HomeMy WebLinkAboutNCC215870_Site Plan or Location Map_20211021BUNCOMBE COUNTY SPORTS PARK
EROSION AND SEDIMENT CONTROL SEQUENCE OF CONSTRUCTION:
EROSION CONTROL SEQUENCE - PHASE I:
1. A PRE -CONSTRUCTION MEETING IS MANDATORY BEFORE ANY WORK CAN BE DONE AT
SITE. CONTRACTOR SHALL NOTIFY OWNER, ENGINEER AND LOCAL EROSION CONTROL
INSPECTOR AT LEAST 1-WEEK PRIOR TO START OF CONSTRUCTION.
2. INSTALL CONSTRUCTION ENTRANCE(S) WITH WASH RACK(S) AND ESTABLISH
CONSTRUCTION ROUTES AND LAYDOWN AREAS IN ACCORDANCE WITH THE EROSION
CONTROL PLANS.
3. INSTALL PERIMETER SILT FENCE WITH WIRE FENCE (SF), INLET PROTECTIONS (IP),
SEDIMENT TRAPS (ST), TREE PROTECTION (TP) AND SAFETY FENCING (SAF) AS
ILLUSTRATED ON THE EROSION CONTROL PLANS.
4. SEDIMENT BASIN AND TRAP EMBANKMENTS SHALL BE PROVIDED WITH ADEQUATE
GROUNDCOVER IMMEDIATELY UPON CONSTRUCTION.
5. ONCE ALL EROSION CONTROLS ARE ESTABLISHED AND APPROVED BY THE SITE
INSPECTOR, BEGIN CLEARING AND STRIPING THE SITE AND TEMPORARILY STOCKPILING
IN DESIGNATED LOCATION ON EROSION CONTROL PLAN. PROVIDE SILT FENCE WITH
WIRE FENCE AROUND TEMPORARY STOCK PILE AND TEMPORARILY SEED STOCKPILE IF
LEFT OVER 14 DAYS.
6. MONITOR EROSION CONTROLS DAILY AND IMMEDIATELY AFTER RAIN EVENTS. SITE
INSPECTOR AND ENGINEER HAVE THE AUTHORITY TO ADD ADDITIONAL EROSION
CONTROL MEASURES AS NECESSARY TO CONTAIN RUN-OFF.
7. BEGIN BULK GRADING OPERATIONS TO ESTABLISH SUB -GRADE ELEVATIONS AND
PERFORM PLANARITY SURVEY TO BE ACCEPTED BY ENGINEER.
8. CONTRACTOR TO INSTALL REQUIRED STORM DRAINS, GEOTEXTILE FABRIC, STONE
AGGREGATE AND ALL OTHER PROPOSED UNDERGROUND UTILITIES.
9. INLET PROTECTION SHALL BE PLACED AROUND PROPOSED STORM INLETS AS THEY ARE
BEING CONSTRUCTED.
10. ANY INTERRUPTION IN WORK FOR 21 WORKING DAYS OR MORE MUST BE STABILIZED
WITH MULCH.
SYNTHETIC TURF FIELDS
EROSION AND SEDIMENT CONTROL PLAN
EROSION CONTROL SEQUENCE - PHASE II:
1. MAINTAIN, RELOCATE OR REPLACE PHASE I EROSION CONTROL MEASURES WITH ALL
PHASE II EROSION CONTROL MEASURES AS OUTLINED ON THE DRAWINGS IN -ORDER TO
STABILIZE SITE. PERMISSION TO REMOVE ANY CONTROLS MUST BE GRANTED BY THE
SITE INSPECTOR.
2. MONITOR EROSION CONTROLS DAILY AND IMMEDIATELY AFTER RAIN EVENTS. SITE
INSPECTOR AND ENGINEER HAVE THE AUTHORITY TO ADD ADDITIONAL EROSION
CONTROL MEASURES AS NECESSARY TO CONTAIN RUN-OFF.
3. CONTINUE THE INSTALLATION OF SITE UTILITIES, FENCING, CONCRETE, ASPHALT AND
OTHER SITE FEATURES.
4. STABILIZE ALL AREAS THAT HAVE BEEN CONSTRUCTED WITH GRADES APPROVED WITH
VEGETATION, STONE, RIP -RAP OR OTHER GROUND COVER AS SPECIFIED ON THE
DRAWINGS.
5. FILL SLOPES SHALL BE LEFT IN A ROUGHENED CONDITION TO REDUCE THE CHANCE OF
EROSION UNTIL THEY ARE COMPLETELY STABILIZED.
6. PERMANENTLY SEED AND / OR SOD AREAS AS DESIGNATED ON THE EROSION CONTROL
PLAN UPON COMPLETION OF GRADING ACTIVITIES.
7. CONTRACTOR TO INSTALL PARKING LOT IMPROVEMENTS WHILE SEDIMENT TRAP #2 IS
STILL IN COMPLETE WORKING ORDER. ALL PROPOSED STORM INLETS SHALL HAVE
INLET PROTECTION PLACED AROUND THEM IMMEDIATELY AFTER INSTALL TO PREVENT
SEDIMENT BUILD UP FROM RAINFALL EVENTS.
8. SEDIMENT TRAP #2 SHALL REMAIN IN WORKING ORDER UNTIL THE ENTIRE PARKING LOT
AND SURROUNDING GRADES HAVE BEEN COMPLETELY STABILIZED. UPON COMPLETE
STABILIZATION OF THE UPSTREAM DRAINAGE AREAS, CONTRACTOR DEWATER AND
REMOVE ANY SEDIMENT ACCUMULATION FROM SEDIMENT TRAP #2 AND BEGIN
CONVERSION TO PERMANENT BIO-RETENTION.
9. THE BIO-RETENTION CAN BE THEN INSTALLED BY FIRST INSTALLING THE OUTFALL, THEN
EXCAVATING TO THE REQUIRED DEPTHS OF THE BASIN AND PLACING SOIL MEDIA AS
REQUIRED. THE BIO-RETENTION SHALL BE STABILIZED WITH SOD IMMEDIATELY UPON
COMPLETION OF CONSTRUCTION.
10. THE PROPOSED STORM SEWER SYSTEM SHALL BE VISUALLY INSPECTED USING CCTV
OR OTHER METHOD PRIOR TO DIVERTING THE STORM SEWER TO THE STORMWATER
CONTROL MEASURE (BIO-RETENTION). STORM SEWER MAY NEED TO BE FLUSHED TO A
SEDIMENT TRAPPING DEVICE PRIOR FINAL OPERATION OF THE STORMWATER CONTROL
MEASURE.
11. ONCE THE ENTIRE DRAINAGE AREA TO THE SEDIMENT TRAP #1 HAS BEEN STABILIZED,
DEWATER TRAP AND REMOVE ANY SEDIMENT ACCUMULATION THEN FILL THE TRAP
USING STOCKPILED SOIL AND BRING TO FINISHED GRADE IN COMPACTED LIFTS.
SMOOTH THE TRAP SITE TO BLEND WITH SURROUNDING AREA, ENSURING THE TRAP
WILL NOT POND WATER, AND IMMEDIATELY STABILIZE.
12. EROSION CONTROLS SHALL REMAIN IN PLACE UNTIL SITE HAS BECOME STABILIZED.
ANY REMOVAL OF EROSION CONTROL MEASURES MUST BE APPROVED BY THE SITE
INSPECTOR PRIOR. DO NOT REMOVE TEMPORARY SEDIMENT TRAPS UNTIL THE
DRAINAGE AREA TO THE TRAP HAS BEEN PERMANENTLY STABILIZED.
13. CONTRACTOR TO MAINTAIN AND WATER GRASS SEEDED AREAS ON -SITE UNTIL
ACCEPTABLE STAND OF VEGETATION IS ACHIEVED.
STORMWATER MANAGEMENT SEQUENCE OF CONSTRUCTION:
STORMWATER MANAGEMENT TRENCH #1, 2 AND 3 CONSTRUCTION SEQUENCE:
1. CONTRACTOR TO NOTIFY ENGINEER ONCE ALL EROSION CONTROLS ARE IN PLACE AND PRIOR TO MASS EXCAVATION TO REVIEW STORMWATER
MANAGEMENT CONSTRUCTION SEQUENCE.
2. IDENTIFY AND AVOID EXCESSIVE COMPACTION FOR THE AREAS IDENTIFIED AS STORMWATER TRENCH #1, #2 AND #3 ON THE GRADING PLAN (SHEETS
C5.0-05.1). CONSTRUCTION VEHICLES SHALL AVOID TRAVELING ON THESE AREAS.
3. BEGIN BULK GRADING OPERATIONS WHILE ONLY EXCAVATING TO THE REQUIRED FIELD SUB -GRADE AND TOP OF TRENCH ELEVATION. THE FIELD SUBGRADE
SHALL BE LEFT IN A ROUGHENED CONDITION AND SHALL NOT BE COMPACTED. CONTRACTOR SHALL NOT EXCAVATE TRENCH UNTIL UP -GRADE AREAS HAVE
ACHIEVED REQUIRED ELEVATIONS AND HAVE BEEN PROPERLY STABILIZED WITH GEOTEXTILE FABRIC AND #57 STONE.
4. GRADING OF STORMWATER MANAGEMENT TRENCHES SHALL ONLY BE COMPLETED IN THE DRY.
5. ONCE UP -GRADE AREAS HAVE BEEN STABILIZED, FULL EXCAVATION OF THE TRENCH CAN OCCUR. CONTRACTOR TO SCARIFY BOTTOM OF TRENCH AND
PLACE MIN. 3" OF CLEAN WASHED SAND. PLACE AND SECURE GEOTEXTILE FABRIC TO THE SIDES OF TRENCH. DO NOT LINE BOTTOM OF TRENCH WITH
GEOTEXTILE FABRIC.
6. PROCEED WITH INSTALLATION OF ALL REQUIRED STORM DRAINAGE PIPING, OBSERVATION WELLS AND CONTROL STRUCTURES. STORMWATER MANAGEMENT
TRENCHES SHALL REMAIN OFFLINE UNTIL ALL UPSTREAM AREAS HAVE BEEN PROPERLY STABILIZED. THE ENTIRE TRENCH INCLUDING THE PIPING AND ALL
STRUCTURES SHALL BE AS -BUILT BY A PROFESSIONAL LICENSED SURVEYOR IN THE STATE OF NORTH CAROLINA.
7. NOTIFY ENGINEER FOR INSPECTION OF TRENCH AND PIPING WHILE PROVIDING AS -BUILT INFORMATION FOR REVIEW/APPROVAL. DO NOT BACKFILL TRENCH
WITH STONE UNTIL WRITTEN APPROVAL IS ISSUED BY DESIGN ENGINEER.
8. AFTER APPROVAL FROM ENGINEER, BACKFILL TRENCH WITH REQUIRED STONE. STORMWATER SYSTEM CAN BE CONNECTED TO OUTFALL AFTER TRENCH HAS
BEEN STABILIZED. CONTRACTOR TO MAINTAIN STABILIZATION FOR ENTIRE DRAINAGE AREA AFTER COMPLETION OF INSTALLATION.
9. PERFORM IN -SITU INFILTRATION TESTING ON THE FINISHED AGGREGATE BASE PRIOR TO INSTALLATION OF THE SYNTHETIC TURF SURFACING.
10. IF NECESSARY, DE -WATERING OF THE STORMWATER TRENCHES SHALL BE DIRECTED TO AN APPROVED EROSION CONTROL PRACTICE.
11. CONTRACTOR IS RESPONSIBLE FOR ALL EROSION AND SEDIMENT CONTROLS TO PROTECT PRACTICE AS NECESSARY DURING AND AFTER CONSTRUCTION OF
FACILITY UNTIL PROJECT REACHES FINAL COMPLETION.
BIO-RETENTION #1 CONSTRUCTION SEQUENCE:
1. CONTRACTOR TO NOTIFY ENGINEER ONCE ALL EROSION CONTROLS ARE IN PLACE AND PRIOR TO MASS EXCAVATION TO REVIEW STORMWATER MANAGEMENT
CONSTRUCTION SEQUENCE.
2. IDENTIFY AND AVOID EXCESSIVE COMPACTION FOR THE AREA IDENTIFIED AS BIO-RETENTION #1 ON THE GRADING PLAN (SHEET C5.1). CONSTRUCTION
VEHICLES SHALL BE LIMITED TO TRAVELING ON THIS AREA.
3. BEGIN BULK GRADING OPERATIONS TO ACHIEVE REQUIRED SUB -GRADE ELEVATIONS UP -GRADE OF THE BIO-RETENTION AREA. THE STORMWATER
MANAGEMENT TRENCH #3 SHALL BE INSTALLED AND STABILIZED PER THE CONSTRUCTION SEQUENCE ABOVE PRIOR TO THE INSTALLATION OF THE
BIO-RETENTION FACILITY.
4. ONCE THE ENTIRE UPSTREAM DRAINAGE AREA OF THE BIORETENTION HAS BEEN PROPERLY STABILIZED, CONTRACTOR TO NOTIFY SITE EROSION CONTROL
INSPECTOR FOR APPROVAL TO REMOVE SEDIMENT TRAP #2.
5. AFTER SEDIMENT TRAP #2 HAS BEEN PROPERLY REMOVED, CONTRACTOR TO BEGIN EXCAVATION OF BIO-RETENTION FACILITY. CONTRACTOR TO LEAVE
BOTTOM OF FACILITY IN A SCARIFIED CONDITION AND PLACE/SECURE GEOTEXTILE FABRIC TO THE SIDES OF THE TRENCH ONLY.
6. PROCEED WITH INSTALLATION OF ALL REQUIRED STORM DRAINAGE PIPING, OBSERVATION WELLS AND CONTROL STRUCTURES. STORMWATER PRACTICE
SHALL REMAIN OFFLINE UNTIL ALL UPSTREAM AREAS HAVE BEEN PROPERLY STABILIZED. THE ENTIRE TRENCH INCLUDING THE PIPING AND ALL STRUCTURES
SHALL BE AS -BUILT BY A PROFESSIONAL LICENSED SURVEYOR IN THE STATE OF NORTH CAROLINA.
7. NOTIFY ENGINEER FOR INSPECTION OF TRENCH AND PIPING WHILE PROVIDING AS -BUILT INFORMATION FOR REVIEW/APPROVAL. DO NOT BACKFILL TRENCH
WITH STONE AND SOIL MEDIA UNTIL WRITTEN APPROVAL IS ISSUED BY DESIGN ENGINEER.
8. AFTER THE BIO-RETENTION HAS BEEN INSPECTED AND APPROVED BY DESIGN ENGINEER, BACKFILL TRENCH WITH REQUIRED STONE AND APPROVED SOIL
MEDIA MIX. IMMEDIATELY STABILIZE SURROUNDING SIDE SLOPES AND DRAINAGE AREA WITH SOD.
9. PREPARE PLANTING SOD AS OUTLINED ON THE PLANTING PLAN LOCATED ON SHEET L1.0. ALL VEGETATION SHALL BE WATERED REGULARLY (TWICE WEEKLY)
UNTIL GRASS BECOME ESTABLISHED (-6 WEEKS).
10. CONTRACTOR IS RESPONSIBLE FOR ALL EROSION AND SEDIMENT CONTROLS TO PROTECT PRACTICE AS NECESSARY DURING AND AFTER CONSTRUCTION OF
FACILITY UPON PROJECT REACHES FINAL COMPLETION.
58 APAC DRIVE
ASHEVILLE, NORTH CAROLINA 28806
r,es C610
:^.eltan Rd
9y
Eneri:h p!
c
�4
spa`
m
�
r•
hb
�
ra
¢
s�
PRQ.
p•,5rvd�°
� wcr
4
� APpnh'�esld Rd S
.'
a
o1k,
�d
c
e
m
ae
n
� woc�
1z
"°
PROJECT SITE
s
ow
�'�a
iaFmk a` �
•a
8§,e Rid
�a
i1 Sand Wi Rd
.%aAi.
Enka 'Jt.tag. a
4y
S s
r�
4�
_ ��•
u
2018 Mic Ill oft Corporate 1, 418 HE%„ !•
IN
VICINITY MAP
�I ►�
��� ���/
THIS SITE IS LOCATED WITHIN THE
FRENCH BROAD RIVER BASIN
OWNER/DEVELOPER
ASHEVILLE BUNCOMBE YOUTH SOCCER ASSOCIATION
593 AZAELA ROAD EAST
ASHEVILLE, NC 28805
CONTACT: MIKE ROTTJAKOB
PHONE: (828) 299-7277 x 302
EMAIL: MIKER@ABYSA.ORG
SITE/CIVIL ENGINEER
LEADING DESIGN & DEVELOPMENT, LLC
13384 BERLIN TURNPIKE
LOVETTSVILLE, VIRGINIA 20182
CONTACT: MATT VETTER, P.E.
PHONE: (703) 999-9748
EMAIL: MATT.VETTER@LDDSPORTS. COM
DRAWING INDEX
DRAWING
COUNT
SHEET
NUMBER
SHEET NAME
CIVIL
1
C0.0
COVER SHEET
•
2
C1.0
OVERALL EXISTING CONDITIONS, SOILS MAP AND DEMOLITION PLAN
•
3
C1.1
OVERALL EXISTING CONDITIONS, SOILS MAP AND DEMOLITION PLAN
•
4
C1.2
GEOTECHNICAL INFILTRATION REPORT & BORING LOGS
•
5
C2.0
PHASE I - EROSION & SEDIMENT CONTROL PLAN
•
6
C2.1
PHASE I - EROSION & SEDIMENT CONTROL PLAN
•
7
C2.2
PHASE II - EROSION & SEDIMENT CONTROL PLAN
•
8
C2.3
PHASE II - EROSION & SEDIMENT CONTROL PLAN
•
9
C2.4
EROSION AND SEDIMENT CONTROL NOTES & DETAILS
•
10
C2.5
EROSION AND SEDIMENT CONTROL NOTES & DETAILS
•
11
C2.6
EROSION AND SEDIMENT CONTROL NOTES & DETAILS
•
12
C3.0
GENERAL NOTES & DETAILS
•
13
C3.1
GENERAL NOTES & DETAILS
•
14
C3.2
GENERAL NOTES & DETAILS
•
15
C3.3
GENERAL NOTES & DETAILS
•
16
C3.4
GENERAL NOTES & DETAILS
•
17
C3.5
GENERAL NOTES & DETAILS
•
18
C3.6
CONCRETE STEPS DETAIL
•
19
C3.7
CONCRETE STEPS DETAIL
•
20
C4.0
LAYOUT PLAN
•
21
C4.1
LAYOUT PLAN
•
22
C4.2
UTILITY PLAN
•
23
C4.3
UTILITY PLAN
•
24
C4.4
WATERLINE PROFILES
•
25
C4.5
WATERLINE PROFILES
•
26
C4.6
UTILITY DETAILS
•
27
C5.0
GRADING PLAN
•
28
C5.1
GRADING PLAN
•
29
C5.2
STORM SEWER COMPUTATIONS
•
30
C5.3
STORM SEWER PROFILES (PARKING LOT AND FIELD 8)
•
31
C5.4
STORM SEWER PROFILES (FIELDS 1, 2 & 8)
•
32
C6.0
PRE -DEVELOPED DRAINAGE AREA MAP
•
33
C6.1
PRE -DEVELOPED DRAINAGE TR-55 ANALYSIS
•
34
C6.2
POST DEVELOPED DRAINAGE AREA MAP
•
35
C6.3
POST DEVELOPED DRAINAGE TR-55 ANALYSIS
•
36
C6.4
POST DEVELOPED DRAINAGE TR-55 ANALYSIS
•
37
C6.5
STORMWATER MANAGEMENT TRENCH #1 CALCULATIONS
•
38
C6.6
STORMWATER MANAGEMENT TRENCH #2 CALCULATIONS
•
39
C6.7
STORMWATER MANAGEMENT TRENCH #3 CALCULATIONS
•
40
C6.8
STORMWATER MANAGEMENT CALCULATIONS - BIO-RETENTION #1
•
41
C6.9
STORMWATER CONTROL CROSS SECTIONS
•
42
L1.0
BIORETENTION PLANTING PLAN
•
NOTE:
ALL POTENTIAL JURISDICTIONAL SURFACE WATERS OF THE STATE OR WATERS
OF THE UNITED STATES IN THE PROJECT AREA ARE SHOWN ON THE PLANS.
STORMWATER MANAGEMENT PLAN.
THIS DEVELOPMENT IS BOUND BY AN APPROVED STORMWATER MANAGEMENT PLAN ON FILE WITH THE BUNCOMBE COUNTY
STORMWATER MANAGEMENT PROGRAM. ANY CHANGES IN LAND COVER, ADDITIONAL DEVELOPMENT OR REDEVELOPMENT THAT
WOULD INCREASE STORMWATER RUNOFF WILL REQUIRE SUBMITTAL ON AN AMENDED STORMWATER MANAGEMENT PLAN.
THIS DEVELOPMENT IS IN COMPLIANCE WITH THE BUNCOMBE COUNTY STORMWATER MANAGEMENT ORDINANCE.
BUNCOMBE COUNTY STORMWATER ADMINISTRATOR
DATE
SEAL:
CIARO���i.
a SEAL T=
047495 -
�NG I N����
HAW I lse
08/09/2021
THIS DOCUMENT, TOGETHER WITH THE
CONCEPTS AND DESIGNS PRESENTED
HEREIN, AS AN INSTRUMENT OF
SERVICE, IS INTENDED ONLY FOR THE
SPECIFIC PURPOSE AND CLIENT FOR
WHICH IT WAS PREPARED. REUSE OF
AND IMPROPER RELIANCE ON THIS
DOCUMENT WITHOUT WRITTEN
AUTHORIZATION AND ADAPTATION BY
LEADING DESIGN & DEVELOPMENT, LLC
IS NOT PERMITTED.
LDDSPORTS
\S. :jy)
LEADING DESIGN AND
DEVELOPMENT, LLC.
13384 BERLIN TURNPIKE
LOVETTSVILLE, VA 20180
TEL:703.999.9748
www.lddsports.com
CLIENT:
,rot+Trr �e
A��O r..�lAT�41N
w.
F
ISION
DESCRIPTION DATE
COUNTY COMMENTS 05/25/2021COUNTY COMMENTS 06/11/2021NCDEQ COMMENTS 08/09/2021
PROJECT NAME & ADDRESS:
BUNCOMBE COUNTY
SPORTS PARK -
SYNTH ETIC TURF
FIELDS
58 APAC DRIVE
ASHEVILLE, NC 28801
SITE INFORMATION:
FIRE DISTRICT: FEC
PARCEL PIN: 9617-75-0217-00000
SIZE: 44.52 ACRES
LAND USE CODE: COUNTY PARKS
ZONED: PUBLIC SERVICE DIST. (PS)
DEED REF: 2518 / 0086
PLAT BOOK & PLAT PAGE: 0076 / 0143
i
MISS UTILITY NOTE:
FOR LOCATION OF UTILITIES CALL NORTH
CAROLINA CALL CENTER AT 811 OR
1-800-632-4949 (48) HOURS IN ADVANCE OF
ANY WORK WITHIN THIS VICINITY
DRAWN BY I DESIGNED I CHECKED
KWG MSV RJT
PROJECT No: 2018-06
DATE: 08-09-2021
DRAWING TITLE:
COVER SHEET
SCALE: SEE PLAN SHEET
DRAWING No:
CO-0