Sent:Thursday, November 07, 2013 7:57 AM
To:Thomas, John T JR SAW (John.T.Thomas.JR@usace.army.mil); Homewood, Sue
Subject:C4901A Bowers to Lake permit mod
Attachments:TempCrossing-Site9.pdf
John and Sue,
The Contractor on C-4901A/Bowers to Lake Rail Project is proposing a temporary crossing for access to the Hamby Creek
Bridge site. This crossing will be located on the north side of the tracks at the jurisdictional stream shown in the
attached drawing at station 7648+52-M1. The permitted plans show no work taking place at this location, but there is
work on the other side of the tracks at Permit Site #9. The Contractor proposes to install 1-48” pipe into the stream
using the standard temporary stream crossing detail. Attached is their narrative and drawings.
We’ll need an additional 35’ of temporary stream impacts in order to install the crossing.
Do you need a formal mod application or can we handle this via email for the USACE and an in-field mod for DWR?
Amy Euliss
NCDOT Division 9 Environmental Officer
375 Silas Creek Parkway
Winston Salem, NC 27127
336-747-7802 (work)