HomeMy WebLinkAboutSW4210704_O&M Agreement/Plan_20211013Operation & Maintenance Agreement
Project Name:
Project Location:
Dolcetto
Biesecker Road & West Center Street Extension
Cover Page
Maintenance records shall be kept on the following SCM(s). This maintenance record shall be kept in a log in a known set location,
Any deficient SCM elements noted in the inspection will be corrected, repaired, or replaced immediately. These deficiencies can
affect the integrity of structures, safety of the public, and the pollutant removal efficiency of the SCM(s).
The SCM(s) on this project include (check all that apply & co
Infiltration Basin
Quantity:
Infiltration Trench
Quantity:
Bioretention Cell
Quantity:
Wet Pond
Quantity:
Stormwater Wetland
Quantity:
Permeable Pavement
Quantity:
Sand Filter
Quantity:
Rainwater Harvesting
Quantity:
Green Roof
Quantity:
Level Spreader - Filter Strip
Quantity:
Proprietary System
Quantity:
Treatment Swale
Quantity:
Dry Pond
Quantity:
Disconnected Impervious Surface
Present:
User Defined SCM
Present:
Low Density
Present:
g O&M sheets will be added automatically):
Location(s):
Location(s):
Location(s):
Location(s):
Location(s):
Location(s):
Location(s):
Location(s): '
Location(s):
Location(s)i
Location(s):
Location(s):
Location(s): Western portion of site
Location(s):
Location(s):
Type -.,Curb outlets stem
I acknowledge and agree by my signature below that I am responsible for the performance of the maintenance procedures listed for
each SCM above, and attached O&M tables. I agree to notify NCDEQ of any problems with the system or prior to any changes to
the system or responsible party.
Signature:
Responsible Party:
Title & Organization:
Street address:
City, state, zip:
Phone number(s):
Email:
Justin R. Nifong
Director, Dolcetto Community Association, Inc.
3409 Union Grove Rd.
Winston-Salem NC 27127
919-348-2194
jrnifong@nkpatentlaw.com
Date:
I, >n a Notary Public for the State of p C(AA" `r
County of _ ��$ do hereby certify `thlat,� and
�j ��� t� 1 r) Ca
personally appeared before me this ! l l day of (� �Y 7�� 2 (
acknowledge the due execution of the Operations and Maintenance Agreement .
Witness my hand and official seal, Zaatg�--
U
DORIS CHARMAINE ACKSON
NOTARY PUBLi
Forsyth County
North Carolina
My Commission Expires Mar h 14, 2023
Sea!
My commission expires 3 _l " - 2-vZ 3
STORM-EZ 10111 /202 t
Version 1.5 O&M Agreement Page 1 of 1
Dry Pond Maintenance Requirements
Important operation and maintenance procedures:
- The drainage area will be managed to reduce the sediment load to the dry pond.
- Immediately after the dry pond is established, the vegetation will be watered twice weekly if needed until
the plants become established (commonly six weeks).
- After the initial fertilization to establish vegetation in the dry pond, fertilizer will not be applied to the dry
pond.
- The vegetation in and around the basin will be maintained at a height of approximately six inches.
- At least once annually, a dam safety expert will inspect the embankment. Any problems that are found
will be repaired immediately.
After the dry pond is established, it shall be inspected quarterly and within 24 hours after every storm event greater
than 1.0 inches (or 1.5 inches if in a Coastal County). Records of operation and maintenance shall be kept in a known
set location and shall be available upon request.
Inspection activities shall be performed as follows. Any problems that are found shall be repaired immediately.
SCM element:
Potential problem:
How to remediate the problem:
The entire SCM
Trash/debris is present.
Remove the trash/debris.
Areas of bare soil and/or
Regrade the soil if necessary to remove the gully, plant ground
The perimeter of the SCM
erosive gullies have
cover and water until it is established. Provide lime and a one -
formed.
time fertilizer application.
The inlet pipe is clogged (if
Unclog the pipe. Dispose of the sediment in a location where it
applicable).
will not cause impacts to streams or the SCM.
The inlet pipe is cracked or
The inlet device
otherwise damaged (if
Repair or replace the pipe.
applicable).
Regrade the swale if necessary and provide erosion control
Erosion is occurring in the
devices such as reinforced turf matting or riprap to avoid future
swale (if applicable).
problems with erosion.
Sediment has accumulated
Search for the source of the sediment and remedy the problem if
to a depth greater than the
possible. Remove the sediment and dispose of it in a location
original design depth for
where it will not cause impacts to streams or the SCM.
sediment storage.
The forebay
Provide additional erosion protection such as reinforced turf
Erosion has occurred.
matting or riprap if needed to prevent future erosion problems.
Remove the weeds, preferably by hand. If pesticide is used, wipe
Weeds are present.
it on the plants rather than spraying.
Sediment has accumulated
Search for the source of the sediment and remedy the problem if
to a depth greater than the
possible. Remove the sediment and dispose of it in a location
original design depth for
where it will not cause impacts to streams or the SCM.
sediment storage.
The main treatment area
Water is standing more
Check the outlet structure for clogging. If it is a design issue,
than 5 days after a storm
consult an appropriate professional.
event.
Weeds and noxious plants
are growing in the main
Remove the weeds, preferably by hand. If pesticide is used, wipe
treatment area.
it on the plants rather than spraying.
Dry Pond Maintenance Requirements (continued)
SCM element:
Potential problem:
How to remediate the problem:
Shrubs have started to
Remove shrubs immediately.
grow on the embankment.
Evidence of muskrat or
Consult a professional to remove muskrats or beavers and repair
beaver activity is present.
any holes or erosion.
A tree has started to grow
Consult a dam safety specialist to remove the tree.
The embankment
on the embankment.
An annual inspection by an
appropriate professional
Make all needed repairs immediately.
shows that the
embankment needs repair.
Clogging has occurred.
gg g
Clean out the outlet device. Dispose of the sediment in a location
where it will not cause impacts to streams or the SCM.
The outlet device
The outlet device is
Repair or replace the outlet device.
damaged
Erosion or other signs of
damage have occurred at
Repair the damage and improve the flow dissipation structure.
the outlet.
Discharges from the dry
The receiving water
pond are causing erosion
Contact the local NCDEQ Regional Office.
or sedimentation in the
receiving water.
Dry Detention Pond Design Summary
Dry Pond Diagram
DRY POND ID FOREBAY MAIN POND
1 Temporary Pool El: 729 Temporary Pool El: 729
Clean Out Depth: 5 Clean Out Depth: 5
Pretreatment No Sediment Storage El: 724 Sediment Storage El: 724
Has Veg. Filter No Bottom Elevation: 720 Bottom Elevation: 720
Low Density Maintenance Requirements
Important maintenance procedures:
The drainage area to the vegetated conveyance or vegetated receiving area will be carefully managed
to reduce the sediment load to the vegetated conveyance or vegetated receiving area.
After the initial fertilization to establish the grass in the vegetated conveyance or the vegetated receiving
area, fertilizer will not be applied to the vegetated receiving areas.
The vegetated conveyance or vegetated receiving area will be inspected quarterly. Records of operation and
maintenance will be kept in a known set location and will be available upon request.
Inspection activities shall be performed as follows. Any problems that are found shall be repaired immediately.
SCM element:
Potential problem:
How to remediate the problem:
Vegetation
Vegetation is too short or
too long.
Maintain grassed vegetation such that the swale or vegetated
area does not erode during the peak flow from the 10-year storm
Trash/debris is present.
Remove the trash/debris.
Areas of bare soil and/or
Regrade the soil if necessary to remove the gully, and then re -
Vegetated receiving
erosive gullies have
formed.
sod (or plant with other appropriate species) and water until
established. Provide lime and a one-time fertilizer application.
areas
Trees and/or other woody
Remove the trees and woody vegetation from the swale, regrade
vegetation are present in
the swale if necessary and re-establish grass as shown on the
the swale.
approved plans.
Trash/debris is present.
Remove the trash/debris.
Areas of bare soil and/or
Regrade the soil if necessary to remove the gully, and then re -
erosive gullies have
sod (or plant with other appropriate species) and water until
formed.
established. Provide lime and a one-time fertilizer application.
Sediment covers the grass
Remove sediment and dispose in an area that will not impact
Vegetated conveyances /
at the bottom of the swale.
streams or SCMs. Re -sod if necessary.
swales / roadside ditches
(other than curb outlet
swales)
The side slope is steeper
than the approved
configuration.
Regrade the slopes to the permitted configuration per the
approved plan and reestablish vegetation. If as -built or existing
conditions do not allow the slopes to be regraded, contact the
applicable permitting agency.
Determine the source of the problem: soils, hydrology, disease,
Grass is dead, diseased or
etc. Remedy the problem and replace plants. Provide a one -
dying.
time fertilizer application to establish the ground cover if
necessary.
Trees and/or other woody
Remove the trees and woody vegetation from the vegetated
vegetation are present in
conveyance, regrade the vegetated conveyance if necessary and
the vegetated conveyance.
re-establish grass as shown on the approved plans.
The longitudinal slope
Regrade to meet the permitted longitudinal slope as shown on
exceeds 5%.
the approved plans.
Curb outlet swales or
The swale profile does not
Regrade the swale to the approved profile as shown on the
vegetated areas
match the approved detail.
approved plans.
The length of the swale or
Extend the swale to achieve the 100-foot minimum length. If as -
vegetated area is less than
built or existing conditions do not allow the slopes to be regraded,
100 feet.
contact the applicable permitting agency.
Clogging has occurred.
Clean out the outlet device. Dispose of the sediment off -site.
The outlet device (if
applicable)
The outlet device is
Repair or replace the outlet device.
damaged
Erosion or other signs of
damage have occurred at
Repair the damage and improve the flow dissipation structure.
the outlet.
Discharges from the site
The receiving water
are causing erosion or
Contact the local NCDEQ Regional Office.
sedimentation in the
receiving water.