HomeMy WebLinkAboutSW6210901_Plansheet - SCM Detail_20210908CONSTRUCTION SEQUENCE FOR WET DETENTION POND: 1, INSTALL EROSION CONTROLS, 2. CONSTRUCT DAM BASE AND AREAS BELOW THE NORMAL POOL. CONSTRUCTION TO BE PERFORMS UNDER THE INSPECTION OF THE GEOTECHNICAL ENGINEER, SEED UPON COMPLETION, 3. INSTALL.OUTLET PIPE, RIP -RAP APRON AND STONE FILTER RING, 4. CONSTRUCT OUTLET STRUCTURE. 5. REMOVE ACCUMULATED SEDIMENT AND SEED UPON COMPLETION. 24" HDPE WITH WATER TIGHT SEAL PIPE TO BE BEDDED PER DIRECTION OF GEOTECHNICAL ENGINEER 2 T MIN APPROXIMATE SIZE EXCAVATE AND BACKFILL WITH COMPACTED STRUCTURAL FILL AS DIRECTED BY GEOTECHNICAL ENGINEER 26'-24" HDPE @ 0.77% SILT FENCE AS NEEDED rap0F �583 4' MIN EMBANKMENT WIDTH 6" TOPSOIL FOR ALL AREAS ABOVE THE NORMAL POND LEVATION 6" CLAY SOIL LINER ON INSIDE FACE OF EMBANKMENT TRASH RACK REFER TO DETAIL THIS SHEET 6" TOPSOIL ABOVE 6" CLAY LINER NLITTORAL ORAL SHELF 3�1 6I--. 1 INV=295.4 1 ELEV=293,4 1 41 11N. ASTM C-923 SEAL KEY BETWEEN BARREL& RISER. RISER BASE TO BE FILLED WITH CONC. TO 8"X8"X1"X12" LONG ANGLE (6 TOT, REQUIRED) TNA"IllARRECO BASE, PROVIDE 2-314"A307 BOLTS FROM ANGLE TO RISER AND 2-A307 "J" HOOKS 314" DIA, X 12" LONG FROM ANGLE TO BASE, ANGLE TO BE FIELD COATED WITH ZINC RICH PAINT AFTER CONSTRUCTION, "J" HOOKS TO BE PLACED UNDER LOWER REINFORCING STEEL, FILTER MEDIA (SEE NOTE 2) _...-_F1QiI5L PRIOR TO INSTALLATION, MANUFACTURER SPECIFICATIONS OF FILTER MEDIA SHALL BE REVIEWED TO ENSURE THAT DISCHARGE FROM FILTER MEDIA SHALL MEET OR EXCEED THE PROVISIONS OF THE CLEAN WATER ACT, ENSURE THAT PUMP PRESSURE DOES NOT EXCEED FILTER MEDIA PRESSURE RATING, FILTER MEDIA MAY BE BUT NOT LIMITED TO SAND MEDIA FILTRATION DEVICES, RATED FILTER FABRIC BAGS OR POLYMER BASED DEWATERING PRACTICES. PUMP STRAINER SHALL NOT BE IN CONTACT WITH BOTTOM OF POND. BMP POND DEWATERING OF POINT SEEDBED PREPARATION: 1. CHISEL COMPACTED AREAS AND SPREADTOPSOJL THREE INCHES DEEP OVER ADVERSE SOIL CONDITIONS, IF AVAILABLE. 2. RIP THE ENTIRE AREA TO SIX INCHES DEEP, 3. REMOVE ALL LOOSE ROCK, ROOTS AND OTHER OBSTRUCTIONS, LEAVING SURFACE REASONABLY SMOOTH AND UNIFORM. 4. APPLY AGRICULTURAL LIME, FERTILIZER, AND SUPERPHOSPHATE UNIFORMLY AND MIX WITH SOIL (SEE SEEDING MIXTURE). 5. CONTINUE TILLAGE UNTIL A WELL -PULVERIZED, FIRM, REASONABLY UNIFORM SEEDBED IS PREPARED FOUR TO SIX INCHES DEEP, 6. SEED ON A FRESHLY PREPARED SEEDBED AND COVER SEED LIGHTLY WITH SEEDING EQUIPMENT OR CULTIPACK AFTER SEEDING. 7, MULCH IMMEDIATELY AFTER SEEDING AND ANCHOR MULCH, 6. INSPECT ALL SEEDED AREAS AND MAKE NECESSARY REPAIRS OR RE-SEEDINGS WITHIN THE PLANTING SEASON, IF POSSIBLE. IF STAND SHOULD BE MORE THAN 60°!" DAMAGED, RE-ESTABLISH FOLLOWING THE ORIGINAL LIME, FERTILIZER AND SEEDING RATES. 9. CONSULT 58EC ENVIRONMENTAL ENGINEERS ON MAINTENANCE TREATMENT AND FERTILIZATION AFTER PERMANENT COVER IS ESTABLISHED. LANDSCAPE NOTES; ALL LANDSCAPING SHALL BE IN COMPLIANCE WITH THE NCDEQ BMP REQUIREMENTS. LANDSCAPE CONTRACTOR SHALL PROVIDE A IWO-YEAR WARRANTY FOR BMP PLANTING SURVNAUREPLACEMENT. AT THE END OF THE FIRST YEAR ANDAT THE END OF THE Two -YEAR WARRANTY PERIOD, ALL PLANTS THAT DO NOT SURVIVE MUST BE REPLACED. ESTABLISHMENT PROCEDURES, SUCH AS CONTROL OF INVASIVE WEEDS, ANIMAL AND VANDAL DAMAGE, MULCHING, RE -STAKING, WATERING, AND MESH OR TUBE PROTECTION REPLACEMENT, SHALL BE IMPLEMENTED TO THE EXTEND NEEDED TO ENSURE PLANT SURVIVAL, STAKING MUST BE REMOVED AFTER ESTABLISHMENT (APPROXIMATELY 12 MONTHS), TO PREVENT GIRDLING (STRANGLING) OFALL WOODY PLANTS, SOD WITHIN BMP AND SURROUNDING AREAS TO BE BERMUDA OR CENTIPEDE GRASS. GRASS OR WILDFLOWER SEED MUST BE APPUEO AT THE RATES SPECIFIER BY THE SUPPLIERS. IF PLANT ESTABLISHMENT CANNOT BE ACHIEVED WITH SEEDING BY THE TIME OF SUBSTANTIAL COMPLETION OF THE STORMWATER FACILITY PORTION OF THE PROJECT, THEN THE CONTRACTOR SHALL PLANT THE AREA WITH WILDFLOWER SOD, PLUGS, CONTAINER PLANTS, OR OTHER MEANS TO COMPLETE THE SPECIF€ED PLANTING AND PROTECT AGAINST EROSION BEFORE WATER 15 ALLOWED TO ENTER THE STORMWATER BMP FACILITY. ALL MATERIALS SHALL BE ACQUIRED FROM AN APPROVED NCDEQ PLANT VENDOR, PLANT MATERIAL SHOULD BE PURCHASED FROM A LOCAL SOURCE TO ENSURE SURVIVABILITY. LOCAL VENDORS FOR THIS SITE INCLUDE: CILL ICE NA-5VE PLANT NURSERY 919-662.5566 GROWING WILD NURSERY 910-25M361 NC FOREST SERVICE 919-731-7988 -PLANT DEUGHTSNURSERY 919-772-4794. TARHEEL NATIVE TREES 919,553.5927 IMMEDIATELY AFTER THE WET DETENTION BASIN IS ESTABLISHED, THE PLANTS ON THE VEGETATED SHELF AND PERIMETER OF THE BASIN SHOULD BE WATERED TWICE WEEKLY IF NEEDED UNTIL THE PLANTS BECOME ESTABLISHED (COMMONLY SIX WEEKS) NO PORTION OF THE WET DETENTION POND SHOULD BE FERTILIZED AFTER THE FIRST INITIAL FERTILIZATION THAT IS REQUIRED TO ESTABLISH THE PLANTS ON THE VEGETATED SHELF. LANDSCAPING NOTES. 1. CONTRACTOR SHALt COMPLY WITH ALL APPLICABLE CODES AND ORDINANCES REGARDING LANDSCAPING. 2. IT IS THE RESPONSIBILITY OF THE CONTRACTORTO ESTABLISH A HEALTHY STANDGRASS ON ALLSEEDED AREAS. 3, CONTRACTOR SHALL PROVIDE NATURAL TOPSOIL THAT IS FERTILE, FRIABLE, WITHOUT MIXTURE OF SUBSOIL MATERIALS, AND OBTAINED FROM A'NELL DRAINED, AVAILA$LE SITE, IT SHALL NOT CONTAIN SUBSTANCES WHICH MAY BE HARMFUL TO PLANT GROWTH. TOPSOIL SHALL BE SCREENED AND FREE FROM CLAY, LUMPS, STONES, ROOTS, PLANTS, OR SIMILAR SUBSTANCES 1' OR MORE IN DIAMETER, DEBRIS, OR OTHER OBJECTS WHICH MIGHT. BE AHINDERANCE TO PLANTING OPERATIONS. TOPSOIL SHALL CONTAIN AT LEAST4-67, ORGANIC MATTER BY WEIGHT AND HAVE A PH RANGE OF 5.5 TO 7.0. 4. CONTRACTOR SHALL BE RESPONSIBLE FOR THE WATERING AND THE MAINTENANCE OF ALL LANDSCAPED AREAS UNTIL THE LATER OF; (a) THIRTY (30) DAYS FOLLOWING THE PLANTING OF THE GRASS AND SHRUBS, OR (b) THE DATE THAT STORE OPENS FOR BUSINESS TO THE PUBLIC. CONTRACTOR SHALL ALSO BE RESPONSIBILITY FOR THE SURVIVAL OF THE BMP PLANTING MATERIALS DURING THE TWO-YEAR WARRANTY PERIOD AND SHALL REPLACE ALL PLANTS THAT DO NOT SURVIVE AT THE END OF THE FIRST YEAR AND AT THE END OF THE SECOND YEAR OF THE WARRANTY PERIOD. 5. CONTRACTOR TO VERIFY QUANTITIES PRIOR TO COMMENCING WORK. 6, ANY DISTURBED AREAS NOT SCHEDULED FOR HARDSCAPE, PLANTINGS; OR MULCH SHALL BE SEEDED LAWN. REFER TO SITE PLAN FOR LOCATION OF AREAS TO BE SODDED. 1. NO PLANT SUBSTITUTIONS ARE PERMITTED WITHOUT WRITTEN APPROVAL OF THE OWNERS REPRESENTATIVE 8. FOR NEW PLANTING AREAS, REMOVE ALL PAVEMENT, GRAVEL SLIMASE AND CONSTRUCTION DEBRIS, REMOVE COMPACTED SOIL AND ADD 16" NEW TOPSOIL, OR 11LL AND AMEND THE TOP 16" OF EXISTING SOIL TO MEET TOPSOE RLANTINO MIX STANDARDS FOR TREES. 9. ADJUST TREE PLANTING LOCATIONS TO AVOID UNDERGROUND UTILITIES. PLANT 15' FROM ALL UNDERGROUND UTILITIES (SEWER AND STORM DRAINAGE, GAS, WATER, PHONE, AND ELECTRICAL LINES.) LEVEL REFER TO DETAIL �- FOR INCREMENTAL WEIR 44' PRECAST CONCRETE RISER (INSTALL STEPS AS NECESSARY) PVC ELBOW SEE DETAIL p� I� 2 NOTE: PUMPS SHALL BE USED TO DRAIN 1 THE POND WHEN NECESSARY. REFER TO DETAIL CONCRETE SHALL BE ` I 1 PLACED IN RISER AFTER ANGLES ARE SECURED TO BASE AND RISER. 5'x5'x1.5' CONC, BASE REINFORCE WITH #4 BARS AT 12" O.C. TOP AND BOTTOM OF EACH DIRECTION PROVIDE 3" MIN, CLEARANCE BETWEEN EDGE OF CONC. AND STEEL REINFORCING, PROFILE OF WET POND DETENTION SYSTEM SCALE: N,T,S, TOP OF EMBANKMENT ELEVATION-300.0 100 YEAR STORM ELEVATION=299.27 10 YEAR STORM ELEVATION=298.24 2 YEAR STORM ELEVATION497,18 1 YEAR STORM ELEVATiONz297,01. 1.0-INCH STORM ELEVATION=295,53 NORMAL POND ELEVATION=295,4 THIS SHEET FOR DEWATERING REQUIREMENTS, BOTTOM OF POND (TOP OF SEDIMENT STORAGE)=292.0 (BOTTOM OF SEDIMENT STORAGE)=291,0 RIS. EXISTING GRADE=300.0f rnn nr nrRUCTURE NOT SHOWN FOR CLARITY .E TRASH RACK) OUTLET CONTROL STRUCTURE - INCREMENTAL WEIR SCALE: N.T.S, 6" TOPSOIL FOR ALL-) AREAS ABOVE THE NORMAL POND ELEVATION FOREBAY BERM 6° TOPSOIL ABOVE 6" CLAY LINER 3,1 ON LITTORAL _ SHELF I I 6FT 6:1 �! LITTORAL I I 6" CLAY SOIL NOTES: LINER 1. SEE DESIGN PLANS FOR SPECIFIED DIMENSIONS OF RISER, MAIN POOL 2. TRASH RACK DIMENSION CRITERIA SPECIFIED IS APPROXIMATE AND VARIES BY MANUFACTURER. 3. INSTALLATION OF TRASH RACK SHALL BE ACCORDING TO MANUFACTURER'S RECOMMENDATIONS, 4. ALL COMPONENTS OF TRASH RACK SHALL BE OF STAINLESS STEEL OR OTHER NON -CORROSIVE MATERIAL. 5. ALL MOUNTING HARDWARE SHALL BE OF STAINLESS STEEL OR OTHER NON -CORROSIVE MATERIAL, TRASH RACK NON CORROSIVE MATE / r 1 \ @ 5.5' SPACING / / \ N 5.5 i I I NOTE: RISER TRASH RACK SHALL BE INSPECTED PERIODICALLY AND ANY DEBRIS ON THE TRASH RACK IS TO BE REMOVED AND PROPERLY DISPOSED OF. TRARP RAf.K nPTAII . OREBAY WEIR 303 300 93 I l r rl I rl rl I __j it FOREBAYAREACN CREBAYAREA 0 �GClOa' U o °O.�O`�`i� �j/ .- - ,. __. - y,. - - - - - \ LITTORAL SHEL Iltr c a AREA-3,310SF REFER TO ( c rr DETALFORPLANTINGS a\N\ NNPOND AREA rr o�° Cal � i ao p57 C%4 CD 58 1 0 ° UTLET CONTROL 49 STRUCTURE REFER TO SOD AREASABOV �i asoo �\ DETAILS THIS SHEET NORMAL POOL cc , _ G ELEVATICN 24" OUTLET PIPE REFERTOop 4 1 GRADING PLAN 000 \\ Dicer00000 ap 40 o / TOP OF EMBANKMENT=300. °n° /i' % // �✓// 000010 40 / .�`/ / x / GRAPHIC SCALE PLAN VIEW 30 0. 15 .30 60 120 1 INCH =30 FEET I I' MiN. GRASS FOREBAY WEIR AT ELEV=294.0 FOREBAY TOP ELEV= 296.4 WIDTH AT TOP = 2.0 FT RISER STRUCTURE 4" PVC SCREW CAP FOR CLEANING ACCESS 12" MIN. 4"x4" PVC TEE PERM, POND ELEV.=295,4 2 z"DIA. HOLE DRILLED J INTO BOTTOM CAP PVC DRAIN OUTLET SCALE; N.T.S. NOTE; PUMPS SHALL BE USED TO DRAIN FOREBAY BOTTOM THE FOREBAY WHEN NECESSARY. REFER TO DETA1 THIS SHEET FOR DEWATERING REQUIREMENTS, ELEV=293,5 33 NORMAL POND ELEVATION11 i FOREBAY ENTRANCE SHALL. BE--" BOTTOM OF SEDIMENT DEEPER THAN FOREBAY EXIT STORAGE ELEV=292,5 FOREBAY 6" TOPSOIL FOR ALL -- AREAS ABOVE THE NORMAL POND ELEVATION SHALLOW LAND ZONE SHALLOW WATER ZONE HERBACEOUS PLANTS HERBACEOUS PLANTS r(NORMALPOOL) 1I TYPICAL LITTORAL`�SH-E-L-F VEGETATION DETAIL SCALE:N.T.S. SCIENTIFIC NAME COMMON NAME PLANTING ZONE QUANTITY NURSERY CONTAINER TYPE SPACING PLANTING SEASON Janus effusus Soft Rush SHALLOW WATER 138 PEAT POT 6' Q.C. SPRING/SUMMER Iris virgWw Blue Flag Iris SHALLOW WATER 138 PEAT POT 6' O.C, SPRINGISUMMER Schoenoplectus tabernaemontani Eupatoriadelphus maculatus Soft Stem Bulrush Spotted Trumpetweed SHALLOW WATER SHALLOW LAND 13B 138 PEAT POT PEAT POT 6' O.C. 6' O.C, SPRINGlSUMMER SPRINGISUMMER Eupatorium purpureum Joe -Rye Weed SHALLOW LAND 138 PEAT POT 6' O.C. SPRINGISUMMER Rhynchospara colorafa Starrush VI SHALLOW LAND 13.8 PEAT POT 6' O,C, SPRINGISUMMER TYPICAL LITTORAL SHELF PLANTING SCHEDULE STORMWATER MANAGEMENT NOTES: 1, THE DEVELOPER OR HIS AGENT SHALL CONTACT THE DESIGNENGINEER WHEN THE BEST MANAGEMENT PRACTICES) ARE CONSTRUCTEDAND ABOUT TO BECOME OPERATIONAL SOA FINAL INSPECTION CAN BE PERFORMED TO DETERMINE COMPLIANCE WITH THEAPPROVED PLAN CAN BEPERFORMED, 2. ANNUAL MAINTENANCE INSPECTIONAND REPORT REQUIRED - THE OWNER OFA PERMITTED STRUCTURAL STORMWATER BMPICONTROL SHALL ANNUALL YSUBMIT A MAINTENANCEAND INSPECTIONREPORTFOR EACHBMP TO THESTORMWATER ADMINISTRATOR. ANNUAL INSPECTIONS SHALL BEGIN WJ77 WN ONE YEAR OF THE RECORDATION OFANY DEED(S) SHOWING STORMWATER BMPsICONTROL STRUCTURES. 3, UPON COMPLETION OF THE PROJECT, AND BEFOREA CERTIFICATE OF OCCUPANCYSHALL BE GRANTED, THEENGINEER OFRECORD SHALL CERTIFY THAT THE COMPLETED PROJECT MW ACCORDANCEWITH THEAPPROVED STORMWA TER MANAGEMENTPLANS AND DESIGNS. 4. A FINAL INSPECTION OF THE SITEAND STORMWA TER MANAGEMENT BMP/CONTROLS TO BE SCHEDULED WITHAND COMPLETED BY THE PROJECT ENGINEER. 5. NCDEQ AND THEIRASSIGNS HAVERIGHT TO ACCESS THESTORMWATER CONTROL(s) FOR INSPECTIONS OR MA INTENANCEA5NECESSARY. 6. THE ENGINEERS CERTIFICATIONOFCOMPLETIONWILL BEREQUIREOPRIOR TO THE FINAL PLA T OR CERTIFICATE OF OCCUPANCY THE STORMWA TER CONTROL IS TO BE INSPECTED TO ENSURE ITIS FUNCTIONING AS DESIGNEDAND HAS FULL DESIGN VOLUME PRIOR TO ISSUANCE OF THE FINAL CERTIFICATE OF OCCUPANCY. 11, THE PROPERTY OWNER ISRESPONSIBLE FOR MAINTAININGTHE STORMWATER CONTROLS(s)ACCORDING TO THEAPPROVEO MAINTENANCE PLANAND DIRECTION OF NCDEQ STORMWATER MANAGEMENT DESIGN WET DETENTION POND RIVER BASIN: LUMBER RECEIVING STREAM: TONEY'S CREEK (RAFT SWAMP} STREAM INDEX: 14.10.1.2 STREAM CLASS: C; Sw HUG: 031)40203 PROJECT COORDINATES: 34.987031 °N,-79.26057B°W POND DESIGN SUMMARY DRAINAGE AREA TO POND: 1533 ACRES SITE IMPERVIOUS AREA TO POND: 7.01 ACRES OFF -SITE DESIGN IMPERVIOUS AREA TO POND: 0.9 ACRES TOTAL DESIGN IMPERVIOUS AREA TO POND: 7.01 ACRES PRE -DEVELOPED POST -DEVELOPED POST DEVELOPED POST DEVELOPED POST DEVELOPED TO POND TO POND THROUGH POND BYPASS COMBINED DRAINAGE AREA; 17.43 AC 15.83 AC 1.60 AC CURVE NUMBER: 793 77.8 73.5 TIME OF CONCENTRATION: 27.2 MIN 10 MI I N. 10 MN 1,0" STORM EVENT: 0.285 CFS 0,027 CFS 1-YEAR STORM EVENT: 19.86 CFS 26.27 CFS 1.131 CFS 2,055 CFS 3.186 CFS 2-YEAR STORM EVENT: 27.93 CFS 37.33 CFS 4.166 CFS 3,073 CFS 7.239 CFS 10-YEAR STORM EVENT: 51.46 CF5 70.12 CFS 18.04 CFS 6.171 CF5 24.21 CFS 100-YEAR STORM EVENT: 90.40 CFS 124.68 GFS 86.18 CFS 11.56 GFS 97.74 CF5 STAG EISTO RAGE TABLE STAGE ELEVATION CONTOUR (FT) (FT) AREA (SF) 0.0 295.4 23635 0.5 295.9 26060 0.6 296.0 26385 1.0 2964 276BO 1.6 297.0 29690 2.6 298.0 32250. 3.6 299.0 34865 4.6 300.0 37090 INCREMENTAL TOTAL STORAGE(CF} STORAGE(CF, 0 0 12424 12424 2622 15046 10813 25859(0v) 17211 43070 30970 74040 33558 107598 35978 143575 OPERATION & MAINTENANCE BMP element: Potential roblem: How I will remedlate the problem The entire BMP Trashldebns Is present KefnoVe the has debris The Perimeter of the wet Areas of barc soil ancifor Ragra - the soI if necessa o detention basin erosive gullies have formed remove he gully, and then pp ant a ground eover and water until it is established. Provide lime and a one-time fe1¢er appkafien Vegetalion is too short or too Maintain vegetation at a height Ion of opproxngtely six in6e , The inlet device; pipe or The pipe is clogged, Unciog the pipe. Dispose of the Swale sedlmento -site, Replace lihe pipe. The pipe is cracked or Regrade the Swale if necessary to smooth it aver and provide Erosion Is occurring in the Swale, erosion control devices such aS reinforced turf matting or riprap to avoid future problems with erosion, The forebay Sediment has accumulated to adepinggreaterthanthe -5 rcri for Ine so-0-rce-bTff e sediment and rern the origginal design depth for problem rf possibie. f ewe the sediment slorage, sediment and dispose of i1 in a Iocallon where it will not cause impacts to streams or the BMP. Provide additional erosion protection such as reinforced turf Erosion has occured, matting or riprap if needed to prevent future erosion problems, Remove the weeds, preferably by Weeds are present hand, If pesticide is used, wipe it on the plants rather than spraying. The vegelaled shelf es pro esslona prat Ices show that pruning Is needed rune actor Ing o es professional practices to maintain optmal plant health Determine the source of the Plants are dead, disease or dying. problem: soils hydrology, disease, etc, Remedy the problem and repiace plants. Provide a one-time fertilizer application to establish the ground cover if a soil test indicates it is necessary, Weeds are present Remove tlhe weeds, preferably qy hand. If pesticido is used, wipe It the than on plants rather spraying. The main treatment area Sediment has accumulated to a depth ggreat-rthan the Seara for t e source at Te im n r sed e f and erredy the if Remove t o sloo a� ddep n sediment problem possible, ediment ad dispose of It in a g p�' location where it will not cause impacts to streams or the BMP. Consult a professional to remove a growl covers ov-r 50 o c)fare and control the al al growth. Remove iho by Cattails, phragmites or other plants wiping invasive plants cover 50"1" or them with pesticide (do no the basin surface, s ra The embankmunt Shrubs have started to grow on he-embankwi Hemove s ru s Imme Ia y. Use traps to remove muskrats Evidence of muskrat or beaver active is present, and consult a professional to remove beavers. Consult a dam safely specialist A tree has started to grow en the embankment. 10 remove the tree. An annual innsppecton by an Make all needed repairs. appropriate professicnai shows that th- embankment needs Tpair. (if applicable) The outlet device C egging has occurr-tl. Clean out the cudel devin. Dispose of the sediment off site, The outlet device is damaged Repair or replace the outlet device. The receiving water . Erosion or other signs of damage have occurred at the Gantace local N(; DI o Water Quali Re Tonal Of [ce, or h` g oullet. the 401 Oversight Unit at LU Z w W Q W N w� CONSULTANT: TRIANGLE SITE DESIGN, PLLC 4004 BARRETT DR, STE 101 RALEIGH, NC 27609 (919) 553.6570 LICENSE 9P-0619 mlowder@trianglesitedesign.com .�'%,� CARo 0 A� " s P *s� ••rrr•••a O,� DEVELOPER: Spout Springs Holdings, LLC Attn. Allen Jordan 275 South Bennett Street Southern Pines, NC 28387 (919) 693.1700 johnallenjordanjr@grnail.com Z3 . cu C3 U � la_ a� 2 c This document, together with the concepts and designs presented herein, as an instrument of services, is intended Only for the specific purpose and client for which it was prepared, Reuse of and improper reliance on this document without written authorization and adaptation by Triangle Site Design, PLLC shall be without liability to Triangle Site Design, PLLC, 0 �n a, Drawn Checked Approved Project No, 002003 Original Submittal Dale: August 23, 2021 Title STORMWATER MANAGEMENT DETAILS Sheet No. C1 r5B _ m c � _. , •'-R-+, -� r44HA