Homewood, Sue
From:Daniel Taylor [dtaylor@wildlandseng.com]
Sent:Tuesday, July 23, 2013 10:33 AM
To:Homewood, Sue
Subject:RE: upper Swep
Hello Sue. From what we could tell during the survey, there was very little sediment behind the crib walls.
Also, we are requesting a waiver of the dewatering requirement. We do plan on performing construction activities
during August when the water level is low (assuming it stops raining).
Thanks and let me know if you have any other questions.
Daniel Taylor
From: Homewood, Sue [mailto:sue.homewood@ncdenr.gov]
Sent: Monday, July 22, 2013 11:56 AM
To: Daniel Taylor
Subject: upper Swep
Hi Daniel,
Just a quick verification so I can issue the Upper Swep Dam Removal 401. I know we discussed this when I
toured the lower dam removal project, but can you verify for my file that there is very little sediment behind
any of these crib wall areas. Also, our General Certification requires dewatering when working in the stream.
I just want to clarify that you guys are requesting formal waiver of that requirement due to the nature of the
project. Thanks.
Sue Homewood
NC DENR Winston-Salem Regional Office
Division of Water Quality
585 Waughtown Street
Winston-Salem, NC 27107
Voice: (336) 771-4964
FAX: (336) 771-4630