Loading...
HomeMy WebLinkAbout20001432 Ver 1_NOV Response_20110930I am STATE OF NORTH CAROLINA DEPARTMENT OF TRANSPORTATION BEVERLY EAVES PERDUE GOVERNOR September 28, 2011 Mason Herndon NCDWQ Fayetteville regional office 225 Green Street Fayetteville, NC 28301 1 9" JENR-FRO $' ]A " 11,11P Nfl � I EwENE A. CONTI, JR. SECRETARY The following is in response to your letter sent from the NCDWQ Fayetteville Regional Office dated September 1, 2011 concerning compliance issues on TIP Project R-2417AA in Lee County. In your letter you had sited issues at three separate locations within the project area that required corrective actions or explanation. The following is a listing of your comments followed by our responses. Your letter listed comments on 8 separate sites. In our response I am only including 3 sites (sites 5, 6, 9) for which a response is required at this time. The issues at Ramp B, Sites 1, 2a, 3 and 4 have all been resolved. At site 2a the bore has been completed. The discharge water was pumped into a sprayer truck and used on the project for dust control. Comment: Site 5 Station 87+90(LTIRT) 54" RCP has been installed. Nylon net matting has been placed in the stream bed; this material is unsuitable for this application and needs to be removed. This matting has a long life and aquatic species are prone to getting tangled up in this material. Permanent impacts to the stream extended beyond their permitted limits and extend all the way to the right of way. The areas permitted for temporary impacts have been permanently impacted due to changes in the stream dimension and profile throughout this reach. The outlet of the pipe is perched approximately 2.5 ft. above the natural stream bed at the permitted limits per elevations take by Mr. Johnson with your staff. This is not in compliance with the conditions of the 401 WQC issued to this project. The permit requires that the pipe be buried one foot below the natural stream bed. DWQ request that DOT review the permit drawings and provide an explanation to why the stream was permanently impacted beyond the permanent impact limits and how the improper installation of the 54" culvert occurred. Furthermore, the Department needs to submit plans on how they propose to rectify these non-compliance issues. Based upon DOT's proposal, additional mitigation may be required for these impacts. This information must be submitted to DWQ in writing within 30 days of receipt of this letter. Failure to comply with this request within 30 days will result in a Notice of Violation. P.O. BOX 1067, ABERDEEN, NORTH CAROLINA 28315 PHONE (910) 944-2344 FAX (910) 944-5623 Response: The matting has been removed from the channel. Although the pipe was initially installed properly at the correct invert of 1 foot below stream bed level, subsequent work for grading and stabilization along the bank and in the channel by the subcontractor caused the pipe to become perched. Additional grading work by the subcontractor has also impacted the stream from the permitted areas at both ends of the pipe, out to the right of way limits (both ends). We have tentatively proposed that a series of log cross veins be installed to restore the proper invert of one foot below bed level by using the logs as grade control devices to raise the stream bed, and then to gradually lower it back to the natural level as the cross veins progress downstream, by lowering each subsequent vein by 8 inches. It is possible that the depth to rock at this location may make this repair impractical. As we discussed during our phone conversation, we may need to revisit this site at a future date after we have had a chance to observe the effects of flow through the site. As you are aware this channel has intermittent flow limited primarily to rainfall events The Division is also requesting that NEU obtain an additional 50 feet of stream mitigation at site 5 (30 feet upstream, and 20 feet downstream) to cover the areas impacted between the temporarily impacted area denoted in the plans on both ends of the pipe, out to the right of way limits. Comment: Site 6 Station 120 +20(LT) and 120 +57(LTlRT) 8' x 6' RCBC has been constructed; flow is still going through diversion channel because channel work has not been completed. Based on the non - compliance issues pertaining to the channel work completed at Site 5, DWQ strongly suggest that DOT schedules a preconstruction site meeting with the DOT Hydraulic and Natural Environmental Units to ensure that everyone is clear on the proposed scope of work and permitted limits at this site. If stream impacts occur beyond their permitted limits a NOV will be issued. Earthen plugs for temporary access roads have placed in the stream channel within the temporary impact area on both the inlet and outlet end of the culverts. These structures were not included in the permit application and therefore are not considered approved. Per the permit drawings the only activities proposed in these areas include channel improvements, bank stabilization and dewatering BMP's. Furthermore, if these structures had been authorized they were not constructed in accordance with the NCDOT BMP Manual for Construction and Maintenance Activities. Filter fabric would be required in the stream bed so the natural stream profile would not be disturbed during removal of the temporary fill. DWQ request that DOT provide DWQ with revised permit drawings depicting all temporary stream crossing required for the construction of this project and a detail of how they will be constructed. This information must be submitted to DWQ in writing within 30 days of receipt of this letter. Failure to comply with this request within 30 days will result in a Notice of Violation. Response: An approved Temporary stream crossing plan drawing was included in the construction plans (Sheet EC -21)). This plan is suitable for a crossing that does not require that flow be maintained by simply removing the pipe. This plan was not followed by the contractor at this location. Instead, an earthen dike without a fabric liner was placed in the dewatered stream channel between the diversion device and the upstream end of the newly constructed culvert by the contractor. This area was used as a crossing point to move equipment around the culvert during construction. We acknowledge that the crossing was improperly installed and has impacted the existing stream channel. We are requesting that NEU obtain 30 feet of additional stream mitigation at this location to cover the impacted area. The earthen dike will be removed and the channel will be restored to its original contours, re-vegetated, and allowed to stabilize before the stream is turned into the new culvert. Comment: Site 9 Station 178+82(RT) Construction of (2) 9' x 7' RCBC is in progress. Rip rap and stone access road has been installed on outlet of culvert. DWQ's comments for this activity are the same as those stated above for Site 6. Proposed channel work has not been completed at this time. As state above in the comments for Site 6, DWQ strongly suggest that DOT schedules a preconstruction site meeting with the DOT Hydraulic and Natural Environmental Units to ensure that everyone is clear on the proposed scope of work and permitted limits at this site. Response: An approximately 10 foot area of the original stream channel was filled with an earthen dike by the contractor as a means to move his equipment around the culvert structure. We are also requesting an additional 10 feet of mitigation at this site. The earthen dike will be removed and the channel will be restored to its original contours, re- vegetated, and allowed to stabilize before the stream is turned into the new culvert. If you require additional information or material, please contact me. Sincerely, Art C. King DEO Highway Division 8 Cc: Ronnie Smith, US Army Corps of Engineers John Olinger, PE Division 8 Construction Engineer Rachelle Beauregard, NCDOT, NEU Marty Tillman, Resident Engineer n Oti CACA P) r a' �j ` c o�L r ro r _ �a z e i 1 a m n m i rpyn �I� N � m O m � 0 1 m N H H OLIQ O f1�m w not bCm 0,0 ZLiP my c�0 �m m O w z n Y m H �K i� 1 mi m 0 a N m CA Z a) as •nc eR -�. -r r PROJECT EFTTkENCE NO. SHEET NO. L = 4,485,60 T = 2271B' R 11,459J6' ALGERIA STAMPS = SE = 0.02 V = 70 MPH 25 x12 x3 24 x12 x3 1.5 inch Skimmer 1.5 inch Skimmer will 0.375 inch with 0.375 inch Orifice Diameter Orifice Diameter 4 ft. weir 4 ft. weir I 9.4 F ID 9.5 F O.C. HOLLER R. JOSEPHINE H. N ACK BERM DITCH 08 425 PC 2 W /CL B RIP RAP EST TONS 6 ESi 130 SY FF SEE DETAIL 'P' RFA DITCH � �1 at 3 I C 80 1 \ 18' 1 56 x14 x3 1.5 inch Skimmer ����••��J/J R- 2417AA Ec- 97coNsr.9 r RAY SHEET 140. 9 Pl Sta 85 +338! 6 ft. weir • ROADWAY DESIGN ENGINEER HYDRWUCS ENGINEER C x a SE Q = 22' 25'409 (RT) Basin Detail) I 9.1 F 0 = 0' 30' 00.0' L = 4,485,60 T = 2271B' R 11,459J6' ALGERIA STAMPS = SE = 0.02 V = 70 MPH 25 x12 x3 24 x12 x3 1.5 inch Skimmer 1.5 inch Skimmer will 0.375 inch with 0.375 inch Orifice Diameter Orifice Diameter 4 ft. weir 4 ft. weir I 9.4 F ID 9.5 F O.C. HOLLER R. JOSEPHINE H. N ACK BERM DITCH 08 425 PC 2 W /CL B RIP RAP EST TONS 6 ESi 130 SY FF SEE DETAIL 'P' RFA DITCH � �1 at 3 I C 80 1 \ 18' 1 i �m0 s= fgyt�-r6q� jP. aJyW its SQL E M19 q2 9 �o 56 x14 x3 1.5 inch Skimmer "ELtNA EDWARDS.et with 0.875 inch \\ r Orifice Diameter P' 6 ft. weir • (See Tiered Skimmer C x a SE A NE Basin Detail) I 9.1 F i �m0 s= fgyt�-r6q� jP. aJyW its SQL E M19 q2 9 �o � r T 47,19R 5 1 F N�r p 1 i ! 11i JJL(jf31`K(E N ��T7? 1 I I 5 F T IL 'N I I WAR S. a a�Cj pp 2 PC Sc , 2 } LEGEND \\ ® PAVED SHOULDER FOR -L- PROFILE. SEF SHEET NOS. 28 & 29 f z t 3 l r1 F �Y `r 3 } ji "ELtNA EDWARDS.et US 324 PC 943 P' PLAT SLIDE 4-12 R]� 2.ax • /1 C x a SE A NE r, AS W is 1 Safi E.— •,i�// II! / /iG/ / / / /j/ MOW 11 /�111f�f��/1 r x: rrM .�rr���r +raarawrr� IIf I/II!!l�I�►�vi��n�r����irir�� � r T 47,19R 5 1 F N�r p 1 i ! 11i JJL(jf31`K(E N ��T7? 1 I I 5 F T IL 'N I I WAR S. a a�Cj pp 2 PC Sc , 2 } LEGEND \\ ® PAVED SHOULDER FOR -L- PROFILE. SEF SHEET NOS. 28 & 29 f z t 3 l r1 F �Y `r 3 } ji AIAi NPE - 8 TYPE - k AT tic O�X,o 1� 4 18 x9 x3 38 x12 x3 1.5 inch Skimmer 1.5 inch Skimmer with 0.125 inch with 0.5 inch T�rf�a Orifice Diameter Orifice Diameter �� 4 ft. weir 4 k. wait ID 12.1 F ID 12.2 E� 40 x15 x3 ID 12.3 F WIMAM HORNER. of of OB 610 PG 277 PLAT SLIDE 7 -9A PLAT SLi9E 3-51 Ste'• -�� w /FL GR LL iP AAP .2 Tc}N E57. T 5 F \ � DO 610 PG 2T3 AT SLi A i1T SLIDE 3-61 Ir. -o'y "Y� �%� ...a .- ._ -` -eN __ -sew_ �1 ... � ,r.:- .�.:. ::. � > -� '�•+.� M A c� A 5 47.09' 18.3' PRDPOSED GUARDRAIL J' X50' P +2! P AP Q t�' p P. LCT" CNAN l 1+68.72 r FR EL. 242.7 TDJfL.zA2. ST. 10 T NS W/ CL 'k' RIP, RAP 4NR5 Y Es T. 2;S FF +74 T 15 ONS �. 25x 20 207, x 3 2o t, fs o FF I ID 12.1 CG DDE BO CY 1 W + 20 x 20 x 3 \ 22 x 20 x 3 6 ft. weir 4 ft. weir 34 x 16 x 3 r W ID 12.2 CG 117 12.3 CG ID 12.4 F =s E �TION SEQUENCE STA. 120 + 57 VITH LINER (2 FT. BASE, 3 FT. DEEP, 2:1 SIDE SLOPES), DIVERTING FLOW. MENTS. WING FLOW THROUGH PROPOSED CULVERT. K� 30 '� _ r A f �2 �% 4 �` i4 C`� � � 2 � fit% i�• ��s//++ #";�� �., s,ik.k 'ir,�.F� 6 ti f�;i tf. F.t � ;'•` PROJECT REFEI R -241 RA'J ROADWAY DESK EN'I'4EER :)N SEQUENCE STA, 177 + 29 -L- 2 FT. BASE, 3 FT. DEEP, 2:1 SIDE SLOPES), DIVERTING FLOW. THROUGH PROPOSED CULVERT. CFIANI�f1 rn uHex