From:Conchilla, Ryan
Sent:Wednesday, October 20, 2021 1:47 PM
To:King, Art C
Cc:Young, Joshua M; Chapman, Amy
Subject:FW: 20120142- US 74-Ellerbe Bypass
Art,
Thanks for the update. If Vecellio & Grogan, Inc has removed suspected sediment from the JS at Permit site 4, that is
OK. However, I would recommend that no further removal takes place without an approved plan.
Photo documentation with a description of the sediment removal activities already performed at Permit Site 4 should be
provided, estimating the quantity removed and the location selected for on-site stabilization.
Ryan Conchilla, PWS
Environmental Specialist II
401 and Buffer Transportation Permitting Branch (DOT Divisions 7+8)
Division of Water Resources, NC Department of Environmental Quality
Ryan.Conchilla@ncdenr.gov
From: King, Art C <acking@ncdot.gov>
Sent: Wednesday, October 20, 2021 1:26 PM
To: Conchilla, Ryan <ryan.conchilla@ncdenr.gov>; Young, Joshua M <jmyoung@ncdot.gov>
Cc: Chapman, Amy <amy.chapman@ncdenr.gov>
Subject: RE: 20120142- US 74-Ellerbe Bypass
Ryan,
In the response submitted to Ms. Chapman by the contractor, Vecellio & Grogan, Inc., they have indicated that they
have proceeded with the sediment removal at site 4. This is in direct conflict with the direction given in the email below
that you sent to Joshua Young. I’m not sure at who’s direction that V&G has proceeded but, I just wanted to know if
their actions constitutes a problem with the compliance of the NOV.
It is not uncommon that we would ask the contractor to proceed with the cleanup as soon as possible after photos and
documentation. This is usually tied to pending weather events and our desire to remove the sediment before additional
rain occurs and compounds the problem.
As always, we will defer to NCDENR direction in such matters.
Thanks,
Art C. King
Division Environmental Supervisor
NCDOT Highway Division 8
1
910 773 8015 office
acking@ncdot.gov
121 Dot Drive
Carthage, NC 28327
From: Conchilla, Ryan <ryan.conchilla@ncdenr.gov>
Sent: Wednesday, October 20, 2021 10:14 AM
To: Young, Joshua M <jmyoung@ncdot.gov>; King, Art C <acking@ncdot.gov>
Cc: Chapman, Amy <amy.chapman@ncdenr.gov>
Subject: 20120142- US 74-Ellerbe Bypass
Joshua,
This email is a follow up to our phone call yesterday afternoon regarding the Ellerbe Bypass.
The NOV issued on Friday 10-15-21 (attached) listed several items of non-compliance for the site and those items will
need to be completed before a follow up inspection can be scheduled.
As stated in the NOV, the first step is to submit a written plan to address each non-compliance issue.
Once the plan is reviewed and approved by DWR, site remediation activities recommended at Permit Site 4 and 6 can
begin.
Sediment removal activities should not begin on-site prior to approval.
Once the work is complete as approved, and documentation has been provided, a follow up inspection can be
scheduled.
Let me know what support I can provide at this time.
Thanks-
Ryan Conchilla, PWS
Environmental Specialist II
401 and Buffer Transportation Permitting Branch (DOT Divisions 7+8)
Division of Water Resources, NC Department of Environmental Quality
Ryan.Conchilla@ncdenr.gov