Attached is a copy of the inspection report which was prepared following an on -site inspection of the
subject site. This report is intended to provide you with information concerning the status of the site as
it relates to compliance with the North Carolina Sedimentation Pollution Control Act of 1973.
Please review this report carefully as it may contain corrective actions needed or comments which will
assist you in meeting the required performance standards of the Act.
It is our desire that any and all possible problems be discussed and resolved at the earliest possible time.
To facilitate this effort, please contact the named inspector at the address shown on the inspection
report if you have any questions.
Sincerely,
Land Quality Section
Mooresville Regional Office
North Carolina Department of Environmental Quality Division of Energy, Mineral and Land Resources
ICK Q� Mooresville Regional Office 1610 East Center Avenue, Suite 3011 Mooresville, North Carolina 28115
704-663-1699
North Carolina Department of Environmental Quality
Land Resources: 610 East Center Avenue, Suite 301, Mooresville, NC 28115 (704) 663-1699
County: Cabarrus Project: Tommy's Express Car Wash
Person financially responsible: Elzinga & Volkers, Inc. DBA EV
Construction - Chase Burns, Principal
Address: 86 E. 6th Street, Holland, MI 49423
1. Project Location: 2493 Coldwater Ridge Drive, Kannopois
Pictures: No
2. Weather and soil conditions: Sunny, Workable Soils
3. Is site currently under notice of violation? No
4. Is the site in compliance with S.P.C.A. and rules? Yes
5. Violations:
River basin: Yadkin-PeeDee
Project #: CABAR-2020-077
Initial inspection: No
If no, check violations below:
6. Is the site in compliance with NPDES Permit NCGO10000 Construction Stormwater requirements?
Describe:
7. Has sedimentation damage occurred since last inspection? No If Yes, where? (check all that apply)
Degree of damage:
8. Contact made with (name): No one on site Title:
Inspection report: Sent Report Date given/sent: August 13, 2021
9. Corrective action needed:
10. Comments: Permanent ground cover sufficient to restrain erosion has been established. No additional
self -monitoring or self -inspections are required. Project is in compliance and released under
the SPCA. Termination of coverage under the NPDES General Stormwater Permit for
Construction Activities (NCG01) must be requested by the permittee via a Notice of
Termination (NOT). The NOT is available at:
https: "edocs.deq.nc.gov/Forms/NCGOI-Termination. Please note that this correspondence
must be uploaded as part of completing the NOT process.
All projects that have been approved prior to April Ol, 2019, under the old permit system, are
not required to take any additional actions. The stormwater permit is terminated at the same
time as the termination of this erosion control permit.
Reported by: Kenny Llywelyn
Date of inspection: August 10, 2021
cc:
Yes
Others present:
Time arriving on site: 10:25 Ail Time leaving site: 10:30 AM