13 -0634 MacGregor Downs Deck Addition - CONDITION
Attachments:
13 -0634 MacGregor Downs Deck Addition - CONDITION.docx
Cherri,
Condition attached. Sorry so slow — I was waiting for Hunter to send me the O &M. I plan to review Colleymore -Bey this
afternoon.
Hope you are doing well!
A
Annette M. Lucas, PE
Environmental Engineer
NCDENR I DEMLR I Stormwater Program
1612 Mail Service Center, Raleigh, NC 27699 -1612 (N111a.i.l.)
512 N. Salisbury St, Raleigh, NC 27604 1 9th Floor (i ocatior &, Parcels)
Phone: (919) 807 -6381 1 Fax: (919) 807 -6494 1 Email: l nnetLe.1 -u as'(rLL(- Uicnr.��t-ry
Website: http: / /portal.ncdenr.org /web /lr /stormwater
Before printing this email, please consider your budget and the environment.
E -mail correspondence to and from this address may be subject to the North Carolina Public Records Law and may be disclosed to
third parties.
13 -0634 MacGregor Downs Deck Addition - CONDITION
AML comments
September 5, 2013
Stormwater Management Plan (SMP) Approval by the Division
The Division approves the SMP consisting of one rain water harvesting system and all associated stormwater
conveyances, inlet and outlet structures, and the grading and drainage patterns depicted on plan sheets dated
August 7, 2013, which are incorporated by reference and are enforceable by the Division. The following
conditions also apply:
a) The maximum allowable drainage area for the approved rain water harvesting system shall be 2,000
square feet. Any changes to these maximum areas shall require the applicant to submit and receive
approval for a revised stormwater management plan by the Division.
b) The footprint of all stormwater management devices as well as an additional 10 -foot wide area on all
sides of the devices shall be located in either public rights -of -way, dedicated common areas or recorded
easement areas. The final plats for the project showing all such rights -of -way, common areas and
easement areas shall be in accordance with the approved plans.
c) The approved SMP shall be constructed and operational before any permanent building or other structure
is occupied at the site.
d) The SMP may not be modified without prior written authorization from the Division. A copy of the
approval letter and the modified SMP shall be submitted to the DWR Webscape Unit prior to the
commencement of the modifications.
e) Maintenance activities for the wet detention basins shall be performed in accordance with the notarized
O &M agreements signed by Mr. Russ Curtis (General Manager) on September 5, 2013. The O &M
agreement shall transfer with the sale of the land or transfer of ownership /responsibility for the BMP
facility. The Division shall be notified promptly of every transfer.
f) The applicant and /or authorized agent shall provide a completed Certificate of Completion form to the
Division within thirty (30) days of project completion (available at
http: / /porta 1. ncden r.org /web /wq /swp /ws /401 /certsa nd perm its /apply /forms).