HomeMy WebLinkAboutSW3210803_Plansheet - Notes_20210915PART III
SELF -INSPECTION, RECORDKEEPING AND REPORTING
SECTION A: SELF-iNSPEc T ION
Self -inspections are required during normal business hours in accordance with the table
below. When adverse weather or site conditions would cause the safety of the inspection
personnel to be in jeopardy, the inspection may be delayed until the next business day on
which it is safe to perform the inspection. In addition, when a storm event of equal to or
greater than 1.0 inch occurs outside of normal business hours, the self -inspection shall be
performed upon the commencement of the next business day. Any time when inspections
were delayed shall be noted in the Inspection Record.
Frequency
Inspect
(during normal
Inspection records must include:
business hours)
(1) Rain gauge
Daily
Daily rainfall amounts.
maintained in
If no daily rain gauge observations are made during weekend or
good working
holiday periods, and no individual -day rainfall information is
order
available, record the cumulative rain measurement for those un-
attended days (anc this will determine if a site inspection is
needed). Days on which no rainfall occurred shall be recorded as
"zero." The permittee may use another rain -monitoring device
approved by the Division.
(2) E&SC
At least once per
1. Identification of the measures inspected,
Measures
7 calendar days
2. Date and time of the inspection,
and within 24
3. Name of the person performing the inspection,
hours of a rain
4. Indication of whether the measures were operating
P g
event> 1.0 inch in
properly,
24 hours
S. uescription of maintenance needs for the measure,
6. Description, evidence, and date of corrective actions taken.
(3) Stormwater
At least once per
1 Identification of the discharge outfalls inspected,
discharge
7 calendar days
2. Date and time of the inspection,
outfalls (SDCs)
and within 24
3. Name of the person performing the inspection,
hours of a rain
4. Evidence of indicators of Stormwater pollution such as oil
event > 1.0 inch in
sheen, floating or suspended solids or discoloration,
24 hours
5. Indication of visible sediment leaving the site,
6. Description, evidence, and date of corrective actions taken.
(4) Perimeter of
At least once. per
If visible sedimentation is found outside site limits, then a record
site.
7 calendar days
of the following shall be made:
and within 24
1. Actions taken to cleanup or stabilize the sediment that has left
hours of a rain
the site limits,
event > 1.0 inch in
2. Description, evidence, and date of corrective actions taken, and
24 hours
3. An explanation as to the actions taken to control future
releases,
(5) Streams or
At least once per
If the stream or wetland has increased visible sedimentation or a
wetlands onsite
7 calendar days
stream has visible increased turbidity from the construction
or offsite
and within 24
activity, then a record of the following shall be made:
(where
hours of a rain
1. Description, evidence and date of corrective actions taken, and
accessible)
event > 1.0 inch in
2. Records of the required reports to the appropriate Division
24 hours
Regional Office per Part III, Section C, Item (2)(a) of this permit.
(6) Ground
After each phase
1. The phase of grading (installation of perimeter E&SC
stabilization
of grading
measures, clearing and grubbing, installation of storm
measures
drainage facilities, completion of all land -disturbing
activity, construction or redevelopment, permanent
ground cover).
2. Documentation that the required ground stabilization
measures have been provided within the required
timeframe or an assurance that they will be provided as
soon as possible.
NOTE: The rain inspection resets the required 7 calendar day inspection requirement.
PART III
SELF -INSPECTION, RECORDKEEPING AND REPORTING
SECTION B: RECORDKEEPING
1. E&SC Plan Documentation
The approved E&SC plan as well as any approved deviation shall be kept on the site. The
approved E&SC plan must be kept up-to-date throughout the coverage under this permit.
The following items pertaining to the E&SC plan shall be kept on site and available for
inspection at all times during normal business hours.
Item to Document
Documentation Requirements
(a) Each E&SC measure has been installed
Initial and date each E&SC measure on a copy
and does not significantly deviate from the
of the approved E&SC plan or complete, date
locations, dimensions and relative elevztions
and sign an inspection report that lists each
shown on the approved E&SC plan.
E&SC measure shown on the approved E&SC
plan. This documentation is required upon the
initial installation of the E&SC measures or if
the E&SC measures are modified after initial
installation.
(b) A phase of grading has been completed.
Initial and date a copy of the approved E&SC
plan or complete, date and sign an inspection
report to indicate completion of the
construction phase.
(c) Ground cover is located and installed
E&SC
Initial and date a copy of the approved E&SC
-complete, gate
„ a� rda. c ..th the app"owed
plan.
pia„.,, and sign a..
report to indicate compliance with approved
ground cover specifications.
(d) The maintenance and repair
Complete, date and sign an inspection report.
requirements for all E&SC measures
have been performed.
(e) Corrective actions have been taken
Initial and date a copy of the approved E&SC
to E&SC measures.
plan or complete, date and sign an inspection
report to indicate the completion of the
corrective action.
2. Additional Documentation to be Kept on Site
In addition to the E&SC plan documents above, the following items shall be kept on the
site and available for inspectors at all times during normal business hours, unless the
Division provides a site -specific exemption based on unique site conditions that make
this requirement not practical:
(a) This General Permit as well as the Certificate of Coverage, after it is received.
(b) Records of inspections made during the previous twelve months. The permittee shall
record the required observations on the Inspection Record Form provided by the
Division or a similar inspection form that includes all the required elements. Use of
electronically -available records in lieu of the required paper copies will be allowed if
shown to provide equal access and utility as the hard -copy records.
3. Documentation to be Retained for Three Years
All data used to complete the e-NOI and all inspection records shall be maintained for a period
of three years after project completion and made available upon request. [40 CFR 122.41]
PART II, SECTION G, ITEM (4)
DRAW DOWN OF SEDIMENT BASINS FOR MAINTENANCE OR CLOSE OUT
Sediment basins and traps that receive runoff from drainage areas of one acre or more shall use outlet structures that withdraw water from the surface when these devices need to be drawn down
for maintenance or close out unless this is infeasible. The circumstances in which it is not feasible to withdraw water from the surface shall be rare (for example, times with extended cold weather).
Non -surface withdrawals from sediment basins shall be allowed only when all of the following criteria have been met:
(a) The E&SC plan authority has been provided with documentation of the non -surface withdrawal and the specific time periods or conditions in which it will occur. The non -surface withdrawal
shall not commence until the E&SC plan authority has approved these items,
(b) The non -surface withdrawal has been reported as an anticipated bypass in accordance with Part III, Section C, Item (2)(c) and (d) of this permit,
(c) Dewatering discharges are treated with controls to minimize discharges of pollutants from stormwater that is removed from the sediment basin. Examples of appropriate controls include
properly sited, designed and maintained dewatering tanks, weir tanks, and filtration systems,
(d) Vegetated, upland areas of the sites or a properly designed stone pad is used to the extent feasible at the outlet of the dewatering treatment devices described in Item (c) above,
e Velocity dissipation devices such as check dams sediment traps, and ri ra are provided at the discharge points of all dewaterin devices and
() Y p p, riprap p g p g ,
(f) Sediment removed from the dewatering treatment devices described in Item (c) above is disposed of in a manner that does not cause deposition of sediment into waters of the United States.
PART III
SELF -INSPECTION, RECORDKEEPING AND REPORTING
SECTION C: REPORTING
1. Occurrences that Must be Reported
Permittees shall report the following occurrences:
(a) Visible sediment deposition in a stream or wetland.
(b) Oil spills if:
« They are 25 gallons or more,
« They are less than 25 gallons but cannot be cleaned up within 24 hours,
« They cause sheen on surface waters (regardless of volume), or
They are within 100 feet of surface waters (regardless of volume).
(c) Releases of hazardous substances in excess of reportable quantities under Section 311
of the Clean Water Act (Ref: 40 CFR 110.3 and 40 CFR 117.3) or Section 102 of CERCLA
(Ref: 40 CFR 302.4) or G.S. 143-215.85.
(d) Anticipated bypasses and unanticipated bypasses.
(e) Nnnrmmnlianre with the rnnditinns of this nermit that may endanger health or the
environment.
2. Reporting Timeframes and Other Requirements
After a permittee becomes aware of an occurrence that must be reported, he shall contact
the appropriate Division regional office within the timeframes and in accordance with the
other requirements listed below. Occurrences outside normal business hours may also be
reported to the Department's Environmental Emergency Center personnel at (800)
858-0368.
Occurrence
Reporting Timeframes (After Discovery) and Other Requirements
(a) Visible sediment
• Within 14 hours, an oral or electronic notification.
deposition in a
• Within 7 colendardays, a report that contains a description of the
stream or wetland
sediment and actions taken to address the cause of the deposition.
Division staff may waive the requirement for a written report on a
case -by -case basis.
• If the stream is named on the NC 303(d) list as impaired for sediment -
related causes, the permittee may be required to perform additional
monitoring, inspections or apply more stringent practices if staff
determine that additional requirements are needed to assure compliance
with the federal or state impaired -waters conditions.
(b) Oil spills and
« Within 24 hours, an oral or electronic notification. The notification
release of
shall include information about the date, time, nature, volume and
hazardous
location of the spill cr release.
substances per Item
1(b)-(c) above
(c) Anticipated
• A report at least ten days before the date of the bypass, if possible.
bypasses [40 CFR
The report shall include an evaluation of the anticipated quality and
122.41(m)(3)]
effect of the bypass.
(d) Unanticipated
« Within 24 hours, an oral or electronic notification.
bypasses [40 CFR
. Within 7 calendar days, a report that includes an evaluation of the
122.41(m)(3)]
quality and effect of the bypass.
(e) Noncompliance
• Within 24 hours, an oral or electronic notification.
with the conditions
. Within 7 calendardays, a report that contains a description of the
of this permit that
noncompliance, and its causes; the period of noncompliance,
may endanger
including exact dates and times, and if the noncompliance has not
health or the
been corrected, the anticipated time noncompliance is expected to
environmenL[40
continue; and steps taken or planned to reduce, eliminate, and
CFR 122.41(1)(7)]
prevent reoccurrence of the noncompliance. [40 CFR 122.41(I)(6).
• Division staff may waive the requirement for a written report on a
case -by -case basis.
h.
r r
I
�i
Environmental Quality
NCGO1 SELF -INSPECTION, RECORDKEEPING AND REPORTING EFFECTIVE: 04/01/19I
SEEDBED PREPARATION:
1. CHISEL COMPACTED AREAS AND SPREAD TOPSOIL 3 INCHES DEEP OVER ADVERSE SOIL CONDITIONS, IF AVAILABLE.
2. RIP THE ENTIRE AREA TO 6 INCHES DEPTH.
3. APPLY AGRICULTURAL LIME, FERTILIZER, AND SUPER PHOSPHATE UNIFORMLY AND MIX WITH SOIL (SEE SEED SCHEDULE). DO NOT
USE LIME OR FERTILIZER ON STREAM BANKS OR IN WETLAND AREAS. MULCH DOES NOT NEED TO BE USED IN WETLAND AREAS.
4. SEED ON A FRESHLY PREPARED SEEDBED AND COVER SEED LIGHTLY WITH SEEDING EQUIPMENT OR CULTI PACK AFTER SEEDING
5. MULCH IMMEDIATELY AFTER SEEDING AND ANCHOR MULCH.
6. INSPECT ALL SEEDED AREAS AND MAKE NECESSARY REPAIRS OR RESEEDINGS WITHIN THE PLANTING SEASON, IF POSSIBLE. IF
STAND SHOULD BE OVER 60% DAMAGED, REESTABLISH FOLLOWING ORIGINAL LIME, FERTILIZER AND SEEDING RATES.
7. CONSULT CONSERVATION INSPECTOR ON MAINTENANCE TREATMENT AND FERTILIZATION AFTER PERMANENT COVER IS
ESTABLISHED.
PERMANENT SEEDING NOTES:
1. PERMANENT SEEDING, SODDING, OR OTHER MEANS OF STABILIZATION ARE REQUIRED WHEN ALL CONSTRUCTION WORK IS COMPLETED
ACCORDING TO THE "SEEDING STABILIZATION TIMEFRAMES" CHART.
2. A NORTH CAROLINA DEPARTMENT OF AGRICULTURE SOILS TEST (OR EQUAL) SHOULD BE OBTAINED FOR ALL AREAS TO BE SEEDED,
SPRIGGED, SODDED OR PLANTED. RECOMMENDED FERTILIZER AND pH ADJUSTING PRODUCTS SHOULD BE INCORPORATED TO THE SOIL.
3. USE A SEEDING MIX OF NON-INVASIVE, NATIVE SPECIES THAT WILL EVENTUALLY PROVIDE A PERMANENT GROUNDCOVER.
4. IMMEDIATE VEGETATIVE COVER WILL ALWAYS REQUIRE ADDITIONAL FERTILIZATION, SOIL TESTS, OVERSEEDING AND MAINTENANCE UNTIL
PERMANENT VEGETATIVE COVER IS ESTABLISHED.
TEMPORARY SEEDING SPECIFICATION:
TEMPORARY SEEDING RECOMMENDATIONS FOR LATE WINTER AND EARLY SPRING
SEEDING MIXTURE RATE (LB/AC)
RYE (GRAIN) 120
ANNUAL LESPEDEZA (KOBE IN 50
PIEDMONT AND COASTAL
PLAIN, KOREAN IN
MOUNTAINS)
OMIT ANNUAL LESPEDEZA WHEN DURATION OF TEMPORARY COVER IS NOT TO EXTEND BEYOND JUNE
SEEDING DATES:
MOUNTAINS - ABOVE 2500 FEET, FEB. 15 - MAY 15
BELOW 2500 FEET, FEB. 1 - MAY 1
PIEDMONT - JAN. 1 - MAY 1
COASTAL PLAIN - DEC. 1 - APR. 15
SOIL AMENDMENTS:
FOLLOW RECOMMENDATIONS OF SOIL TESTS OR APPLY A MINIMUM OF 2 TONS/ACRE (3 TONS/ACRE IN CLAY SOILS) GROUND
AGRICULTURAL LIMESTONE AND 750 LB/ACRE 10-10-10 FERTILIZER.
MULCH:
APPLY 4,000 LB/ACRE STRAW. ANCHOR STRAW BY TACKING WITH ASPHALT, NETTING, OR A MULCH ANCHORING TOOL. A DISK WITH
BLADES SET NEARLY STRAIGHT CAN BE USED AS A MULCH ANCHORING TOOL.
MAINTENANCE:
RE -FERTILIZE IF GROWTH IS NOT FULLY ADEQUATE. RESEED, RE -FERTILIZE AND MULCH IMMEDIATELY FOLLOWING EROSION OR
OTHER DAMAGE.
B ADDRESSED COMMENTS FROM TOWN OF WEDDINGTON AND NCDEQ 0911012021
A ADDRESSED COMMENTS FROM TOWN OF WEDDINGTON AND NCDOT 0810412021
REV.NO. DESCRIPTIONS DATE
REVISIONS
TEMPORARY SEEDING SPECIFICATION (CONTINUED):
TEMPORARY SEEDING RECOMMENDATIONS FOR SUMMER
SEEDING MIXTURE RATE (LB/AC)
GERMAN MILLET 40
IN THE PIEDMONT AND MOUNTAINS, A SMALL -STEMMED SUDANGRASS MAY BE SUBSTITUTED AT A RATE OF 50 LB/ACRE
SEEDING DATES
MOUNTAINS - MAY 15 -AUG. 15
PIEDMONT - MAY 1 - AUG. 15
COASTAL PLAIN - APR. 15 - AUG. 15
SOIL AMENDMENTS:
FOLLOW RECOMMENDATIONS OF SOIL TESTS OR APPLY A MINIMUM OF 2 TONS/ACRE (3 TONS/ACRE IN CLAY SOILS) GROUND
AGRICULTURAL LIMESTONE AND 750 LB/ACRE 10-10-10 FERTILIZER.
MULCH:
APPLY 4,000 LB/ACRE STRAW. ANCHOR STRAW BY TACKING WITH ASPHALT, NETTING, OR A MULCH ANCHORING TOOL. A DISK WITH
BLADES SET NEARLY STRAIGHT CAN BE USED AS A MULCH ANCHORING TOOL.
MAINTENANCE:
RE -FERTILIZE IF GROWTH IS NOT FULLY ADEQUATE. RESEED, RE -FERTILIZE AND MULCH IMMEDIATELY FOLLOWING EROSION OR
OTHER DAMAGE.
TEMPORARY SEEDING RECOMMENDATIONS FOR FALL
SEEDING MIXTURE RATE (LB/AC)
RYE (GRAIN) 120
SEEDING DATES:
MOUNTAINS - AUG. 15 - DEC. 15
COASTAL PLAIN AND PIEDMONT - AUG. 15 - DEC. 30
SOIL AMENDMENTS:
FOLLOW RECOMMENDATIONS OF SOIL TESTS OR APPLY A MINIMUM OF 2 TONS/ACRE (3 TONS/ACRE IN CLAY SOILS) GROUND
AGRICULTURAL LIMESTONE AND 750 LB/ACRE 10-10-10 FERTILIZER.
MULCH:
APPLY 4,000 LB/ACRE STRAW. ANCHOR STRAW BY TACKING WITH ASPHALT, NETTING, OR A MULCH ANCHORING TOOL. A DISK WITH
BLADES SET NEARLY STRAIGHT CAN BE USED AS A MULCH ANCHORING TOOL.
MAINTENANCE:
REPAIR AND RE -FERTILIZE DAMAGED AREAS IMMEDIATELY. TOPDRESS WITH 50 LB/ACRE OF NITROGEN IN MARCH. IF IT IS
NECESSARY TO EXTEND TEMPORARY COVER BEYOND JUNE 15, OVERSEED WITH 50 LB/ACRE KOBE (PIEDMONT AND COASTAL PLAIN)
OR KOREAN (MOUNTAINS) LESPEDEZA IN LATE FEBRUARY OR EARLY MARCH.
EA
t4 : z,
««4r,
NFKEW&CREED
8020 Tower Point Drive
Charlotte, North Carolina 28227
Phone: (704) 841-2588, Fax: (704) 841-2567
NC License# F-1222
www.mckimcreed.com
GROUND STABILIZATION AND MATERIALS HANDLING PRACTICES FOR COMPLIANCE WITH
THE NCGO1 CONSTRUCTION GENERAL PERMIT
Implementing the details and specifications on this plan sheet will result in the construction
activity being considered compliant with the Ground Stabilization and Materials Handling
sections of the NCGO1 Construction General Permit (Sections E and F, respectively). The
permittee shall comply with the Erosion and Sediment Control plan approved by the
delegated authority having jurisdiction. All details and specifications shown on this sheet
may not apply depending on site conditions and the delegated authority having jurisdiction.
SECTION E: GROUND STABILIZATION
Required Ground Stabilization
Timeframes
Stabilize within this
Site Area Description
many calendar
Timeframe variations
days after ceasing
land disturbance
(a) Perimeter dikes,
swales, ditches, and
7
None
perimeter slopes
(b) High Quality Water
7
None
(HQW) Zones
(c) Slopes steeper than
If slopes are 10' or less in length and are
3:1
7
not steeper than 2:1, 14 days are
allowed
-7 days for slopes greater than 50' in
length and with slopes steeper than 4:1
-7 days for perimeter dikes, swales,
(d) Slopes 3:1 to 4:1
14
ditches, perimeter slopes and HQW
Zones
-10 days for Falls Lake Watershed
-7 days for perimeter dikes, swales,
(e) Areas with slopes
ditches, perimeter slopes and HQW Zones
flatter than 4:1
14
-10 days for Falls Lake Watershed unless
there is zero slope
Note: After the permanent cessation of construction activities, any areas with temporary
ground stabilization shall be converted to permanent ground stabilization as soon as
practicable but in no case longer than 90 calendar days after the last land disturbing
activity. Temporary ground stabilization shall be maintained in a manner to render the
surface stable against accelerated erosion until permanent ground stabilization is achieved.
GROUND STABILIZATION SPECIFICATION
Stabilize the ground sufficiently so that rain will not dislodge the soil. Use one of the
techniques in the table below:
Temporary Stabilization Permanent Stabilization
• Temporary grass seed covered with straw or • Permanent grass seed covered with straw or
other mulches and tackifiers other mulches and tackifiers
• Hydroseeding • Geotextile fabrics such as permanent soil
• Rolled erosion control products with or reinforcement matting
without temporary grass seed • Hydroseeding
• Appropriately applied straw or other mulch • Shrubs or other permanent plantings covered
• Plastic sheeting with mulch
• Uniform and evenly distributed ground cover
sufficient to restrain erosion
....................
Structural methods such as concrete, asphalt or
retaining walls
• Rolled erosion control products with grass seed
POLYACRYLAMIDES (PAMS) AND FLOCCULANTS
1. Select flocculants that are appropriate for the soils being exposed during
construction, selecting from the NC DWR List of Approved PAMS/Flocculants.
2. Apply flocculants at or before the inlets to Erosion and Sediment Control Measures.
3. Apply flocculants at the concentrations specified in the NC DWR List of Approved
PAMS/Flocculants and in accordance with the manufacturer's instructions.
4. Provide ponding area for containment of treated Stormwater before discharging
offsite.
5. Store flocculants in leak -proof containers that are kept under storm -resistant cover
or surrounded by secondary containment structures.
EQUIPMENT AND VEHICLE MAINTENANCE
1. Maintain vehicles and equipment to prevent discharge of fluids.
2. Provide drip pans under any stored equipment.
3. Identify leaks and repair as soon as feasible, or remove leaking equipment from the
project.
4. Collect all spent fluids, store in separate containers and properly dispose as
hazardous waste (recycle when possible).
5. Remove leaking vehicles and construction equipment from service until the problem
has been corrected.
6. Bring used fuels, lubricants, coolants, hydraulic fluids and other petroleum products
to a recycling or disposal center that handles these materials.
LITTER, BUILDING MATERIAL AND LAND CLEARING WASTE
1. Never bury or burn waste. Place litter and debris in approved waste containers.
2. Provide a sufficient number and size of waste containers (e.g dumpster, trash
receptacle) on site to contain construction and domestic wastes.
3. Locate waste containers at least 50 feet away from storm drain inlets and surface
waters unless no other alternatives are reasonably available.
4. Locate waste containers on areas that do not receive substantial amounts of runoff
from upland areas and does not drain directly to a storm drain, stream or wetland.
5. Cover waste containers at the end of each workday and before storm events or
provide secondary containment. Repair or replace damaged waste containers.
6. Anchor all lightweight items in waste containers during times of high winds.
7. Empty waste containers as needed to prevent overflow. Clean up immediately if
containers overflow.
8. Dispose waste off -site at an approved disposal facility.
9. On business days, clean up and dispose of waste in designated waste containers.
PAINT AND OTHER LIQUID WASTE
1. Do not dump paint and other liquid waste into storm drains, streams or wetlands.
2. Locate paint washouts at least 50 feet away from storm drain inlets and surface
waters unless no other alternatives are reasonably available.
3. Contain liquid wastes in a controlled area.
4. Containment must be labeled, sized and placed appropriately for the needs of site.
5. Prevent the discharge of soaps, solvents, detergents and other liquid wastes from
construction sites.
PORTABLE TOILETS
1. Install portable toilets on level ground, at least 50 feet away from storm drains,
streams or wetlands unless there is no alternative reasonably available. If 50 foot
offset is not attainable, provide relocation of portable toilet behind silt fence or place
on a gravel pad and surround with sand bags.
2. Provide staking or anchoring of portable toilets during periods of high winds or in high
foot traffic areas.
3. Monitor portable toilets for leaking and properly dispose of any leaked material.
Utilize a licensed sanitary waste hauler to remove leaking portable toilets and replace
with properly operating unit.
EARTHEN STOCKPILE MANAGEMENT
1. Show stockpile locations on plans. Locate earthen -material stockpile areas at least
50 feet away from storm drain inlets, sediment basins, perimeter sediment controls
and surface waters unless it can be shown no other alternatives are reasonably
available.
2. Protect stockpile with silt fence installed along toe of slope with a minimum offset of
five feet from the toe of stockpile.
3. Provide stable stone access point when feasible.
4. Stabilize stockpile within the timeframes provided on this sheet and in accordance
with the approved plan and any additional requirements. Soil stabilization is defined
as vegetative, physical or chemical coverage techniques that will restrain accelerated
erosion on disturbed soils for temporary or permanent control needs.
fm /
f-,
i P�.i i " nvironmentat Quality
NCGOI GROUND STABILIZATION AND MATERIALS HANDLING
PERMANENT SEEDING SPECIFICATION:
3:1 SLOPES OR FLATTER:
1. APPLY AGRICULTURAL LIME AT THE RATE OF "75 LBS/1000 S.F.
2. APPLY COMMERCIAL FERTILIZER AT THE RATE OF 48 LBS/1000 S.F. FOR 5-10-10
FERTILIZER, 24 LBS/1000 S.F. FOR 10-20-20 FERTILIZER, OR 20 LBS/1000 S.F. FOR 18-24-6 FERTILIZER.
3. SEED IN ACCORDANCE WITH THE FOLLOWING SCHEDULE AND APPLICATION RATES:
DATE: TYPE: PLANTING RATE:
AUG. 15 - NOV. 1 TALL FESCUE 300 LBS/AC OR 7 LBS/1000 S.F.
RYE GRAIN 120 LBS/AC OR 3 LBS/1000 S.F.
NOV. 1 - MAR. 1' TALL FESCUE AND 300 LBS/AC OR 7 LBS/1000 S.F.
ABRUZZI RYE 25 LBS/AC OR 1/2 LB/1000 S.F.
MAR. 1 -APR. 15 TALL FESCUE 300 LBS/AC OR 7 LBS/1000 S.F.
APR. 15 - JUL. 30 HULLED COMMON
BERMUDA GRASS 25 LBS/AC OR 1/2 LB/1000 S.F.
JUL. 1 -AUG. 15 TALL FESCUE AND 300 LBS/AC OR 7 LBS/1000 S.F.
BROWN TOP MILLET 35 LBS/AC OR 3/4 LB/1000 S.F.
OR SORGHUM SUDAN
HYBRIDS 30 LBS/AC OR 3/4 LB/1000 S.F.
4. MULCH WITH STRAW APPLIED AT THE RATE OF 95 LBS/1000 S.F.
HEAVILY MULCHED DURING JANUARY - MARCH PERIOD.
CONTRACTOR MAY OBTAIN SOIL TEST TO DETERMINE AMOUNT OF LIME REQUIRED TO OBTAIN A pH RANGE OF 6.5 TO 7.0.
SEED TYPE, RATES AND/OR SOIL AMENDMENTS SPECIFIED ABOVE MAY BE MODIFIED AND/OR ELIMINATED IF REQUIRED BY OTHER
LOCAL, STATE OR FEDERAL AGENCIES (EG. NRCS, NC COOPERATIVE EXTENSION OFFICE, ETC.). PRIOR TO MODIFICATIONS OR
ELIMINATIONS, CONTRACTOR SHALL SUBMIT WRITTEN DOCUMENTATION SUPPORTING THE REQUEST FOR APPROVAL PRIOR TO MAKING
MODIFICATION.
SLOPES GREATER THAN 3:1
1. APPLY AGRICULTURAL LIME AT A RATE OF "90 LBS/1000 S.F.
2. APPLY COMMERCIAL FERTILIZER AT THE RATE OF 48 LBS/1000 S.F. FOR 5-10-10
FERTILIZER, 24 LBS/1000 S.F. FOR 10-20-20 FERTILIZER, OR 20 LBS/1000 S.F. FOR 18-24-6 FERTILIZER.
3. SEED IN ACCORDANCE WITH THE FOLLOWING SCHEDULE AND APPLICATION RATES:
DATE: TYPE: PLANTING RATE:
MAR. -JUN. 1 SERICEA LESPEDEZA 50 LBS/AC OR 1 1/2 LBS/1000 S.F.
RYE GRAIN 25 LBS/AC OR 3/4 LBS/1000 S.F.
(SCARIFIED) AND
MAR. -APR. 1 ADD TALL FESCUE 150 LBS/AC OR 3 1/2 LBS/1000 S.F.
JUN. - SEPT. 1"' TALL FESCUE AND 120 LBS/AC OR 2 1/2 LBS/1000 S.F.
BROWN TOP MILLET 35 LBS/AC OR 3/4 LB/1000 S.F.
OR SORGHUM SUDAN
HYBRIDS 30 LBS/AC OR 3/4 LB/1000 S.F.
SEPT. - MAR. 1 SERICEA LESPEDEZA 70 LBS/AC OR 1 3/4 LBS/1000 S.F.
(UNHULLED - UNSCARIFIED)
TALL FESCUE 120 LBS/AC OR 2 1/2 LBS/1000 S.F.
MILLET OR SUDAN 20 LBS/AC OR 1/2 LB/1000 S.F.
4. MULCH APPLIED AT THE RATE OF 95 LBS/1000 S.F. AND ANCHOR WITH ASPHALT EMULSION TACK COAT APPLIED AT THE RATE OF 10-15
GAU1000 S.F. OR 450 GAUAC.
TEMPORARY RESEED SEPT. 1 AT RECOMMENDED RATES.
CONTRACTOR MAY OBTAIN SOIL TEST TO DETERMINE AMOUNT OF LIME REQUIRED TO OBTAIN A pH RANGE OF 6.5 TO 7.0.
SEED TYPE, RATES AND/OR SOIL AMENDMANTS SPECIFIED ABOVE MAY BE MODIFIED AND/OR ELIMINATED IF REQUIRED BY OTHER
LOCAL, STATE OR FEDERAL AGENCIES (EG. NRCS, NC COOPERATIVE EXTENSION OFFICE, ETC.). PRIOR TO MODIFICATIONS OR
ELIMINATIONS, CONTRACTOR SHALL SUBMIT WRITTEN DOCUMENTATION SUPPORTING THE REQUEST FOR APPROVAL PRIOR TO MAKING
MODIFICATION.
CONCRETE WASHOUTS
1. Do not discharge concrete or cement slurry from the site.
2. Dispose of, or recycle settled, hardened concrete residue in accordance with local
and state solid waste regulations and at an approved facility.
3. Manage washout from mortar mixers in accordance with the above item and in
addition place the mixer and associated materials on impervious barrier and within
lot perimeter silt fence.
4. Install temporary concrete washouts per local requirements, where applicable. If an
alternate method or product is to be used, contact your approval authority for
review and approval. If local standard details are not available, use one of the two
types of temporary concrete washouts provided on this detail.
5. Do not use concrete washouts for dewatering or storing defective curb or sidewalk
sections. Stormwater accumulated within the washout may not be pumped into or
discharged to the storm drain system or receiving surface waters. Liquid waste must
be pumped out and removed from project.
6. Locate washouts at least 50 feet from storm drain inlets and surface waters unless it
can be shown that no other alternatives are reasonably available. At a minimum,
install protection of storm drain inlet(s) closest to the washout which could receive
spills or overflow.
7. Locate washouts in an easily accessible area, on level ground and install a stone
entrance pad in front of the washout. Additional controls may be required by the
approving authority.
8. Install at [east one sign directing concrete trucks to the washout within the project
limits. Post signage on the washout itself to identify this location.
9. Remove leavings from the washout when at approximately 75% capacity to limit
overflow events. Replace the tarp, sand bags or other temporary structural
components when no longer functional. When utilizing alternative or proprietary
products, follow manufacturer's instructions.
10. At the completion of the concrete work, remove remaining leavings and dispose of
in an approved disposal facility. Fill pit, if applicable, and stabilize any disturbance
caused by removal of washout.
HERBICIDES, PESTICIDES AND RODENTICIDES
1. Store and apply herbicides, pesticides and rodenticides in accordance with label
restrictions.
2. Store herbicides pesticides and rodenticides in their original containers with the
,p
label, which lists directions for use, ingredients and first aid steps in case of
accidental poisoning.
3. Do not store herbicides, pesticides and rodenticides in areas where flooding is
possible or where they may spill or leak into wells, stormwater drains, ground water
or surface water. If a spill occurs, clean area immediately.
4. Do not stockpile these materials onsite.
IIAZARDOUS AND TOXIC WASTE
1. Create designated hazardous waste collection areas on -site.
2. Place hazardous waste containers under cover or in secondary containment.
3. Do not store hazardous chemicals, drums or bagged materials directly on the ground
EFFECTIVE: 04/01 / 19
WETLAND / RIPARIAN SEEDING SPECIFICATION:
Botanical Name
Common Name
% Mix
Panicumrigidulum
Red -top panicgrass
20
Schizachyrium scoparium
Camper little blue stem
20
Coreopsis lanceolata
Lance -leaved coreopsis
10
Rudbeckia hirta
Black-eyed Susan
10
Chamaecrista fasiculata
Partridge pea
5
Panicumanceps
Beaked panicgrass
5
Chasmanthium latifolium
River oats
3
Dichantheliumclandestinum
Deer tongue
3
Elymus virginicus
Virginia wild rye
3
Heleniumautumnale
Common sneezeweed
3
11chanthus angustifolius
Swamp sunflower
3
Partheniumintegrifolium
Wild quinine
3
Penstemon laevigatus
Appalachian beardtongue
3
Tridens flavus
Purple top
3
Monarda punctata
Spotted beebalm
2
Venlonia noveboracencis
Ironweed
2
Aglvstis perennans
Upland bentgrass
1
Bidens aristosa
Tickseed sunflower
1
NOTES:
1. THE LIST SHOWN ABOVE PROVIDES A SEEDING MIX CONTRACTORS CAN USE IF WETLANDS OR RIPARIAN BUFFERS ARE DISTURBED DURING
CONSTRUCTION.
2. RESOURCES SHOWN HEREIN REPRESENT THE ENGINEERS BEST EFFORT TO PROVIDE AN ADEQUATE SOLUTION. HOWEVER, CONTRACTOR
SHALL REFER TO THE APPROVED 401/404 PERMITS TO ENSURE ALL REQUIREMENTS ARE ADHERED TO DURING CONSTRUCTION.
3. CONTRACTOR SHALL NOT IMPACT ANY WETLANDS OR STREAMS OUTSIDE THE 401/404 PERMIT.
BELLE MAR RESIDENTIAL
0 OLD MILL ROAD
TOWN OF WEDDINGTON, NC
NCDEQ NOTES
r
DATE:
MAY 2021
MCE PROJ. #
07780-0013
DRAWN
JPM
DESIGNED
JPM
CHECKED
PMN
PROJ. MGR.
PMN
SCALE
HORIZONTAL:
N/A
VERTICAL:
N/A
C1.2
DRAWING NUMBER
GN
REVISION
STATUS: PRELIMINARY DRAWING
NOT FOR CONSTRUCTION
I:\07780\0013\PDNR\80-DWG\86-DESIGN\PLAN SHEETS\C1.1 NOTES.DWG - - - - 09/10/2021 16:22:56
LEGEND
0 ANGLE IRON STORM DRAIN MANHOLE
0 AXLE YARD INLET
9.E ARC=258.65 0 IRON PIPE FND CLEAN OUT
N: 464873.65--'" IRF R=1384.10 0 IRON ROD FND SANITARY SEWER MANHOLE
E: 147246180 D=10*42'23" 0 IRON ROD SET SEPTIC TANK
WATER VALVE
CH BRG=S 55-11'34" E NAIL FND
< CH LENGTH=258.25 cS FIRE HYDRANT
Fl CONCRETE MON FND
10 ELECTRIC BOX
+ COMPUTED POINT
ELECTRIC METER
REBAR AND CAP
-0- GUY POLE
00 RIGHT OF WAY MON
GUY WIRE
MAILBOX LIGHT POLE
FLAGPOLE c- POWER AND LIGHT POLE
SIGN # POWER POLE
wir
9 WELL ELECTRIC TRANSFORMER
Lz 0
z
GAS METER
0CATCH BASIN
D8 ?M PC 395
DROP INLET GAS VALVE
PC 0 PC 3#4 40
,v .v
-0615:50o�q
x
/N/F/
Hm "REAL /ESTA
D -349'8 PG 7! v
5�C'
16,996,-A60ES_
A .,.,.SATE CF�
Xx
o
IPF
0
co.
cv,
��___-__�-/ �,� �r � / f'1�I��I@�@I� III ICIj� 1 ��\��t��,v°,v�v''`�����'�, _,/ 0
X,
f
MARY N 97Z Er AL
DS 9V PO
.17T
IPF
N 0
x
, x \
co
4x
LrriW
X,cti
V
0)
0)
Z
co -7.
oll
Ir
SIV
0)
7, PA
-J
-- ---- go-
EK W000S
.v
685—
is
ZF
310.60
'
' 'Nl . .....
3,2 9'14 W 356.20 21
MA r0rA0E5w4Y78 mPC w77m7 w MAW7 \1 PF 262.80
REVISIONS 83t4'31 28395OTAL),
/pr BY DATE DESCRIPTION
OWSMANIaW HEDGES
00 78f6 PG 793 0615"o
DANNY rSMO"
W OW M 875
NN
100 0 100 200
GRAPHIC SCALE (IN FEET)
1 inch = 100 ft.
AF
0
WZ
O
O
GAS MARKER
ITI
TELEPHONE PEDESTAL
Cj
TV PEDESTAL
01
BUSH
PINE TREE
DECIDUOUS TREE
VICINITY MAP
NOTTO SCALE
1. ALL DISTANCES ARE HORIZONTAL GROUND IN U.S. SURVEY
FEET UNLESS OTHERWISE SHOWN.
2. BEARINGS BASED ON NORTH CAROLINA STATE PLANE COORDINATES
NAD83 (2011), VERTICAL ELEVATIONS ARE BASED ON NAVD88.
3. SURVEYOR HAS MADE NO INVESTIGATION OR INDEPENDENT
SEARCH FOR EASEMENTS OF RECORD, ENCUMBRANCES,
RESTRICTIVE COVENANTS, OWNERSHIP, TITLE EVIDENCE, OR
ANY OTHER FACTS THAT AN ACCURATE AND CURRENT TITLE
SEARCH MAY DISCLOSE.
4. UNDERGROUND UTILITIES ARE SHOWN ONLY WHERE ABOVEGROUND
SERVICES WERE VISIBLE.
5. SUBSURFACE AND ENVIRONMENTAL CONDITIONS WERE NOT
EXAMINED OR CONSIDERED AS A PART OF THIS SURVEY. NO
STATEMENT IS MADE CONCERNING THE EXISTENCE OF
UNDERGROUND OR OVERHEAD CONTAINERS OR FACILITIES
THAT MAY AFFECT THE USE OR DEVELOPMENT OF THIS TRACT,
6. THE EXISTENCE OR NONEXISTENCE OF WETLANDS ON
SUBJECT PROPERTY HAS NOT BEEN DETERMINED BY THIS SURVEY.
7. SUBJECT TO ALL EASEMENTS, RIGHT OF WAYS, AND OR
ENCUMBRANCES THAT MAY EFFECT THIS PROPERTY.
SURVEYORS CERTIFICATE
1, W. ANDREW EADES, CERTIFY THAT THIS PROJECT WAS COMPLETED UNDER MY DIRECT AND
RESPONSIBLE CHARGE FROM AN ACTUAL SURVEY MADE UNDER MY SUPERVISION; THAT THIS
GROUND SURVEY WAS PERFORMED 95 PERCENT CONFIDENCE LEVEL TO MEET FEDERAL
GEOGRAPHIC DATA COMMITTEE ACCURACY OF CLASS A AND VERTICAL ACCURACY WI-IEN
APPLICABLE TO THE CLASS B STANDARD, AND THAT THE ORIGINAL DATA WAS OBTAINED ON
AUGUST 8,2020; THAT THE SURVEY WAS COMPLETED ON SEPTEMBER 9,2020; THAT CONTOURS
SHOWN MAY NOT MEET THE STATED STANDARD: AND ALL COORDINATES ARE BASED ON NAD83
(2011) AND REALIZATION AND ELEVATIONS ARE BASED ON NAVD88.
WITNESS MY ORIGINAL SIGNATURE, REGISTRATION NUMBER AND SEAL THIS 9TH DAY OF JULY,
2021.
C A
W. ANDREW EADES, PLS L-3413 DATE: 07-09-21 Esslo s
S EAL
L-3413
c)
su
E
Iffillimill]
EXISTING CONDITIONS SURVEY
�n]'M=kVAF,milil
CITY OF WEDDINGTON UNION COUNTY, NC
SCALE: 1 100' —�DATE: JULY 9, 2021
A '
PLS WAE 4-A NfM4& ED JOB 800NO.
49$� 8020 TOWER POINT DRIVE — 077007
TECH SHEET NO.
A C G CHARLOTTE, NORTH CAROLINA 28227
TELEPHONE: (704) 841-2588
C H K E D FAX: (704) 841-2567
WEHI NORTH CAROLINA FIRM LICENSE NUMBER: F- 1222 OF