HomeMy WebLinkAbout20211336 Ver 1_Staff Comments_20211104 Wanucha, Dave From:Homewood, Sue Sent:Thursday, October 28, 2021 3:26 PM To:Carrie Caviness; Fuemmeler, Amanda J CIV (US) Cc:Wanucha, Dave Subject:RE: \[External\] B-5979 Hunting Hills Bridge (Boone, NC) Hi Carrie, Dave Wanucha will continue to be the DWR rep for this project. Sue Homewood Division of Water Resources, Winston Salem Regional Office Department of Environmental Quality 336 776 9693 office 336 813 1863 mobile Sue.Homewood@ncdenr.gov 450 W. Hanes Mill Rd, Suite 300 Winston Salem NC 27105 From: Carrie Caviness <carrie.caviness.1@gmail.com> Sent: Thursday, October 28, 2021 3:00 PM To: Fuemmeler, Amanda J CIV (US) <amanda.jones@usace.army.mil>; Homewood, Sue <sue.homewood@ncdenr.gov> Subject: \[External\] B-5979 Hunting Hills Bridge (Boone, NC) CAUTION: External email. Do not click links or open attachments unless you verify. Send all suspicious email as an attachment to Report Spam. Good afternoon- You may have already been alerted by Lori Beckwith and/or Dave Wanaucha about this project coming your way. The Town of Boone is proposing to replace Bridge #346 on Hunting Hills Lane. They have been assisted throughout the planning, NEPA, and permitting process by DOT, but this is not a DOT project. Kevin Hining with Division 11 had me submit an epcn to them yesterday (as a ncdot project); but then they collectively decided this was incorrect since the TOB is the owner and in charge of the project. I've told Kevin that this project, in my opinion, may fall under a non-notifying situation, but we submitted anyway since there is the NLEB issue. Please confirm the NW/GC are correct and advise on if we are notifying/non-notifying. Maps are attached as well as pertinent correspondence. Project impacts: Trout watershed, South Fork New River mainstem Bridge to be replaced almost exactly in place in phases (closed loop neighborhood). 26lf of new permanent impact in the form of riprap bank stabilization adjacent to 25lf of existing (NW13, GC4134) 1 51lf of temporary construction impacts in the form of dewatering and causeway (NTE 50% of stream channel) (NW33, GC414) No work proposed during trout moratorium, although USFWS has rec'd taking out the few necessary trees before 04/01 although they are generally in the 25' buffer. T/E I did a tree and bridge survey a couple years ago. No evidence of roosting in the structure or riparian buffer. Not really any suitable trees in terms of bark or cavities. Surveyed for all other potential T/E species for the Natural Resources Technical Report that accompanies the approved Categorical Exclusion. And we had Lori Williams out to do a Hellbender survey this summer and they concluded no other survey was necessary. Also, scoping was performed for Historic Properties and Archeology via NCDOT. Documentation is attached. Please be in touch at your convenience. Thanks, Carrie Carrie Caviness, PhD Interface Environmental Consulting, LLC. 476 Hidden Pond Rd Boone, NC 28607 (919) 656-4543 2