HomeMy WebLinkAboutWQ0042899_Application Attachment_20211115 (2)CHARLOTTE
WTER
November 10, 2021
Mrs. Kristin Jamison
Landworks Design Group
1230 West Morehead Street
Suite 304
Charlotte, NC 28208
SUBJECT: WATER AND SEWER FLOW ACCEPTANCE
BEATTIES FORD ROAD SITE
530 BEATTIES FORD ROAD, CHARLOTTE, NC 28216
CLTWATER TRACKING# 20211996
After an analysis of the sanitary sewer associated with the proposed design of project, 20211996,
BEATTIES FORD ROAD SITE, it was determined that there is sufficient capacity to accommodate
the proposed sewer flow of 2,660 gallons per day (14 units x 190 gpd/unit) at the connection
point(s) indicated on the submitted utility plan for transmission to the Irwin Creek Wastewater
Treatment Plant; NPDES permit number NC0024945, for treatment. This acceptance of flow is
based upon the existing capacity of the designated publicly owned treatments works.
Please see attached NCDEQ-FTSE form.
Charlotte Water (CLTWater) agrees to furnish water to the subject project. The water quality to the
subject project is regulated by the State Drinking Water Act Amendments of 1986 and The Water
Supply Management Plan, PWS ID # 0160010 on file with the Public Water Supply Section of
NCDEQ. However, CLTWater cannot guarantee a constant pressure or quality of flow.
The applicant should understand that due to the involvement of other agencies and continuing
growth of the water system, the ability to provide service for future projects cannot be guaranteed
nor reserved. Connection to the CLTWater system is accepted on a first come, first served basis.
The applicant should understand that this letter is not authorization to construct or extend private
water or sewer systems, as the appropriate local or State permits are required prior to construction.
If the appropriate authorization to construct permits are not obtained construction has not started
within two (2) years of issuance of this flow acceptance, and payment for any service connections
have not been received within two (2) years of issuance of this flow acceptance letter, this flow
acceptance approval shall be rescinded, and a new flow acceptance request must be made.
The CAP analysis performed determines available capacity within the existing public gravity sewer
system. The developer is responsible for any additional private or public sewer infrastructure
required to convey flow from the proposed development to the existing public gravity sewer.
If you have any questions, please do not hesitate to contact me at (704) 432-5801.
Sincerely,
wi.U,Qrpno--A .o-la'
Guillermo Anzola
Engineering Assistant
Charlotte Water 5100 Brookshire Blvd, Charlotte, NC 28216 charlottewater.org
Operated by the City of Charlotte