HomeMy WebLinkAbout20140762 Ver 6_401 Request Attachment_20210923
STATE OF NORTH CAROLINA
DEPARTMENT OF TRANSPORTATION
ROY COOPER J. ERIC BOYETTE
GOVERNOR SECRETARY
Mailing Address:
NC DEPARTMENT OF TRANSPORTATION
ENVIRONMENTAL ANALYSIS UNIT
1598 MAIL SERVICE CENTER
RALEIGH NC 27699-1598
Telephone: (919) 707-6000
Fax: (919) 250-4224
Customer Service: 1-877-368-4968
Website: www.ncdot.gov
Location:
1000 BIRCH RIDGE DRIVE
RALEIGH NC 27610
September 24, 2021
U. S. Army Corps of Engineers
Regulatory Field Office
151 Patton Avenue, Room 208
Asheville, NC 28801-5006
ATTN: Ms. Lori Beckwith
NCDOT Coordinator
Subject: Request for Modification to the Section 404 Individual Permit and Section 401
Water Quality Certification for the proposed US 221 Widening from US 421 to US
221 Business/NC 88 in Jefferson in Watauga and Ashe Counties. Federal Aid Project
No. STP-0221(13), Division 11, TIP No. R-2915. Debit $570 from WBS 34518.1.FR6.
Reference: USACE Individual Permit Action ID SAW-2012-00882, January 7, 2015.
USACE Individual Permit Modification ID SAW-2012-00882, August 31, 2016
USACE Individual Permit Modification ID SAW-2012-00882, December 7, 2017
USACE Individual Permit Modification ID SAW-2012-00882, December 27, 2019
NCDWR Project No. 20140762, Certification No. 4001, September 8, 2014.
NCDWR Project No. 20140762_v2, Certification No. 4001, August 23, 2016
NCDWR Project No. 20140762_v3, Certification No. 4001, April 28, 2017
NCDWR Project No. 20140762, e-mail authorization, November 27, 2017
NCDWR Project No. 20140762_v4, Certification No. 4001, June 26, 2018
NCDWR Project No. 20140762_v5, Certification No. 4001, May 22, 2019
Dear Madam:
The purpose of this letter is to request a modification of the United Stated Army Corps of Engineers
(USACE) Section 404 Individual Permit and North Carolina Division of Water Resources Section 401
Certification for the above referenced project. This modification presents changes to one permit site
R-2915 Individual Permit Modification Application Page 2 of 9
in the E section (Site 8B) where installation of a new stormwater pipe will result in additional temporary
stream and wetland impacts as well as stream bank stabilization impacts to Little Buffalo Creek and
wetland W110 due to a temporary bore pit required for the stormwater pipe installation.
All changes in impacts due to the new stormwater pipe and the associated temporary bore pit at Site
8B in the E Section are in red italics. Please see the enclosed DWR Pre-Filing Meeting Request Form
and revised permit drawings for Section E.
Summary of R-2915 Jurisdictional Impacts:
Impacts for the overall (Sections A-E) project will include 3.05 acres of permanent wetland impacts,
0.28 acre of temporary wetland impacts, and 0.05 acre of hand clearing in wetlands. There will also be
9,147 linear feet of permanent stream impacts (7,485 linear feet of fill and 1,662 linear feet of bank
stabilization), and 0.42 acre of temporary stream impacts (see Tables 1 and 2 for a breakdown of impacts
by Section).
Table 1 – Summary of Wetland Impacts for R-2915
Section Design
Stage Wetland Impact Type
Wetland
Impact Area
(ac)
Wetland Impacts
Requiring
Mitigation (ac)*
R-2915A Final
Perm. Wetland Fill 0.48
0.57 Excavation in Wetlands 0.01
Mechanized Clearing in Wetlands 0.08
Hand Clearing in Wetlands 0.05†
R-2915B Final
Perm. Wetland Fill 0.32
0.43 Excavation in Wetlands 0.04
Mechanized Clearing in Wetlands 0.06
Temporary Fill in Wetlands 0.15
R-2915C Final
Perm. Wetland Fill 0.22
0.27 Excavation in Wetlands --
Mechanized Clearing in Wetlands 0.05
R-2915D Final
Perm. Wetland Fill 1.01
1.32 Excavation in Wetlands 0.01
Mechanized Clearing in Wetlands 0.30
R-2915E Final
Perm. Wetland Fill 0.28
0.46
Excavation in Wetlands 0.05
Mechanized Clearing in Wetlands 0.13
Temporary Fill in Wetlands 0.13
Total 3.05
†Additionally, 0.01 acre of temporary fill in wetlands will occur in the hand clearing areas for erosion control measures
* Values are based on rounding, due to calculating totals with actual numbers to the thousandths
R-2915 Individual Permit Modification Application Page 3 of 9
Table 2 – Summary of Stream Impacts for R-2915
Section Design
Stage Stream Impact Type Impact
Length (lf)
Temporary
Impacts (ac)
Stream Impacts
Requiring
Mitigation (lf)
R-2915A Final
Permanent Fill 1,119 --
1,119 Bank Stabilization 402 --
Temporary -- 0.05
R-2915B Final
Permanent Fill 493 --
493 Bank Stabilization 431 --
Temporary -- 0.15
R-2915C Final
Permanent Fill 2,339 --
2,339 Bank Stabilization 234 --
Temporary -- 0.09
R-2915D Final
Permanent Fill 2,627 --
2,627 Bank Stabilization 126 --
Temporary -- 0.05
R-2915E Final
Permanent Fill 907 --
907 Bank Stabilization 469 --
Temporary -- 0.08
Total 9,147 0.42 7,485
Tables 3 and 4 summarize the impacts to jurisdictional water resources for the final design of R-2915E.
Site numbers correspond with the permit (hydraulic) drawings included in this application. A
description of the changes to impact site 8B will follow the tables.
Table 3 – R-2915E Wetland Impacts*
Site Wetland
Number
Wetland
Size (ac)
Permanent Fill
in Wetlands (ac)
Temporary Fill
in Wetlands (ac)
Excavation
(ac)
Mechanized
Clearing (ac)
Impacts
Requiring
Mitigation (ac)
1 W96 0.30 -- -- -- <0.01 <0.01
2B W98 0.07 0.02 -- -- <0.01 0.03
3 W100a 0.39 <0.01 -- -- 0.03 0.03
4A W101** <0.01 <0.01 -- -- -- <0.01
4B W102 0.27 <0.01 -- -- 0.03 0.03
5 W102 0.27 <0.01 -- -- 0.01 0.01
6A W104 0.17 0.04 -- -- 0.02 0.07
8B W110 0.71 -- 0.13 -- -- 0
9A W109** 0.09 0.09 -- -- -- 0.09
10 W112 0.46 <0.01 -- -- <0.01 <0.01
13B W113** 0.01 0.01 -- -- -- 0.01
15A W115 0.03 0.01 -- -- <0.01 0.02
15B W117 0.22 -- -- -- 0.01 0.01
16 W116** 0.03 0.03 -- -- -- 0.03
21 W121 0.06 0.03 -- 0.01 <0.01 0.04
26A W123** 0.05 0.01 -- 0.04 -- 0.05
31 W125** 0.02 0.02 -- -- -- 0.02
Total Impacts 0.28 0.13 0.05 0.13 0.46***
* All wetlands impacted are riparian ** Total take of wetland
*** Values are based on rounding, due to calculating totals with actual numbers to the thousandths
R-2915 Individual Permit Modification Application Page 4 of 9
Table 4 – R-2915E Stream Impacts
Site
Stream Name &
Intermittent (I) or
Perennial (P) 1
Stream
Number Impact Type
Impact
Length
(linear feet)
Temporary
Impacts (acres)
(feet)
Mitigation
Requirement
(linear feet)
1 N/A (wetland) -- -- -- -- --
2A UT to Beaver
Creek (P) S128
Perm. Fill -- -- --
Bank Stabilization 14 -- --
Temp Fill -- <0.01 (17’) --
2B UT to Beaver
Creek (P) S128
Perm. Fill 57 -- USACE
Bank Stabilization -- -- --
Temp Fill -- <0.01 (21’) --
3 N/A (wetland) -- -- -- -- --
4A N/A (wetland) -- -- -- -- --
4B UT to Cole
Branch (I) S132
Perm. Fill -- -- --
Bank Stabilization 11 -- --
Temp Fill -- <0.01 (10’) --
5 N/A (wetland) -- -- -- -- --
6A UT to Cole
Branch (P) S134
Perm. Fill 52 -- USACE
Bank Stabilization -- -- --
Temp Fill -- <0.01 (10’) --
6B UT to Cole
Branch (P) S134
Perm. Fill -- -- --
Bank Stabilization 27 -- --
Temp. Fill -- <0.01 (10’) --
7 Little Buffalo
Creek (P) S135
Perm. Fill -- -- --
Bank Stabilization -- -- --
Temp. Fill -- <0.01 (24’) --
8A Little Buffalo
Creek (P) S135
Perm. Fill -- -- --
Bank Stabilization -- -- --
Temp Fill -- <0.01 (32’) --
8B Little Buffalo
Creek (P) S135
Perm. Fill -- -- --
Bank Stabilization 10 -- --
Temp Fill -- 0.01 (170’) --
9A UT to Little
Buffalo Creek (I) S136
Perm. Fill 33 -- USACE
Bank Stabilization 10 -- --
Temp Fill -- <0.01 (7’) --
9B Little Buffalo
Creek (P) S135
Perm. Fill -- -- --
Bank Stabilization -- -- --
Temp Fill -- <0.01 (19’) --
10 N/A (wetland) -- -- -- -- --
11A Little Buffalo
Creek (P) S135
Perm. Fill -- -- --
Bank Stabilization -- -- --
Temp Fill -- <0.01 (22’) --
11B UT to Little
Buffalo Creek (P) S139
Perm. Fill -- -- --
Bank Stabilization -- -- --
Temp Fill -- <0.01 (10’) --
R-2915 Individual Permit Modification Application Page 5 of 9
Table 4 Continued – R-2915E Stream Impacts
Site
Stream Name &
Intermittent (I) or
Perennial (P) 1
Stream
Number Impact Type
Impact
Length
(linear feet)
Temporary
Impacts (acres)
(feet)
Mitigation
Requirement
(linear feet)
11C UT to Little
Buffalo Creek (P) S140
Perm. Fill -- -- --
Bank Stabilization -- -- --
Temp Fill -- <0.01 (11’) --
11D Little Buffalo
Creek (P) S135
Perm. Fill 27 -- USACE
Bank Stabilization -- -- --
Temp Fill -- <0.01 (10’) --
12 Little Buffalo
Creek (P) S135
Perm. Fill -- -- --
Bank Stabilization 17 -- --
Temp Fill -- <0.01 (10’) --
13A UT to Little
Buffalo Creek (P) S141
Perm. Fill 31 -- USACE
Bank Stabilization 11 -- --
Temp Fill -- <0.01 (10’) --
13B UT to Little
Buffalo Creek (P) S141
Perm. Fill 60 -- USACE
Bank Stabilization -- -- --
Temp Fill -- -- --
13C UT to Little
Buffalo Creek (I) SA
Perm. Fill 25 -- USACE
Bank Stabilization -- -- --
Temp Fill -- <0.01 (23’) --
14A UT to Little
Buffalo Creek (P) S142
Perm. Fill 23 -- USACE
Bank Stabilization 23 -- --
Temp Fill -- <0.01 (10’) --
14B UT to Little
Buffalo Creek (P) S142
Perm. Fill 63 -- USACE
Bank Stabilization -- -- --
Temp Fill -- -- --
15A UT to Little
Buffalo Creek (P) S143
Perm. Fill 31 -- USACE
Bank Stabilization 15 -- --
Temp Fill -- <0.01 (10’) --
15B UT to Little
Buffalo Creek (P) S143
Perm. Fill -- -- --
Bank Stabilization -- -- --
Temp Fill -- <0.01 (23’) --
16 N/A (wetland) -- -- -- -- --
17A UT to Little
Buffalo Creek (P) S144
Perm. Fill 115 -- USACE
Bank Stabilization -- -- --
Temp Fill -- -- --
17B UT to Little
Buffalo Creek (I) SB
Perm. Fill 146 -- USACE
Bank Stabilization -- -- --
Temp Fill -- -- --
18 UT to Little
Buffalo Creek (P) S145
Perm. Fill 39 -- USACE
Bank Stabilization -- -- --
Temp Fill -- <0.01 (12’) --
19 UT to Naked
Creek (P) S147
Perm. Fill 22 -- USACE
Bank Stabilization 8 -- --
Temp Fill -- <0.01 (10’) --
R-2915 Individual Permit Modification Application Page 6 of 9
Table 4 Continued – R-2915E Stream Impacts
Site
Stream Name &
Intermittent (I) or
Perennial (P) 1
Stream
Number Impact Type
Impact
Length
(linear feet)
Temporary
Impacts (acres)
(feet)
Mitigation
Requirement
(linear feet)
20 UT to Naked
Creek (P) S146
Perm. Fill -- -- --
Bank Stabilization -- -- --
Temp Fill -- <0.01 (25’) --
21 N/A (wetland) -- -- -- -- --
22A UT to Naked
Creek (P) S148
Perm. Fill -- -- --
Bank Stabilization -- -- --
Temp Fill -- <0.01 (22’) --
22B UT to Naked
Creek (P) S148
Perm. Fill 61 -- USACE
Bank Stabilization 31 -- --
Temp Fill -- <0.01 (10’) --
23 UT to Naked
Creek (P) S155
Perm. Fill 55 -- USACE
Bank Stabilization -- -- --
Temp Fill -- -- --
24A UT to Naked
Creek (P) S156
Perm. Fill 30 -- USACE
Bank Stabilization -- -- --
Temp Fill -- <0.01 (22’) --
24B UT to Naked
Creek (P) S156
Perm. Fill -- -- --
Bank Stabilization 18 -- --
Temp Fill -- -- --
24C Naked Creek (P) S151
Perm. Fill -- -- --
Bank Stabilization 20 -- --
Temp Fill -- <0.01 (20’) --
25A UT to Naked
Creek (P) S157
Perm. Fill 13 -- USACE
Bank Stabilization -- -- --
Temp Fill -- <0.01 (12’) --
25B Naked Creek (P) S151
Perm. Fill -- -- --
Bank Stabilization 17 -- --
Temp Fill -- <0.01 (20’) --
26A UT to Naked
Creek (P) S158
Perm. Fill 19 -- USACE
Bank Stabilization -- -- --
Temp Fill -- <0.01 (8’) --
26B UT to Naked
Creek (P) S158
Perm. Fill -- -- --
Bank Stabilization 8 -- --
Temp Fill -- -- --
26C Naked Creek (P) S151
Perm. Fill -- -- --
Bank Stabilization 32 -- --
Temp Fill -- <0.01 (20’) --
27A UT to Naked
Creek (P) S159
Perm. Fill -- -- --
Bank Stabilization 15 -- --
Temp Fill -- -- --
27B Naked Creek (P) S151
Perm. Fill -- -- --
Bank Stabilization 18 -- --
Temp Fill -- <0.01 (30’) --
28A Naked Creek (P) S151
Perm. Fill -- -- --
Bank Stabilization 88 -- --
Temp Fill -- <0.01 (10’) --
R-2915 Individual Permit Modification Application Page 7 of 9
Table 4 Continued – R-2915E Stream Impacts
Site
Stream Name &
Intermittent (I) or
Perennial (P) 1
Stream
Number Impact Type
Impact
Length
(linear feet)
Temporary
Impacts (acres)
(feet)
Mitigation
Requirement
(linear feet)
28B Naked Creek (P) S151
Perm. Fill -- -- --
Bank Stabilization 59 -- --
Temp Fill -- <0.01 (10’) --
29 UT to Naked
Creek (P) S163
Perm. Fill 5 -- USACE
Bank Stabilization -- -- --
Temp Fill -- <0.01 (15’) --
30 Naked Creek (P) S151
Perm. Fill -- -- --
Bank Stabilization 17 -- --
Temp Fill -- <0.01 (21’) --
31 N/A (wetland) -- -- -- -- --
Total Temporary Impacts: -- 0.082 (726’) --
Total Perm. Impacts (Perm. Fill + Bank Stabilization): 1,376 -- --
Permanent Impacts Requiring DWR Mitigation: 0 -- --
Permanent Impacts Requiring USACE Mitigation: 907 -- --
Total Impacts Requiring Mitigation: 907 -- †
1 – Naked Creek and its UTs are Class C+ waters. All other streams are Class C; Tr+ waters.
2 – Values are based on rounding
† – Final mitigation requirement will be up to the USACE and DWR
Permit Site 8B:
At Station 746 to Station 747, there is an existing slope failure directly beside the north bound lane, on
the east side of the road. This issue has been ongoing for several years, and has resulted in several
similar slope failures, although the existing slope failure is relatively recent. The issue is believed to be
caused by saturated soils and originating from the hillside on the west side of the road.
Following a recent review of this issue, the permitted stormwater system for R-2915E at this location
was found to be inadequate. The NCDOT Hydraulics Unit studied the issue and recommended a change
in the permitted stormwater plans at Station 748, with the primary change including the addition of a
42” welded steel pipe. Installing this pipe should alleviate the saturated soils and help convey
stormwater from the west side of the road to the eastern side and into Little Buffalo Creek.
Closing the road and excavating/trenching in the new 42” stormwater pipe is not an option due to very
high traffic volumes (several businesses and Ashe County High School are at this location), and there is
no good detour option. In order to excavate/trench the road and install the pipe, NCDOT would need to
cut into and slope the hillside on the west side of the road and expand the roadway, which will be done
eventually in order to compete the R-2915E project. However, that cannot be done until NCDOT dries
that hillside up, which will first require the pipe installation. As a result of these issues, the best course
of action is to bore and jack the 42” pipe into place. With limited area to put the bore pit, it will be
placed partially within a stream wetland complex on the east side of the road, resulting in temporary
impacts to both the stream (Little Buffalo Creek), and part of the adjacent wetland (W110).
Dewatering Little Buffalo Creek to accommodate the bore pit will be accomplished by installing a
diversion pipe, which will remain in place until the project is complete (estimated 2-4 weeks). This
activity will result in a total of 170 lf (0.01 acre) of temporary stream impacts. The temporary
R-2915 Individual Permit Modification Application Page 8 of 9
dewatering pipe will be buried 42” (the diameter of the pipe), and will not be covered, but instead held
in place by Class B stone, placed every 10’ on top of the pipe. Class I riprap wrapped in geotextile will
be used to create a temporary headwall and endwall to stabilize the inlet and outlet of the temporary
diversion pipe. This will keep the pipe in place during high flow events and prevent water from running
around the pipe. All stream material excavated from where the diversion pipe connects to the stream
channel and bore pit will be stockpiled and returned to the stream once the project is completed. All
disturbed streambanks will be sloped to 2:1, seeded with native/riparian seed mix and covered with coir
fiber. In addition, live stakes of willow and silky dogwood will be planted.
Part of the stream diversion pipe and the bore pit will be installed within a wetland area (wetland W110)
adjacent to Little Buffalo Creek resulting in 0.13 acre of temporary wetland impacts. After the bore pit
has been removed, NCDOT plans to re-establish wetland habitat in these impacted areas. To allow for
this, any wetland soils excavated for the temporary diversion pipe and the bore pit will be stockpiled
and returned to the wetland upon completion of the project. All disturbed areas in the wetland will be
seeded with native/riparian seed mix, covered with coir fiber, and live stakes of willow and silky
dogwood will be planted.
To keep the work area dry (since the bore pit will be located partly within a stream and wetland area),
all water entering the bore pit will be pumped into a special stilling basin/silt bag, which will be located
downstream of the project on the west bank of the stream. This will keep the silt bag out of the wetland
area, and all water treated by the silt bag will be allowed to flow over existing vegetation and into the
creek. Once the project is complete, the geotextile and 57 stone base, and silt bag will be discarded, and
the area impacted will be seeded with native/riparian seed mix and covered with coir fiber.
Once the dewatering activities have been completed, there will also be 10 lf of streambank stabilization
with Class II riprap to Little Buffalo Creek at the outlet of the new 42” pipe to dissipate flow from the
pipe and prevent scouring of the streambank.
Previously permitted impacts at this site were <0.01 acre (20 lf) of temporary impacts to stream S135
(Little Buffalo Creek) and <0.01 acre of temporary wetland impacts in wetland W110 due to plugging
and filling the nearby 24” CMP.
Total impacts to this site due to this modification are now 0.01 acre (170 lf) of temporary impacts to
stream S135 (Little Buffalo Creek) and 0.13 acre of temporary wetland impacts in wetland W110 due
to temporary dewatering to accommodate the new bore pit. Additionally, there will now be 10 lf of
stream bank stabilization at this site at the outlet of the new stormwater pipe.
MITIGATION
At this time, DMS is providing compensatory mitigation for all impacts. Table 5 summarizes the total
mitigation needs as 3.05 acres of wetland impacts and 7,485 linear feet of stream impacts. No additional
mitigation is required due to the additional temporary stream and wetland impacts and added stream
bank stabilization at Site 8B in the E Section (described above) as these activities do not constitute a
loss of water.
R-2915 Individual Permit Modification Application Page 9 of 9
Table 5 – Summary of Mitigation Requested from DMS
Section Design Stage Wetland Impacts Requiring
Mitigation (ac)
Stream Impacts Requiring
Mitigation (ac)
R-2915A Final 0.57 1,119
R-2915B Final 0.43 493
R-2915C Final 0.27 2,339
R-2915D Final 1.32 2,627
R-2915E Final 0.46 907
Total 3.05 7,485
REGULATORY APPROVALS
Section 404: Application is hereby made for a modification to the USACE Individual 404 Permit as
required for the above-described activities.
Section 401: We are hereby requesting a modification to the 401 Water Quality Certification from the
N. C. Division of Water Resources for the above-described activities.
A copy of this application and distribution list will also be posted on the NCDOT website at:
http://connect.ncdot.gov/resources/Environmental. If you have any questions or need additional
information, please contact Erin Cheely at ekcheely@ncdot.gov or (919) 707-6108.
Sincerely,
Philip S. Harris III, P.E., C.P.M.
Environmental Analysis Unit Head
ec:
NCDOT Permit Application Standard Distribution List
ID#* 20140762 Version* 6
Regional Office* Winston-Salem Regional Office - (336) 776-9800
Reviewer List* Dave Wanucha
Pre -Filing Meeting Request submitted 1/5/2021
Contact Name * Erin Cheely
Contact Email Address* ekcheely@ncdot.gov
Project Name* R-2915
Project Owner*
Project County*
Owner Address:
NCDOT
Ashe
Street Address
1598 Mail Service Center
Address Line 2
aty
Raleigh
Rbstal / Zip Code
27699
Is this a transportation project?* r Yes r No
State / Frovince / Region
NC
Country
United States of America
Type(s) of approval sought from the DWR:
W 401 Water Quality Certification - F 401 Water Quality Certification -
Regular Express
W Individual Permit W Modification
r- Shoreline Stabilization
Does this project have an existing project ID#?*
r Yes r No
Please list all existing project ID's associated with this projects.*
20140762 v1-v5
Do you know the name of the staff member you would like to request a meeting with?
No meeting is requested.
Please give a brief project description below.*
Widening of US 221 from US 421 in Watauga County to US 221
Bus/NC 88 in Jefferson in Ashe County
Please give a couple of dates you are available for a meeting.
Please attach the documentation you would like to have the meeting about.
pdf only
By digitally signing below, I certify that I have read and understood that per the Federal Clean Water Act Section
401 Certification Rule the following statements:
This form completes the requirement of the Pre -Filing Meeting Request in the Clean Water Act Section 401 Certification
Rule.
I understand by signing this form that I cannot submit my application until 30 calendar days after this pre -filing
meeting request.
I also understand that DWR is not required to respond or grant the meeting request.
Your project's thirty -day clock started upon receipt of this application. You will receive notification regarding meeting location
and time if a meeting is necessary. You will receive notification when the thirty -day clock has expired, and you can submit an
application.
Signature
FjkiAtlkG4AFSV_Y
Submittal Date 1/5/2021
09/08/99
7
w
0
0
N
/
U
5
L
O
/
0
0
0
E
0
0
i
0
IIi
0,
EL
6
7)
U
0
0,0
5La)
N7
=L
\!0
nit 0
PROJECT: R-2915E
r See Sheet 1-A For Index of Sheets, General Notes, and List of Standards
See Sheet FB For Conventional Symbols
See Sheet IC-1- IC-4 For Survey Control Sheets
VICINITY MAP (NTS)
1 7
/ / I CV ,'
\\ \// Jy
--- 0%
1
pF G
w...e.noo _Citys�;� —\
\� SITE 2
T 0 DEEP GAP
SITE 1
BEGIN TIP PROJECT R-2915E
—L— Sta.668+25.00
SITE 5
SITE 4
ATE OF NOR
H CAROLINA
DIVISION OF HIGHWAYS
ASHE COUNTY
LOCATION: US 221 FROM US 221 BYPASS TO
US 221 B USINESS/NC 88 IN JEFFERSON
TYPE OF WORK: GRADING, DRAINAGE, PAVING, WIDENING,
RESURFACING, CULVERTS, AND SIGNALS
STATE
STATE PROJECT REFERENCE NO.
SHEET
NO.
TOTAL
SHEETS
N.C.
R-2915E
1
SPATE PROJ.NO.
F. A. PROD. NO.
DESCRIPTION
34518.1.FR6
STP-0221(45)
PE
34518.2.6
STP-0221(45)
RAN
34518.2.7
STP-0221(45)
UTIL.
34518.3.8
STP-0221(45)
CONST.
WETLAND AND STREAM IMPACTS
SITE 9
SITE 120,
SITE 11
/
SITE 8
SITE 7
7 //
THIS IS A PARTIAL CONTROLLED —ACCESS PROJECT WITH ACCESS BEING LIMITED TO POINTS AS SHOWN ON PLANS.
7
/
a /
SITE 17
SITE 16
0÷
(r
�\ C.4".
y33. SITE 14
C.S. SITE 15
SITE 10 SITE 13
* PROPOSED TRAFFIC SIGNAL
SITE 21
SITE 18
SITE 23
SITE 24
SITE 25
SITE 22
.`
s,P 616.
SITE 26
SITE 27
SITE 28
SITE 29
\ END TIP PROJECT R-2915E
—L— Sta.855+00.00
PERMIT DRAWING
SHEET 1 OF 46
SITE 31
SITE 30
DOCUMENT NOT CONSIDERED FINAL
UNLESS ALL SIGNATURES COMPLETED
GRAPHIC SCALES
50 25 0
50
100
PLANS
50 25 0 50 1 0
`1111���
PROFILE (HORIZONTAL)
10 5 0 10 20
PROFILE (VERTICAL)
DESIGN DATA
ADT 2019 = 15,900
ADT 2039 = 19,400
K = 8%
D = 55%
T = 6%*
V = 60 MPH
FUNC. CLASSIFICATION
RURAL ARTERIAL
* TTST=3% + DUALS=3%D
PROJECT LENGTH
LENGTH ROADWAY TIP PROJECT R-2915E 3.533 mi
LENGTH CULVERT TIP PROJECT R-2915E 0.004 mi
TOTAL LENGTH TIP PROJECT R-2915E 3.537 mi
PLANS PREPARED BY:
RAC
RUMMEL, KLEPPER 8 KAHL, LLP
900 RIDGEFIELD DRIVE, SUITE 350
RALEIGH, NORTH CAROLINA 27609
NC LICENSE NO. F-0112
FOR NORTH CAROLINA
DEPARTMENT OF TRANSPORTATION
NCDOT CONTACT
Joe Laws, P.E.
PROJECT ENGINEER - DIVISION II
2018 STANDARD SPECIFICATIONS
RIGHT OF WAY DATE:
MAY 8, 2018
LETTING DATE:
SEPTEMBER 17, 2019
Scott D. Blevins, P.E.
PROJECT ENGINEER
RK&K, LLP
Cathy S. Houser, P.E.
PROJECT DESIGN ENGINEER
RK&K, LLP
HYDRAULICS
ENGINEER
P.E.
SIGNATURE,
ROADWAY
DESIGN
ENGINEER
SIGNATURE,
P.E.
m
Ltj
LLE
25 0 25 50
PERMIT DRAWING
SHEET 18 OF 46
SCALE FOR INSET JEMSICHARLESLR. COPE (20%)(40%),
MLR (0
50 250 50 100 ANDJIMMY PHIL G I STEVENS/(4
20%)
SCALE
//)/
DENOTES FILL IN
WETLAND
DENOTES IMPACTS IN
SURFACE WATER
DENOTES TEMPORARY
IMPACTS IN SURFACE WATER
DENOTES TEMPORARY
FILL IN WETLAND
SP. CAT. V DITCH
.} W/85 TONS
CL B RIPRAP,
O� 237 SY
ti GEOTEXTILE SEE
BERM BASE DITCH DETAIL Q
W081 TONS CL 1 RIPRAP,
371 SY GEOTEXTILE
SEE DETAIL R
W/773 TONS CL BASE DITCH
PRAP BERM BASE DITCH /O— POE '- PpE
1937 SY GEOTEXTILE SEE DETAIL N 'Apt SEE DETAIL 0
Boo DES' `����� ---
,/�y-rawAm �— = SITE 9A
�iGi1lE. *
POE
111
TB 2GI
— -- _—__-- —"F—STDAECT W/TO B
GEOTEXTILERIF SY
T H
SEE DETAIL H
TONS CL 1 RIPRAP,,,
W/15 SY GEOTEXTILvy
:UFFALO CREEK
NG R/WW tt
0,
CIS
COUNTY OF ASHE II
20
WOODS
SEE INSET A
9`rT,
SITE 8A1
INSET A
V10=3.6 Wsl
2SBW —
0SPRING
x
‘gl SIA
4OTCB
CAT-1
TL
30" CMP - Sd7r.R.�71li1 ^ /l
DROP STRUCTURE /
(DROP DEPTH=1.4') /
30" RCP —III
11 TONS CL I RIPRAP SEE INSET B
W22 SY GEOTEXTILE
ON BANKS ONLY
SEE DETAIL AF IV10=8.3i
9
xsr„ D
o �\
EX! IN
W
INSET B / INSET C
72. CHL
A -A
3.10'
1.071-\2 V9�
1.0' INFALL
\
1"V FENCE _.
BST PA
Q x —
0A/
a // /
,
/ \wpV C \\
'V' DITCH
SEE DETAIL X
B-B
13.0'
2.00
I
8.0' OUTFALL
JOHNNY J. SULLIVAN
BST DA
W \\ /\�NC CV
o / OST PA \ \
��g
C—C
8.0'
0.2
3.0'1 Sr_
5.0' OUTFALL
T. V DIT
W/595.5
CONC.PAD
EXISPINGA
CONC
PLUG & FILL
SYSTEM W/
FLOWABLE FILL
SITE 8B
BDO
REMOVE RISER
& 9' EX.
24" CMP
':BI4SE DITC
E ETAIL N
30" RCP —III
PROJECT REFERENCE NO.
SHEET NO.
R-29/5E
9
RAY SHEET NO
ROADWAY DESIGN
ENGINEER
HYDRAULICS
ENGINEER
DOCUMENT NOT CONSIDERED FINAL
UNLESS ALL SIGNATURES COMPLETED
Sf �S�
U
� Q
G 72' CHL & 3SBW
— E 7,NG R/W -.
ORNER OF Yi7 exisri BUILDING
cor✓c I CS PROPERTIES OF ASHE. INC. AT CONTROL
URV.= 309061
---- (SURVEYED 1006R6)
EXISTING R/WR/w
BST PA
50 PR
CS PROPERTIES OF
ASHE, INC.
• M930
EXISTING R/W
BST PA
DI
FOR DRN. DETAILS SEE SHTS. 2D-1 OR 2D-2
FOR -L- PROFILE SEE SHT. 20
FOR -SR1- PROFILE SEE SHT. 26
C
V)
W
W
O
O
1-
RK 'i(
Pi (919)878-9560
900 Ridgefield Drive Suite 350 Raleigh, North Carolina 27609-3960
NC License No. F-0112
Engineers I Construction Managers I Planners I Scientists
www.rkk.ccm
Responsive People I Creative Solutions
Hand Existing Existing
Permanent Temp. Excavation Mechanized Clearing Permanent Temp. Channel Channel Natural
Site Station Structure Fill In Fill In in Clearing in SW SW Impacts Impacts Stream
No. (From/To) Size / Type Wetlands Wetlands Wetlands in Wetlands Wetlands impacts impacts Permanent Temp. Design
(ac) (ac) (ac) (ac) (ac) (ac) (ac) (ft) (ft) (ft)
1 -L- 670+03 to 670+45 RT DITCH < 0.01
2A -L- 675+33 to 675+66 LT BANK STABILIZATION < 0.01 < 0.01 14 17
2B -L- 676+43 to 677+27 RT 42" RCP-III 0.02 < 0.01 0.01 < 0.01 57 21
DITCH 0.01
30" RCP-III < 0.01 0.02
4A -L- 705+04 to 705+37 LT FILL < 0.01
30" RCP-III < 0.01 0.03
BANK STABILIZATION < 0.01 < 0.01 11 10
5 -L- 706+60 to 707+07 RT DITCH & EXIST. 18" CMP < 0.01 0.01
6A -L- 711+85 to 713+30 LT 42" RCP-III 0.04 0.02 < 0.01 < 0.01 52 10
6B -L- 711+15 to 711+42 RT BANK STABILIZATION < 0.01 < 0.01 27 10
7 -L- 735+40 to 735+61 RT DITCH < 0.01 24
8A -L- 740+22 to 740+56 RT DITCH < 0.01 32
TEMPORARY BORE PIT 0.13 0.01 170
BANK STABILIZATION < 0.01 10
9A -L- 742+35 to 743+21 LT 24" CSP, 30" RCP-III 0.09 < 0.01 33
-L- 742+06 to 742+11 RT BANK STABILIZATION-TRIB < 0.01 < 0.01 10 7
9B -L- 741+98 to 742+15 RT
BANK STABILIZATION- LITTLE
BUFFALO CREEK < 0.01 19
10 -L- 754+26 to 754+54 RT 15" RCP-III < 0.01 < 0.01
11A < 0.01 22
11B < 0.01 10
11C < 0.01 11
11D < 0.01 < 0.01 27 10
12 -Y35- 9+25 to 9+50 LT BANK STABILIZATION < 0.01 < 0.01 17 10
30" RCP-III < 0.01 31
BANK STABILIZATION < 0.01 < 0.01 11 10
13B -L- 763+07 to 763+40 RT 30" RCP-III 0.01 < 0.01 60
13C -L- 762+53 to 762+38 LT SPRING BOX < 0.01 < 0.01 25 23
60" RCP-III < 0.01 23
BANK STABILIZATION < 0.01 < 0.01 23 10
14B -L- 765+28 to 765+72 RT 60" RCP-III < 0.01 63
36" RCP-III 0.01 < 0.01 < 0.01 31
BANK STABILIZATION < 0.01 < 0.01 15 10
15B -L- 770+68 to 770+93 RT EXIST. 36" CMP 0.01 < 0.01 23
16 -L- 769+54 to 770+29 RT EXIST. 36" CMP 0.03
17A -L- 776+79 to 777+26 LT 42" RCP-III 0.01 115
17B -L- 775+45 to 776+91 RT DITCH < 0.01 146
18 -L- 780+80 to 781+00 LT 24" RCP-III & DITCH < 0.01 < 0.01 39 12
24" RCP-III < 0.01 22
BANK STABILIZATION < 0.01 < 0.01 8 10
20 -L- 793+05 to 793+30 RT DITCH < 0.01 25
21 -L- 797+03 to 799+22 LT FILL & DITCH 0.03 0.01 < 0.01
22A -L- 802+05 to 802+32 RT EXIST. 48" CMP < 0.01 22
66" RCP-III < 0.01 61
BANK STABILIZATION < 0.01 < 0.01 31 10
23 -L- 810+70 to 811+24 RT FILL < 0.01 55
24A -L- 815+76 to 815+87 RT 60" RCP-III < 0.01 < 0.01 30 22
24B BANK STABILIZATION- TRIB < 0.01 18
24C BANK STABILIZATION- NAKED
CREEK < 0.01 < 0.01 20 20
25A -Y36- 16+29 to 16+46 RT EXIST. 24" CMP < 0.01 < 0.01 13 12
25B -Y36- 16+72 to 17+17 LT BANK STABILIZATION < 0.01 < 0.01 17 20
26A -L- 823+43 to 826+83 LT DITCH & 60" RCP-III 0.01 0.04 < 0.01 < 0.01 19 8
26B BANK STABILIZATION-TRIB < 0.01 8
26C BANK STABILIZATION- NAKED
CREEK < 0.01 < 0.01 32 20
27A BANK STABILIZATION-TRIB < 0.01 15
27B BANK STABILIZATION- NAKED
CREEK < 0.01 < 0.01 18 30
28A -L- 838+81 to 839+70 LT BANK STABILIZATION 0.01 < 0.01 88 10
28B -L- 837+00 to 837+71 RT BANK STABILIZATION 0.02 < 0.01 59 10
29 -L- 844+25 to 844+38 RT 42" RCP-IV < 0.01 < 0.01 5 15
30 -L- 849+47 to 849+82 LT BANK STABILIZATION < 0.01 < 0.01 17 21
31 -L- 848+81 to 848+99 LT PLUG/FILL 0.02
TOTALS*: 0.28 0.13 0.05 0.13 0.14 0.08 1376 726 0
*Rounded totals are sum of actual impacts
NOTES:
Revised 2019 03 11 SHEET 46 OF 46
8B -L- 747+64 to 747+86 RT
1. Temporary Surface Water Impacts are expected during installation of the existing pipes that require a smooth liner
WETLAND AND SURACE WATER IMPACTS SUMMARY
WETLAND IMPACTS SURFACE WATER IMPACTS
ASHE
R-2915E
NC DEPARTMENT OF TRANSPORTATION
DIVISION OF HIGHWAYS
REVISED SEPTEMBER 2021
-L- 701+14 to 702+66 RT3
4B -L- 704+66 to 704+84 RT
19 -L- 788+03 to 788+42 RT
22B -L- 804+49 to 805+11 LT
13A -L- 762+53 to 762+76 LT
14A -L- 763+31 to 763+73 LT
15A -L- 768+02 to 768+66 LT
-L- 816+22 to 816+61 LT
-L- 826+80 to 827+32 RT
-L- 832+48 to 832+87 RT
-L- 750+89 to 751+24 RT Existing 66" CMP