLUME.
e. COMPLETE BANK TRIMMING AND EROSION PROTECTION. IF
SANDBAGS ARE USED FOR THE DAMS, PLACE AND REMOVE BY
HAND TO AVOID EOUIPMEN7 BREAKING BAGS.
CONTRACTOR SHALL RESTORE THE STREAM BED AND BANKS TO
APPROXIMATE PRE-CONSTRUCTION CONTOURS, BUT NOT TO
EXCEED 2:1 SLOPE.
o. CONTRACTOR SHALL INSTALL PERMANENT EROSION AND
SEDIMENT CONTROL STRUCTURES AS INDICATED ON A SffE
SPECIFlC BASIS. IN THE ABSENCE OF SITE SPECIFlC INFOR-
MATION, AFLEXIBLE CHANNEL LINER SUCH AS NAG C125 OR
C350 WHICH IS CAPABLE OF WITHSTANDING ANTICIPATED FLOW
SHALL BE INSTALLED. ALTERNATIVELY, ROCK RIP-RAP SHALL
BE INSTALLED.
b. ANY MATERAS PLACED IN THE STREAM TO FACILITATE
CONSTRUCTION SHALL BE REMOVED DURING RESTORATION.
BANKS SHALL BE STABILIZED AND TEMPORARY SEDIMENT
BARRIERS INSTALLED AS SOON AS POSSIBLE AFTER IN-STREAM
WORK, BUT WITHIN 24 HOURS OF COMPLETING THE IN-STREAM
WORK.
c. MAINTAIN A SILT FENCE OR HAY BALE BARRIER ALONG
THE WATERBODY UNTIL VEGETATION IS ESTABLISHED IN
ADJACENT DISTURBED AREAS.
TEMPORARY EQUIPMENT CROSSING CAN BE CONSTRUCTED USING ERHER
A FLUME CROSSING OR A TEMPORARY BRIDGE. FOR BRIDGE CROSSING
DETAILS, REFER TO THE TYPICAL RAILCAR BRIDGE CROSSING OR
TYPICAL MAT CROSSING DRAWINGS.
11
12.
Hrs I of-~-zoa I us
COLONIAL PIPELINE COMPANY
ATLANTA, GEORGIA
TYPICAL OPEN CUT DRY FLUME
MAINTENANCE DIG
AT WATERBODY FROM 15' TO 50'
mow vaa. pro. oa~wwc sN¢r
nesoososet coy-ooo~o z a 2
APPENDIX D
CPC'S SOIL EROSION AND SEDIMENTATION CONTROL PLAN
Colonial Pipeline Company
Soil Erosion and Sediment Control Plan
For
Pipeline Maintenance Activities
Objective
Disturbed areas are to be restored as close as practical to their original contours and
conditions so that once vegetation is reestablished, erosion will be reduced to the same
or lower level that existed prior to disturbance.
Description
This section defines the soil erosion and sediment control measures that Colonial
Pipeline Company will implement during and after inspection and repairs of the pipeline
are complete. The objectives of this plan are to establish general guidelines for
controlling erosion and sedimentation and to specify criteria for sensitive or particularly
susceptible soil areas. The plan incorporates measures to control erosion and
sedimentation, including minimizing cover removal, limiting the time of exposure,
limiting the flow of water onto the disturbed right-of-way, and filtering or settling out
sediment from water flowing from the right-of--way.
The primary objective of the soil erosion and sediment control plan is to reduce the area
and duration of soil disturbance and reestablish permanent vegetation as soon after
construction as possible, thereby minimizing long-term erosion and sedimentation.
Some erosion is inevitable during construction; however, the plan includes measures to
reduce erosion to the minimum practical.
Colonial Pipeline Company plans to reduce soil erosion and provide sediment control
during the repair of the pipeline at the project site by incorporating the following
measures:
• Water pumped from the construction area as part of the dewatering operation
from the excavation will be filtered through silt filtration bags and discharged to
awell-vegetated area.
• All work will be confined within the existing right-of--way. Staked hay bales and
silt fence will be installed around the worksite and maintained until vegetation is
established. Proper controls will be added if necessary during construction.
• All terms and conditions within Nationwide Permit 3 will be followed.
• Erosion control measures will be installed prior to conducting any soil disturbing
activities associated with the pipeline maintenance activity.
1 of 2
• Clearing of vegetation will be kept to an absolute minimum and confined to the
existing pipeline easement area. The easement area is 6o feet in width and devoid
of large trees. The right of way is vegetated with undergrowth grasses and other
short vegetation.
• Vegetation will be reestablished within disturbed areas and along stream banks
as soon as possible upon completion of work. Disturbed areas will be seeded
with a native seed mixture
• All erosion and sediment control measures will be inspected every two weeks at a
minimum and after every significant rainfall event of o.5 inch or more until
disturbed areas have been stabilized. Identified damages to control measures
must be repaired immediately.
Refuse and Waste Disposal
Colonial's representative will not allow the Contractor to discard any litter, including
paper, bottles, cans, rags, sacks, welding rod stubs, fuel, crankcase draining, coating
materials, equipment, and junk pipe in the ditch or along the right-of--way. All refuse
must be collected and disposed in accordance with company specifications. Personnel
will be instructed regarding the correct procedure for waste disposal.
Maintenance/Inspection Procedures
The following inspection and maintenance practices will be implemented to maintain
erosion and sediment controls:
i. All control measures will be inspected every two weeks at a minimum and following
any storm event of o.5 inch or greater.
2. All control measures will be maintained in good working order. If a repair is
necessary, it will be initiated within 24 hours of the report.
3. Built-up sediment will be removed from silt fences when it has reached one-third the
height of the fence.
4. Silt fences will be inspected for depth of sediment, tears, secure attachment of the
fabric to the fence posts, and firm placement of the fence posts in the ground.
5. Temporary and permanent seeding and planting will be inspected for bare spots,
washouts, and healthy growth.
6. Colonial Pipeline Company will select individuals to be responsible for inspections,
maintenance and repair activities, and completion of the inspection and
maintenance report. Personnel selected for inspection and maintenance
responsibilities will receive training from Colonial Pipeline Company or its
representative. Personnel must be trained in all practices necessary for maintaining
the erosion and sediment controls used on-site.
2 of 2
APPENDIX E
APPROVED JURISDICATIONALbETERMINATION FORM
APPROVED JURISDICTIONAL DETERMINATION FORM
U.S. Army Corps of Engineers
This form should be completed by following the instructions provided in Section IV of the JD Form Instructional Guidebook.
SECTION I: BACKGROUND INFORMATION
A. REPORT COMPLETION DATE FOR APPROVED JURISDICTIONAL DETERMINATION (JD):
B. DISTRICT OFFICE, FILE NAME, AND NUMBER: Wilmington
C. PROJECT LOCATION AND BACKGROUND INFORMATION:
State:NC County/parish borough: Rowan City: Kannapolis
Center coordinates of site (lat/long in degree decimal format): Lat. 35 30.902° hi, Long. 80 42.445° W.
Universal Transverse Mercator: 17N 526530E 3930200 N
Name of nearest waterbody: Park Creek
Name of nearest Traditional Navigable Water (TNW) Into which the aquatic resource flows: Caddle Creek Reservoir
Name of watershed or Hydrologic Unit Code (HUC): Rocky 03040105
® Check if map/diagram of review area and/or potential jurisdictional areas is/are available upon request.
Check if other sites (e.g., offsite mitigation sites, disposal sites, etc...) are associated with this action and are recorded on a
different JD form.
D. REVIEW PERFORMED FOR SITE EVALUATION (CHECK ALL THAT APPLY):
Office (Desk) Determination. Date:
® Field Determination. Date(s): 6-26-07 by Wetland & Ecological Consultants, LLC
SECTION II: SUMMARY OF FINDINGS
A. RHA SECTION 10 DETERMINATION OF JURISDICTION.
There Are no "navigable waters of the U.S." within Rivers and Harbors Act (RHA) jurisdiction (as defined by 33 CFR part 329) in the
review area. [Required]
Q Waters subject to the ebb and flow of the tide.
Waters are presently used, or have been used in the past, or may be susceptible for use to transport interstate or foreign commerce.
Explain:
B. CWA SECTION 404 DETERMINATION OF JURISDICTION.
There Aie "waters o the U.S" within Clean Water Act CWA urisdiction as defined b 33 CFR art 328 m the review area. Re wire
.r ( ) j ( Y P ) ~ [ q d]
1. Waters of the U.S.
a. Indicate presence of waters of U.S. in review area (check all that apply):'
Q TNWs, including territorial seas
Q Wetlands adjacent to TNWs
® Relatively permanent waters2 (RPWs) that flow directly or indirectly into TNWs
Q Non-RPWs that flow directly or indirectly into TNWs
Q Wetlands directly abutting RPWs that flow directly or indirectly into TNWs
Wetlands adjacent to but not directly abutting RPWs that flow directly or indirectly into TNWs
Wetlands adjacent to non-RPWs that flow directly or indirectly into TNWs
Impoundments of jurisdictional waters
Q Isolated (interstate or intrastate) waters, including isolated wetlands
b. Identify (estimate) size of waters of the U.S. in the review area:
Non-wetland waters: 70 linear feet: 20 width (ft) and/or acres.
Wetlands: acres.
c. Limits (boundaries) of jurisdiction based on: 1987 Delineation Manual
Elevation of established OHWM (if known):
2. Non-regulated waters/wetlands (check if applicable):3
Potentially jurisdictional waters andlor wetlands were assessed within the review area and determined to be not jurisdictional.
Explain:
~ Boxes checked below shall be supported by completing the appropriate sections in Section III below.
Z For purposes of this form, an RPW is defined as a tributary that is not a TNW and that typically flows year-round or has continuous flow at least "seasonally"
(e.g., typically 3 months).
Supporting documentation is presented in Section III.F.
SECTION III: CWA ANALYSIS
A. TNWs AND WETLANDS ADJACENT TO TNWs
The agencies will assert jurisdiction over TNWs and wetlands adjacent to TNWs. If the aquatic resource is a TNW, complete
Section III.A.1 and Section III.D.1. only; if the aquatic resource is a wetland adjacent to a TNW, complete Sections III.A.1 and 2
and Section III.D.1.; otherwise, see Section III.B below.
1. TNW
Identify TNW:
Summarize rationale supporting determination:
Wetland adjacent to TNW
Summarize rationale supporting conclusion that wetland is "adjacent":
B. CHARACTERISTICS OF TRIBUTARY (THAT IS NOT A TNW) AND ITS ADJACENT WETLANDS (IF ANY):
This section summarizes information regarding characteristics of the tributary and its adjacent wetlands, if any, and it helps
determine whether or not the standards for jurisdiction established under Rapaaoshave been met.
The agencies will assert jurisdiction over non-navigable tributaries of TNWs where the tributaries are °`relatively permanent
waters" (RPWs), i.e. tributaries that typically flow year-round or have continuous flow at least seasonally (e.g., typically 3
months). A wetland that directly abuts an RPW is also jurisdictional. If the aquatic resource is not a TNW, but has year-round
(perennial) flow, skip to Section III.D.2. If the aquatic resource is a wetland directly abutting a tributary with perennial flow,
skip to Section IILD.4.
A wetland that is adjacent to but that does not directly abut an RPW requires a significant nexus evaluation. Corps districts and
EPA regions will include in the record any available information that documents the existence of a significant nexus between a
relatively permanent tributary that is not perennial (and its adjacent wetlands it any) and a traditional navigable water, even
though a significant nexus finding is not required as a matter of law.
If the waterbody° is not an RPW, or a wetland directly abutting an RPW, a JD will require additional data to determine if the
waterbody has a significant nexus with a TNW. If the tributary has adjacent wetlands, the significant nexus evaluation must
consider the tributary in combination with all of its adjacent wetlands. This significant nexus evaluation that combines, for
analytical purposes, the tributary and all of its adjacent wetlands is used whether the review area identified in the JD request is
the tributary, or its adjacent wetlands, or both. if the JD covers a tributary with adjacent wetlands, complete Section III.B.1 for
the tributary, Section III.B.2 for any onsite wetlands, and Section III.B.3 for all wetlands adjacent to that tributary, both onsite
and offsite. The determination whether a significant nexus exists is determined in Section III.C below.
1. Characteristics of non-TNWs that flow directly or indirectly into TNW
(i) General Area Conditions:
Watershed size: Pick List
Drainage area: Tick List
Average annual rainfall: inches
Average annual snowfall: inches
(ii) Physical Characteristics:
(a) Relationship with TNW:
^ Tributary flows directly into TNW.
r-, ~-
Tributary flows through iclil,ist tributaries before entering TNW.
Project waters are Pcl: List river miles from TNW.
Project waters are Pick List river miles from RPW.
Project waters are `Pick~Lst aerial (straight) miles from TNW.
Project waters are Plck*List aerial (straight) miles from RPW.
Project waters cross or serve as state boundaries. Explain:
Identify flow route to TNWS:
Tributary stream order, if known:
° Note that the Instructional Guidebook contains additional information regarding swales, ditches, washes, and erosional features generally and in the arid
West.
s Flow mute can be described by identifying, e.g., tributary a, which flows through the review area, to flow into tributary b, which then flows into TNW.
(b) General Tributary Characteristics (check all that applvl:
Tributary is: ^ Natural
^ Artificial (man-made). Explain:
^ Manipulated (man-altered). Explain:
Tributary properties with respect to top of bank (estimate):
Average width: feet
Average depth: feet
Average side slopes: Pick List.
Primary tributary substrate composition (check all that apply):
^ Silts ^ Sands
^ Cobbles ^ Gravel
^ Bedrock ^ Vegetation. Type/% cover:
^ Other. Explain:
^ Concrete
^ Muck
Tributary condition stability [e.g., highly eroding, sloughing banks). Explain:
Presence of run/riffle/pool complexes. Explain:
Tributary geometry Pick List
Tributary gradient (approximate average slope):
(c) Flow:
Tributary provides for: ~ckLlBt
Estimate average number of flow events in review area/year: Pick List
Describe flow regime:
Other information on duration and volume:
Surface flow is: Plck List. Characteristics:
Subsurface flow: Pick List. Explain findings:
^ Dye (or other) test performed:
Tributary has (check all that apply):
^ Bed and banks
^ OHWM6 (check all indicators that apply):
^ clear, natural line impressed on the bank ^
^ changes in the character of soil ^
^ shelving ^
^ vegetation matted down, bent, or absent ^
^ leaf litter disturbed or washed away ^
^ sediment deposition ^
^ water staining ^
^ other (list):
the presence of litter and debris
destruction of terrestrial vegetation
the presence of wrack line
sediment sorting
scour
multiple observed or predicted flow events
abrupt change in plant community
^ Discontinuous OHWM.~ Explain:
If factors other than the OHWM were used to determ
High Tide Line indicated by:
^ oil or scum line along shore objects
^ fine shell or debris deposits (foreshore)
^ physical markings/characteristics
^ tidal gauges
^ other (list):
ine lateral extent of CWA jurisdiction (check all that apply):
Mean High Water Mark indicated by:
^ survey to available datum;
^ physical markings;
^ vegetation lines/changes in vegetation types.
(iii) Chemical Characteristics:
Characterize tributary (e.g., water color is clear, discolored, oily film; water quality; general watershed characteristics, etc.).
Explain:
Identify specific pollutants, if known:
6A natural or man-made discontinuity in the OHWM does not necessarily sever jurisdiction (e.g., where the stream temporarily flows underground, or where
the OHWM has been removed by development or agricultural practices). Where there is a break in the OHWM that is unrelated to the waterbody's flow
regime (e.g., flow over a rock outcrop or through a culvert), the agencies will look for indicators of flow above and below the break.
'Ibid.
(iv) Biological Characteristics. Channel supports (check all that apply):
^ Riparian corridor. Characteristics (type, average width):
^ Wetland fringe. Characteristics:
^ Habitat for:
^ Federally Listed species. Explain findings:
^ Fish/spawn areas. Explain findings:
^ Other environmentally-sensitive species. Explain findings:
^ Aquatic/wildlife diversity. Explain findings:
2. Characteristics of wetlands adjacent to non-TNW that flow directly or indirectly into TNW
(i) Physical Characteristics:
(a) General Wetland Characteristics:
Properties:
Wetland size: acres
Wetland type. Explain:
Wetland quality. Explain:
Project wetlands cross or serve as state boundaries. Explain:
(b) General Flow Relationship with Non-TNW:
Flow is: Pick List. Explain:
Surface flow is: Pick'List
Characteristics:
Subsurface flow: Pick List. Explain findings:
^ Dye (or other) test performed:
(c) Wetland Adjacency Determination with Non-TNW:
^ Directly abutting
^ Not directly abutting
^ Discrete wetland hydrologic connection. Explain:
^ Ecological connection. Explain:
^ Separated by berm barrier. Explain:
(d) Proximit,LRelationship) to TNW
Project wetlands are ~ICk Li31 river miles from TNW.
Project waters are Pick List aerial (straight) miles from TNW.
Flow is from: ~ck~List. s~,
Estimate approximate location of wetland as within the C~CkLiBt floodplain.
(ii) Chemical Characteristics:
Characterize wetland system (e.g., water color is clear, brown, oil film on surface; water quality; general watershed
characteristics; etc.). Explain:
Identify specific pollutants, if known:
(iii) Biological Characteristics. Wetland supports (check all that apply):
^ Riparian buffer. Characteristics (type, average width):
^ Vegetation type/percent cover. Explain:
^ Habitat for:
^ Federally Listed species. Explain findings:
^ Fish/spawn areas. Explain findings:
^ Other environmentally-sensitive species. Explain findings:
^ Aquatic/wildlife diversity. Explain findings:
3. Characteristics of all wetlands adjacent to the tributary (if any)
All wetland(s) being considered in the cumulative analysis: Pick List
Approximately ( )acres in total are being considered in the cumulative analysis.
For each wetland, specify the following:
Directly abuts? (Y/Nl Size (in acresl Directly abuts? (Y/Nl Size (in acresl
Summarize overall biological, chemical and physical functions being performed:
C. SIGNIFICANT NEXUS DETERMINATION
A significant nexus analysis will assess the flow characteristics and functions of the tributary itself and the functions performed
by any wetlands adjacent to the tributary to determine if they significantly affect the chemical, physical, and biological integrity
of a TNW. For each of the following situations, a significant nexus exists if the tributary, in combination with all of its adjacent
wetlands, has more than a speculative or insubstantial effect on the chemical, physical and/or biological integrity of a TNW.
Considerations when evaluating significant nexus include, but are not limited to the volume, duration, and frequency of the flow
of water in the tributary and its proximity to a TNW, and the functions performed by the tributary and all its adjacent
wetlands. It is not appropriate to determine significant nexus based solely on any specific threshold of distance (e.g. between a
tributary and its adjacent wetland or between a tributary and the TNW). Similarly, the fact an adjacent wetland lies within or
outside of a floodplain is not solely determinative of significant nexus.
Draw connections between the features documented and the effects on the TNW, as identified in the Rapanos Guidance and
discussed in the Instructional Guidebook. Factors to consider include, for example:
• Does the tributary, in combination with its adjacent wetlands (if any), have the capacity to carry pollutants or flood waters to
TNWs, or to reduce the amount of pollutants or flood waters reaching a TNW?
• Does the tributary, in combination with its adjacent wetlands (if any), provide habitat and lifecycle support functions for fish and
other species, such as feeding, nesting, spawning, or rearing young for species that are present in the TNW?
• Does the tributary, in combination with its adjacent wetlands (if any), have the capacity to transfer nutrients and organic carbon that
support downstream foodwebs?
• Does the tributary, in combination with its adjacent wetlands (if any), have other relationships to the physical, chemical, or
biological integrity of the TNW?
Note: the above list of considerations is not inclusive and other functions observed or known to occur should be documented
below:
Significant nexus findings for non-RPW that has no adjacent wetlands and flows directly or indirectly into TNWs. Explain
findings of presence or absence of significant nexus below, based on the tributary itself, then go to Section III.D:
Significant nexus findings for non-RPW and its adjacent wetlands, where the non-RPW flows directly or indirectly into
TNWs. Explain findings of presence or absence of significant nexus below, based on the tributary in combination with all of its
adjacent wetlands, then go to Section tII.D:
Significant nexus findings for wetlands adjacent to an RPW but that do not directly abut the RPW. Explain findings of
presence or absence of significant nexus below, based on the tributary in combination with all of its adjacent wetlands, then go to
Section IILD:
D. DETERMINATIONS OF JURISDICTIONAL FINDINGS. THE SUBJECT WATERS/V1'ETLANDS ARE (CHECK ALL
THAT APPLY):
TNWs and Adjacent Wetlands. Check all that apply and provide size estimates in review area:
Q TNWs: linear feet width (ft), Or, acres.
Wetlands adjacent to TNWs: acres.
RPWs that flow directly or indirectly into TNWs.
® Tributaries of TNWs where tributaries typically flow year-round are jurisdictional. Provide data and rationale indicating that
tributary is perennial: see photographs, USGS quadsheet.
Tributaries of TNW where tributaries have continuous flow "seasonally" (e.g., typically three months each year) are
jurisdictional. Data supporting this conclusion is provided at Section III.B. Provide rationale indicating that tributary flows
seasonally:
Provide estimates for jurisdictional waters in the review area (check all that apply):
® Tributary waters: 701inear feet20 width (ft).
Other non-wetland waters: acres.
Identify type(s) of waters:
3. Non-RPWss that flow directly or indirectly into TNWs.
Waterbody that is not a TNW or an RPW, but flows directly or indirectly into a TNW, and it has a significant nexus with
TNW is jurisdictional. Data supporting this conclusion is provided at Section III.C.
Provide estimates for jurisdictional waters within the review area (check all that apply):
Tributary waters: linear feet width (ft).
Other non-wetland waters: acres.
Identify type(s) of waters:
Wetlands directly abutting an RPW that flow directly or indirectly into TNWs.
Wetlands directly abut RPW and thus are jurisdictional as adjacent wetlands.
Wetlands directly abutting an RPW where tributaries typically flow year-round. Provide data and rationale
indicating that tributary is perennial in Section III.D.2, above. Provide rationale indicating that wetland is
directly abutting an RPW:
Wetlands directly abutting an RPW where tributaries typically flow "seasonally." Provide data indicating that tributary is
seasonal in Section III.B and rationale in Section III.D.2, above. Provide rationale indicating that wetland is directly
abutting an RPW: .
Provide acreage estimates for jurisdictional wetlands in the review area: acres.
Wetlands adjacent to but not directly abutting an RPW that flow directly or indirectly into TNWs.
Wetlands that do not directly abut an RPW, but when considered in combination with the tributary to which they are adjacent
and with similarly situated adjacent wetlands, have a significant nexus with a TNW are jurisidictional. Data supporting this
conclusion is provided at Section III.C.
Provide acreage estimates for jurisdictional wetlands in the review area: acres.
Wetlands adjacent to non-RPWs that flow directly or indirectly into TNWs.
[] Wetlands adjacent to such waters, and have when considered in combination with the tributary to which they are adjacent and
with similarly situated adjacent wetlands, have a significant nexus with a TNW are jurisdictional. Data supporting this
conclusion is provided at Section III.C.
Provide estimates for jurisdictional wetlands in the review area: acres.
Impoundments of jurisdictional waters.9
As a general rule, the impoundment of a jurisdictional tributary remains jurisdictional.
Demonstrate that impoundment was created from "waters of the U.S.," or
Demonstrate that water meets the criteria for one of the categories presented above (1-6), or
Demonstrate that water is isolated with a nexus to commerce (see E below).
E. ISOLATED [INTERSTATE OR INTRA-STATE] WATERS, INCLUDING ISOLATED WETLANDS, THE USE,
DEGRADATION OR DESTRUCTION OF WHICH COULD AFFECT INTERSTATE COMMERCE, INCLUDING ANY
SUCH WATERS (CHECK ALL THAT APPLY):10
which are or could be used by interstate or foreign travelers for recreational or other purposes.
from which fish or shellfish are or could be taken and sold in interstate or foreign commerce.
which are or could be used for industrial purposes by industries in interstate commerce.
Interstate isolated waters. Explain:
Q Other factors. Explain:
Identify water body and summarize rationale supporting determination:
gSee Footnote # 3.
9 To complete the analysis refer to the key in Section IILD.6 of the Instructional Guidebook.
10 Prior to asserting or declining CWA jurisdiction based solely on this category, Corps Districts will elevate the action to Corps and EPA HQ for
review consistent with the process described in the Corps/EPA Memorandum Regarding CWA Act Jurisdiction Following Rapanos
Provide estimates for jurisdictional waters in the review area (check all that apply):
Tributary waters: linear feet width (fr).
Other non-wetland waters: acres.
Identify type(s) of waters:
^ Wetlands: acres.
F. NON-JURISDICTIONAL WATERS, INCLUDING WETLANDS (CHECK ALL THAT APPLl~:
If potential wetlands were assessed within the review area, these areas did not meet the criteria in the 1987 Corps of Engineers
Wetland Delineation Manual and/or appropriate Regional Supplements.
^ Review area included isolated waters with no substantial nexus to interstate (or foreign) commerce.
^ Prior to the Jan 2001 Supreme Court decision in "SWANCC," the review area would have been regulated based solely on the
"Migratory Bird Rule" (MBR).
Waters do not meet the "Significant Nexus" standard, where such a finding is required for jurisdiction. Explain:
Other: (explain, if not covered above):
Provide acreage estimates for non jurisdictional waters in the review area, where the sole potential basis of jurisdiction is the MBR
factors (i.e., presence of migratory birds, presence of endangered species, use of water for irrigated agriculture), using best professional
judgment (check all that apply):
Non-wetland waters (i.e., rivers, streams): linear feet width (ft).
Lakes/ponds: acres.
Other non-wetland waters: acres. List type of aquatic resource:
^ Wetlands: acres.
Provide acreage estimates for non jurisdictional waters in the review area that do not meet the "Significant Nexus" standard, where such
a finding is required for jurisdiction
Non-wetland waters (i.e., river
Lakes/ponds: acres.
Other non-wetland waters:
Wetlands: acres.
SECTION IV: DATA SOURCES.
(check all that apply):
streams): linear feet, width (ft).
acres. List type of aquatic resource:
A. SUPPORTING DATA. Data reviewed for JD (check all that apply -checked items shall be included in case file and, where checked
and requested, appropriately reference sources below):
Maps, plans, plots or plat submitted by or on behalf of the applicant/consultant:Wedand & Ecological Consultants, LLC and
Submar Inc..
Data sheets prepared/submitted by or on behalf of the applicant/consultant.
^ Office concurs with data sheets/delineation report.
^ Office does not concur with data sheets/delineation report.
Data sheets prepared by the Corps:
Corps navigable waters' study:
U.S. Geological Survey Hydrologic Atlas:
^ USGS NHD data.
^ USGS 8 and 12 digit HUC maps.
® U.S. Geological Survey map(s). Cite scale & quad name:Enochville, NC, 1993.
USDA Natural Resources Conservation Service Soil Survey. Citation:
National wetlands inventory map(s). Cite name:
State/Local wetland inventory map(s):
^ FEMA/FIRM maps:
100-year Floodplain Elevation is: (National Geodectic Vertical Datum of 1929)
® Photographs: ^ Aerial (Name & Date):
or ®Other (Name & Date):6-26-07.
Previous determination(s). File no. and date of response letter:
Applicable/supporting case law:
^ Applicable/supporting scientific literature:
Other information (please specify):
B. ADDITIONAL COMMENTS TO SUPPORT JD:
Office Use Only: Form Version March OS
0 7- 1 2 6 4
USACE Action ID No. DWQ No.
(lf any particular item is not applicable to this project, please enter "Not Applicable" or "N/A".)
I. Processing ~~~~'T~~-~
1. Check all of the approval(s) requested for this project: e°~P~
® Section 404 Permit ^ Riparian or Watershed Buffer Rules
^ Section 10 Permit ^ Isolated Wetland Permit from DWQ
^ 401 Water Quality Certification ^ Express 401 Water Quality Certification
2. Nationwide, Regional or General Permit Number(s) Requested: NWP 18
3. If this notification is solely a courtesy copy because written approval for the 441 Certification
is not required, check here:
4. If payment into the North Carolina Ecosystem Enhancement Program (NCEEP) is proposed
for mitigation of impacts, attach the acceptance letter from NCEEP, complete section VIII,
and check here: ^
5. If your project is located in any of North Carolina's twenty coastal counties (listed on page
4), and the project is within a North Carolina Division of Coastal Management Area of -~ ,.~
Environmental Concern (see the top of page 2 for further details) check h ~ ' h' ~ ~ ~'`'~'~~-~ '"'"
.. r,~..-_ ~~
II. Applicant Information ~`'~ ~; ~ z ''"
Ji,~. ~ ~ ~Du/
1. Owner/Applicant Information
Name: Mr. Jeff Richards, Colonial Pipeline Company '.~~~t:~:U^ F'`"~ c~~ ~~?~~.`!`~'~~t=° iR~!CN!
Mailing Address:
391 Scruggs Road
_ Ringgold, GA 30736
----
Telephone Number:~706) 891-6658 Fax Number:_ (706) 891-9916
E-mail Address: irichard(a~col~ipe.com
2. Agent/Consultant Information (A signed and dated copy of the Agent Authorization letter
must be attached if the Agent has signatory authority for the owner/applicant.)
Name: Sharma Cahill /Richard W. Whiteside
Company Affiliation: Wetland & Ecological Consultants
Mailing Address: 3225 S. Cherokee Lane
Bldg. 800
Woodstock, GA 30188
Telephone Number:~770) 591-9990 Fax Number: (770) 591-9993
E-mail Address: secahill(a,wet-eco.com
Updated 11/1/2005
Page 5 of 12
III. Project Information
Attach a vicinity map clearly showing the location of the property with respect to local
landmarks such as towns, rivers, and roads. Also provide a detailed site plan showing property
boundaries and development plans in relation to surrounding properties. Both the vicinity map
and site plan must include a scale and north arrow. The specific footprints of all buildings,
impervious surfaces, or other facilities must be included. If possible, the maps and plans should
include the appropriate USGS Topographic Quad Map and NRCS Soil Survey with the property
boundaries outlined. Plan drawings, or other maps maybe included at the applicant's discretion,
so long as the property is clearly defined. For administrative and distribution purposes, the
USAGE requires information to be submitted on sheets no larger than 11 by 17-inch format;
however, DWQ may accept paperwork of any size. DWQ prefers full-size construction
drawings rather than a sequential sheet version of the full-size plans. If full-size plans are
reduced to a small scale such that the final version is illegible, the applicant will be informed that
the project has been placed on hold until decipherable maps are provided.
1. Name of project: Park Creek/Exposed Petroleum Pipeline
2. T.I.P. Project Number or State Project Number (NCDOT Only): N/A
3. Property Identification Number (Tax PIN): N/A
4. Location
County: Rowan Nearest Town: Kannapolis
Subdivision name (include phase/lot number): N/A
Directions to site (include road numbers/names, landmarks, etc.): From I-85 North take exit
55 turn north onto Trinity Church Road, turn west onto Mooresville Road turn north onto
Tuckasee~ee Road, turn north onto Beaver Road turn northwest onto Wright Road CPC's
ROW is sourth of Wright Road and east of Parks Field Drive.
5. Site coordinates (For linear projects, such as a road or utility line, attach a sheet that
separately lists the coordinates for each crossing of a distinct waterbody.)
Decimal Degrees (6 digits minimum): 35° 30.902" N 80° 42.445 W
6. Property size (acres): N/A
7. Name of nearest receiving body of water: Park Creek
8. River Basin:
(Note -this must be one of North Carolina's seventeen designated major river basins. The
River Basin map is available at httu://h2o.enr.state.nc.us/admin/maps/.)
9. Describe the existing conditions on the site and general land use in the vicinity of the project
at the time of this application: The site is an existing maintained Ripeline ROW that is
periodically mowed.
Updated 11/1/2005
Page 6 of 12
10. Describe the overall project in detail, including the type of equipment to be used: See the
description in the "Background" and "Proposed Activities in Waters of the U.S." sections of
the attached cover letter.
11. Explain the purpose of the proposed work: To repair and protect an existin exposed
petroleum pipeline, and to prevent future exposure.
IV. Prior Project History
If jurisdictional determinations and/or permits have been requested and/or obtained for this
project (including all prior phases of the same subdivision) in the past, please explain. Include
the USACE Action ID Number, DWQ Project Number, application date, and date permits and
certifications were issued or withdrawn. Provide photocopies of previously issued permits,
certifications or other useful information. Describe previously approved wetland, stream and
buffer impacts, along with associated mitigation (where applicable). If this is a NCDOT project,
list and describe permits issued for prior segments of the same T.I.P. project, along with
construction schedules.
N/A
V. Future Project Plans
Are any future permit requests anticipated for this project? If so, describe the anticipated work,
and provide justification for the exclusion of this work from the current application.
VI. Proposed Impacts to Waters of the United States/Waters of the State
It is the applicant's (or agent's) responsibility to determine, delineate and map all impacts to
wetlands, open water, and stream channels associated with the project. Each impact must be
listed separately in the tables below (e.g., culvert installation should be listed separately from
riprap dissipater pads). Be sure to indicate if an impact is temporary. All proposed impacts,
permanent and temporary, must be listed, and must be labeled and clearly identifiable on an
accompanying site plan. All wetlands and waters, and all streams (intermittent and perennial)
should be shown on a delineation map, whether or not impacts are proposed to these systems.
Wetland and stream evaluation and delineation forms should be included as appropriate.
Photographs may be included at the applicant's discretion. If this proposed impact is strictly for
wetland or stream mitigation, list and describe the impact in Section VIII below. If additional
space is needed for listing or description, please attach a separate sheet.
1. Provide a written description of the proposed impacts:
See the "Proposed Activities in Waters of the U.S." section of the attached letter
Updated 11/1/2005
Page 7 of 12
2. Individually list wetland impacts. Types of impacts include, but are not limited to
mechanized clearing, grading, fill, excavation, flooding, ditching/drainage, etc. For dams,
separately list impacts due to both structure and flooding.
Wetland Impact
Site Number
(indicate on map)
Type of Impact Type of Wetland
(e.g., forested, marsh,
herbaceous, bog, etc.) Located within
100-year
Floodplain
( es/no Distance to
Nearest
Stream
(linear feet) Area of
Impact
(acres)
N/A
Total Wetland Impact (acres) 0
3. List the total acreage (estimated) of all existing wetlands on the property: N/A
4. Individually list all intermittent and perennial stream impacts. Be sure to identify temporary
impacts. Stream impacts include, but are not limited to placement of fill or culverts, dam
construction, flooding, relocation, stabilization activities (e.g., cement walls, rip-rap, crib
walls, gabions, etc.), excavation, ditching/straightening, etc. If stream relocation is proposed,
plans and profiles showing the linear footprint for both the original and relocated streams
must be included. To calculate acreage, multiply length X width, then divide by 43,560.
Stream Impact
Number
(indicate on ma
Stream Name
Type of Impact Perennial or
Intermittent? Average
Stream Width
Before Im act Impact
Length
linear feet Area of
Impact
(acres
Park Creek Riprap Perennial 20 foot 70 0.03
Total Stream Impact (by length and acreage) 70 0.03
5. Individually list all open water impacts (including lakes, ponds, estuaries, sounds, Atlantic
Ocean and any other water of the U.S.). Open water impacts include, but are not limited to
fill, excavation, dredging, flooding, drainage, bulkheads, etc.
Open Water Impact
Site Number
(indicate on ma)
Name of Waterbody
(if applicable)
Type of Impact Type of Waterbody
(lake, pond, estuary, sound, bay,
ocean, etc.) Area of
Impact
(acres)
N/A
Total Open Water Impact (acres) 0
Updated 11/1/2005
Page 8 of 12
6. List the cumulative impact to all Waters of the tLS. resulting from the nrn;ect•
Stream Impact (acres): 0.03
Wetland Impact (acres): 0
Open Water Impact (acres): 0
Total Impact to Waters of the U.S. (acres) 0.03
Total Stream Impact (linear feet): 70
7. Isolated Waters
Do any isolated waters exist on the property? ^ Yes ®No
Describe all impacts to isolated waters, and include the type of water (wetland or stream) and
the size of the proposed impact (acres or linear feet). Please note that this section only
applies to waters that have specifically been determined to be isolated by the USACE.
8. Pond Creation
If construction of a pond is proposed, associated wetland and stream impacts should be
included above in the wetland and stream impact sections. Also, the proposed pond should
be described here and illustrated on any maps included with this application.
Pond to be created in (check all that apply): ^ uplands ^ stream ^ wetlands
Describe the method of construction (e.g., dam/embankment, excavation, installation of
draw-down valve or spillway, etc.):
Proposed use or purpose of pond (e.g., livestock watering, irrigation, aesthetic, trout pond,
local stormwater requirement, etc.):
Current land use in the vicinity of the pond:
Size of watershed draining to pond: Expected pond surface area:
VII. Impact Justification (Avoidance and Minimization)
Specifically describe measures taken to avoid the proposed impacts. It maybe useful to provide
information related to site constraints such as topography, building ordinances, accessibility, and
financial viability of the project. The applicant may attach drawings of alternative, lower-impact
site layouts, and explain why these design options were not feasible. Also discuss how impacts
were minimized once the desired site plan was developed. If applicable, discuss construction
techniques to be followed during construction to reduce impacts.
The proposed project is desisrned to minimize impacts to jurisdictional waters as much as
practicable. The revetment mat and riprap will only be used to protect CPC's existing_pipeline
and to stabilize the stream bank that is significantly eroded.
VIII. Mitigation
DWQ - In accordance with 15A NCAC 2H .0500, mitigation may be required by the NC
Division of Water Quality for projects involving greater than or equal to one acre of impacts to
freshwater wetlands or greater than or equal to 150 linear feet of total impacts to perennial
streams.
Updated 1 I / 1 /2005
Page 9 of 12
USACE - In accordance with the Final Notice of Issuance and Modification of Nationwide
Permits, published in the Federal Register on January 15, 2002, mitigation will be required when
necessary to ensure that adverse effects to the aquatic environment are minimal. Factors
including size and type of proposed impact and function and relative value of the impacted
aquatic resource will be considered in determining acceptability of appropriate and practicable
mitigation as proposed. Examples of mitigation that may be appropriate and practicable include,
but are not limited to: reducing the size of the project; establishing and maintaining wetland
and/or upland vegetated buffers to protect open waters such as streams; and replacing losses of
aquatic resource functions and values by creating, restoring, enhancing, or preserving similar
functions and values, preferable in the same watershed.
If mitigation is required for this project, a copy of the mitigation plan must be attached in order
for USACE or DWQ to consider the application complete for processing. Any application
lacking a required mitigation plan or NCEEP concurrence shall be placed on hold as incomplete.
An applicant may also choose to review the current guidelines for stream restoration in DWQ's
Draft Technical Guide for Stream Work in North Carolina, available at
http://h2 0. enr.state.nc.us/ncwetlands/strmgide.html.
Provide a brief description of the proposed mitigation plan. The description should provide
as much information as possible, including, but not limited to: site location (attach directions
and/or map, if offsite), affected stream and river basin, type and amount (acreage/linear feet)
of mitigation proposed (restoration, enhancement, creation, or preservation), a plan view,
preservation mechanism (e.g., deed restrictions, conservation easement, etc.), and a
description of the current site conditions and proposed method of construction. Please attach
a separate sheet if more space is needed.
N/A
2. Mitigation may also be made by payment into the North Carolina Ecosystem Enhancement
Program (NCEEP). Please note it is the applicant's responsibility to contact the NCEEP at
(919) 715-0476 to determine availability, and written approval from the NCEEP indicating
that they are will to accept payment for the mitigation must be attached to this form. For
additional information regarding the application process for the NCEEP, check the NCEEP
website at http://h2o.enr.state.nc.us/wrp/index.htm. If use of the NCEEP is proposed, please
check the appropriate box on page five and provide the following information:
Amount of stream mitigation requested (linear feet):
Amount of buffer mitigation requested (square feet):
Amount of Riparian wetland mitigation requested (acres):
Amount ofNon-riparian wetland mitigation requested (acres):
Amount of Coastal wetland mitigation requested (acres):
Updated 11/1/2005
Page 10 of 12
IX. Environmental Documentation (required by DWQ)
1. Does the project involve an expenditure of public (federal/state/local) funds or the use of
public (federal/state) land? Yes ^ No
2. If yes, does the project require preparation of an environmental document pursuant to the
requirements of the National or North Carolina Environmental Policy Act (NEPA/SEPA)?
Note: If you are not sure whether a NEPA/SEPA document is required, call the SEPA
coordinator at (919) 733-5083 to review current thresholds for environmental documentation.
Yes ^ No ^
3. If yes, has the document review been finalized by the State Clearinghouse? If so, please
attach a copy of the NEPA or SEPA final approval letter. Yes ^ No ^
X. Proposed Impacts on Riparian and Watershed Buffers (required by DWQ)
It is the applicant's (or agent's) responsibility to determine, delineate and map all impacts to
required state and local buffers associated with the project. The applicant must also provide
justification for these impacts in Section VII above. All proposed impacts must be listed herein,
and must be clearly identifiable on the accompanying site plan. All buffers must be shown on a
map, whether or not impacts are proposed to the buffers. Correspondence from the DWQ
Regional Office may be included as appropriate. Photographs may also be included at the
applicant's discretion.
1. Will the project impact protected riparian buffers identified within 15A NCAC 2B .0233
(Meuse), 15A NCAC 2B .0259 (Tar-Pamlico), 15A NCAC 02B .0243 (Catawba) 15A NCAC
2B .0250 (Randleman Rules and Water Supply Buffer Requirements), or other (please
identify )? Yes ^ No
2. If "yes", identify the square feet and acreage of impact to each zone of the riparian buffers.
If buffer mitigation is required calculate the required amount of mitigation by applying the
buffer multipliers.
* Impact Required
Zone rte,,, ~rP f P*~ Multiplier ,,~,~,__,,__
1 ~ I 3 (2 for Catawba)
2 ~ 1.5
Total
* Zone 1 extends out 30 feet perpendicular from the top of the near bank of channel; Zone 2 extends an
additional 20 feet from the edge of Zone 1.
3. If buffer mitigation is required, please discuss what type of mitigation is proposed (i.e.,
Donation of Property, Riparian Buffer Restoration /Enhancement, or Payment into the
Riparian Buffer Restoration Fund). Please attach all appropriate information as identified
within 15A NCAC 2B .0242 or .0244, or .0260.
Updated 11/1/2005
Page 11 of 12
XI. Stormwater (required by DWQ)
Describe impervious acreage (existing and proposed) versus total acreage on the site. Discuss
stormwater controls proposed in order to protect surface waters and wetlands downstream from
the property. If percent impervious surface exceeds 20%, please provide calculations
demonstrating total proposed impervious level. The proiect will not result in im ep rvious
surfaces. BMP's will be incorporated as described under General Condition 9 of the attached
cover letter.
XII. Sewage Disposal (required by DWQ)
Clearly detail the ultimate treatment methods and disposition (non-discharge or discharge) of
wastewater generated from the proposed project, or available capacity of the subject facility.
XIII. Violations (required by DWQ)
Is this site in violation of DWQ Wetland Rules (15A NCAC 2H .0500) or any Buffer Rules?
Yes ^ No
Is this anafter-the-fact permit application? Yes ^ No
XIV. Cumulative Impacts (required by DWQ)
Will this project (based on past and reasonably anticipated future impacts) result in additional
development, which could impact nearby downstream water quality? Yes ^ No
If yes, please submit a qualitative or quantitative cumulative impact analysis in accordance with
the most recent North Carolina Division of Water Quality policy posted on our website at
http://h2o.enr.state.nc.us/ncwetlands. If no, please provide a short narrative description:
Upon completion of the protect the ~peline should be repaired and protected from future
damage. No other work will be needed.
XV. Other Circumstances (Optional):
It is the applicant's responsibility to submit the application sufficiently in advance of desired
construction dates to allow processing time for these permits. However, an applicant may
choose to list constraints associated with construction or sequencing that may impose limits on
work schedules (e.g., draw-down schedules for lakes, dates associated with Endangered and
Threatened Species, accessibility problems, or other issues outside of the applicant's control).
Updated 11/1/2005
Page 12 of 12
Applicant/Agent's Signature Date
(Agent's signature is valid only if an authorization letter from the applicant is provided.)
APPENDIX G
WILMINGTON DISTRICT PCN AUTHORIZATION LETTER
CD
Jeff W. Richards
Southeast District Environmental Manager
April 2, 2007
U.S. Army Corps of Engineers
Wilmington District, Raleigh Field Office
6508 Falls of the Neuse Road, Suite 120
Raleigh, North Carolina 27615
Division of Water Quality
401 Wetland Unit
1650 Mail Service Center
Raleigh, North Carolina 27699
Subject: Authorization Letter
To Whom It May Concern:
Colonial Pipeline Company
Telephone: (706) 891-6658
Colonial Pipeline Company (CPC) gives authorization to Wetland & Ecological Consultants (WEC) to
serve as our agent regarding North Carolina Division of Water Quality (DWQ)/U.S. Army Corps of
Engineers {USAGE) Pre-Construction Notification {PCN) Application Forms. Should you have any
questions or concerns please contact me at the letterhead address or telephone number.
Sincerely,
lw ~2~
Jeff Richards
Environmental Manager
Southeast District
391 Scruggs Ringgold, GA 30736
APPENDIX H
PHOTOGRAPHS
PCN NWP No. i8 Photos taken June 26, 200
Colonial Pipeline Company WEC Project No. o2-o4i9oi -Park Creek-Line 2
Photograph No. 1: View of where the pipeline is exposed within Park Creek (obscured by a
thin layer of sediment).
rYt ~ ~,i i f. ~ ~ 1 ,,
~~' ~yd~'{~ i Y - ~h, i > ~ ~ 1
~.
~ G- -;
~
~~
d'
~ ~~
~
r
C
~
~ x T ;h
,e.
~6lC~~ ...i.
}~z;
!,. a r,3 ~ ,4, ,~
.4:. q+ ak
~
~6
~ .~
..pper~ `~ r'
~
~~ C, r 'r
-~.,-.~
!`~ ~'
~
~~ ~;, ..,
~~ ~
s~
~
^
.
~
~~ 'SQ'L'' "~ a i ~ y~ ~
~~ ~
~~`
d ~;
-
~
--'
~
~ ~
j
~ `~ ~
Y
~~ ,
~
x ,,_
~,. ~
~
~
~
.
'.g*.'.. -g
a T
~.'
,
y~
R i ~
l
~ ~
.. ~ ref
~~aa~ ~ )
~
t.{~ i'S* x
X* ~
~
~
i
~y ~L
r~
~q 4~ ~
K :ta
4!`~ 'd~ ~~~~` v y
a
a
•
XY ~J
~~~. ~
-
~'^s
^ ~t.
w Ft
`r
~
t~ ,~ba ,~! ~~'
*
"
~
+'~'°
~ ° t~~~~.~
`d
r ~
k
,~,~..~
r'
"
t
~ y
t+-=
.,
'.g
_ ~
~j
`
~`~ w .. ~ ` ;.F ?~~ ~
t
i
4
~"
f r l
'
'
g
°
~
~ J ~ ~F j
~
~
~
~,
~
.~
r . ~ R
~ :
~„ =
i di
-~ ~
,
.
:'y
11
V
~
C
~
" , `
~
`, , g~
'
~
'
~
~~~
Li
~~~vw.€.~
c
„~ .
R~
H
,~ r,'~r~~. A I jy"-ry,F. mo'o' 1't.. 3'~ ~w~~!3G!r~~.~ ~' t ::~
~
~
~
~ ~4
~ ,,
.Lt ~t ~l
•.,~ i E ~ `...-.
~~~,,
r'(O+t~!~~~s~~"
1 .~` t'~ ~'..rS
''1F~y~ ~ ~ ? ~ ,A~ 'ti~i~`~~4 9 r`
> r ° '
$
~
1. ~~1~~ i ; ' ,
'• • ^~ 'q -~+~, ~ 4 ` b n~ ~ J.
~ ~ ~ ,'~, i,'. i ~',~' ~~ '~ air°ry1 ~~;~r s ~~,~~ ' ''''
` `.. t
Photograph No. 2: View of the reach of Park Creek downstream of the project area.