HomeMy WebLinkAbout20001432 Ver 1_Staff Report_20110901September 1.2O11
MEMORANDUM
To: John Olinger, Division Construction Engineer, NODOT Division 8
From: Mason Herndon, NCDVVQ. Fayetteville Regional Office
Subject: Site Visit Follow-up
TIP No. R-2417AA
Lee County
This memo isa follow-up ba our site visit of the Sanford Bypass project (R-2417AA)in Lee County on
August 24.2O11h$ inspect non compliance items that were noted in our letter dated August 18.2D11.
Ronnie Smith with the U.8. Army Corps of Engineers was also present atthis visit. | appreciate the time
your staff spent with us to review this project.
The following comments are provided to help document technical
guidance and assistance hu DOT staff to ensure that this project isoonstmunh*d|ncnmpUanoew|ththe
permits issued to this project.
NFDE0Rmcord Review
The following items need tobe addressed and corrected on all future inspections and reporting:
• SDO's were identified by ID # only on reporting form, DWQ suggest including station number of
device on the form to clearly identify its location and/or have plan sheets with the report
identifying the device location and the assigned |Dnumber.
• When multiple inspections are required |na week, each inspection should be entered ona
separate line. Multiple inspections were noted ono single line.
• All SOO'n must be inspected within 24hnepfe0.5" rain event, During our review of the reports,
we noted aowmra| incidences where some devices where not reviewed within the required time
period.
• Qualitative monitoring nf discharges |o not being documented onreport.
Doe Freeman
Secretary
Ramp B
Repairs ho Structures 197 and 13O have been completed and excessive turbidity ct Site 2. noted during
previous inspection appears tn have been resolved. |n addition, the area surrounding these structures
has been temporary seeded and mulched byDOT. Outlet protection has been installed out the outlet uf
these two structures. DOT needs to continue tm monitor this area after each rain event to make sure
the problem has been corrected.
Site 2m Sta. 33+Q0/33+66
Contractor ceased using the silt basin for dgvvatghngthe jack and bore pit for the 54^ culvert sdthis
location on Monday per DOT after finding that the addition of flocculants and other improvamenbytothe
basin were ineffective. DOT and their contractor have yet ho develop en alternative plan tod$wate[this
piL High turbidity was noted downstream of Patterson Creek below the confluence of this tributary. It is
anticipated that the turbidity ioa result of the ineffectiveness of the basin treating the effluent from the
bore during its previous use. DOT needs tudevelop a better plan for devvatmrimgthe bore site that
will not create mturbid discharge into PmfteYaemCreek.
225 Green 0,Suite 714, Fayetteville, NC 28301-5043
Phm*910433-3300\FAK810486-0707
Internet: www.nowaterwality,orci
An Equal Opportunity\ Affirmative Acton Employer — 5V% Recycled\ 101% Post Consumer Paper
One
NorthCarolina
Nahlraliff
R- 2417AA
September 1, 2011
Site 1 Station 23 +32(RT)
Bore and jack of 24" pipe complete. The stream bank is undisturbed and stable at outlet into Patterson
Creek. DOT asked if rip rap bank stabilization required. DWQ and USACE agree that rip rap bank
stabilization is not necessary.
Site 3 Station 35 +20136 +30(RT)
Mechanical clearing complete, no fill has been placed in wetland. No issues noted.
Site 4 Station 52 +08(LTIRT)
No issues noted. Good stand of vegetation has been established on the east slope. Permitted site at
Station 63 +00(RT) was not reviewed.
Site 5 Station 87 +80(LTfRT)
54" RCP has been installed. Nylon net matting has been placed in the stream bed; this material is
unsuitable for this application and needs to be removed. This matting has a long life and aquatic species
are prone to getting tangled up in this material. Permanent impacts to the stream extended beyond their
permitted limits and extend all the way to the right of way. The areas permitted for temporary impacts
have been permanently impacted due to changes in the stream dimension and profile throughout this
reach. The outlet of the pipe is perched approximately 2.5 ft above the natural stream bed at the
permitted limits per elevations take by Mr. Johnson with your staff. This is not in compliance with the
conditions of the 401 WQC issued to this project. The permit requires that the pipe be buried one foot
below the natural stream bed. DWQ request that DOT review the permit drawings and provide an .
explanation to why the stream was permanently impacted beyond the permanent impact limits
and how the improper installation of the 54" culvert occurred. Furthermore, the Department
needs to submit plans on how they propose to rectify these non compliance issues. Based upon
DOT's proposal, additional mitigation may be required for these impacts. This information must
be submitted to DWQ in writing within 30 days of receipt of this letter. Failure to comply with this
request within 30 days will result in a Notice of Violation.
Site 6 Station 120 +20(LT) and 920 +57(LTIRT)
8'x 6' RCBC has been constructed; flow is still going through diversion channel because channel work
has not been completed. Based on the non compliance issues pertaining to the channel work completed
at Site 5, DWQ strongly suggest that DOT schedules a preconstruction site meeting with the DOT
Hydraulic and Natural Environmental Units to ensure that everyone is clear on the proposed
scope of work and permitted limits at this site. If stream impacts occur beyond their permitted
limits a NOV will be issued. Earthen plugs for temporary access roads have placed in the stream
channel within the temporary impact area on both the inlet and outlet end of the culverts. These
structures were not included in the permit application and therefore are not considered approved. Per the
permit drawings the only activities proposed in these areas include channel improvements, bank
stabilization and dewatering BMP's. Furthermore, if these structures had been authorized they were not
constructed in accordance with the NCDOT BMP Manual for Construction and Maintenance Activities.
Filter fabric would be required in the stream bed so the natural stream profile would not be disturbed
during removal of the temporary fill. DWQ request that DOT provide DWQ with revised permit
drawings depicting all temporary stream crossing required for the construction of this project and
a detail of how they will be constructed, This information must be submitted to DWQ in writing
within 30 days of receipt of this letter. Failure to comply with this request within 30 days will
result In a Notice of Violation.
Site 9 Station 178 +82(RT)
Construction of (2) 9'x 7' RCBC is in progress. Rip rap and stone access road has been installed on
outlet of culvert. DWQ's comments for this activity are the same as those stated above for Site 6.
Proposed channel work has not been completed at this time. As state above in the comments for Site
6, DWQ strongly suggest that DOT schedules a preconstruction site meeting with the DOT
Hydraulic and Natural Environmental Units to ensure that everyone is clear on the proposed
scope of work and permitted limits at this site.
R- 2417AA
September 1, 2011
Summary: DWQ is very concerned with the consistent non compliance issues that have been occurring
on this project. Future non compliance issues on this project will be unacceptable and will likely result in
the issuances of a NOV. To assist the Department with this project, DWQ suggests that the Department
coordinate a regularly scheduled monthly field inspection (ie. second Thursday of every month) with DOT
staff, the contractor, DWQ and the USACE, so we can work together in getting this project in compliance.
Please let me know what day each month will work for your staff and the USACE as soon as possible so I
can reserve it on my calendar.
If you have any questions on the items described above or need a clarification of the information that has
been requested, please do not hesitate to give me a call at (910) 3084021 or contact me via e-mail.
Cc: Marty Tillman, PE, Division 8 Resident Engineer, Lee County
Sarah Lentine, PE, Division 8 Assistant Resident Engineer
Art King, Division 8 Environmental Officer
Belinda Henson, SWPS, Fayetteville Regional Office
Ronnie Smith, US Army Corps of Engineers, Wilmington District Office
Barry Harrington, NCOOT Roadside Environmental, Div. 7 & 8
Brian Wrenn, DWQ Wetlands /401 Transportation Group
File Copy