Loading...
HomeMy WebLinkAbout20210553 Ver 1_U-5896 CE_20211011U-5896 Categorical Exclusion January 2019 1 of 16 Type III Categorical Exclusion Action Classification Form STIP Project No.U-5896 WBS Element 44674.1.2 Federal Project No.N/A A. Project Description: The proposed project involves the reconstruction of the U.S. 29-70/ I-85 Business and S.R. 1009 (South Main Street) interchange in High Point, Guilford County (Appendix A, Figure 1). B. Description of Need and Purpose: The primary purposes of the proposed project include the following: · Improve mobility in the U.S. 29-70/ I-85 and S.R. 1009 (South Main Street) interchange by limiting driveway access along and in proximity to the interchange · Alleviate existing congestion at several of the existing unsignalized ramp terminals · Upgrade interchange design to meet current design standards The primary needs of the proposed project include the following: · Numerous driveways along and in proximity to the existing interchange ramps reduce mobility in the interchange, indicating a need to reduce the number of conflict points · Traffic congestion at several of the existing unsignalized ramp terminals indicates a need for improving operations at the ramp terminals · The ramps do not meet current AASHTO and NCDOT standards for the length of acceleration and deceleration lanes, nor safety standards for control of access at interchanges. C. Categorical Exclusion Action Classification: Type III D. Proposed Improvements: Two alternatives to reconstruct the U.S. 29-70/I-85 Business and S.R. 1009 (South Main Street) interchange were studied: · Alternative 1 would construct a diamond interchange at the existing U.S. 29-70/ I-85 Business and S.R. 1009 (South Main Street) interchange · Alternative 2 would construct a partial cloverleaf interchange at the existing U.S. 29-70/I-85 Business and S.R. 1009 (South Main Street) interchange STIP Project B-5353 involves replacement of Bridge No. 147 carrying U.S. 29-70 and I-85 Business over S.R. 1009 (South Main Street) in High Point. The bridge will be replaced on the existing alignment with an onsite detour to the south. A Type I B Categorical Exclusion for STIP Project B-5353 was approved by NCDOT and FHWA in August 2017. DocuSign Envelope ID: D10EFD0C-D71A-456B-8B0C-FF7F08F5E6DD U-5896 Categorical Exclusion January 2019 2 of 16 E. Special Project Information: Alternatives Discussion: The No-Build Alternative was considered but was eliminated because it offers no improvements to the traffic operations at the interchange. This alternative will not improve traffic flow nor reduce traffic congestion at the U.S. 29-70/I-85 Business and S.R. 1009 (South Main Street) interchange. Therefore, the No-Build Alternative was eliminated from further consideration. Two build alternatives to reconstruct the U.S. 29-70/I-85 Business and S.R. 1009 (South Main Street) interchange were studied. Alternative 1 proposed to construct a diamond interchange at the existing U.S. 29-70/ I-85 Business and S.R. 1009 (South Main Street) interchange, while Alternative 2 proposed to construct a partial cloverleaf interchange at this location. The proposed typical section for Alternative 1 along U.S. 29-70 and I-85 Business through the interchange includes two 12-foot travel lanes in each direction and a 10-foot median (Appendix A,Figure 2A). The proposed typical section for Alternative 2 along U.S. 29-70 and I-85 Business through the interchange includes three 12-foot travel lanes in each direction and a 10-foot median (Appendix A,Figure 2B). Under both alternatives, the proposed four-lane divided curb and gutter typical section along S.R. 1009 (South Main Street) includes two travel lanes in each direction, a 4-foot bicycle lane along the outside travel lanes, and a 23-foot raised median (Appendix A, Figure 2C). The proposed typical section along S.R. 1009 (South Main Street) would accommodate a sidewalk along the outside travel lane. However, the pedestrian accommodations are subject to change pending coordination with the City of High Point. Both alternatives would require restricting Greenview Terrace to right-in, right-out access and realigning Model Farm Road to the south. Alternatives 1 and 2 both provide adequate traffic capacity and operations along S.R. 1009 (South Main Street). Alternative 1 was selected as the preferred alternative after considering the public comments received at and following the public meeting. Under Alternative 1, SW Cloverleaf Place is anticipated to remain open as a service road to the Salvation Army Boys & Girls Club and the William Booth Apartments (Appendix A,Figure 3). Alternative 1 is also the preferred alternative from a hydraulic design perspective as it would have the least impact at the Richland Creek crossing. The diamond interchange would impact the Richland Creek Tributary crossing, located immediately west of the existing ramp terminals, which is undersized and is recommended to be resized. DocuSign Envelope ID: D10EFD0C-D71A-456B-8B0C-FF7F08F5E6DD U-5896 Categorical Exclusion January 2019 3 of 16 Estimated Cost: Alternative 1 (Preferred) Construction Cost $ 6,700,000 Right-of-Way Cost $ 13,813,700 Utility Cost $ 1,755,400 Total Project Cost $22,269,100 Note: Based on 2018 prices Estimated Traffic: Location 2018 (vpd) 2040 (vpd) Dual, TTST (%) U.S. 29-70 / I-85 Business North of South Main Street 37,600 42,700 5,4 South of South Main Street 33,800 38,000 5,4 S.R. 1009 (South Main Street) Kendall Avenue to Greenview Terrace 28,900 31,600 4,2 Greenview Terrace to U.S. 29-70/I-85 Bus.29,000 31,700 4,2 U.S. 29-70/I-85 Bus. To Model Farm Road 26,600 28,400 3,2 Model Farm Road to Moore Avenue 26,400 28,200 3,2 Note: vpd - denotes vehicles per day Source: Traffic Forecast, HNTB (March 2018) Accidents:NCDOT Traffic Engineering evaluated a recent five-year period (2013-2018) and found a total of 337 accidents occurring in the vicinity of the project. No fatal crashes occurred in the project area. Crashes are often the visible result of deficiencies in the capacity and safety characteristics of a transportation facility. Furthermore, they contribute to delays, congestion, and driver frustration, including more crashes. The most common crash patterns within the project study area included rear-end slow or stopped collisions and lane departure collisions. Rear-end collisions accounted for 24% (36) of the total crashes along S.R. 1009 (South Main Street); 17% (16) along I-85 Business/ U.S. 29-70; and 42% (37) along the interchange ramps. This pattern is typical of congested conditions on roadways with little or no control of access and is common in stop-and-go conditions. Lane departure collisions accounted for 56% of the total crashes along I-85 Business/ U.S. 29-70 and 32% along the southwest interchange ramp. This pattern is typical of tight merges and diverges, particularly on interchange ramps. Reported crashes in the project study area are listed below. DocuSign Envelope ID: D10EFD0C-D71A-456B-8B0C-FF7F08F5E6DD U-5896 Categorical Exclusion January 2019 4 of 16 Accident Type S.R. 1009 (S Main Street) I-85 Business / U.S. 29-70 Interchange Ramps Number % of Total Number % of Total Number % of Total Turning Movements 58 38%1 1%11 12% Rear-End 36 24%16 17%37 42% Run Off Road & Fixed Object 14 9%51 54%27 30% Angle 16 10%0 0%1 1% Sideswipe 22 14%16 17%10 11% Other 7 5%11 11%3 4% Total 153 100%95 100%89 100% Source: NCDOT Traffic Engineering, April 2018 A substantial number of the total accidents occurred near the ramp terminals with S.R. 1009 (South Main Street) and I-85 Business/ U.S. 29-70. These locations are listed below. The most accidents (63) occurred at the northwest and southwest ramp terminals with I-85 Business and U.S. 29-70. Location Number of Accidents NW & SW Ramps & I-85 Business 63 NW Ramp & S.R. 1009 44 SE Ramp & S.R. 1009 30 NE Ramp & S.R. 1009 22 Nathan Hunt Drive & S.R. 1009 18 Springfield Road & S.R. 1009 17 NE & SE Ramps & I-85 Business 16 Moore Avenue & S.R. 1009 10 SW Ramp & S.R. 1009 8 Source: NCDOT Traffic Engineering, April 2018 Cultural Resources: Historic Architecture- A review of the State Historic Preservation Office (HPO) data and relevant background reports was undertaken by NCDOT on March 28, 2018. Based on this review, several properties greater than 50 years of age were identified in the Area of Potential Effects (APE), including the First Pentecostal Holiness Church of High Point and Fellowship Hall. A copy of the correspondence is included in Appendix B. In June 2018, Dovetail Cultural Resource Group (Dovetail) conducted an evaluation to determine the National Register eligibility of the property. The report recommended that the First Pentecostal Holiness Church of High Point and Fellowship Hall is not eligible for listing in the National Register of Historic Places (NRHP). In a letter dated January 28, 2019, HPO concurred with the recommendation. A copy of this correspondence is included in Appendix B. DocuSign Envelope ID: D10EFD0C-D71A-456B-8B0C-FF7F08F5E6DD U-5896 Categorical Exclusion January 2019 5 of 16 Archaeology- A map review and site file search were conducted by NCDOT at the Office of State Archaeology on March 9, 2018. A comprehensive archaeological survey has never been conducted around this interchange location and no archaeological sites have been recorded within one mile of the proposed project. Based on the poor soil conditions and developed nature within the Study Area and the results of previously reviewed/ surveyed projects in the vicinity, there is a low probability for significant prehistoric and/or historic archaeological materials to be present. Therefore, it is believed that the current Study Area is unlikely to contain intact and significant archaeological resources. No archaeological survey is required for this project. A copy of this correspondence is included in Appendix B. Environmental Considerations:Water resources in the study area are part of the Cape Fear River basin (U.S. Geological Survey [USGS] Hydrologic Unit 03030003). Streamside riparian zones within the study area are protected under provisions of the Randleman Lake Water Supply Watershed Buffer Rules; therefore, regulatory riparian buffer rules will apply to this project. The North Carolina 2016 Final 303(d) list of impaired waters identifies Richland Creek within the study area as an impaired water due to Fish Community (Fair). Richland Creek and its tributaries carry a best usage classification of ‘WS-IV’ (Drinking, Culinary, Food Processing) by the N.C. Division of Water Resources. All potential jurisdictional streams in the study area have been designated as warm water streams for the purposes of stream mitigation. Guilford County is a participant in the National Flood Insurance Program, administered by the Federal Emergency Management Agency (FEMA). Based on the most current information available from the N.C. Floodplain Mapping Program (FMP), Richland Creek and Richland Creek Tributary 14 (SA) are in a designated flood hazard zone. This project involves construction activities on or adjacent to FEMA-regulated streams. Relocations:Potential business relocations for Alternatives 1 and 2 are presented below and included in Appendix C. These estimates are based upon preliminary engineering designs and are subject to change as the project progresses through the design phases. Residential Relocations Business Relocations Non-Profit Relocations Alternative 1 0 15 1 Alternative 2 2 13 1 Hazardous Materials: A field investigation to identify geoenvironmental sites of concern (underground storage tank sites [USTs], dry cleaning facilities, hazardous waste sites, regulated landfills, unregulated dumpsites) within the project study area was conducted by NCDOT on April 27, 2018. Sixteen sites of concern were identified within the project study area. The sites are listed below and shown in Appendix A,Figure 4. DocuSign Envelope ID: D10EFD0C-D71A-456B-8B0C-FF7F08F5E6DD U-5896 Categorical Exclusion January 2019 6 of 16 Facility ID Property Name Property Address Anticipated Risk -----Custom Drum Services Inc.2000 2010 2020 Jarrell Street Low 10624 Sunshine Tree and Fence Inc.145 Kenilworth Drive Low -----Henry James BBQ 2201 S. Main Street Low 17524 Highland Automotive 2122 S. Main Street Low -----Southside Mission 2113 S. Main Street Low 10470 Furniture City Gulf/Best Auto Used Tires/MGM Auto Sales, Inc.2107-2111 S. Main Street Low -----Former Flea Market 2100 2106 S. Main Street Low -----O’Reilly Auto Parts 2020 S. Main Street Low 21680 Sun Mart Co.2010 S. Main Street Low -----Christos Global Cathedral/ Happy Rentz 125 NW Cloverleaf Place Low 35680 Fast Fuels #6741 1921 South Main Street Low -----Woods Produce II 1908 S. Main Street Low -----High Point Nissan 1810 S. Main Street Low 38966 Sheetz 1813 S. Main Street Low 10757 Blair Park Mtnce 1901 Nathan Hunt Drive Low 6763 NC DMV 1300 Blue Ridge Road Low Source: NCDOT GeoEnvironmental Planning Report (May 2018) Design Information:A 60 mile per hour (mph) design speed is proposed for US 29-70/I-85 Business. A 40-mph design speed is proposed for S.R. 1009 (South Main Street). There are no design exceptions anticipated for this project. Pedestrian, Bicycle, and Greenway Accommodations: Pedestrian Sidewalks do not exist on the existing bridge; however, there are existing sidewalks on the northeast side of S.R. 1009 (South Main Street) under the bridge. The City of High Point requested that the bridge span be wide enough to accommodate sidewalks along both sides of South Main Street in the future. The City of High Point Comprehensive Pedestrian Plan (2017) indicates this segment of Main Street is a “highest priority” corridor for sidewalk on both sides of South Main Street. Bicycle This section of U.S. 29-70 and I-85 Business is not part of a designated bicycle route nor is it shown as needing bicycle improvements in the High Point Metropolitan Planning Organization (HPMPO) Comprehensive Transportation Plan (CTP). The City of High Point requested that the bridge span be wide enough to accommodate potential bike lanes on South Main Street in the future. Although current plans do not show South Main Street as a bicycle facility, the City of High Point anticipates it will be included in the bicycle master plan, currently in development. DocuSign Envelope ID: D10EFD0C-D71A-456B-8B0C-FF7F08F5E6DD U-5896 Categorical Exclusion January 2019 7 of 16 Greenway The High Point Bikeway, Greenway, and Trails Master Plan proposes a multi-use greenway path within the project study area, west of the existing interchange, along Richland Creek. The Piedmont Triad Regional Council developed a Southwest High Point Greenway Feasibility Study, which also identifies a proposed greenway along Richland Creek. Agency Coordination: NCDOT held a project scoping meeting on March 28, 2018 with resource agencies to begin the planning process for this project. NCDOT has coordinated with appropriate local, state, and federal agencies throughout this project study. Appropriate coordination will continue throughout the design and construction phases of the project. Comments from the agencies invited to the scoping meeting, listed below, were recorded as part of the scoping meeting and are included in the scoping meeting summary (Appendix D). Specific project-related comments or concerns were addressed within this environmental document. · U.S. Army Corps of Engineers (USACE) · U.S. Environmental Protection Agency (USEPA) · U.S. Fish and Wildlife Service (USFWS) · Federal Highway Administration (FHWA) · N.C. Division of Water Resources (NCDWR) · N.C. State Historic Preservation Office (HPO) · N.C. Wildlife Resources Commission (NCWRC) · High Point Metropolitan Planning Organization (HPMPO) Public Involvement:A landowner notification letter was sent to all property owners located within the project study area. No comments were received. A public meeting was held on July 31, 2018 at the High Point Theatre in High-Point, North Carolina. The purpose of the meeting was to provide the public the opportunity to review project maps, ask questions, provide comments, informally discuss the project with the project team, and involve the public in the project planning process. Participants at this meeting could view maps that depicted the proposed project, including the proposed use of land from the Blair Park Golf Course. A postcard announcing the public meeting was mailed to approximately 2,500 residents and business owners within the project study area prior to the public meeting. Prior to the public meeting, a meeting was held with local officials on the same day and at the same location as the public meeting. The meeting was held to provide information about the proposed project to the local officials and obtain input from them regarding the proposed project. Approximately 27 people attended the public meeting, including local officials. A total of seven comments were received at the public meeting or during the comment period following the meeting. Most of the comments expressed by citizens included a preference for Alternative 1 to provide the best traffic flow on Model Farm Road and Baltimore Street and to avoid impacts to the Blair Park Golf Course. Another property owner is concerned about DocuSign Envelope ID: D10EFD0C-D71A-456B-8B0C-FF7F08F5E6DD U-5896 Categorical Exclusion January 2019 8 of 16 access to their property off Model Farm Road, as well as the acquisition of a portion of their property included in the proposed roadway right of way. F. Project Impact Criteria Checklists: Type III Actions Yes No If the proposed improvement is identified as a Type III Class of Action answer all questions. · The Categorical Exclusion will require FHWA approval. · If any questions are marked “yes” then additional information will be required for those questions in Section G. 1 Does the project involve potential effects on species listed with the US Fish and Wildlife Service (USFWS) or National Marine Fisheries (NMFS)?☐☒ 2 Does the project result in impacts subject to the conditions of the Bald and Golden Eagle Protection Act (BGPA)?☐☒ 3 Does the project generate substantial controversy or public opposition, for any reason, following appropriate public involvement?☐☒ 4 Does the project cause disproportionately high and adverse impacts relative to low-income and/or minority populations?☐☒ 5 Does the project involve substantial residential or commercial displacements or right of way acquisition?☒☐ 6 Does the project include a determination under Section 4(f)?☒☐ 7 Is a project-level analysis for direct, indirect, or cumulative effects required based on the NCDOT community studies screening tool?☐☒ 8 Is a project level air quality Mobile Source Air Toxics (MSAT) analysis required?☐☒ 9 Is the project located in anadromous fish spawning waters?☐☒ 10 Does the project impact waters classified as Outstanding Resource Water (ORW), High Quality Water (HQW), Water Supply Watershed Critical Areas, 303(d) listed impaired water bodies, buffer rules, or Submerged Aquatic Vegetation (SAV)? ☒☐ 11 Does the project impact waters of the United States in any of the designated mountain trout streams?☐☒ 12 Does the project require a U.S. Army Corps of Engineers (USACE) Individual Section 404 Permit?☒☐ 13 Will the project require an easement from a Federal Energy Regulatory Commission (FERC) licensed facility?☐☒ 14 Does the project include Section 106 of the National Historic Preservation Act (NHPA) effects determination other than a no effect, including archaeological remains? Are there project commitments identified?☐☒ 15 Does the project involve hazardous materials and/or landfills?☒☐ 16 Does the project require work encroaching and adversely effecting a regulatory floodway or work affecting the base floodplain (100-year flood) elevations of a water course or lake, pursuant to Executive Order 11988 and 23 CFR 650 subpart A? ☒☐ DocuSign Envelope ID: D10EFD0C-D71A-456B-8B0C-FF7F08F5E6DD U-5896 Categorical Exclusion January 2019 9 of 16 Type III Actions Yes No 17 Is the project in a Coastal Area Management Act (CAMA) county and substantially affects the coastal zone and/or any Area of Environmental Concern (AEC)?☐☒ 18 Does the project require a U.S. Coast Guard (USCG) permit?☐☒ 19 Does the project involve construction activities in, across, or adjacent to a designated Wild and Scenic River present within the project area?☐☒ 20 Does the project involve Coastal Barrier Resources Act (CBRA) resources?☐☒ 21 Does the project impact federal lands (e.g. USFS, USFWS, etc.) or Tribal Lands?☐☒ 22 Does the project involve any changes in access control?☒☐ 23 Does the project have a permanent adverse effect on local traffic patterns or community cohesiveness?☐☒ 24 Will maintenance of traffic cause substantial disruption?☐☒ 25 Is the project inconsistent with the STIP or the Metropolitan Planning Organization’s (MPO’s) Transportation Improvement Program (TIP) (where applicable)?☐☒ 26 Does the project require the acquisition of lands under the protection of Section 6(f) of the Land and Water Conservation Act, the Federal Aid in Fish Restoration Act, the Federal Aid in Wildlife Restoration Act, Tennessee Valley Authority (TVA), Tribal Lands, or other unique areas or special lands that were acquired in fee or easement with public-use money and have deed restrictions or covenants on the property? ☐☒ 27 Does the project involve Federal Emergency Management Agency (FEMA) buyout properties under the Hazard Mitigation Grant Program (HMGP)?☐☒ 28 Is the project considered a Type I under the NCDOT's Noise Policy?☐☒ 29 Is there prime or important farmland soil impacted by this project as defined by the Farmland Protection Policy Act (FPPA)?☐☒ 30 Are there other issues that arose during the project development process that effected the project decision?☐☒ DocuSign Envelope ID: D10EFD0C-D71A-456B-8B0C-FF7F08F5E6DD U-5896 Categorical Exclusion January 2019 10 of 16 G. Additional Documentation as Required from Section F Response to Question 5:Based on the preliminary engineering designs, the proposed interchange reconstruction would involve 15 business and one non-profit displacements. Potential commercial relocation impacts are included in Appendix C. These estimates are based on preliminary engineering designs and are subject to change as the project progresses through the final design phase. Response to Question 6: Section 4(f) De Minimis Impact Background:In 2005, Congress amended Section 4(f) in its passage of the Safe, Accountable, Flexible, Efficient Transportation Equity Act: A Legacy for Users (SAFETEA-LU), specifically in Section 6009(a). An important change was the introduction of the de minimis procedures for processing minor impacts to Section 4(f) resources. Subsequent to the passage of SAFETEA-LU, the FHWA amended the Section 4(f) regulations and issued guidance for determining de minimis findings. Based on these regulations and guidance documents, the use of land from a publicly- owned park, recreation area, or wildlife and waterfowl refuge may be determined to be de minimis if: 1. The transportation use of the park, together with any impact avoidance, minimization, and mitigation or enhancement measures do not adversely affect the activities, features, and attributes that qualify the resource for protection under Section 4(f). 2. The official(s) with jurisdiction over the property are informed of FHWA’s intent to make the de minimis impact finding, based on their written concurrence that the project will not adversely affect the activities, features, and attributes that qualify the property for protection under Section 4(f). 3. The public has been afforded an opportunity to review and comment on the effects of the project on the proposed activities, features, and attributes of the Section 4(f) resource. According to the provisions set forth in Section 6009(a) of SAFETEA-LU, once the U.S. Department of Transportation determines that a transportation use of property from a Section 4(f) resource constitutes a de minimis impact, analysis of avoidance alternatives is not required and the Section 4(f) evaluation process is complete. Area of Concern - Blair Park Golf Course: Blair Park Golf Course, the oldest of High Point’s two municipally owned courses, was a gift to the City from descendants of Solomon Blair. Today’s modern 18-hole facility was originally constructed as a nine-hole course in 1931, with a second nine added in the mid-1940s. The proposed project will lie to the southeast of the golf course, which is located at 1901 S. Main Street in High Point adjacent to Greenview Terrace. Impacts to Blair Park Golf Course: The preferred alternative will require the use of approximately 0.16 acre of land from the extreme southern corner of the golf course (Appendix A,Figure 3). The land impacted is undeveloped and wooded, including DocuSign Envelope ID: D10EFD0C-D71A-456B-8B0C-FF7F08F5E6DD U-5896 Categorical Exclusion January 2019 11 of 16 approximately 0.11 acre which is within a Duke Energy Easement containing large transmission towers. Access to the golf course will be maintained at its current location. The proposed project would not impact the recreation activities of the golf course, including the greens or driving areas. After coordination with officials from the City of High Point Parks and Recreation Department and the NCDOT and review of the project’s impacts, the FHWA finds that the Proposed Reconstruction of the U.S. 29-70/I-85 Business and S.R. 1009 (South Main Street) Interchange will not adversely affect the activities, features, and attributes that qualify the golf course for protection under Section 4(f). This de minimis finding includes the Section 4(f) requirement that all possible planning to minimize harm to the resource have been achieved. The City of High Point was informed of FHWA’s determination that no adverse effects to the golf course will result from the project and of the agency’s expectation that the impact will constitute a de minimis use of land from a Section 4(f) resource. The City concurs that the Proposed Interchange Reconstruction will have no adverse effect on the Blair Park Golf Course (see letter dated September 24, 2018 in Appendix D). Response to Question 8:The purpose of this project is to improve mobility in the U.S. 29-70/I-85 Business and S.R. 1009 (South Main Street) interchange, alleviate existing congestion at several of the existing unsignalized ramp terminals, and upgrade the interchange design to meet current design standards by reconstructing the interchange and limiting driveway access along and in proximity to the interchange. This project has been determined to generate minimal air quality impacts for Clean Air Act criteria pollutants and has not been linked with any special mobile source air toxic (MSAT) concerns. As such, this project will not result in changes in traffic volumes, vehicle mix, basic project location, or any other factor that would cause a meaningful increase in MSAT impacts of the project from that of the no-build alternative. Response to Question 10: The North Carolina 2016 Final 303(d) list of impaired waters identifies Richland Creek within the study area as an impaired water due to Fish Community (Fair). Streamside riparian zones within the study area are protected under provisions of the Randleman Lake Water Supply Watershed Buffer Rules administered by N.C. Division of Water Resources. Response to Question 12:Five potential jurisdictional wetlands were identified within the study area (Appendix A,Figure 5). Wetland classification, quality rating data, and estimated impacts are presented below. All wetlands in the study area are within the Cape Fear River basin (USGS Hydrologic Unit 03030003). Additional information regarding the wetlands can be found in the Natural Resources Technical Report. DocuSign Envelope ID: D10EFD0C-D71A-456B-8B0C-FF7F08F5E6DD U-5896 Categorical Exclusion January 2019 12 of 16 Map ID NCWAM Classification Hydrologic Classification NCWAM Rating Impact* (acres) WA Floodplain Pool Riparian High 0.00 WB Bottomland Hardwood Forest Riparian Low 0.00 WC Floodplain Pool Riparian High 0.04 WD Headwater Forest Riparian Medium 0.00 WE Bottomland Hardwood Forest Riparian Low 0.03 TOTAL WETLAND IMPACT:0.07 Note: * Impacts based on anticipated construction limits plus an additional 25-feet Ten potential jurisdictional streams were identified within the study area (Appendix A, Figure 5). Stream classification, buffer applicability, and estimated impacts are presented below. All jurisdictional streams in the study area have been designated as warm water streams for the purposes of stream mitigation. Map ID Classification Compensatory Mitigation Req’d River Basin Buffer Impact* (linear feet) Richland Creek Perennial Yes Subject NW Ramp: 304 SR 1009 Crossing: 128 SA (UT 14)Perennial Yes Subject 54 SB-I Intermittent Undetermined Subject 0 SB-P Perennial Yes Subject 0 SC Perennial Yes Subject 5 SD Perennial Yes Subject 0 SE-I Intermittent Undetermined Subject 0 SE-P Perennial Yes Subject 0 SF Intermittent Undetermined Subject 33 SG Intermittent Undetermined Subject 0 Note: * Impacts based on anticipated construction limits plus an additional 25-feet In the vicinity of the northwest ramp terminal, 304 linear feet of parallel impacts to Richland Creek are anticipated. During final design, if the construction limits along U.S. 29-70/I-85 Business south of the interchange encroach upon Richland Creek, construction of a retaining wall along U.S. 29-70/I-85 Business in that area would be studied. With mitigation of the parallel impacts to Richland Creek near the northwest ramp terminal, the proposed project is estimated to impact 0.07 acres of wetlands and 220 linear feet of streams. Under the current Section 404 permitting requirements, it is anticipated the project would not require an Individual Permit (IP). In general, the U.S. Army Corps of Engineers issues an IP for projects that result in more than 0.5 acres of fill to Waters of the U.S. or more than 300 linear feet of stream impacts or if the project is considered by the agency to be a major action. Exact impacts, including required extent of fill placement, will be determined during final design. The amount of impacts to water resources and wetlands within the study area, described above, likely represents the maximum extent of potential fill in Waters of the United States. The selection of Alternative 1 avoided several hundred feet DocuSign Envelope ID: D10EFD0C-D71A-456B-8B0C-FF7F08F5E6DD U-5896 Categorical Exclusion January 2019 13 of 16 of impacts to Richland Creek incurred under Alternative 2 and minimized 4(f) impacts to the Blair Park Golf Course. The current design will be refined and NCDOT may further minimize the impacts as final design is completed. As indicated in the Preliminary Hydraulic Technical Report, the elevation of S.R. 1009 (South Main Street) cannot be raised above the existing elevation near the Richland Creek crossing at S.R. 1009 (South Main Street). This includes not just the centerline elevation, but the shoulder point, top of curb, or any proposed raised island elevations along S.R. 1009 (South Main Street) that must be at or below the maximum existing elevation along the roadway. South Main Street currently overtops during flood events and any roadway elevation increases will worsen the flooding issues upstream. As stated above, if the construction limits along U.S. 29-70/I-85 Business south of the interchange encroach upon Richland Creek, construction of a retaining wall along U.S. 29-70/I-85 Business in that area would be studied in final design. Response to Question 15:Sixteen possible UST facilities (all low-risk) were identified within the project study area. The current construction limits for Alternative 1 may impact several of these UST sites. If further design confirms an impact to UST’s, preliminary site assessments for soil and groundwater contamination will be performed prior to right-of-way acquisition. Response to Question 16:Guilford County is a participant in the National Flood Insurance Program, administered by the Federal Emergency Management Agency (FEMA). Based on the N.C. Floodplain Mapping Program (FMP), Richland Creek and Richland Creek Tributary 14 (SA) are in a designated flood hazard zone. This project involves construction activities on or adjacent to FEMA-regulated streams. Response to Question 22: The existing interchange includes driveway connections along the interchange ramps, which does not meet current safety standards for control of access at interchanges. The proposed interchange reconstruction will provide full control of access along S.R. 1009 (South Main Street) on either side of the proposed interchange (approximately Greenview Terrace to SW Cloverleaf Place), eliminating driveway access along the proposed ramps. Access to businesses would be relocated to surrounding roads or existing ramps that will be converted to access roads. DocuSign Envelope ID: D10EFD0C-D71A-456B-8B0C-FF7F08F5E6DD U-5896 Categorical Exclusion January 2019 14 of 16 H. Project Commitments Guilford County Proposed Reconstruction of the U.S. 29-70/ I-85 Business and S.R. 1009 (South Main Street) Interchange in High Point WBS No. 44674.1.2 STIP No. U-5896 Division 7 Construction, Resident Engineer’s Office / Right-of-Way Unit / Project Management Unit - Local Coordination NCDOT Division of Bicycle and Pedestrian Transportation and Work Zone Safety will be contacted prior to construction to evaluate the necessary level of pedestrian access accommodation during construction. Hi Point Transit System officials will be contacted prior to construction to evaluate the necessary level of bus rider access accommodation during construction. Guilford County Emergency Services and the City of High Point Fire Chief will be contacted prior to construction regarding potential construction-related delays so that the necessary temporary reassignments to primary response units can be made. NCDOT Community Studies will be contacted regarding a suitable level of coordination that should be undertaken as part of relocation assistance with the Southside Mission that serves the nearby homeless population. Project Management Unit - Roadway Design / Hydraulics Unit During final design, impacts to Richland Creek will be minimized. As indicated in the Preliminary Hydraulic Technical Report, the elevation of S.R. 1009 (South Main Street) cannot be raised above the existing elevation near the Richland Creek crossing at S.R. 1009 (South Main Street). This includes not just the centerline elevation, but the shoulder point, top of curb, or any proposed raised island elevations along S.R. 1009 (South Main Street) that must be at or below the maximum existing elevation along the roadway. South Main Street currently overtops during flood events and any roadway elevation increases will worsen the flooding issues upstream. During final design, if the construction limits along U.S. 29-70/I-85 Business south of the interchange encroach upon Richland Creek, construction of a retaining wall along U.S. 29-70/I- 85 Business in that area would be studied. Hydraulic Unit - FEMA Coordination The Hydraulics Unit will coordinate with the North Carolina Floodplain Mapping Program (FMP) to determine the status of the project with regard to applicability of NCDOT’s Memorandum of Agreement, or approval of a Conditional Letter of Map Revision (CLOMR) and subsequent final Letter of Map revision (LOMR). DocuSign Envelope ID: D10EFD0C-D71A-456B-8B0C-FF7F08F5E6DD U-5896 Categorical Exclusion January 2019 15 of 16 Hydraulics Unit / Division 7 Construction - FEMA - As-Built Construction Plans This project involves construction activities on or adjacent to FEMA-regulated stream(s). Therefore, the Division shall submit sealed as-built construction plans to the Hydraulics Unit upon completion of project construction, certifying that the drainage structure(s) and roadway embankment that are located within the 100-year floodplain were built as shown in the construction plans, both horizontally and vertically. GeoEnvironmental Section - Impacts to Underground Storage Tanks (UST’s) If further design indicates potential impact to UST’s, preliminary site assessments for soil and groundwater contamination will be performed prior to right of way purchase. DocuSign Envelope ID: D10EFD0C-D71A-456B-8B0C-FF7F08F5E6DD U-5896 Categorical Exclusion January 2019 16 of 16 I.Categorical Exclusion Approval STIP Project No.U-5896 WBS Element 44674.1.2 Federal Project No.N/A Prepared By: Date Aileen S. Mayhew, P.E. - Senior Project Manager Mott MacDonald Prepared For: Reviewed By: Date Bryan C. Key, P.E. - Senior Project Manager North Carolina Department of Transportation NCDOT certifies that the proposed action qualifies as a Type III Categorical Exclusion. Date Laura Sutton, P.E. - Project Management Team Lead North Carolina Department of Transportation FHWA Approval: Date John F. Sullivan, III, P.E. - Division Administrator Federal Highway Administration United States Department of Transportation Federal Highway Administration and North Carolina Department of Transportation Division of Highways DocuSign Envelope ID: D10EFD0C-D71A-456B-8B0C-FF7F08F5E6DD 1/31/2019 2/4/2019 2/5/2019 2/6/2019 APPENDIX A Figures DocuSign Envelope ID: D10EFD0C-D71A-456B-8B0C-FF7F08F5E6DD K endall A vE K e ar n s Av Au s ti n St ColtraneAvSchirra PlDane St C o p e la n d A vOgden St Fraley Rd E Springfield Rd E Moore AvKenilworthDr BellemeadeStPark St King St PlazaLnSCent enni al StKettering Rd ValleyRidgeDrElva PlBranch St Vista CirF i n c h A v F rid d le D rRo bbi nsSt P la y e r D rJay Pl F ult o n P l Model Farm RdJarr el l StNathanHuntDr GreenviewTerFrancis StBrevard Rd610 SR-4053 SurrettDrSR -1961WMarketCenterDrS R-3668 E ConnectorSR-1961EMarketCenterDrSR-1962SCollegeDrSR-1232Service Rd I-85SR-1009 S MainSt SR-1009 S MainSt Figure 1 GUILFORD RAN DOLPH DAVIDSO N Kern ersville HighPoint Wins ton -Sa le m Greensboro Lexing ton Thomas ville Study Area North Ca rolina Departm ent of TransportationProject Devel opm ent & Environmental An alysis Unit U-5896US 29-70/I-85 Bu sinessReconstruct Inte rcha nge at SR 10 09 (S outh Main S tree t)High Poin t, Guilford County Pro ject Location Ma p BUS85 BUS85 2970 2970 0 850 1,700425Feet DocuSign Envelope ID: D10EFD0C-D71A-456B-8B0C-FF7F08F5E6DD Figure 2 North Ca rolina Departm ent of TransportationProject Devel opm ent & Environmental An alysis Unit U-5896US 29-70/I-85 Bu sinessReconstruct Inte rcha nge at SR 10 09 (S outh Main S tree t)High Poin t, Guilford County Typical Sections FIGURE 2C S.R. 1009 (South Main Street) Roadway Typical Cross Section4-Lane Divided with 23' median Alternatives 1 & 2 FIGURE 2B U.S. 29-70/I-85 Business Roadway Typical Cross Section6 Lane Divided with 10' median Alternative 2 FIGURE 2A U.S. 29-70/I-85 Business Roadway Typical Cross Section4 Lane Divided with 10' median Alternative 1 DocuSign Envelope ID: D10EFD0C-D71A-456B-8B0C-FF7F08F5E6DD 12'18'10'6'6:130'4'4:1 MAX4'FDPS4'FDPSFOR CUTSHINGE POINT0.08GRADEPOINTFOR FILLSHINGE POINT(15' W/GR)12'6:14:1VAR.2:1 MAX(15' W/GR)12'RAMPS0.020.04CL0.020.02BARRIER18'-0"12'-0"12'-0"10'-0"94'-0" CLEAR ROADWAY12'-0"12'-0"18'-0"POINTGRADECL -L-PS4'2'PS4'11'-6"2:1 TO 4:1VAR.2:1 TO 4:12'GRADEPOINT11'-6"2'2:1 TO 4:12:1 TO 4:1VAR.10'4'12'12'12'12'4'10'CL0.020.020.020.02(14' W/ GR)(14' W/ GR)103'-Y- (S MAIN STREET)BIKEBIKEWALKSIDE5'6"WALKSIDE5'6"-Y- STA. 7+25.00 TO 27+30.00TO CHANGE PENDING COORDINATION WITH LOCAL MUNICIPALITIES.******PEDESTRIAN ACCOMMODATIONS SHOWN ARE PRELIMINARY AND SUBJECTVAR.VAR.0.020.02FOR CUTSHINGE POINT0.040.04?(15' W/ GR)12'FDPS10'15'6'10'12'12'10'12'12"(15' W/ GR)12'FDPS10'2'FDPS4'FDPS4'30'FOR FILLSHINGE POINT0.040.046"2:16:1BARRIER2:14:16:16:16"CL -L- (I 85 BUSINESS)GRADE TO THIS LINEPOINTGRADEAlternative 1Figure 3DocuSign Envelope ID: D10EFD0C-D71A-456B-8B0C-FF7F08F5E6DD kj kj kjkj kj kj kj kj kj kj kj kj kj kj kj kj 1000 feet from B-5353 Study AreaS urrett Dr K endall A vPlayer DrSElmStColtrane AvValleyRidge DrDane StOgden St F raley Rd C lo v e r d a l e S t E Moore Av Tyson StW S p r in g f i e ld R d Kenilworth Dr E Springfield Rd B a lti mo r eSt BellemeadeStW M o o r e A v King St ElvaPlPorter StBranch St Vista CirFixture Pl W K earns A vArdale DrD a v id s o n A v Martha Pl F u lt o n P lGreer AvOsborne PlSurrett CtRobbi ns St Finch Av Jay Pl Spring Brook CirModel Farm RdJarrel l StGreenview TerBrevard RdFrancis StFrancis StBrentwood StTimber StNathan Hunt DrRichlandCreekRichland Creek SR -4 053Su rr ett Dr S R -1 9 6 2 S C o lle g e D rSR-1962SCollegeDrSR-1961EMarketCenterDrSR-1231FinchAvSR-1961WMarketCenterDrSR-1009 S MainSt SR-1009 S MainStSR-1232Service Rd I-85Custom DrumServices Inc. Sunshin e Treeand Fence Inc.HenryJames BBQ High land Automotive Sou thside MissionFurniture City Gulf /Best Auto Used Tires/ MGM Au to Sales, Inc FormerFleaMarket O’ReillyAuto Parts Sun Mart Co. Christos GlobalCathedral FastFuels#6741 WoodsProduce II High P ointNissan She etz Bla ir ParkMaintenance NC DMV Nor th Carolina Department of TransportationProject Development & Environmental Analysis Unit U-5896US 29-70/I-85 BusinessReconstruct Interchange at S R 1009 (South Main Street)High Point, Guilford County GeoEnvironmental Sites §¨¦BUS85 §¨¦BUS85 £¤2970 £¤2970 0 530 1,060265Feet ± kj Hazardou s Sites Study Area Figure 4 DocuSign Envelope ID: D10EFD0C-D71A-456B-8B0C-FF7F08F5E6DD 5FigureReconstruct US 29/ US 70/ I-85 Business Interchange at SR 1009 (South Main St) STIP U-5896 Jurisdictiona l Feature s Map Guilford County, North Carolina SC SF SG SB SE SB SA RichlandCreek RichlandCreek SD WC WA WB WB WD WE NC Center for Geographic Information & Analysis Prepared For:Date: Checked By: Job No.: Drawn By: Scale:0 400200 Feet 18-011 NMS NDH June 2018 [ Potential Perennial Stream Potential Interm ittent Stream Culvert Potential Wetland U-5896 Project Study Area DocuSign Envelope ID: D10EFD0C-D71A-456B-8B0C-FF7F08F5E6DD APPENDIX B Cultural Resources DocuSign Envelope ID: D10EFD0C-D71A-456B-8B0C-FF7F08F5E6DD HISTORIC ARCHICTECTURE AND LANDSCAPES **SURVEY REQUIRED FORM** This form only pertains to Historic Architecture and Landscapes for this project. It is not valid for Archaeological Resources. You must consult separately with the Archaeology Group. PROJECT INFORMATION Project No: U-5896 County: Guilford WBS No.: 44674.1.1 Document Type: CE Fed. Aid No: NSP-0029(068) Funding: State Federal Federal Permit(s): Yes No Permit Type(s): Project Description: Reconstruct interchange at US 29/US 70/Business 85 abd SR 1009 (S. Main St) in High Point SUMMARY OF HISTORIC ARCHICTECTURE AND LANDSCAPES REVIEW Description of review activities, results, and conclusions: On March 28, 2018 a search of NC HPOWEB GIS Service map reveals several properties over 50 years of age in the Area of Potential Effect for this project. An architectural historian will need to conduct a site visit to determine if there are any properties that warrant a full National Register evaluation. SUPPORT DOCUMENTATION Map(s) Previous Survey Info. Photos Correspondence Design Plans FINDING BY NCDOT ARCHITECTURAL HISTORIAN Historic Architecture and Landscapes -- **SURVEY REQUIRED** Shelby Reap March 28, 2018 NCDOT Architectural Historian Date Anticipated Fieldwork Completion Date: September 28, 2018 18-03-0003 Project Tracking No. (Internal Use) Historic Architecture and Landscapes SURVEY REQUIRED form for Minor Transportation Projects as Qualified in the 2007 Programmatic Agreement. Page 1 of 2 DocuSign Envelope ID: D10EFD0C-D71A-456B-8B0C-FF7F08F5E6DD Historic Architecture and Landscapes SURVEY REQUIRED form for Minor Transportation Projects as Qualified in the 2007 Programmatic Agreement. Page 2 of 2 DocuSign Envelope ID: D10EFD0C-D71A-456B-8B0C-FF7F08F5E6DD DocuSign Envelope ID: D10EFD0C-D71A-456B-8B0C-FF7F08F5E6DD DocuSign Envelope ID: D10EFD0C-D71A-456B-8B0C-FF7F08F5E6DD Project Tracking No.: “No ARCHAEOLOGY SURVEY REQUIRED” form for Minor Transportation Projects as Qualified in the 2007/2015 Programmatic Agreement. 1 of 3 18-03-0003 NO ARCHAEOLOGICAL SURVEY REQUIRED FORM This form only pertains to ARCHAEOLOGICAL RESOURCES for this project. It is not valid for Historic Architecture and Landscapes. You must consult separately with the Historic Architecture and Landscapes Group. PROJECT INFORMATION Project No: U-5896 County: Guilford WBS No: 44674.1.1 Document: Federal CE F.A. No: NHP-0029(068) Funding: State Federal Federal Permit Required? Yes No Permit Type: USACE (not specified) Project Description: NCDOT’s Division 7 proposes to reconstruct the interchange at US 29/US 70/Business 85 with SR 1009 (South Main Street) in High Point, Guilford County. This project has been combined with the replacement of Bridge No. 147 on US 29/US 70/Business 85 over SR 1009 (South Main Street) (TIP# B-5353 [PA 15-09-0015]). The existing cross-section for Business 85 consists of a 4- lane divided facility whereas the existing cross-section for South Main Street consists of a 5-lane facility. Existing ROW along the interstate corridor is 150 feet whereas along South Main Street the existing ROW is about 100 feet. Project length is listed as about 1.00 mile. Since Preliminary Design Plans have not been developed yet, a Study Area for the project has been generated in order to facilitate environmental planning purposes at this stage. The Study Area will be centered around the interchange location and encompass about 151 acres, inclusive of the existing roadways and any modern development. SUMMARY OF CULTURAL RESOURCES REVIEW Brief description of review activities, results of review, and conclusions: This project was accepted on Thursday, March 8, 2018. A map review and site file search was conducted at the Office of State Archaeology (OSA) on Friday, March 9, 2018. A comprehensive archaeological survey has never been conducted around this particular interchange location, and no archaeological sites have been recorded within one (1) mile of the proposed project. Digital copies of HPO’s maps (High Point East and High Point West Quadrangles) as well as the HPOWEB GIS Service (http://gis.ncdcr.gov/hpoweb/) were last reviewed on Tuesday, March 13, 2018. There are no known historic architectural resources located within or adjacent to the Study Area for which intact archaeological deposits would be anticipated within the footprint of the proposed project. In addition, topographic maps, historic maps (NCMaps website), USDA soil survey maps, and aerial photographs were utilized and inspected to gauge environmental factors that may have contributed to historic or prehistoric settlement within the project limits, and to assess the level of modern, slope, agricultural, hydrological, and other erosive-type disturbances within and surrounding the Study Area. Brief Explanation of why the available information provides a reliable basis for reasonably predicting that there are no unidentified historic properties in the APE: This is a Federally funded project for which a Federal permit may be necessary. Permanent/temporary easements will not be necessary; however, the need for additional ROW was not conveyed as part of the submittal. The size and shape of the Study Area have been drawn in a way to capture any possible impacts beyond the NCDOT’s existing ROW along US 29/US 70/Business 85 and SR 1009 (South Main DocuSign Envelope ID: D10EFD0C-D71A-456B-8B0C-FF7F08F5E6DD Project Tracking No.: “No ARCHAEOLOGY SURVEY REQUIRED” form for Minor Transportation Projects as Qualified in the 2007/2015 Programmatic Agreement. 2 of 3 18-03-0003 Street). At this time, we are in compliance with NC GS 121-12a, since there are no eligible (i.e. National Register-listed) archaeological resources located within the project’s Study Area that would require our attention. Based on the description of the proposed project, activities may take place beyond the NCDOT’s existing ROW. From an environmental perspective, the Study Area falls within a highly developed interchange location along the interstate system in the Piedmont physiographic region of North Carolina. The Study Area consists of several soil types, all of which have been heavily disturbed by modern development or succumbed to erosion (Mecklenburg-Urban land complex, 2-10% slopes [MuB], Mecklenburg sandy clay loam, 2-6% slopes, eroded [MhB2], and Mecklenburg sandy clay loam, 6-10% slopes, eroded [MhC2]). Based on the poor soil conditions and the level of development, the preservation of intact archaeological resources would not be anticipated. The Office of State Archaeology (OSA) has reviewed various projects within the vicinity of the Study Area for environmental compliance, including residential development (ERs 94-0261, 99-8874, and 98-7811), transportation improvements (ERs 08- 2555, 95-7472, 12-2152, and 03-2905), commercial/industrial development (ERs 94-8091 and 06-1031), a recreational project (CH 06-2618), utility upgrades (ER 09-0680), and a cell tower (CT 02-0319). Stating a low probability for intact and significant archaeological sites to be present, OSA did not require an archaeological survey for any of these projects. Within five (5) miles of the Study Area, NCDOT’s Archaeology Group has reviewed at least nine (9) transportation-related projects for environmental compliance under the Programmatic Agreement (PA) with the State Historic Preservation Office (NC- HPO), two of which are located within one (1) mile of the proposed project. In fact, a portion of the current Study Area was reviewed and cleared as part of PA 15-09-0015. Only two (2) of these projects required an archaeological survey (TIP# U-5864 [PA 17-04-0031] and TIP# U-5770 [PA 16-08-0014]), based on the presence of intact pockets of undeveloped land and buffers adjacent to steams/rivers. As a result of those surveys, no archaeological sites were documented. Given the poor soil conditions and developed nature within the Study Area and the results of previously reviewed/ surveyed projects in the vicinity, there is a low probability for significant prehistoric and/or historic archaeological materials to be present. Therefore, it is believed that the current Study Area, as depicted, is unlikely to contain intact and significant archaeological resources. No archaeological survey is required for this project. If design plans change or are made available prior to construction, then additional consultation regarding archaeology will be required. At this time, no further archaeological work is recommended. If archaeological materials are uncovered during project activities, then such resources will be dealt with according to the procedures set forth for “unanticipated discoveries,” to include notification of NCDOT’s Archaeology Group. SUPPORT DOCUMENTATION See attached: Map(s) Previous Survey Info Photos Correspondence Photocopy of County Survey Notes Other: FINDING BY NCDOT ARCHAEOLOGIST NO ARCHAEOLOGY SURVEY REQUIRED March 13, 2018 NCDOT ARCHAEOLOGIST Date DocuSign Envelope ID: D10EFD0C-D71A-456B-8B0C-FF7F08F5E6DD Project Tracking No.: “No ARCHAEOLOGY SURVEY REQUIRED” form for Minor Transportation Projects as Qualified in the 2007/2015 Programmatic Agreement. 3 of 3 18-03-0003 Figure 1: High Point West, NC (USGS 1969 [PR87]) and High Point East, NC (USGS 1950 [PR82]). Study Area DocuSign Envelope ID: D10EFD0C-D71A-456B-8B0C-FF7F08F5E6DD Springfield Friends 3rd & 4th Meeting Houses Strickland Furniture Company - Sylvania Television Cabinet Plant R ic h la n d C re e k MuB Ur Ch MuB MuB MhC2 EuB MhB2 EuB MuB EnC McE2 EnB MhC2 McE2 MhC2 MhB2 S MAIN ST BUSINESS LOOP 85 SBUSINESS LOOP 85 NNATHAN HUNT DRKIN G ST S COLLEGE DRMODEL FARM RD JAY PL FRANCIS STK E N D A L L A V BRANCH ST JARRELL STE SPRINGFIELD RD KENIL W O RTH D R E M O OR E AV DANE STTYSON STS W C L O V E R L E A F P L ARDALE DRGREENVIEW TRW M O O R E A V B A L T I MOR E S T FIXTURE PL NW CLOVERLEAF PLW MARKET CENTER DRBREVARD RDMAIN ST ACCESS RAMPW S P R I N G F I E L D R DMAIN ST ACCESS RAMPSource: Esri, DigitalGlobe, GeoEye, Earthstar Geographics, CNES/Airbus DS, USDA,USGS, AEX, Getmapping, Aerogrid, IGN, IGP, swisstopo, and the GIS User Community TIP# U-5896 (PA 18-03-0003)Interchange Reco nstruction atUS 29/US 70/Business 85 withSR 1009 (South Main Street)Guilford County, NC U-5896_Study_Area 2015-16 M aster PA NCHPOpoints Local_District_Boundaries NCHPO_NR_SL_D OE_Boundaries Nam ed_streams HYARUT mapfldhazar GF Cem etery Streets Soils_All Guilford_2014Parcels ¹ 0 400 800 1,200 1,600200Feet DocuSign Envelope ID: D10EFD0C-D71A-456B-8B0C-FF7F08F5E6DD APPENDIX C Relocation Report DocuSign Envelope ID: D10EFD0C-D71A-456B-8B0C-FF7F08F5E6DD DocuSign Envelope ID: D10EFD0C-D71A-456B-8B0C-FF7F08F5E6DD DocuSign Envelope ID: D10EFD0C-D71A-456B-8B0C-FF7F08F5E6DD DocuSign Envelope ID: D10EFD0C-D71A-456B-8B0C-FF7F08F5E6DD DocuSign Envelope ID: D10EFD0C-D71A-456B-8B0C-FF7F08F5E6DD APPENDIX D Agency Coordination DocuSign Envelope ID: D10EFD0C-D71A-456B-8B0C-FF7F08F5E6DD STATE OF NORTH CAROLINA DEPARTMENT OF TRANSPORTATION ROY COOPER JAMES H.TROGDON,III GOVERNOR SECRETARY Mailing Address: NC DEPARTMENT OF TRANSPORTATION DIVISION OF HIGHWAYS 1582 MAIL SERVICE CENTER RALEIGH, NC 27699-1582 Telephone: (919) 707-6200 Customer Service: 1-877-368-4968 Website:www.ncdot.gov Location: 1000 BIRCH RIDGE DRIVE RALEIGH, NC 27610 April 13, 2018 Subject: Internal/External Scoping Meeting Summary Proposed reconstruction of the US 29-70/ I-85 Business and S.R. 1009 (South Main Street) interchange in High Point, Guilford County, WBS 44674.1.1, STIP U-5896 From:Verrol McLeary Project Development Engineer An Internal/External Scoping Meeting for the subject project was held on March 28, 2018 at 8:30 a.m. in the Structure Design Conference Room located in the Century Center. The following people were in attendance: Felix Davila FHWA felix.davila@dot.gov April Norton NCDWR april.norton@ncdenr.gov Verrol McLeary Project Management Unit vmcleary1@ncdot.gov Beverly Robinson Project Management Unit brobinson@ncdot.gov Laura Sutton Project Management Unit lsutton@ncdot.gov Carla Dagnino Environmental Analysis Unit cdagnino@ncdot.gov Jeff Hemphill Environmental Analysis Unit jhemphill@ncdot.gov Harrison Marshall PI & Comm. Studies hmarshall@ncdot.gov Bernie Bumgarner Utilities bbumgarner@ncdot.gov Nick Lineberger Congestion Management nclineberger@ncdot.gov Jamshid Hafshejani DMP Inc.jhafshejani@dmp.inc.com Tim Jordan Mott MacDonald tim.jordan@mottmac.com Jordan Woodard Mott MacDonald jordan.woodard@mottmac.com Aileen Mayhew Mott MacDonald aileen.mayhew@mottmac.com Rebecca Jackson Mott MacDonald rebecca.jackson@mottmac.com Alexandria Sentilles Mott MacDonald alexandria.sentilles@mottmac.com Via Skype Meeting: David Bailey USACE david.e.bailey2@usace.army.mil Greg Venable High Point Urban Area MPO greg.venable@highpointnc.gov Patty Eason Highway-Division 7 peason@ncdot.gov Mark Staley Roadside Environmental Unit mstaley@ncdot.gov David Langston Location & Surveys DLangston@ncdot.gov Rick Lakata STIP rjlakata@ncdot.gov Jeff Hess HNTB jhess@hntb.com Paige Hunter HNTB phunter@hntb.com The purpose of the meeting was to transfer pertinent information from NCDOT staff to the Project Development Engineer, as well as begin early coordination efforts by discussing the project with resource agencies and other stakeholders. The meeting began with introductions and a brief DocuSign Envelope ID: D10EFD0C-D71A-456B-8B0C-FF7F08F5E6DD U-5896 Internal/External Scoping Meeting Page | 2 April 13, 2018 description of the federally funded project. A slide presentation provided a review of the information included in the project data sheet. The presentation included a brief description of each of the potential alternative concepts, including: ·Alternative 1- Tight Diamond Interchange ·Alternative 2- Partial Cloverleaf Interchange ·Alternative 3- Partial Cloverleaf Interchange with Ramps and Loops in opposite (Northwest and Southeast) Quadrants During the presentation, HNTB discussed the results of the preliminary traffic capacity analysis: ·All three Alternatives exhibit acceptable traffic operations; Alternative 2 (Partial Cloverleaf Interchange) operates best in the preliminary analysis ·Under Alternatives 1 and 3, recommends allowing left turns into Greenview Terrace but restricting left turns out of Greenview Terrace ·Under Alternative 2, recommends limiting the turning movements on Greenview Terrace to right-in and right-out only ·All Alternatives include traffic signals at the ramp terminals on South Main Street The Meeting Agenda and Project Data Sheet (including maps) are attached. Information relayed to the project team by each group is provided below: USACE ·The existing wetland in the project area contains a stream within it, which runs towards Richland Creek ·Alternative 3 (Partial Cloverleaf Interchange with Ramps and Loops in Opposite Quadrants) may require a Section 404 Individual Permit and may have more stream impacts than the other alternatives FHWA ·Inquired about Section 4(f) resources in the project area ·Asked for additional information on the buildings being acquired during right of way acquisition ·Joe Geigle will be the point of contact for FHWA for this project NCDWR ·Randleman Lake Water Supply Watershed buffer rules apply ·Project is located within a Critical Supply Watershed ·Richland Creek is classified as Class WS-IV High Point Metropolitan Planning Organization (HPMPO) ·City of High Point Bicycle Master Plan is currently under development; there is no draft available for review nor any funding allocated for the plan ·The proposed greenway located south of the US 29-70/I-85 Business Interchange is part of a long-range greenway plan; currently there is no funding allocated for the greenway trail ·Stated a preference for Alternative 1 (Tight Diamond Interchange) Division 7 ·NCDOT is pursuing advanced ROW acquisition in interchange area ·Stated a preference for Alternative 1 (Tight Diamond Interchange) DocuSign Envelope ID: D10EFD0C-D71A-456B-8B0C-FF7F08F5E6DD U-5896 Internal/External Scoping Meeting Page | 3 April 13, 2018 Public Involvement & Community Studies ·Noted the presence of Environmental Justice (EJ) and Limited English Proficiency (LEP) populations in the area ·Stated that impacts to populations during construction should be considered and minimized ·The High Point Furniture Market (April and November) will generate a lot of traffic on South Main Street ·Consider avoiding construction during High Point Furniture Market timeframe to minimize impacts Natural Environment ·Stream located through the wetland in the northwest ramp quadrant is subject to the Randleman Lake Water Supply Watershed STIP ·Cost estimates for Right-of-Way have increased to $13.4 million due to new estimates for acquisition of properties within the proposed interchange Congestion Management ·No additional comments Roadside Environmental ·No additional comments Location and Surveys ·Surveys are being completed now and should be finished by the end of April 2018 Utilities ·Stated all three project alternatives would have high impacts on utilities ·Requested roadway plans with hydraulic design to better determine the utility conflicts OPEN DISCUSSION ·Alternative 3 was removed from consideration due to the potential for high impacts to Richland Creek and other environmental features in the northwest quadrant ·This project will not go through the merger process on the recommendation of the USACE and NCDWR ·STIP Project Nos. B-5353 and U-5896 will be let for construction together ·Proposed project may impact culvert carrying Richland Creek under S.R. 1009 (South Main Street) ·Design Considerations o Bicycle and pedestrian accommodations on South Main Street ·Project schedule is aggressive. The current schedule is below: o Categorical Exclusion: July 2018 o Right-of-Way:February 2019 o Construction:August 2020 DocuSign Envelope ID: D10EFD0C-D71A-456B-8B0C-FF7F08F5E6DD U-5896 Internal/External Scoping Meeting Page | 4 April 13, 2018 ACTION ITEMS/ NEXT STEPS ·PMU will forward Final Surveys to Mott MacDonald when transmitted ·A copy of the presentation was requested by Patty Eason, Division 7 o The presentation was uploaded to SharePoint under “Project Development: Reference Info and Links” on 04/04/18 If any meeting participants have any comments, questions, or edits to this memorandum, please contact Verrol McLeary at vmcleary1@ncdot.gov or 919.707.6044. After the meeting, NCDOT’s Structures Management Unit expressed a preference for Alternative 1, which would include a bridge with a smaller deck area than the other alternatives. cc: Meeting Attendees Attachments Agenda; Project Data Sheet (including maps) DocuSign Envelope ID: D10EFD0C-D71A-456B-8B0C-FF7F08F5E6DD DocuSign Envelope ID: D10EFD0C-D71A-456B-8B0C-FF7F08F5E6DD DocuSign Envelope ID: D10EFD0C-D71A-456B-8B0C-FF7F08F5E6DD DocuSign Envelope ID: D10EFD0C-D71A-456B-8B0C-FF7F08F5E6DD