HomeMy WebLinkAbout20211077 Ver 1_WRC Comments_202108189 North Carolina Wildlife Resources Commission 9 Cameron Ingram, Executive Director August 18, 2021 Ms. Amanda Fuemmeler U.S. Army Corps of Engineers, Regulatory Branch 151 Patton Avenue, Room 208 Asheville, North Carolina 28801-5006 SUBJECT: 20 South Bear Creek UT to Hominy Creek, Buncombe County Dear Ms. Fuemmeler: Biologists with the North Carolina Wildlife Resources Commission (NCWRC) reviewed an application to culvert 60 ft of an unnamed tributary (UT) to Hominy Creek, fill 0.018 acre of wetland, and temporarily impact 30 ft of stream and 0.004 acre of wetland in Buncombe County. Our comments on this application are offered for your consideration under provisions of the Clean Water Act of 1977 (33 U.S.C. 466 et. seq.) and Fish and Wildlife Coordination Act (48 Stat. 401, as amended; 16 U.S.C. 661-667d). Wild trout reproduction should not be impacted by the project, and a trout moratorium is not needed. However, Blotched Chub (Erimystax insignis, NC Significantly Rare) is found downstream of the project, and effective erosion and sediment control on site is important to conserve habitat for this species. The project application proposes to culvert the stream with two 72-inch culverts. Double culverts set at the same elevation often result in one culvert carrying most or all of the flows over time; this can cause channel instability and problems with aquatic organism passage. We recommend replacing the double culverts with a spanning structure such as a bridge or bottomless arch instead. If a culvert must be used, we recommend using a single larger squash (or elliptical) pipe capable of carrying base and stormflows, possibly with a floodplain culvert placed at a higher elevation to pass flood flows. In addition, culvert material is not specified. We recommend against slick -walled high -density polyethylene (HDPE) and reinforced concrete, as these materials are smooth and are less likely to retain substrate and allow passage of aquatic organisms like salamanders and crayfish. Mailing Address: Habitat Conservation • 1721 Mail Service Center • Raleigh, NC 27699-1721 Telephone: (919) 707-0220 • Fax: (919) 707-0028 20 South Bear Creek Page 2 August 18, 2021 UT to Hominy Creek, Buncombe Co It also appears that part of the development will be in the 100-year floodplain. The NCWRC does not support commercial or residential development within the 100-year floodplain. The filling of floodplains increases the potential for flooding and degrades in -stream habitats for fish and other aquatic organisms. We offer the following recommendations to minimize impacts to fish and wildlife: 1. In -channel work should be accomplished as quickly as possible and vigilance used in sediment and erosion control during site preparation, construction, and clean up. Disturbed areas should be seeded, mulched and/or matted as soon as possible, preferably at the end of each workday. 2. Any erosion control matting used should be free of plastic or nylon mesh, as this type of mesh frequently entangles wildlife and is slow to degrade, resulting in a hazard that may last for years. 3. We recommend that the stream running through the property be planted with a riparian buffer at least 30 ft in width comprised of native trees, shrubs, and herbaceous vegetation. In addition, we recommend widening the buffer on Hominy Creek to at as wide as possible and using this area as green space. A wide forested buffer can ensure greater bank stability, filter overland pollutants, and provide habitat for birds and other wildlife. 4. We strongly recommend using a spanning structure such as a bridge or arch pipe; if a culvert must be used, we recommend a single corrugated squash/elliptical pipe, possibly with an additional floodplain culvert set at a higher elevation. In addition, smooth -walled culvert material should not be used. 5. If temporary wetland impacts involve heavy equipment access, then equipment should work from mud mats to lessen wetland soil compaction. 6. Effective stormwater management is essential in minimizing impacts to downstream waters. Stormwater control measures should mimic the hydrograph consistent with an impervious coverage of less than 10%. We recommend the use of Low Impact Design techniques, such as grassed swales and pervious pavement; curb and gutter, catch basins, and underground piping of stormwater should be avoided. As stormwater runoff from pavement can cause short-term temperature spikes in downstream waters, mechanisms to lower stormwater temperature should be incorporated into the stormwater management design. Thank you for the opportunity to review and comment on this project. Please contact me at (828) 400-4223 if you have any questions about these comments. Sincerely, Andrea Leslie Mountain Region Coordinator, Habitat Conservation Program ec: Jon Swaim, McGill Associates Andrew Moore, NC Division of Water Resources NOTES SEE GRADING, EROSION CONTROL, AND STORM DRAINAGE DETAIL SHEETS FOR ALL GENERAL NOTES. CONTRACTOR RESPONSIBLE FOR INCLUSION OF DETAILS SHEETS WITH ALL PLANS. 2. SOME PORTION OF THIS PROJECT LIES WITHIN THE 100-YR FEMA FLOODPLAIN. 3. SOIL TYPE: IoA, UhE, EwD, CsD, BkD2, BkC2, EvD2, Ew, EwE, TsA. 4. TO SCHEDULE THE REQUIRED INSPECTIONS ON ALL WORK, CALL THE CIVIL DESIGN CONCEPTS INSPECTIONS HOTLINE AT 828-771-4755, OR EMAIL AT INSPECTIONSOCDCGO.COM. FAILURE TO SCHEDULE INSPECTIONS MAY RESULT IN UNCOVERING OR REDOING WORK 5. RETAINING WALLS: ALL RETAINING WALL ELEVATIONS SHOWN ARE FROM TOP OF WALL TO FINISH GRADE ELEVATION. CONTRACTOR TO ACCOUNT FOR FOOTER/COVER OVER FOOTER. REFER TO WALL DESIGN FOR FOOTER DESIGN. WALL DESIGN TO ALSO ACCOMMODATE STORM PIPE PENETRATIONS PER PLANS. WALL DESIGN TO INCLUDE FOOTING DRAIN AND MINIMUM WIDTH OF 12" OF #57 WASHED STONE BEHIND WALL FROM BOTTOM TO TOP OF WALL. ALL RETAINING WALLS PROVIDING A CHANGE OF GRADE OF 30" OR MORE SHALL BE PROTECTED WITH A GUARDRAIL. THE GUARDRAIL SHALL BE 42" MINIMUM IN HEIGHT, AND PREVENT THE PASSAGE OF A 21" SPHERE UNLESS ADJACENT TO A WALKING SURFACE. COORDINATE BARRIER STYLE AND COLOR WITH ARCHITECT AND ENGINEER. SEE SITE PLAN FOR APPROXIMATE LOCATION OF FENCING/BARRIERS. CONTRACTOR TO SUBMIT TO OWNER AND ENGINEER FOR REVIEW PRIOR TO ORDERING MATERIALS. CONTRACTOR TO COORDINATE WALL STYLE AND COLOR WITH ARCHITECT AND ENGINEER. CONTRACTOR RESPONSIBLE FOR OBTAINING BUILDING PERMIT FOR ALL RETAINING WALLS PRIOR TO ORDERING MATERIALS OR CONSTRUCTION. CONTRACTOR RESPONSIBLE FOR CONSTRUCTING RETAINING WALLS IN ACCORDANCE WITH ALL WALL MANUFACTURERS STANDARDS AND SPECIFICATIONS. ALL RETAINING WALLS 4' OR GREATER TO BE SUBMITTED TO BUNCOMBE COUNTY BUILDING SAFETY DIVISION FOR REVIEW AND APPROVAL AND CERTIFIED BY THE WALL ENGINEER UPON COMPLETION. RETAINING WALLS SUBJECT TO ADDITIONAL LANDSCAPING DEPENDING ON HEIGHT AND MATERIAL. � I I F4 \ \ I y `� °w oo A DS D9I I I II �ll 11 I \ V A \V \ D7 PROPERTY LINE (TYP) PROPOSED DOUBLE 48" PERMANENT HDPE PIPE ®� 1 I l I j 6 00 CULVERT WETLAND CROSSING. PIPE INVERT TO \ I I ( I BE BURIED 12" BELOW STREAM BED LESSER \ I I OF, ONE FOOT OR 2OX PIPE DIAMETER). (CONTRACTOR TO FOLLOW REQUIREMENTS OF \ I I I I USACE & NCDEQ) (SEE DETAIL & SHEETS \ I II II I I ICD C507-0509 FOR TABLE) I I I I II III I I I N I �� I II II I J1 PROPOSED STORM PIPE (TYP) (SEE DETAIL & SHEETS 1 C507-0509 FOR TABLE) \ D10 I \ \ \ \ PROPOSED STORM STRUCTURE \ \ TYP SEE DETAIL &SHEETS \ C507-0509 FOR TABLE)! \ V A \� o D6 0010% T� PROPOSED CONTROL STRUCTURE 'D1' / N ZO D�VA�vv� vv vvv AV A v SEE DETAIL /CD to PROPOSED BIO-RETENTION CELL 'G'� (SEE SHEET C955) W LU co CIO) 0 o Z1 PROPOSED RIP RAP APRON 'J' _ \ I f \ _ � A LENGTH: 10' ' D4 i� WIDTH AT START: 9' \ W -- - _ — — — � � �, I WIDTH AT END: 13 W - _ DEPTH: 18" _ � I I STONE CLASS: B I (SEE DETAIL) � 1 I o I - --- --- 2008 W— \I,DO --- D 1 N\ \ \ I \ a 2028- 1 I \ \ FLOODPLAIN (TYP) <00 ,. . . i t •tom t � J / � . \ � 0 l o � / i N r i r i r i r i r i r i B1 ' 1 o B 0 100 i EXISTING WETLAND - - PROPOSED DRY DETENTION PON cn (SEE SHEET C952) V) / PROPOSED CONTROL STRUCTURE 'B1' / (SEE DETAIL) 0 i r i r i r i r r r r r r r r r r r r r I MATCHLINE (S`E SHEET C503) 7/' / F2 I Fn I I I I� / NI I I I IlloCD I I IIIE V7 I N N II EXISTING STRE�(Typ) I D I II II \ \ FLOODPLAIN (TYP) I\ \ \ NI 00 STREAM BUFFER TYP N W � OD LO 0) to 0 Ln DCCOCIDZ WnCOvv SUBJECT 00 Cli0 W N N N C" PROPERTY Z z N N Z a -it�� c m O J W W W J as W X W X R° o N� a W ¢ z�WLLL =LL soN L �aa \ ZQa INTERSTATE O INTERSTATE 240 cm ID2 GLO 1 I I I / \\ I I 000 II �� II I I I I II — -- - I I — 2090 — W _-- CD 2080 PROPOSED 2' — - _ -- -- W CONTOURS (TYP) — — — -- - -, W ---- � — — — 2070 PROPOSED PERMANENT DRAINAGE DITCH "D" — — — — _ — �_ _ _ \ — — — — — `OO BOTTOM WIDTH: 4' SIDE SLOPE: 2:1 — — � \� DEPTH: 1' -----_-- W SLOPE: 2% MIN. 2060 \ CHANNEL LINER: C125BN - — — — — — — \ \ (SEE SHEET C936)- ---- J \ CONTRACTOR TO MAINTAIN 2050 , T PREVIOUSLY INSTALLED CHECK _ --- \ \ v DAM (TYP) (SEE DETAIL) -- \ PROPOSED PERMANENT DRAINAGE DITCH "C" BOTTOM WIDTH: 4' SIDE SLOPE: 2:1 DEPTH: 1' SLOPE: 2% MIN. DEVELOPMENT DATA OWNER/DEVELOPER: CONTACT: CIVIL ENGINEER: CONTACT: SURVEYOR: CONTACT: PROJECT DATA m BEAR VICINITY MAP (NOT TO SCALE) CROSSROADS COMMUNITY VENTURE, LLC 330 FRANKLIN ROAD BRENTWOOD, TN 37027 SEAN MCGUIRE (615) 727-7949 CIVIL DESIGN CONCEPTS, P.A. 168 PATTON AVENUE ASHEVILLE, NC 28801 WARREN SUGG, P.E. (828) 252-5388 ED HOLMES & ASSOCIATES, P.A. 300 RIDGEFIELD COURT, SUITE 301 ASHEVILLE, NC 28806 JOSHUA E. HOLMES (828) 225-6562 PIN: 9627-89-6780 ADDRESS: 20 S. BEAR CREEK ROAD DEED BOOK/PAGE: 5453/963 SITE ACREAGE: 55.40 ACRES ZONING: PS - PUBLIC SERVICE SETBACKS: FRONT: 20' SIDES: 10' REAR: 20' DISTURBED AREA: 35.74 AC PROPOSED UNITS: 660 MULTI -FAMILY RESIDENTIAL UNITS DENSITY SUMMARY: ALLOWED: 12.0 UNITS/ACRE PROPOSED: 11.9 UNITS/ACRE = 660 UNITS EXISTING USE: RESIDENTIAL/VACANT PROPOSED USE: MULTI -FAMILY RESIDENTIAL PARKING CALCULATIONS: 1.75:1 MULTI -FAMILY RESIDENTIAL 1.10:1 SENIOR HOUSING RESIDENTIAL PROJECT AREA IMPERVIOUS CALCULATIONS: IMPERVIOUS PERVIOUS PRE -DEVELOPMENT: 0.00 ACRES (0%) 35.74 ACRES (100%) POST -DEVELOPMENT: 1.25 ACRES (3.5%) 34.49 ACRES (96.5%) STORM LEGEND EXISTING STORM PIPE PROPOSED STORM PIPE ■ ■ PROPOSED HEADWALL PROPOSED INLET STRUCTURE CQ PROPOSED JUNCTION BOX O PROPOSED DETENTION STRUCTURE OO PROPOSED FLARED END SECTION PROPOSED RIP —RAP APRON Know what's below. Call before you dig. NORTH PHASE I STORM DRAINAGE PLAN GRAPHIC SCALE 40 0 20 40 80 ( IN FEET ) 1 inch = 40 ft. m J Q m D cn U w U m 0 U Q y Q. a C 0 N U _ 2 (.) > �Cn a U Z 4) 0 3 V�V 3 00 T N U W W z W U J Cl) J W m 0 z rlm z 0 k- U w p N 0 NLLJ Q N p _n 0 o z /v Q z J 0 Q 0 0 z z} z 0 0 w m C) 5 0 G 0 O z D m U U J � �/A/ J OW U / W m z D Q F- � z m w > Q < � z It z Q D o V, o 0 U)♦^ O Q 0 m w cn cn cn Q o V U DRAWN BY: CDC CDC PROJECT NO.: 11925 BC PERMIT NO. N/A SHEET i I C502 2030- 2030 2020— 020 2030 PROPOSED GRADE 2030 PROPOSED GRADE PE ® 7.6% 24LF-15" HDPE @ 6.5% PROPOSED GRADE 70LF-15" HDPE ® 0.5% PROPOSED GRADE (CHURCH DRIVE) 2020 (ROAD A) 2020 201 010 2020 2020 46LF-15" HDPE 0 0.5% 92LF-48" HDPE ® 0.5% 84LF-48" DPE ® 0.5% 87LF-48" HDPE @0.5% 2010- 0 200 r 0 I I r ^ EXISTING GRADE N -H 00 NOo (0r- NI�0 +per r O N} 7 0 0 Z 1990 0Q� �Q0 Qf�O> o ��z a_ V) 1980 O O o o O o O N STORM LINE Y 2010 200 2000 2010-- '� Q N Q ^ a Q - 2010 Q I Q N Q I I O N \Qi ro Q v � vr10 v HDPE PIPE Q N v `. oLEXISTING 9 o ,�i o +I o N EXISTING o rn ��O N00ro N "Oo `� o�oaMiN ~ / __ .. +10 +�N+3 ro ON It GRADE N �o aooNzQo QN�N M� O O+�N �� p� O NZ p O r 2000 199 °' -1990 2000- a o o '•a CL j j aoN I r�0 0) NZ �Q0HOZ Z 0 a» 0'HOI+er 0r,0) d CL(nHZ Z(nH— — 0 �Z Z a-0 N00M� ON0 Lp. N 0 0_ �? O No +I o LO ~ Z o Q GRADE N +pN r7 +0 a_ V) >_ N 0 O N Z N p o- ....- 0_ •• 1990 1980-- 1980 1990-- - 1990 Qf� O j o Z a_(nE-Z � �- 1980 1970- 1970 1980-- 1980 o O O O O 00 o) o O 00 + + + + + + + M M O O O STORM LINE Z STORM LINE A 2030- 2030 2070 2070 PROPOSED GRADE (ROAD A) _ V PROPOSED GRADE EXISTING GRADE (POND) 31LF-15" HDPE ® 0.5% 27LF-15" HDPE ®0.6% 2020 65LF-15" HDPE ® 0.5% 2020 2060— 2060 62LF-15" HDPE ®4.2% — 55LF-18" HDPE ®0.5% � 24LF-15" HDPE @ 0.6% 29LF-15" HDPE @ 0.6% 2010 2010 2050 / 2050 PROPOSED GRADE \� N U ^ I � M U ovUI � N Lr7I �r, ocN 2000-- 000 2040 pN 0N o o- v -2040 U U±O O N 0. I 014 n� NIt CL �NZ M+MN UNO� -H +Ip OQCL j U NZ O D_�N0 r +I(O �o �00 OON CL V OZ O ..� 0Q0_ j-- -- +IrM rn� O -It O -� NN rnN-- ItU0 00 » 0=F-0 O t N N OHO N Lndo 000 O+pN +�H d F- Z 0_NHZ O+�O +'tN N+�N M+�N H ±OF- Up0 Uo00 L��O �NZ —Np L� O WO0 LL_ �..p �NZO �N� NZ -NZ O Z p O 0 �HO> �HO> O' d 0QCLjj0<a— j afQpjj �Qpj 1990- o (n ? o (n ? 1990 2030- o' O> � 0 Z Z� O z z (n z z o r- -2030 0_ HZ 0_(nH——0_(nH— — -- EXISTING GRADE -- - - 1980— 1980 2020 2020 O o O L o O u O o O Un o O 00 O N N O STORM LINE C STORM LINE F ?030 ?020 2010 1990-- 1980-- 0 0 O PROPOSED GRADE 95LF-15" HDPE ® 7.1% PROPOSED GRADE (POND) 50LF-15" HDPE ® 7.9% t r7 c� v ^ O � -HO LOAN N 0±O 0 -H0 > LO X�O00 0_Z C� 00ON O N +I N O 0 10 O rM N 0 N 0✓ O > Z 0 O O a H N Z j 0= 0 N � Z O O STORM LINE G 2030- 2020 2010 2000- 1990- 1980 O O O STORM LINE B 2040- 2040 2030 rr--��25LF-105!"' ED GRADE 2030 2020 HDPE @ 1.1 / ^ 2020-- -2020 c° N- c� 2010 ^ ^^LO\ I co m 0 o v I O p OR N 0 -- N -- CD � -- `-� O °' N o +I LO O N (m� O NN�NNN 1 PO NNN 0 0L0- j 0C4 N O (0 oLO 2010-- 010 No � Zz O a_ a0 r, x O O jj o > �� Z (nHz �OZ EXISTING GRADE EXISTING GRADE 2000- 2000 - 1990 1990- 1990 1980 O o 't m o + + + + O O cli N STORM LINE D (D10-D6) 2030 2020 2010 2000 1990 1980 u> N 2030- -2030 PROPOSED GRADE 2020 25LF-15" HDPE ® 0.6% 201 2010 � o vo O o 2000-- --2000 +I o ^N N0O N + 04 CL z 0 N� W p > > > -- Z Z -- O CL � • a- 0_ HZ p> C � Z 1990-- 1990 EXISTING GRADE STORM LINE D (D11-D4) Know what's below. Call before you dig. PHASE I STORM DRAINAGE PROFILE 0 20 40 80 "O!!!� 1 inch = 40 ft. (H) 0 4 8 16 "O!!!� 1 inch = 8 ft. (V) m Y J Q H m N U W U m W O OD Ln Z W OD 0W CDCD O Cn 00 Cn Z 00 0 co N ~ W V U) W a LO N N N U S Z N Z O W N N -1 W W N N [o W W J OD a >wx (LWz 2 W (A W ao 0 coQa W O 0. z a� 3 N Cn E 0 Q C a a 0 N U .y 2)V > .N r U .� O O 3 vaU 3 00 N 0 W W z w 0 J W J W m IL) z 9 Z O n ry U Lj 0 N 0 N Ln 0 Q L0 o z 00 0II Poo Nb X/'- o \ oo o�y Q Y,o C�d 0 \( WO� 00000� �G Q z J O Q U o' 0 z Zr Z O U W m C) O U O z D m U O L� // J W _^ / _J Li 0. L� O F_ 0 Z W Ld W 0 Q Z cr Z Q D ' w O v J r O ♦ U G_ v ) O Q (~ O Q O o' W (n (n (n Q ♦ , o = � d V U DRAWN BY: CDC CDC PROJECT NO.: 11925 BC PERMIT NO. N/A SHEET C507