HomeMy WebLinkAbout20211296 Ver 1_SAW-2021-01565-PN_20210723Version 6.15.2017 Page 1
PUBLIC NOTICE
Issue Date: July 22, 2021
Comment Deadline: August 20, 2021
Corps Action ID Number: SAW-2021-01565
The Wilmington District, Corps of Engineers (Corps) received an application from
Fujifilm Diosynth Biotechnologies U.S.A., Inc. seeking Department of the Army (DA)
authorization to discharge fill material into waters and wetlands in the Cape Fear River
Basin, Hydrologic Unit Code (HUC) 03030004, associated with Project Galaxy, in Holly
Springs, in Wake County, North Carolina.
Specific plans and location information are described below and shown on the attached
plans. This Public Notice and all attached plans are also available on the Wilmington
District Web Site at:
https://www.saw.usace.army.mil/Missions/Regulatory-Permit-Program/Public-Notices/
Applicant: Fujifilm Diosynth Biotechnologies U.S.A., Inc.
Attn: Thomas Schmalzbauer
101 J Morris Commons Lane
Morrisville, North Carolina 27560
AGENT (if applicable): Timmons Group
Attn: Matt J. Michel
428 Eastwood Road
Wilmington, North Carolina 28403
Authority
The Corps evaluates this application and decides whether to issue, conditionally issue, or
deny the proposed work pursuant to applicable procedures of the following Statutory
Authorities:
Section 404 of the Clean Water Act (33 U.S.C. 1344)
Section 10 of the Rivers and Harbors Act of 1899 (33 U.S.C. 403)
Section 103 of the Marine Protection, Research and Sanctuaries Act of 1972
(33 U.S.C. 1413)
Location
US Army Corps
Of Engineers
Wilmington District
Version 6.15.2017 Page 2
Location Description: The proposed project (Project) is located south of New Hill Road,
approximately 0.5 miles form the intersection of New Hill Road and Green Oaks
Parkway, in Holly Springs, Wake County, North Carolina.
Project Area (acres): ~147.5 acres Nearest Town: Holly Springs
Nearest Waterway: Unnamed tributary to Utley Creek River Basin: Cape Fear
Latitude and Longitude: 35.652909N, -78.875637W
Existing Site Conditions
The project area (Site) is bound to the north by a residential development and New Hill
Road, to the east by a commercial development that is presently under construction
(Oakview Innovation Park), an existing commercial development (Seqirus), a mixed pine
plantation, and mature hardwood forest. The site is bound to the south by a mixed pine
plantation and mature hardwood forest, and to the west by residential development and
mixed hardwood/pine forest.
The entirety of the Site is located within an area identified as Zone X, according to NC
Flood Insurance Rate Map 3720062800J with an effective date May 2, 2006. This
designation means that the area is within a minimal flood hazard and is above the 500-
year flood level. The Project has been designed to comply with applicable Federal
Emergency Management Agency (FEMA) approved state and local floodplain
management requirements and no increase in the 100-year flood elevations is anticipated.
The Corps issued a Jurisdictional Determination for an approximately 216-acre area,
which includes the entirety of the Site, on August 4, 2020. An additional Jurisdictional
Determination Request for the Project was submitted on July 2, 2021, to update stream
and wetland areas that had been previously delineated in 2016. In total, the delineations
have identified 72,816 Square feet (sq. ft.) (1.67 acres) of Palustrine Forested (PFO)
wetlands, 3,034 sq. ft. (0.07 acre) of Palustrine Open Water (POW), 3,073 linear feet
(15,725 sq. ft. / 0.36 acre) of perennial streams, and 5,362 linear feet (12,225 sq. ft. / 0.28
acre) of intermittent streams within the Site.
Applicant’s Stated Purpose
The purpose of the Project is to construct a biopharmaceutical manufacturing facility and
campus within an established business park with access to major interstate thoroughfares
in proximity to the Research Triangle Park (RTP) and an existing Fujifilm Diosynth
Biotechnologies U.S.A., Inc. (FDBU) facility located in Morrisville, NC. Project Galaxy
is expected to have a projected investment of more than $1.5 billion and result in over
700 new jobs.
The facility would offer large-scale cell culture manufacturing of bulk drug substance
production with eight (8) 20,000 L bioreactors per drug substance manufacturing building
with the potential to expand and add an additional twenty-four (24) 20,000 L bioreactors
based on market demand. The facility would also provide commercial scale, automated
Version 6.15.2017 Page 3
fill-finish and assembly, packaging, and labeling services. A warehouse building would
provide storage of raw materials and finished drug products and serve as the facility’s
distribution hub. The facility would also consist of Quality Control (QC) Laboratory and
Administration Buildings where drug samples would be managed, and QC tested.
Construction of the facility would proceed under four phases, with Phases 1 and 2 being
concentrated at the eastern portion of the Site and Phases 3 and 4 concentrated at the
western portion.
Once completed, the facility would become the largest end-to-end cell culture
biopharmaceutical contract development and manufacturing organization (CDMO)
facility in North America. As a CDMO, FDBU’s focus is to combine technical
leadership in cell culture, microbial fermentations and gene therapies with world class
Good Manufacturing Practices (GMP) facilities to advance tomorrow’s medicine. For
over 30 years, FDBU’s focus has been on supporting their customers with the
development and manufacture of recombinant proteins, viral vaccines, and gene
therapies. FDBU’s commitment to GMP ensures that finished drug products are of the
highest quality and are safe for human consumption and use.
The need for expanded domestic production of drug products and other
biopharmaceuticals has become evident in recent years due to increased international
instability, the heightened risk of global pandemics, and significant commerce
disruptions. In 2019, it was estimated that only 28% of active pharmaceutical ingredients
(API) are produced domestically, and this percentage has dropped in the subsequent
years. The increased reliance of the United States on outsourced drug products and
ingredients potentially represents a security risk and a public health hazard that can be
addressed with increased domestic production. Demand for a secure domestic drug-
supply chain would only increase in the future as the nation’s median age increases and
average life expectancies continue to rise.
Additionally, Wake County and the Town of Holly Springs has a need for jobs to support
its growing population. Among all U.S. counties with greater than 1 million residents,
Wake County experienced the third-highest growth rate from 2010 to 2019. The county
is growing twice as fast as the rest of the state and has an estimated labor force of over
590,000 as of April 2021. Unemployment rates in Wake County have slightly rebounded
from pre-COVID-19 levels but remain high for low-wage workers. This proposed
project is expected to create 700 full-time new jobs and an additional number of part-time
construction and contracting jobs.
Due to the anticipated need to expand domestic drug production capabilities and the
projected population growth in Wake County, the need exists to develop a
biopharmaceutical manufacturing and distribution facility in Holly Springs, NC. The
Applicant intends to develop the Site quickly in order to meet the growing demands for
pharmaceuticals in the U.S. and hopes that the facility would become operational by
Spring 2025.
Version 6.15.2017 Page 4
Project Description
The proposed site layout for Project Galaxy meets the minimum requirements for the
biopharmaceutical manufacturing facility and campus and was determined to be the most
practicable long-term solution to address the Applicant’s purpose and need. To
accomplish the goals of the project, impacts to potential jurisdictional Waters of the U.S.
are unavoidable. The development of the Site would require permanent impacts to
57,278 sq. ft. (1.31 acres) of PFO wetlands, 986 sq. ft. (0.02 acre) of POW wetlands, 179
linear feet and 1,114 sq. ft. (0.03 acre) of perennial stream channel, and 3,134 linear feet
and 6,643 sq. ft. (0.15 acre) of intermittent stream channel. No temporary impacts are
proposed. The permanent impacts to wetlands and streams are associated with grading,
cut, and fill activities required for the construction of the proposed buildings, parking
areas, access roads, and utility infrastructure development. The total impacts for the
proposed Project are described in the table below.
Storm runoff from the proposed facility would be managed, treated, and ultimately
directed into off-site waters. Therefore, the drainage area of the receiving waters located
off-site would not be significantly reduced. The project would meet all relative
requirements of Best Management Practices and Engineered Stormwater Control
Measures as outlined through State and Local Stormwater rules. Stormwater
management on-site would be managed and treated before discharging into down-
gradient waters to protect receiving waters from degradation.
Avoidance and Minimization
The applicant provided the following information in support of efforts to avoid and/or
minimize impacts to the aquatic environment:
Version 6.15.2017 Page 5
Impacts to jurisdictional features were avoided and minimized to the maximum extent
practicable by incorporating resourceful site selection and site planning, including the use
of multiple preliminary jurisdictional determinations to ensure all jurisdictional features
within the Site were accurately mapped. After the wetlands were delineated, an
engineering plan was developed to meet all needs at the proposed facility, while
minimizing impacts to Waters of the U.S. The Applicant contends that the proposed
location results in the least impacts to Waters of the U.S. while realizing the purpose and
need of the project.
The applicant contends that the proposed Project has minimized the possibility of
secondary impacts through implementation of planning practices that would reduce
impacts on downstream water quality. Efforts to reduce secondary impacts generally
include:
• Innovative site planning and use of confirmed wetland delineation
• Minimization of partial wetland/stream impacts
• Minimization of impacts to primary drainage ways and floodplains
• Strict adherence to all state and local stormwater and sediment control measures
In order to avoid secondary impacts, an Erosion and Sediment Control Plan that meets
the latest State and local regulations and adheres to the methodology described in the
North Carolina Sedimentation and Pollution Control Act of 1973 would be prepared. All
erosion and sediment control measures would be checked for stability and operation
following every runoff producing rainfall (typically, > 1 inch), but in no case less than
once every week. Any necessary repairs would be made immediately to maintain all
measures designed. The project would meet all relative requirements of Best
Management Practices and Engineered Stormwater Control Measures as outlined through
State and Local Stormwater rules.
Compensatory Mitigation
The applicant offered the following compensatory mitigation plan to offset unavoidable
functional loss to the aquatic environment:
Compensatory mitigation for unavoidable impacts would be achieved through the
purchase of off-site mitigation credits from Wetland Mitigation Banks. If credits are
unavailable at the time of permitting, compensatory mitigation would be achieved
through payment into the North Carolina Division of Mitigation Services (NCDMS) in-
lieu fee mitigation program.
It is anticipated that North Carolina Stream Assessment Method (NCSAM) and North
Carolina Wetland Assessment Method (NCWAM) reviews would be conducted in order
to assess feature quality and determine if a lower mitigation ratio is feasible. If features
are determined to be high quality, it is understood that a 2:1 ratio would be required for
wetland and stream mitigation credits. If a 2:1 ratio is required, impacts resulting from
Version 6.15.2017 Page 6
the proposed project would require 2.62 wetland mitigation credits and 6,626 stream
mitigation credits as detailed in the table below.
Essential Fish Habitat
The Corps’ determination is that the proposed project would not effect EFH or
associated fisheries managed by the South Atlantic or Mid Atlantic Fishery Management
Councils or the National Marine Fisheries Service.
Cultural Resources
Pursuant to Section 106 of the National Historic Preservation Act of 1966, Appendix C of
33 CFR Part 325, and the 2005 Revised Interim Guidance for Implementing Appendix C,
the District Engineer consulted district files and records and the latest published version
of the National Register of Historic Places and initially determines that:
Should historic properties, or properties eligible for inclusion in the National
Register, be present within the Corps’ permit area; the proposed activity requiring
the DA permit (the undertaking) is a type of activity that will have no potential to
cause an effect to an historic properties.
No historic properties, nor properties eligible for inclusion in the National
Register, are present within the Corps’ permit area; therefore, there will be no
historic properties affected. The Corps subsequently requests concurrence from
the SHPO (or THPO).
Version 6.15.2017 Page 7
Properties ineligible for inclusion in the National Register are present within the
Corps’ permit area; there will be no historic properties affected by the proposed
work. The Corps subsequently requests concurrence from the SHPO (or THPO).
Historic properties, or properties eligible for inclusion in the National Register,
are present within the Corps’ permit area; however, the undertaking will have no
adverse effect on these historic properties. The Corps subsequently requests
concurrence from the SHPO (or THPO).
Historic properties, or properties eligible for inclusion in the National Register,
are present within the Corps’ permit area; moreover, the undertaking may have an
adverse effect on these historic properties. The Corps subsequently initiates
consultation with the SHPO (or THPO).
The proposed work takes place in an area known to have the potential for the
presence of prehistoric and historic cultural resources; however, the area has not
been formally surveyed for the presence of cultural resources. No sites eligible
for inclusion in the National Register of Historic Places are known to be present
in the vicinity of the proposed work. Additional work may be necessary to
identify and assess any historic or prehistoric resources that may be present.
The District Engineer’s final eligibility and effect determination will be based upon
coordination with the SHPO and/or THPO, as appropriate and required, and with full
consideration given to the proposed undertaking’s potential direct and indirect effects on
historic properties within the Corps-indentified permit area.
Endangered Species
Pursuant to the Endangered Species Act of 1973, the Corps reviewed the project area,
examined all information provided by the applicant and consulted the latest North
Carolina Natural Heritage Database. Based on available information:
The Corps determines that the proposed project would not affect federally listed
endangered or threatened species or their formally designated critical habitat.
The Corps determines that the proposed project may affect federally listed
endangered or threatened species or their formally designated critical habitat.
By copy of this public notice, the Corps initiates consultation under Section 7
of the ESA and will not make a permit decision until the consultation process is
complete.
The Corps will consult under Section 7 of the ESA and will not make a permit
decision until the consultation process is complete.
Version 6.15.2017 Page 8
The Corps has initiated consultation under Section 7 of the ESA and will not
make a permit decision until the consultation process is complete.
The Corps determines that the proposed project may affect federally listed
endangered or threatened species or their formally designated critical habitat.
Consultation has been completed for this type of activity and the effects of the
proposed activity have been evaluated and/or authorized by the National Marine
Fisheries Service (NMFS) in the South Atlantic Regional Biological Opinion or
its associated documents, including 7(a)(2) & 7(d) analyses and Critical Habitat
assessments. A copy of this public notice will be sent to the NMFS.
The Corps is not aware of the presence of species listed as threatened or
endangered or their critical habitat formally designated pursuant to the
Endangered Species Act of 1973 (ESA) within the project area. The Corps will
make a final determination on the effects of the proposed project upon additional
review of the project and completion of any necessary biological assessment
and/or consultation with the U.S. Fish and Wildlife Service and/or National
Marine Fisheries Service.
Other Required Authorizations
The Corps forwards this notice and all applicable application materials to the appropriate
State agencies for review.
North Carolina Division of Water Resources (NCDWR): The Corps will generally not
make a final permit decision until the NCDWR issues, denies, or waives the state
Certification as required by Section 401 of the Clean Water Act (PL 92-500). The receipt
of the application and this public notice, combined with the appropriate application fee, at
the NCDWR Central Office in Raleigh constitutes initial receipt of an application for a
401 Certification. Unless NCDWR is granted a time review extension, a waiver will be
deemed to occur if the NCDWR fails to act on this request for certification within sixty
days of receipt of a complete application. Additional information regarding the 401
Certification may be reviewed at the NCDWR Central Office, 401 and Buffer Permitting
Unit, 512 North Salisbury Street, Raleigh, North Carolina 27604-2260. All persons
desiring to make comments regarding the application for a 401 Certification should do so,
in writing, by August 12, 2021 to:
NCDWR Central Office
Attention: Mr. Rick Trone, 401 and Buffer Permitting Unit
(USPS mailing address): 1617 Mail Service Center, Raleigh, NC 27699-1617
Or,
(physical address): 512 North Salisbury Street, Raleigh, North Carolina 27604
Version 6.15.2017 Page 9
North Carolina Division of Coastal Management (NCDCM):
The application did not include a certification that the proposed work complies
with and would be conducted in a manner that is consistent with the approved
North Carolina Coastal Zone Management Program. Pursuant to 33 CFR 325.2
(b)(2) the Corps cannot issue a Department of Army (DA) permit for the
proposed work until the applicant submits such a certification to the Corps and
the NCDCM, and the NCDCM notifies the Corps that it concurs with the
applicant’s consistency certification. As the application did not include the
consistency certification, the Corps will request, upon receipt,, concurrence or
objection from the NCDCM.
Based upon all available information, the Corps determines that this application
for a Department of Army (DA) permit does not involve an activity which would
affect the coastal zone, which is defined by the Coastal Zone Management (CZM)
Act (16 U.S.C. § 1453).
Evaluation
The decision whether to issue a permit will be based on an evaluation of the probable
impacts including cumulative impacts of the proposed activity on the public interest.
That decision will reflect the national concern for both protection and utilization of
important resources. The benefit which reasonably may be expected to accrue from the
proposal must be balanced against its reasonably foreseeable detriments. All factors
which may be relevant to the proposal will be considered including the cumulative effects
thereof; among those are conservation, economics, aesthetics, general environmental
concerns, wetlands, historic properties, fish and wildlife values, flood hazards, flood plain
values (in accordance with Executive Order 11988), land use, navigation, shoreline
erosion and accretion, recreation, water supply and conservation, water quality, energy
needs, safety, food and fiber production, mineral needs, considerations of property
ownership, and, in general, the needs and welfare of the people. For activities involving
the discharge of dredged or fill materials in waters of the United States, the evaluation of
the impact of the activity on the public interest will include application of the
Environmental Protection Agency’s 404(b)(1) guidelines.
Commenting Information
The Corps of Engineers is soliciting comments from the public; Federal, State and local
agencies and officials, including any consolidated State Viewpoint or written position of
the Governor; Indian Tribes and other interested parties in order to consider and evaluate
the impacts of this proposed activity. Any comments received will be considered by the
Corps of Engineers to determine whether to issue, modify, condition or deny a permit for
this proposal. To make this decision, comments are used to assess impacts on
endangered species, historic properties, water quality, general environmental effects and
the other public interest factors listed above. Comments are used in the preparation of an
Environmental Assessment (EA) and/or an Environmental Impact Statement (EIS)
Version 6.15.2017 Page 10
pursuant to the National Environmental Policy Act (NEPA). Comments are also used to
determine the need for a public hearing and to determine the overall public interest of the
proposed activity.
Any person may request, in writing, within the comment period specified in this notice,
that a public hearing be held to consider the application. Requests for public hearings
shall state, with particularity, the reasons for holding a public hearing. Requests for a
public hearing will be granted, unless the District Engineer determines that the issues
raised are insubstantial or there is otherwise no valid interest to be served by a hearing.
The Corps of Engineers, Wilmington District will receive written comments pertinent to
the proposed work, as outlined above, until 5pm, August 20, 2021. Comments should be
submitted to Mr. George Lyle Phillips III, Raleigh Regulatory Field Office,
3331 Heritage Trade Drive, Suite 105 , Wake Forest, North Carolina 27587 , at (919) 554-