HomeMy WebLinkAbout20190214 Ver 4_Final Minutes I-5986B_etc Preconstruction Meeting 8-24-21_20210824 FINAL MINUTES
Gannett Fleming / NCDOT Div. 6
I-95 Program Management
Page 1 of 6
Purpose: I-95 Program Management – Pre-Construction Meeting
Date/Place/Time: Tuesday, August 24, 2021, from 1:00 PM to 4:00 PM
Attendees: See Attendee List
1. Introductions
• R. Marsh provided opening remarks and each attendee noted their name and who they
represented (see attendees list)
2. Contract Highlights (Marsh)
• Noted the Date of Availability as August 30, 2021, and the Completion Date as October 26,
2026, and associated liquidated damages.
• Noted the Substantial Completion Date of May 1, 2026 (ICT #1) and associated liquidated
damages.
• Noted Day & Time Restrictions for lanes closures (ICT #2) and associated liquidated
damages.
• Noted other Intermediate Contract Times as shown in the contract document
3. Utility Update (Handlin)
• Noted effort put into getting utilities relocated & challenges due to funding and shutdowns
• Noted Duke Energy is partnering to provide as many resources as possible
• Noted that power had been relocated in the area from Hodges Chapel Rd. interchange south
to Jonesboro Rd.
• CenturyLink has begun relocations in this area
• Noted the next area of focus for Duke Energy is around the Spring Branch Rd. interchange
• Noted some of the natural gas facilities have been relocated by Piedmont Natural Gas
• Noted various other utility owners including the Town of Benson, the City of Dunn, and
Harnett County.
• The Contractor questioned if as-builts are being updated as utility relocations are completed?
• It was noted that this was not being done
• R. Wise noted that the utilities as shown in the UBO plans should be close to the final
locations and no issues are anticipated
• Clarification from the contractor noted that the question pertained to the status of
completing the relocations and related updates
• The PNG representative noted hitting contaminated soil near the Burger King.
• C. Linn asked how the contractor may assist with relocation efforts
• R. Handlin noted identifying priorities areas would be helpful
• A suggestion was made to begin the project with a monthly utility update meeting
• Action Item - R. Wise will set up the suggested meeting
• R. McNeill noted DMP would be providing some inspection on municipal facilities and
asked to be included in meetings
FINAL MINUTES
Gannett Fleming / NCDOT Div. 6
I-95 Program Management
Page 2 of 6
4. Right of Way (Baggett)
• Noted NCDOT and is staying on top of claims and trying to get all acquisitions completed as
quickly as possible
• R. Marsh noted parcels listed in contract document that have delayed entry
5. Permits (Rerko)
• Noted there will be ongoing coordination with ACOE representatives
• Anticipates at least one ride-through review per month
• noted planned meetings
• R. Marsh noted NPDES record keeping as being important
6. Contract items (Marsh). The following items from the contract were noted and briefly discussed:
• Specialty items
• Asphalt mixes and liquid price
• Permanent vegetation
• Payout schedule by year
• State Fiscal Year noted as July to June
• MB/WB goals
• Noted that goals were met b he Contractor
• R. wise noted replacement requirements
• Restrictions on ITS equipment
• Drone usage
• R. Wise noted form for approval to be submitted to NCDOT
• Equipment idling guidelines
• Partial payment for concrete barrier
• Guardrail/guiderail maintenance
• Cooperation between contractors
• Noted I-5986A & I-5986C as ongoing projects
• Twelve-month guarantee
• No outsourcing
• Erosion and stormwater certification
• J. Bullard noted need for reclamation plans
• Clearing & Grubbing by Method III
• NCDOT may provide further guidance on clearing small patches of trees with the
Supplementary Clearing & Grubbing pay item or other means if necessary
• No open burning on right of way
• Temporary detours, slopes and fill slope material
• The Contractor noted that no combustible materials or manufactured quarry fines will be
used
• Fabric under slabs to be utilized
• Asphalt Binder was $473.18 per ton on May 1, 2021
• R-16 automated machine guidance, contractor to provide one rover unit
• NCDOT will coordinate with the Contractor after the meeting regarding the possibility of
providing additional devices
FINAL MINUTES
Gannett Fleming / NCDOT Div. 6
I-95 Program Management
Page 3 of 6
• R-17 supplemental surveys rates
• Median hazard protection to be paid by the linear foot
• The contractor noted that the likely guardrail subcontractor is Bullington
• R-47 permanent seeding and mulching incentive
• Standard Special Provision
• SSP-8 Title VI and Non-Discrimination
• R. McNeill noted to the Contractor to make sure to be aware of requirements and to
verify that the trucking plan satisfies the required 50/50 ratio.
• R. McNeill ask if Hyatt Mason is listed for labor or for labor & materials
• Action Item - The Contractor will further investigate
• The Contractor noted that they have an On-the-Job Training program
• Geotech specs for various items
• R. Wise noted aesthetic requirements for walls
• The Contractor noted they would submit test patterns
• Contaminated soil requirements
• The sealed drainage system on I-5878 was specifically noted
• Only non-metal snow plowable markers allowed
• Attention was brought to the item of making sure temporary markers are removed and
pavement patched on lane shifts
• R. Wise noted contract requires removing
• ADA requirements for pedestrians
• Glare screen locations
• TC-6 sequential flashing warning lights
• Work zone presence lighting, performance markings, etc.
• High visibility devices, connected devices
• Attention was brought to coordination with State Traffic Operations Center
• J. Flowers noted the Division is planning to do supplemental agreement to have a towing
contractor to cover the entire work zone
• J. Flowers asked when traffic impacts were expected to begin
• The Contractor noted around the end of September 2021
• Statewide lighting maintenance (LT-22) & Special Provisions for street lighting
• The maintenance contractor was noted to be Brady Services contract handled by NCDOT
Central Unit)
• The Contractor noted Carolina Power will be the subcontractor performing the signal work
• Structures
• The Contractor noted that Truesdale will be the subcontractor performing the PPC
overlays
• R. Wise noted the NC 50 bridge will require salvaging of aluminum rail and delivery to the
NCDOT Bridge Maintenance yard in Johnston County.
• Sound barrier walls were noted to have the same aesthetic requirements of other walls.
• The Contractor noted they have not received a copy of the executed contract
• R. Marsh provided copy
• C. Linn noted the Contractors invoice date will be the 22nd of each month.
FINAL MINUTES
Gannett Fleming / NCDOT Div. 6
I-95 Program Management
Page 4 of 6
• R. Wise noted the appropriate documents required to be furnished at the preconstruction
meeting had been received from the Contractor.
• The Contractor noted they use Procore software for document storage and handling.
• Division staff noted openness to this approach.
• R. Marsh asked for any comments from the on-line meeting participants.
• S Cummings (Harnett County Water) asked about utility items. It was noted that these
would be covered under a separate meeting.
7. As her was no more discussion the meeting concluded and was adjourned at 1:56 PM.
8. Post meeting, J. Salisbury noted the need to set up a standing safety meeting as well as a Work Zone
Traffic Control kick-off meeting.
• Action Item – The Contractor to propose dates for these meetings.
FINAL MINUTES
Gannett Fleming / NCDOT Div. 6
I-95 Program Management
Page 5 of 6
Present By
Phone
ATTENDEES
Name
Email
Representing
X Thomas Roberts elkamino@bellsouth.net Bellsouth
X Dennis Reedy dreedy@dmp-inc.com DMP
X Randy McNeill rmcneill@dmp-inc.com DMP
X Steve McKee smckee@dmp-inc.com DMP
X Linda Scharf-Byers linda.scharf-byers@duke-energy.com Duke Energy
X Chris Bowen Ext-cjbowen6@ncdot.gov ESP Associates
X Dale Privette dale.privette@dot.gov FHWA
X Abbie Schlake aschlake@flatironcorp.com Flatiron Corp.
X Eric Weaver eweaver@flatironcorp.com Flatiron Corp.
X Graham Kuzek gkuzek@flatironcorp.com Flatiron Corp.
X Kayley Adams kadams@flatironcorp.com Flatiron Corp.
X Linda Brumfield lbrumfield@flatironcorp.com Flatiron Corp.
X Pete Ahern Pahern@flatironcorp.com Flatiron Corp.
X Tim Cook tcook@flatironcorp.com Flatiron Corp.
X Caleb Linn clinn@flatironcorp.com Flatiron Corp.
X Colby Reynolds Colby.Reynolds@fredsmithcompany.net Fred Smith Co.
X Joseph Newcomb joseph.newcomb@fredsmithcompany.net Fred Smith Co.
X Noah Blalock Noah.blalock@fredsmithcompany.net Fred Smith Co.
X Trevor Leander Trevor.Leander@fredsmithcompany.net Fred Smith Co.
X Jerry Page jpage@gfnet.com Gannett Fleming
X Shane Cummings scummings@harnett.org Harnett County
X Randy Wise rkwise@ncdot.gov ICE
X Mike Keen mike.keen@johnstonnc.com Johnston County
X Brandy Creech bcreech@mbakerintl.com MBI
X Susan Lancaster Susan.lancaster@mbakerintl.com MBI
X Hannah Sprinkle hannah.sprinkle@ncdenr.gov NCDENR
X Emerina Downey eydowney@ncdot.gov NCDOT
X Gabe Shoffner sgshoffner@ncdot.gov NCDOT
X Greg Price gwprice2@ncdot.gov NCDOT
X Jason Bullard jmbullard1@ncdot.gov NCDOT
X Jason Salisbury jsalisbury@ncdot.gov NCDOT
X Jim Rerko jjrerko@ncdot.gov NCDOT
X Kaye Baggett kdbaggett@ncdot.gov NCDOT
X Paul Atkinson patkinson@ncdot.gov NCDOT
FINAL MINUTES
Gannett Fleming / NCDOT Div. 6
I-95 Program Management
Page 6 of 6
Present By
Phone
ATTENDEES
Name
Email
X Red Simmons jwsimmons1@ncdot.gov NCDOT
X Reginald McNeill rlmcneill@ncdot.gov NCDOT
X Rick Handlin rhandlin@ncdot.gov NCDOT
X Rusty Marsh rmarsh@ncdot.gov NCDOT
X Scott Pridgen gspridgen@ncdot.gov NCDOT
X Sean Matuszewski spmatuszewski@ncdot.gov NCDOT
X Stephen Blakeney stblakeney@ncdot.gov NCDOT
X Todd Whittington twhittington@ncdot.gov NCDOT
X John Walters jcwalters@ncdot.gov RS&H
X Fred Nelson fnelson@townofbenson.com Town of Benson
X Ray Adams radams@townofbenson.com Town of Benson
X Tim Robbins trobbins@townofbenson.com Town of Benson
X Justin Knight Jmknight1@ncdot.gov Volkert
X Walid Selim Walid.selim@volkert.com Volkert