Loading...
HomeMy WebLinkAbout20000723 Ver 1_Mitigation Information_20130523bU - D'723 os stem a PROGRAM MEMORANDUM TO: Eric Kulz, DWQ FROM: Mac Haupt DATE: May 23, 2013 RE: Closeout Request for Payne Dairy Buffer Site (EEP IMS #279) The Payne Dairy Buffer Site is located in Alexander County in the Catawba 01 watershed. The 6t" year monitoring for the site concluded in 2006 and the site was formerly closed out in June of 2007. At the time there was no formal riparian buffer closeout process and while the buffer assets were agreed upon at the time, no formal letter was required or submitted. Based upon our past review, EEP requests closure of the site with the following riparian buffer assets: • 25.4 acres of Riparian Buffer credit (1,106,424 sq ft) Perpetual site protection will be maintained by: Eric Galamb Stewardship Program Office of Conservation, Planning, and Community Affairs, DENR 1601 Mail Service Center Raleigh, NC 27699 919 -715 -8696 Please find attached a copy of the closeout report, which contains a map detailing the final enumeration of credits, and a credit /debit ledger. We respectfully request your concurrence to officially close out the Riparian Buffer assets of the Payne Dairy Buffer Site. CC. Jeff Jurek Guy Pearce Jim Stanfill File fktGu�. zi;I -... Protmtr -q C?�w Stigte ©EN North Carolina Ecosystem Enhancement Program, 1652 Mail Service Center, Raleigh, NC 21699 -1652 / 919 -115 -0416 / www.nceep.net Mitigation Project t, Payne Dairy IMS ID # 279 River Basin CATAWBA Cataloging Unit 03050101 Project Type Riparian Buffer Mitigation Comment: The project was funded by the Statewide ILF Program and verified buffer assets were sold to the Riparian Buffer Restoration Program. Applied Credit Ratios: 1:1 1.5:1 2.5:1 5:1 1:1 3:1 2:1 5:1 1:1 3:1 2:1 5:1 1:1 3:1 2:1 5:1 1:1 3:1 273.1 Ibs /z146.4lbs /ac Beginning Balance (square feet) o Z K C U z w O L z W O d i V U U H L U W N W U O Q lo 217,800.00 Beginning Balance (credits) 217,800.00 EEP Debits (credits): DWQ Permits Impact Project Name 2006 -0014 Fire Station No. 38 (City of Charlotte) 10,022.00 2006 -1903 Rowboat Dock and Dredge Staging Area 1,800.00 2007 -1584 Northeast Pump Station 14,778.00 2007 -1984 438 Tuskarora Trail Lot 23 10,000.00 2007 -2052 Frank Hoguet Swimming Pool 1,600.00 2007 -2030 Griffith Street Pump Station Modifications 3.339,00 2008 -0999 N D T TIP R -3833B - Brawley School Road Widening 47.557.00 2008 -0999 NCDOT TIP R -3833B - Brawley School Road Widening 27,241.0J 2007 -1868 Bridgewater Powerhouse Construction Project 21,487.00 2006 -0972 William Whitley Project 1,050.00 2010 -0527 Slanting Bridge Staging Area 1 2,100.00 Remaining Balance (credits) 76,826-001 0.00 0.00 *NOTE: The Payne Dairy mitigation site generated a total of 1,106,424 square feet (25.40 acres) of buffer mitigation. The amount of buffer assets shown as the beginning balance above represents only the amount of buffer mitigation that has been sold to the Riparian Buffer ILF Program. There is an additional 888,624 square feet (20.40 acres) of buffer mitigation available for sell to the Riparian Buffer ILF Program as needed to meet requirements. r� Ecosystem PROGRAM EEP Project Closeout Summary PrOlectID & Status Proiect Name /Number: Payne Dairy (Jumping Run Creek) EEP ID 279 County: Alexander Project Type: Stream Restoration, Enhancement Central Piedmont Wetland Preservation Current Status: 5 Years of Monitoring complete Project Setting & Classifications Basin: Catawba Physiographic Region: Piedmont Ecoregion: Central Piedmont USGS Hydro Unit: 03050101 - 120040 NCDWQ Subbasin_: 11- 62 -3 -1 Thermal Regime: Warm Trout Water: No Designer: Kimley -Horn Monitoring Kimley -Horn, NCSU, SEC Project Timeline Feet Milestone Date Construction Completed R As -built survey June 2000 Monitoring Year -1 June 2001 Repair and Maintenance Monitoring Year -2 June 2002 Monitoring Year -3 June 2003 Monitoring Year -4 June 2004 Monitoring Year -5 June 2005 Monitoring Year -6 (Vea) June 2006 Table 1. Project Restoration Components and Mitigation Assets Feet SMU Acres WMU R 5177 5177 E Stream 470 313 Ell Asset Data 675 C Watershed Data and Characteristics Drainage /Hydrology Component Restoration Component Asset 6.40 1.28 Ratio 6165 6.40 1.28 Wetland DA Stream % Land Map # Approach Level Ratio Multip Feet SMU Acres WMU P /l /E Type (SM) Order Imper Use 303d Jumping Run Upper (Above Henry Road) Segment 1 1 P1 /P2 R 1.00 1.00 4377 4377 - - P - 12 1st <5% A -Past No Jumping Run lower (Below Payne Store Road) Segment 1 (Down to confluence) 2 P2 R 1.00 1.00 800 800 P - Segment 2 (Confl to Pres se m) 3 P2 El 1.50 0.67 380 253 - - P - Segment 3 (Presery -one side) 4 - - - 0.00 1450 0 - - P - 2.2 2nd 5% A -Past No Tributary Se ment 1 (Upper) 5 Fence /Plan EII 2.00 0.50 1350 675 - - P - Segment 2 (Lower 90 feet) 6 P2 EI 1.50 0.67 90 60 - - P - 0.4 1st <5% A -Past No etland Jumping Run Upper (Above Henry Road) Wetland 1 7 P 5.00 0.20 - - 2.36 0.47 - BLH - - - Wetland 2 8 P 5.00 0.20 0.03 0.01 - BLH - - - Wetland 3 9 - P 5.00 0.20 - - 0.26 0.05 - BLH - - - - - Wetland 4 10 P 5.00 0.20 - - 0.30 0.06 BLH - - Wetland 5 11 - P 5.00 0.20 - - 1.87 0.37 - BLH - - - - - Jumping Run Lower (Below Payne Rd)) Wetland 9 12 - P 5.00 0.20 - 1.40 0.28 - BLH - - - Tributary Wetland 6 13 P 5.00 0.20 - 0.01 0.00 - BLH - - - - Wetland 7 14 - P 5.00 0.20 BLH - - - - Road) Segment 1 1 Wetland 8 15 - P 5.00 0.20 - - 0.07 0.01 - BLH - - Buffer Jumping Run Upper (Above Henry Pt = Priority I Restoration R = Restoration P2 = Priority II Restoration E = Wetland Enhancement P3 = Priority III Restoration El = Stream Enhancement I Ell = Stream Enhancemnt II C = Wetland Creation P = Preservation SMU = Stream Mitigation Units WMU = Wetland Mitigation Units P /I /E = Perennial, Intermittent, Ephemeral Asset Summary Buffer "2531 Level Feet SMU Acres WMU R 5177 5177 E El 470 313 Ell 1350 675 C P 1450 6.40 1.28 8447 6165 6.40 1.28 Road) Segment 1 1 - - - - - - 25.36 - - - - - - - - Level Feet SMU Acres WMU R 5177 5177 E El 470 313 Ell 1350 675 C P 1450 6.40 1.28 8447 6165 6.40 1.28 03040101 4N ~and Asset St�nAsset Site Location Map 1 Monit Areas - 2 :IN y _._ -A.Exa ER 040102 Payne Dairy (Jumping Run) REDE Areal XS 3 EEP Project Number 279 030 101 -Aree2XS -4 ��Pree3XS -5 _ TFt4VBA Wee4XS 6 �' Figure 1. Project Site Map LLq ure 2. Payne Dairy (EEP Project Number 279) Pre - existing Condition Photos Figure 3. Payne Dairy (EEP Project Number 279) As -built comparison photos Channel Stability Dimension The restored channel's dimension exhibited stability. There appeared to be some lateral migration in one of the paired riffle and pool cross - sections at the very upper end of the project, but this may have been a lateral shift in the survey by the monitoring consultant in years 3 -5. In any case, this is not evident in the field and did not represent a systemic reach response. The riffle cross - sectional areas were either maintained or decreased due to a decrease in channel width, primarily below the bankfull elevation (development of an inner berm feature See Area 1 Riffle Cross section below), which was coincident with the development of dense vegetation in year 3. The riffle cross - sections classified as either the C channel that was designed or exhibited tendencies towards development of an E channel as a result of the aforementioned narrowing. In all cases, healthy entrenchment ratios were maintained indicating good floodplain capacity. With the exception of one riffle -pool cross - section pairing, the pool cross - sections exhibited and maintained greater depths than the riffles, indicating the maintenance of distinct bedform features. Collectively, these conditions indicate stability or stable trends of the restored dimension. The plots below describe or typify some of the conditions and trends with regard to channel dimension. Payne Dairy - Area I Rrttk Station 0 +77 Baokfu8 Ek%. (appmi.) IR50 100.00 99.50 - W 99.00 - 9850 - - - - -- - 98•00 - _- - - Inner Berm Feature i 9750 - - - 97A 0.0 10.0 20.0 30.0 40.0 50.0 60.0 70.0 80.0 Distaaee (feet) - As- Bu0tSunev ---- 200ISaner - 2002Sunes - 2003Suseev 2005Sunec- BankfifiDasam Figure 4. Area 1 Riffle cross - section typifying the development of an inner -berm feature Table 2. Cross - Sectional Areas Based on As -built Bkfl Datum Riffle MYO MY1 MY2 MY3 MY4 MY5 Area 1 17.66 17.86 20.46 16.48 16.63 15.09 Area 2 25.71 25.53 28.07 25.04 23.27 25.48 Area 3 17.35 17.03 17.93 17.57 14.93 14.85 Area 4 32.4 29.46 32.22 24.23 22.99 23.05 Mean 20.24 20.14 22.16 19.70 18.27 18.47 20% 15% 10% 5% C 0% -5% V -10% ° -15% -20% -25% -30% -35% Payne Dairy - Percent Change in Riffle Area From As -built 0 1 2 3 4 5 6 Monitoring Year - --Area 1 --- Area 2 Area 3 -m- Area 4 — Mean Figure 5. Percent change from As -built cross - sectional area In order for the reach dimension to be considered stable, the change in the cross - sectional area should not be unidirectional and the amplitude in the variation should not increase over the 5 -year monitoring period. A streams cross - section may exhibit an initial adjustment before a stable variation pattern can be observed around some new point of equilibrium. This is often due to the fact that there is some level of uncertainty in any stream design, and the vegetation often takes 2 -3 years to exert significant influence on the channel. The above plot includes the percent change relative to the as -built for each of the 4 project riffle cross - sections. The mean is also included. The projects cross - sectional area generally demonstrated a healthy pattern of variability. After an initial moderate increase in the cross - section between years 1 and 2, the cross - section generally decreased with the development of an inner berm depositional feature, effectively narrowing the channel. This condition was particularly evident in the cross - section from area 4. The onset of very dense vegetation was coincident with this decrease in area in Year 3. This adjustment was followed by a lower level of variation in years 4 and 5, indicating the cross - section has likely reached a stable equilibrium. The observed pattern indicates that the intended floodplain access was provided and maintained. Maintenance of a mean entrenchment ratio of approximately 5 over the 4 riffle cross - sections supports this observation. Profile The upper section of the reach above Henry road demonstrated some vertical adjustment during year 2 which has since arrested. There was some aggradation above structure 2 near the top of the project and some downcutting below it resulting from a short headcut for this upper section, but the monitoring reports /data for years 3 through 5 indicated this has stabilized. The measured profiles indicated that the project reaches were vertically stable overall. The figure below provides a sampling of the surveyed profile. Bedform slope and spacing distributions naturally varied from year to year, but distinct riffle -pool bedform distributions were maintained, providing diversity in the project bedform. Jumping Run Creek Profile Area #3 Direcly above SR 1614 78 ._ . • 77 • • 2, 76 -- - - - -• A - - - - - - - - A Z 75 - - - - - -- - _ - -- -• . - V �� f .. ♦ y v 74 i 4 73 f w 72 71 — - 0 50 100 150 200 250 300 350 400 450 Down Stream Distance (feet) Vane • Figure 6. Longitudinal Prof le Segment Long Pro 2003 — — — Long Pro 2002 - - - - - - Long Pro 2001 As -built 2000 — — Long Pro 2004 12005 TW - - - 2005 WS ♦ 2005 Bkf Substrate The substrate data collected from the 4 pairs of cross - sections in the 4 restoration reaches was somewhat variable and indicated sediments were being moved by the system, but were not always depositing in bedforms that were typical for the observed substrate distributions The restoration plan indicated that the materials in the existing channel were silt and fine sand and that based on upstream sediment distributions, the restoration reaches should maintain coarse sand to medium gravel in riffles Overall, while there were fluctuations in the distributions, the substrates were in keeping with the classes described in the restoration plan Area 1 XS1 — Riffle 5 year mean - Coarse sand (d50) to Fine gravel (d84) Fines observed in years 2 -4 with coarsening in year 5 Coarser than paired pool Area 2 XS1 — Riffle 5 year mean - Very Coarse sand 050) to Medium Gravel (d84) Fines observed in years 3-4 with some recovery in year 5, but still generally finer than earlier years As -built was extremely coarse, which may have been an artifact of a constructed riffle Paired pool data indicates some of the riffle material may have been dislodged into the pool, because coarsening was observed in the paired pool as well Area 3 XS1 — Riffle 5 Year Mean - Medium (d50) to coarse gravel (d84) Generally much coarser than the upstream riffle cross sections A pattern similar to that of Area 2 riffle cross - section was observed with some fining in years 3 and 4 , but final riffle substrate in year 5 was medium to coarse gravel As with Area 2 it appears some of the riffle material was dislodged into the pool, because the pool distribution exhibited some coarser material Area 4 XS1 — Riffle 5 Year Mean - Medium (d50) to coarse gravel (d84) Table 3 Project Bedform Substrate Means Mean AB -Year 5 D50 D84 Mean AB -Year 5 D50 D84 Riffle Area 1 06 40 Pool Area 1 05 20 Riffle Area 2 1 7 11 3 Pool Area 2 23 98 Riffle Area 3 139 304 Pool Area 3 09 98 Riffle Area 4 102 258 Pool Area 4 09 105 Status of Engineered Structures Grade control structures were comprised of log sills and rock cross vanes. These were 37 in number throughout the project, two of which were identified as significant structural failures and 9 of which were identified as stressed in 2006. This project was constructed in 2000 and the rock cross vanes were not constructed according to current standards. They did not possess a significant vane arm angle and several were oversized, ineffectual and bypassed by flow. The project also included many root wads and single arm log vanes, the vast majority of which are functioning well. Overall, the projects grade has been maintained and the majority of the projects structures are providing the intended function. Macrobenthos Monitoring of the benthos was performed pre- construction and in monitoring years 2 -6 by David Penrose of NCSU. Samples were collected at an upstream reference site (site 1), a site within the restoration reach about 150 feet upstream of Henry road (site 2), and a third site just below the project extent (site 3). Prior to construction, all metrics (EPT metrics and keystone taxa in particular) were considerably lower at sites 2 and 3 as compared to the upstream reference. The first sampling event after construction exhibited even lower biological quality at sites 2 and 3 as compared to the upstream reference, but after this initial response, these sites demonstrated steady improvement in all metrics between 2003 and 2005 and achieved levels that were significantly better than pre- construction and close to the upstream reference. However, sampling in 2006 saw a drop in quality at all stations, particularly at sites 2 and 3. Site 3 still exhibited improvement over pre- construction levels. Sampling took place during high flows in 2006 in November as opposed to October. 2006 also saw the establishment of beaver dams above site 2, which were manually breached by the adjacent landowner. Benthos sampling and measurement will continue at this project site as part of EEP funded research. m i0 D U L N L 2 U co R a M H Abundant and Common taxa were used in the analyses. Overbank Events There is evidence of recent deposition and wrack alonq the project reach (see Figure 7). Figure 7. Fresh overbank deposition near top of project (2007). Site 1, Upstream Reference Site 2 Restored Reach Site 3, Recove Metric/Year 10/00 10/02 10/03 10 /04 10105 11 /06 10 /00 10/02 10103 10/04 10/05 11/06 10 100 10/02 10/03 10/04 10105 11106 Total Taxa 43 37 44 41 44 35 38 12 20 27 43 22 31 28 44 44 42 34 Richness EPT Taxa 19 20 19 20 24 23 8 3 12 11 17 3 9 7 16 16 18 13 Richness EPT 67 88 87 88 88 77 39 7 34 39 61 7 47 28 71 54 93 68 Abundance Dominants in Common - - - - - - 25% 5% 29% 30% 55% 27% 25% 16% 47% 60% 50% 47% Index (%)* # Indicator 10 12 14 19 21 15 2 0 5 6 13 3 4 0 6 12 13 9 taxa Abundant and Common taxa were used in the analyses. Overbank Events There is evidence of recent deposition and wrack alonq the project reach (see Figure 7). Figure 7. Fresh overbank deposition near top of project (2007). Table 5 Project Stem Counts Stem Counts per Acre by Plot Plots rfMY CY Ave 1 1 2 1 3 1 4 5 6 7 8 9 10 Y1 2001 <260 Transects Y2 2002 <260 Transects Y3 2003 490 360 240 840 520 Y4 2004 120 80 0 120 280 Y5 2005 982 809 1255 769 1093 Y6 2006 459 121 40 688 486 1 0 688 1 607 891 1417 457 Project Goals, Outcomes and Conclusions During the six years of vegetation monitoring, 3 different protocols have been applied In year five, the data suggests no distinction was made between planted stems and volunteers Also, some of the change in numbers is attributed to changes in plot locations Regardless, the condition of the vegetation is considered to be adequate for Close -out purposes The above is summary of the salient information from the project restoration plan, mitigation plan and monitoring reports, which should be consulted if additional detail is sought The primary project goal as stated in the project restoration plan is to improve water quality and the natural function of Jumping Run This was to be accomplished through the restoration of the altered /degraded stream corridor, including adjacent riparian zones and flood prone areas, to its natural or referenced, stable condition The project served to connect 3 existing corridors that are nearly completely forested along the Jumping Run mamstem including its headwaters The longest contiguous forested segment was approximately 4700 feet prior to restoration, and is approximately 16,400 feet post - restoration Livestock are excluded from the entire project extent (all stream asset polygons in Figure 1) The fenced easement also encompasses 9 wetland features depicted in Figure 1, which have been preserved, enhanced or restored as a result of project measures The easement surrounding the upper stream segment (asset #1) encompasses an area that exceeds the standard 50 foot buffer acreage by 18 7 acres The tributary in the lower section (Map assets 5 & 6) flows directly through the farm and the enhancement implemented on this segment provides protection not only from direct livestock pressures, but from a wider array of stressors related directly to operations of the farm complex The restored stream segments have exhibited geomorphologic stability, maintained floodplain access, and are surrounded by a dense buffer with a canopy that is providing significant shading to the stream The restored pattern, dimension and profile are maintaining distinct bedforms and have yielded improved quality and distribution of instream habitat The benthjc community exhibited improvement between 2003 and 2005, demonstrating a steady migration from pre - construction conditions towards reference However, the sites within and below the project, sites 1 and 2, exhibited a drop in 2006 as compared to the improvements realized in 2005 This may be related to the development and breach of beaver dams upstream of site 2 in 2006 and /or that sampling occurred at elevated flows in 2006, but the actual cause is unknown Even with what is interpreted as a temporary downturn, given the 3 prior years of improvement, the downstream site (site 3) still indicates improvement over pre - construction conditions This indicates improvement to the catchment has likely been realized Monitoring of the benthos will continue as part of EEP- funded research Collectively, the characteristics of the projects' assets and their measured performance yielded the ratios listed in table 1 EEP considers the project to be functioning well with a trajectory such that the sites potential functional uplift has or will be realized EEP seeks regulatory closure on the assets detailed in Table 1