HomeMy WebLinkAbout20161220 Ver 2_I-5000 Update_20211101 Carpenter,Kristi From:Hood, Donna Sent:Monday, November 01, 2021 9:51 AM To:Chapman, Amy Cc:Steve Kichefski Subject:I-5000 Update Hi All, As an update on I-5000, I went by the site on September 17, 2021 prior to my medical leave in early October and found the job in what would be considered completed condition. There was no heavy equipment and the lay down yards were cleaned up. Guard rail had been installed where at the dead end Rankin Lake Road where the bridge was removed. Rankin Lake Road was supposed to be graded to "match natural overbank topography" per the original permit application, which was not done. The bridge was removed approximately 2 months ago and rip rap was installed for stabilization, but no grading was done on the east side of the receiving stream, simply rip rap stacked up and the road cut off. I would like to know your thoughts before proceeding with issuing the permit. Regards, Donna 1