Michael,
Thanks for reaching out. If the ePCN did not include the buffer selection during submission, that is OK.
If the project requires a buffer cert, we can issue along with the 401.
The design plans should depict the buffer impact locations in Zone 1 and Zone 2, and those impacts should also be
calculated. Let me know if you have additional questions.
Thanks-
Ryan Conchilla, PWS
Environmental Specialist II
401 and Buffer Transportation Permitting Branch (DOT Divisions 7+8)
Division of Water Resources, NC Department of Environmental Quality
Ryan.Conchilla@ncdenr.gov
From: Wanucha, Dave <dave.wanucha@ncdenr.gov>
Sent: Wednesday, October 13, 2021 8:11 AM
To: Turchy, Michael A <maturchy@ncdot.gov>
Cc: Conchilla, Ryan <ryan.conchilla@ncdenr.gov>
Subject: RE: U-5896/B-5353 Error on ePCN
Hey Michael,
I have forwarded this on to Ryan Conchilla who is now covering DOT’s Division 7 and 8 for our Branch.
Ryan,
This one if for you. Let me know if you have any questions.
Thanks.
Dave W.
Division of Water Resources
401 & Buffer Transportation Permitting
NCDOT Divisions 9 and 11
NC Department of Environmental Quality
336-403-5655 mobile
Dave.Wanucha@ncdenr.gov
NC DEQ Winston Salem Regional Office
450 West Hanes Mill Road, Suite 300
1
Winston Salem, NC 27106
From: Turchy, Michael A <maturchy@ncdot.gov>
Sent: Tuesday, October 12, 2021 9:52 PM
To: Wanucha, Dave <dave.wanucha@ncdenr.gov>
Subject: U-5896/B-5353 Error on ePCN
Hi Dave,
Just wanted to let you know we noted an error on the ePCN that was submitted for U-5896/B-5353.
The box below was NOT checked, indicating we are seeking Riparian Buffer Authorization approval.
However, we did indicate that there were buffer impacts, and all of the impacts were disclosed.
Is there anything I need to do on our end to correct this missed check box?
Thanks,
Michael
2
From: Turchy, Michael A
Sent: Monday, October 11, 2021 9:06 PM
To: David.E.Bailey2@usace.army.mil <david.e.bailey2@usace.army.mil>; Chapman, Amy <amy.chapman@ncdenr.gov>
Cc: Wanucha, Dave <dave.wanucha@ncdenr.gov>; Eason, Patty P <peason@ncdot.gov>; Parker, Jerry A
<japarker3@ncdot.gov>; Hemphill, Jeffrey L <jhemphill@ncdot.gov>; Key, Bryan C <bckey@ncdot.gov>; Harmon, Beth
<beth.harmon@ncdenr.gov>; Davenport, Ronald E <rondavenport@ncdot.gov>; Carpenter,Kristi
<kristilynn.carpenter@ncdenr.gov>; Chambers, Marla J <marla.chambers@ncwildlife.org>; Morgan, Stephen R
<smorgan@ncdot.gov>; Al-Dhalimy, Nadia <naaldhalimy@ncdot.gov>; Sanders, Byron <bsanders@ncdot.gov>; Hanks,
Brian <bhanks@ncdot.gov>; NCDOT Service Account - Roadway Design <roadwaydesign@ncdot.gov>; Fischer, Kevin
<wkfischer@ncdot.gov>; Staley, Mark K <mstaley@ncdot.gov>; Griffin, Randy W <rgriffin@ncdot.gov>; Dagnino, Carla S
<cdagnino@ncdot.gov>
Subject: U-5896/B-5353 Permit Application Distribution
The permit application for U-5896/B-5353 (the reconstruction of the interchange with US 29/70/Business 85
and South Main Street (SR 1009) in Guilford County) has been posted to the NCDOT Permit Application
Website.
The file named "U-5896 Guilford October 12 2021" can be viewed/downloaded at:
https://xfer.services.ncdot.gov/pdea/PermApps
or
Direct Link to Application: https://xfer.services.ncdot.gov/pdea/PermApps/U-
5896%20Guilford%20October%2012%202021.pdf
The electronic Pre-Construction Notification (ePCN) was submitted to the USACE, NCDWR, NCWRC and USFWS on