FIELD SCOPING MEETING WORKSHEET
Design-Bid-Build Process
TIP No.: N/A
WBS No.: BP6.R017
Field Scoping Meeting Date: 10/27/2021
Division: 6
Location: Virtual with site visits prior to FSM
Route: SR 1130 (Norrington Rd)
County: Harnett
Project Description: Replace Bridge No. 54 over Big Gully on SR 1130
Tier: Sub-Regional
Funding: State
Municipality: N/A
Attendees
Name
Phone No.
Email
Division Project Development Engineer
Steve Kendall
910-364-0603
sdkendall@ncdot.gov
Div. Bridge Program Manager (outgoing)
Christy Huff
910-364-0682
chuff@ncdot.gov
Div. Bridge Program Manager (incoming)
Adam Britt
910-364-0696
atbritt@ncdot.gov
Asst Div. Bridge Program Manager
Jason Hatfield
910-364-0694
jrhatfield@ncdot.gov
Resident Engineer
Donavon Hunt
910-364-0608
dhunt3@ncdot.gov
Division Bridge Maintenance
Mike Fisher
910-364-0670
mdfisher@ncdot.gov
Division Environmental Officer
Greg Price
910-364-0603
gwprice2@ncdot.gov
Division Utility Coordinator
John Walters
910-639-7345
jcwalters@ncdot.gov
Simpson Engineers, Project Manager
David Simpson
dsimpson@simpsonengr.com
Simpson Engineers
Martha Register
mregister@simpsonengr.com
Simpson Engineers
Mark Averette
maverette@simpsonengr.com
Simpson Engineers
Sandra Stepney
sstepney@simpsonengr.com
Mott McDonald
Tim Jordan
Tim.Jordan@mottmac.com
VHB Engineering
Frank Fleming
ffleming@vhb.com
VHB Engineering
Brandon Barham
bbarham@vhb.com
Subsurface Utility Engineering (SAM)
Freddie Bunn
fbunn@sam.biz
Subsurface Utility Engineering (SAM)
Matthew Ward
Matthew.Ward@sam.biz
HDR, INC
Kenneth Bussey
Kenneth.Bussey@hdrinc.com
HDR, INC
Rzepka, Mike
Mike.Rzepka@hdrinc.com
Gary Jordan (USFWS), Travis Wilson (NCWRC) & Hannah Sprinkle (NCDENR-DWR) provided comments prior to the meeting.
Existing Features
Feature Bridged: Big Gully
Bridge Clear Deck Width: 27.6 (Ft.)
Approach Roadway width: 25 (Ft.) 5’ shoulders w/ 1’ paved
Bridge Length: 53 (Ft.)
Deck Width (Out To Out): 29.3 (Ft.)
Water Depth: 5 (Ft.)
Height Bed-To-Crown: 13 (Ft.)
Year Built: 1972
Posted: SV - 18
TTST - 26
Superstructure: 18” Prestressed Concrete Channel Beam
Substructure: EBs & IBs: PPC Caps with Timber piles
Pier Type: 1@30’-8”, 1@30’, 1@30’-8”
Temp. Shored:
Historic High Water (Elev. to the Exist. Structure): TBD
Status: Structurally Deficient
PRI:
DP: 0
SR: 44.50
School Bussing crossings per day:
Posted Speed Limit Vicinity: 55 mph
Detour
Off-Site
Stage Construction
New Alignment
On-site
Detour listed below is in conflict with BR-0082 (Harnett 56). The let date for Bridge 56 is 2/15/2023.
Description Of Detour Route: SR 1130 Norrington Rd to Clark Rd. W on Clark Rd to NC 27. SW on NC 27 to Nursery Rd. S on Nursery Rd to Darroch Rd. SE on Darroch Rd back to Norrington
Rd.
Approximate Length Of Detour? 10.2 miles (8.2 additional miles)
Improvements Needed To Road(s) On Detour?
Div. Traffic Eng. Recommend Off-site detour signing? Trailblazing with Street/Road names
Improvements Needed To Bridges On Detour? Replacement of Bridge 56, No other improvements needed.
Are future plans for upgrading this roadway either at or in the vicinity of this project?
Are Bridges On Detour Currently Programmed? Yes. Harnett 56
Are There EMS Or Business Access Issues?
Are There Any Railroad Crossings On Detour? No
Should Work Zone Pedestrian Access Be Maintained During Construction? Yes/No
Utilities
Overhead Utility Lines In Conflict
Cable Lines In Conflict
Based on the past history near this project site, what is the Estimated Time Required to complete Utility Adjustments? Months
Is There Any Future Utility Construction Anticipated In The Project Area: No
Environmental
Wetlands At Site: Yes
Comments:
Endangered Species In County: Cape Fear Shiner (no Habitat), Red-cockaded woodpecker (no habitat) & Rough-leafed loosestrife (habitat).
T&E species effect: American Alligator (habitat)
Trout Watershed: No
Natural Heritage Area: Yes
CAMA County: No
Primary Nursery Area: No
Moratoria: No
Which species:
Duration:
Permits discussion: NW3
Water Quality Classification: WS IV, Sw
303d: No
Coast Guard Permit? No
Drainage Basin: Cape Fear River
Riparian Buffer Rules: No
Is The Project Site In Or Near Any Of The Following:
National Forest: No
Wildlife Refuge: No
State, County, Or Local Park: No
Wild And Scenic River: No
Airport: No
Recreation or Power Generation: No
Water Supply Reservoir: No
Nutrient Sensitive Waters: No
Public Use Boat Ramp: No
Cemeteries: No
VAD/Farmland Protection: No
Game Lands: No
Known Or Potential Historic Properties In The Area: No
Architecture: No Survey
Archaeology: No survey
Is the Bridge Structure Itself, or any part thereof, considered Historic: No
Impacts to a Church, Community Center, Or Other Public Facility? No
Is this a Statewide Bicycle Route or a Local Non-Marked Bicycle Route: Yes/No
Comments:
Geotechnical
Are There Any Historical and/or Vibration Sensitive Structures Near By? No:
Are There Any Known Landfills and/or Geo-environmental Hazard Sites at/or Within Close Proximity To The Project Site? No
Are Any Impacts Anticipated To Natural Springs Or Artesian Wells? No
Possible Foundation Type: H-piles (18”)
End Bents: Interior Bents:
Hydraulics
FEMA Approval? Yes (MOA ) Limited Detail Study – maintain road grade
Is There Unusual Scour Potential? Yes
Is Protection Needed? standard end bent protection
Are Banks Stable? Yes
Is Protection Needed? standard end bent protection
Appreciable Amount Of Large Debris? Low
Placement Of Bents In The Water Be Allowed: Yes
Where: 5 ft min. offset from existing interior bent
Structure Type: Bridge
Superstructure Type: 21” cored slab
If girder; why? N/A
Length Of Structure: 53 ft
Min. Number Of Spans: 3
Span Arrangement: 17.667’, 18’ & 17.583’
Waive offset: No; use 5 ft offsets
EB Cap: 2’-6”
Skewed: 90
Add’l Comments:
Items To Be Discussed / Resolved At FSM By Attendees
Off-Site
Stage Construction
New Alignment
On-site
Environmental Document Prepared by: Simpson (Reviewed & Submitted by DEO)
Federal CE Checklist State Minimum Criteria Checklist prepared by TBD
AADT: 950 vpd (2019)
NHS: No
Tier: Sub-Regional
Func. Class: Minor Collector
Bridge Min. Clear Deck Width Recommended by Div.: 30’-10” ft CRW (Out to Out dimension 33 ft)
Roadway lane width: 11’ with 3’ shoulders
Extension of Paved shoulders:
Pave to face of guardrail and taper 8:1 to travel lane/paved shoulder? Yes
Min. Pavement Surface Course:
Existing Roadway: 23 (ft)
Pavement Marking: Thermo existing
Pavement Markers: Raised
Will Railroad Involvement Be Required: No
Method of Clearing: TBD
Truck Percentage: 6% per BIR
Reasonable Safe Speed per SIR: 55 mph
Liquidated damages: will be imposed after _ _ days of closure/construction. Amt: $ _ _ per day
CEI by? NCDOT/On-Call
R/W by? NCDOT/ PEF
R/W monuments? Pin & Cap
Salvageable materials: TBD – Keep Sheet Piles – Contact / Coordinate with Mike Fisher.
Removal of previous structure remnant abutments/piers: Yes- remove or break off any existing piles 1’ below the mud line.
Sequencing priority in construction? N/A
Let Date:
Comments:
Action Items: