HomeMy WebLinkAbout20211076 Ver 1_More Info Received_20210810Strickland, Bev
From: wyatt brown <brownenvgrp@gmail.com>
Sent: Tuesday, August 10, 2021 12:37 PM
To: Hopper, Christopher D CIV (USA)
Cc: Cohn, Colleen M; Goss, Stephanie
Subject: [External] Re: SAW-2021-00833 (Air Flow Site / Oak Tree Drive / Selma NC / Johnston
County) - REQUEST FOR ADDITIONAL INFORMATION
Attachments: 8-10-21 WETLAND IMPACT -OVERALL (4).pdf; Revised Submitted Pre -Construction
Notification (PCN) Form (46).pdf
CAUTION: External email. Do not click links or open attachments unless you verify. Send all suspicious email as an attachment to
Report Spam.
Chris, Colleen
I'm attaching the revised drawings and revised PCN for the SAW-2021-00833 Air Flow Site
additional information email of August 2, 2021. I could not submit through Additional Information on
Laserfiche because I don't have a WQ project number and Version number. I revised the front page of the
previously submitted PCN reflecting the addition of NW 18 permit number and revised the impacts table
breaking out the parking lot impact for NW 39 and the BMP impact for NW 18. All revisions were made in red
and I added today's date to the signature page of the PCN. I also request an email from Colleen that we don't
need a 401 on this one.
Thanks for your time.
Wyatt
On Mon, Aug 2, 2021 at 3:26 PM Hopper, Christopher D CIV (USA)
<Christopher.D.Hopper@usace.army.mil> wrote:
Good Afternoon, Wyatt:
Thank you for your application to construct the Airflow facility in Selma, North Carolina. I have a couple
questions before verifying your use of Nationwide Permit 39. Please see below and let me know if you have
questions.
1. Nationwide Permit 39 Regional Condition a. prohibits discharges to streams and wetlands for
stormwater management facilities. If the applicant wishes to stack this application with another permit
request (e.g. NWP 18), please provide a breakdown of areas required for each impact (i.e.
parking/building and stormwater). Please provide an updated impact exhibit and impact table.
2. Little information was provided on the BMP. Would a discharge to downslope wetland / stream areas be
included in the design? Please provide additional detail.
I.
3. It appears this project may not require an Individual Water Quality Certification from the State of North
Carolina. Please provide written verification from the NC Division of Water Resources for our records.
Thank you,
Christopher D. Hopper
I Regulatory Specialist
I U.S. Army Corps of Engineers
Regulatory Division
3331 Heritage Trade Drive, Suite 105
Wake Forest, NC 27587
(919) 554-4884, Ext. 35
We would appreciate your feedback on how we are performing our duties. Our automated Customer Service
Survey can be accessed by copying and pasting the following link into your web browser:
https://regulatory.ops.usace.army.mil/customer-service-survey/ Thank you for taking the time to visit this site
and complete the survey.
From: RaleighNCREG <RaleighNCREG@usace.army.mil>
Sent: Wednesday, July 7, 2021 8:14 AM
To: brownenvgrp@gmail.com
Cc: Hopper, Christopher D CIV (USA) <Christopher.D.Hopper@usace.army.mil>; Thames, Joyce A CIV
USARMY CESAW (USA) <Joyce.A.Thames@usace.army.mil>
Subject: SAW-2021-00833 (Air Flow Site / Oak Tree Drive / Selma NC / Johnston County)
Good Morning,
We have received your Pre -Construction Notification (PCN) NWP request for the above project and forwarded
it to Mr. Christopher Hopper for further processing.
2
Thank you,
Josephine Schaffer
Regulatory Division
Wilmington District, USACE
(919) 554 4884 ext. 28
Wyatt Brown, LSS, CPESC
Brown's Environmental Group, Inc
919-524-5956
3
Oak Tree Drive60' Public R/W16216216116016116116216116116216115915915915915915915915915916016016016016016016016016416316016216116116116216116116216116015915915915915915915915915916016016016016016016016016316416315815615715916116016216215615815615715916116015943SOURCES OF INFORMATION:
1.EXISTING SURVEY OF SITE PROVIDED BY HALL LAND SURVEYING, INC., 1899 STEVEN'S CHAPEL
ROAD, SMITHFIELD, NC 27577, DATED APRIL 29, 2021
2.EXISTING TOPO OF SITE PROVIDED BY HALL LAND SURVEYING, INC., 1899 STEVEN'S CHAPEL
ROAD, SMITHFIELD, NC 27577, DATED APRIL 29, 2021
3.EXISTING WATER MAIN INFORMATION FROM TOWN OF SELMA WATER PLANT
SUPERINTENDENT, EMAILED MARCH 30, 2021.
4.PARCEL INFORMATION FROM JOHNSTON COUNTY GIS DATED 2018
5.EXISTING WETLANDS FLAGGED BY BROWN'S ENVIRONMENTAL GROUP, INC., 242 BATTEN FARM
ROAD, SELMA, NC 27576 AND SURVEYED BY HALL LAND SURVEYING, INC., 1899 STEVEN'S
CHAPEL ROAD, SMITHFIELD, NC 27577, DATED APRIL 29, 2021
SOURCES OF INFORMATION
NAD83314 East Main StreetClayton, NC 27520donnie@adamsandhodge.com919-243-1332FIRM # C-4187ADAMS & HODGEENGINEERING, PCGRAPHIC SCALE: 1"=40'4020040SHEET 1 OF 1WETLAND IMPACT MAPAIRFLOW INDUSTRIAL SITESELMA, JOHNSTON COUNTY, NORTH CAROLINA0PROJECT BOUNDARY
AIRFLOW INDUSTRIAL SITE
8/10/2021 6:25 AM
REVISED
WETLANDS
WETLAND IMPACT
WETLAND TO BE IMPACTED
0.035 AC
WETLAND TO REMAIN
0.018 AC VICINITY MAP
NTS
SITE WEST STNAD
83
PROPOSED BUILDING
Pre-Construction Notification (PCN) Form
For Nationwide Permits and Regional General Permits
(along with corresponding Water Quality Certifications)
June 1, 2021 Ver 4.1
Please note: fields marked with a red asterisk * below are required. You will not be able to submit the form until all mandatory questions are answered.
Also, if at any point you wish to print a copy of the E-PCN, all you need to do is right-click on the document and you can print a copy of the form.
Below is a link to the online help file.
https://edocs.deq.nc.gov/WaterResources/0/edoc/624704/PCN%20Help%20File%202018-1-30.pdf
County (or Countie s) where the proje ct is locate d:*
Is this a NCDM S Proje ct *
Is this project a public transportation project?*
1a. Type (s) of approv al sought from the Corps:*
Has this PCN pre v iously be e n submitte d?*
1b. What type (s) of pe rmit(s) do you wish to se e k authorization?*
1c. Has the NWP or GP numbe r be e n v e rifie d by the Corps?*
Nationwide Pe rmit (NWP) Numbe r:
NWP Numbe rs (for multiple NWPS):
1d. Type (s) of approv al sought from the DWR:*
Pre-Filing Meeting Information
A. Processing Information
Johnston
Yes No
Click Yes, only if NCDMS is the applicant or co-applicant.
Yes No
This is any publicly funded by municipal,state or federal funds road, rail, airport transportation project.
Section 404 Permit (wetlands, streams and waters, Clean Water Act)
Section 10 Permit (navigable waters, tidal waters, Rivers and Harbors Act)
Yes
No
Nationwide Permit (NWP)
Regional General Permit (RGP)
Standard (IP)
Yes No
39 - Commercial/Institutional Developments
List all NW numbers you are applying for not on the drop dow n list.
check all that apply
401 Water Quality Certification - Regular 401 Water Quality Certification - Express
Non-404 Jurisdictional General Permit Riparian Buffer Authorization
Individual 401 Water Quality Certification
Before submitting this form please ensure you have submitted the Pre-Filing Meeting Request Form as we will not be able to accept your application without this important first step. The Pre-Filing
Meeting Request Form is used in accordance with 40 C.F.R. Section 121.4(a) “At least 30 days prior to submitting a certification request, the project proponent shall request a pre-filing meeting with the
certifying agency” and in accordance with 40 C.F.R. Section 121.5(b)(7), and (c)(5) all certification requests shall include documentation that a pre-filing meeting request was submitted to the certifying
authority at least 30 days prior to submitting the certification request. Click he re to read more information on when this form is needed prior to application submission or he re to view the form.
Is this a courte sy copy notification?*
ID#Ve rsion
Pre -fling M e e ting or Re que st Date *
Yes No
1e . Is this notification sole ly for the re cord be cause writte n approv al is not re quire d?
*
For the re cord only for DWR 401 Ce rtification:
For the re cord only for Corps Pe rmit:
1f. Is this an afte r-the -fact pe rmit application?*
1g. Is payme nt into a mitigation bank or in-lie u fe e program propose d for mitigation of impacts?
Acce ptance Le tte r Attachme nt
1h. Is the proje ct locate d in any of NC's twe nty coastal countie s?*
1j. Is the proje ct locate d in a de signate d trout wate rshe d?*
Link to trout information: http://www.saw.usace.army.mil/Missions/Regulatory-Permit-Program/Agency-Coordination/Trout.aspx
1a. Who is the Primary Contact?*
1b. Primary Contact Email:*
1c. Primary Contact Phone :*
1d. Who is applying for the pe rmit?*
1e . Is the re an Age nt/Consultant for this proje ct?*
2. Owner Information
Attach docume ntation of Pre -Filing M e e ting Re que st he re :*
6/10/2021
Click the upload button or drag and drop files here to attach document
DWR Pre-Filing Meeting Request Form (28).pdf 53.18KB
File type must be PDF
Yes No
Yes No
Yes No
If so, attach the acceptance letter from mitigation bank or in-lieu fee program.
Yes No
Click the upload button or drag and drop files here to attach document
FILE TYPE MUST BE PDF
Yes No
Yes No
B. Applicant Information
Wyatt Brown
brownenvgrp@gmail.com
(xxx)xxx-xxxx
(919)524-5956
Owner Applicant (other than owner)
(Check all that apply)
Yes No
2a. Name (s) on re corde d de e d:*
2b. De e d book and page no.:
2c. Contact Pe rson:
2d. Addre ss *
2e . Te le phone Numbe r:*
2f. Fax Numbe r:
2g. Email Addre ss:*
TOBACCO ROAD PROPERTIES, LLC
05343, 0185
(for Corporations)
Jeff Holt
City
Selma
State / Province / Region
NC
Postal / Zip Code
27576
Country
US
Street Address
100 OAK TREE DR
Address Line 2
(xxx)xxx-xxxx
(919)625-9115
(xxx)xxx-xxxx
4. Agent/Consultant (if applicable)
1a. Name of proje ct:*
1b. Subdivision name :
1c. Ne are st municipality / town:*
2a. Prope rty Identification Numbe r:
2b. Prope rty size :
2c. Proje ct Addre ss
2d. Site coordinate s in de cimal de gre e s
Please collect site coordinates in decimal degrees. Use between 4-6 digits (unless you are using a survey-grade GPS device) after the decimal place as appropriate, based on how the location was
determined. (For example, most mobile phones with GPS provide locational precision in decimal degrees to map coordinates to 5 or 6 digits after the decimal place.)
Latitude :*Longitude :*
3. Surface Waters
3a. Name of the ne are st body of wate r to propose d proje ct:*
3b. Wate r Re source s Classification of ne are st re ce iv ing wate r:*
Surface Water Lookup
jeff@airflowproducts.net
4a. Name :*
4b. Business Name :
4c. Addre ss *
4d. Te le phone Numbe r:*
4e . Fax Numbe r:
4f. Email Addre ss:*
Wyatt Brown
(if applicable)
Brown's Environmental Group, Inc
City
Selma
State / Province / Region
NC
Postal / Zip Code
27576
Country
US
Street Address
242 Batten Farm Road
Address Line 2
(919)524-5956
(xxx)xxx-xxxx (xxx)xxx-xxxx
brownenvgrp@gmail.com
C. Project I nformation and Prior Project History
1. Project Information
Air Flow Site
(if appropriate)
Selma
2. Project Identification
(tax PIN or parcel ID)
260520-81-5652 (in acres)
City
Selma
State / Province / Region
NC
Postal / Zip Code
27576
Country
US
Street Address
not assigned
Address Line 2
Oak Tree Drive
35.53869
ex: 34.208504
-78.29867
-77.796371
Mill Creek
WS-IV, NSW
3c. What riv e r basin(s) is your proje ct locate d in?*
3d. Ple ase prov ide the 12-digit HUC in which the proje ct is locate d.*
River Basin Lookup
4. Project Description and History
4a. De scribe the e xisting conditions on the site and the ge ne ral land use in the v icinity of the proje ct at the time of this application:*
4b. Hav e Corps pe rmits or DWR ce rtifications be e n obtained for this project (including all prior phase s) in the past?*
4f. List the total e stimate d acre age of all e xisting we tlands on the prope rty:
4g. List the total e stimate d line ar fe e t of all e xisting stre ams on the prope rty:
4h. Explain the purpose of the propose d proje ct:*
4i. De scribe the ov e rall proje ct in de tail, including indirect impacts and the type of e quipme nt to be use d:*
5. Jurisdictional Determinations
5a. Hav e the we tlands or streams be e n de line ate d on the prope rty or propose d impact are as?*
Comme nts:
5b. If the Corps made a jurisdictional de te rmination, what type of de te rmination was made ?*
Corps AID Numbe r:
5c. If 5a is ye s, who de line ate d the jurisdictional are as?
Name (if known):
Age ncy/Consultant Company:
Othe r:
6. Future Project Plans
6a. Is this a phase d proje ct?*
Are any othe r NWP(s), re gional ge ne ral pe rmit(s), or indiv idual pe rmits(s) use d, or intende d to be use d, to authorize any part of the propose d project or re lated activ ity? This
include s othe r se parate and distant crossing for line ar proje cts that re quire De partme nt of the Army authorization but don’t re quire pre -construction notification.
1. Impacts Summary
1a. Whe re are the impacts associate d with your proje ct? (che ck all that apply):
2. Wetland Impacts
If there are wetland impacts proposed on the site, then complete this question for each wetland area impacted.
"W." will be use d in the table be low to re pre se nt the word "wetland".
Neuse
030202011105
The site is an existing 5 acre tract located on Oak Tree Drive in an industrial park. The site is routinely mowed grass.
The general land use in the vicinity is industrial with some existing homes to the west of the industrial park.
Yes No Unknown
0.053
(intermittent and perennial)
0
The purpose of the project is to construct a manufacturing building for Airflow filters. The site plan includes the building, parking and stormwater bmp.
The project will be to construct a manufacturing building, parking lot and bmp. The site is mostly mowed lawn with a few trees on the north side and the back of the property. The runoff
from the building and asphalt will be diverted to a BMP in the back of the property. The sewage will be carried by sanitary sewer going out the front of the property to Oak Street.
Motor Graders will be used to grade the property and a trackhoe will be used to construct the bmp. The parking lot will be asphalt.
There should be no indirect impacts from this project.
Yes No Unknown
Preliminary Approved Not Verified Unknown N/A
Example: SAW-2017-99999
SAW-2021-00833
Wyatt Brown
Brown's Environmental Group, Inc
Yes No
Not to my knowledge
D. Proposed Impacts Inventory
Wetlands Streams-tributaries Buffers
Open Waters Pond Construction
2a. Site #*(?)2a1 Reason *(?)2b. Impact type *(?)2c. Type of W.*2d. W. name *2e . Fore ste d *2f. Type of
Jurisdicition *(?)
2g. Impact
are a *
2g. Total Te mporary We tland Impact
2g. Total Pe rmane nt We tland Impact
2g. Total We tland Impact
2i. Comme nts:
1. Avoidance and Minimization
1a. Spe cifically de scribe me asure s take n to av oid or minimize the propose d impacts in de signing the proje ct:*
1b. Spe cifically de scribe me asure s take n to av oid or minimize the propose d impacts through construction te chnique s:*
2. Compensatory Mitigation for Impacts to Waters of the U.S. or Waters of the State
2a. Doe s the proje ct re quire Compe nsatory M itigation for impacts to Wate rs of the U.S. or Wate rs of the State ?
2b. If this proje ct DOES NOT re quire Compe nsatory M itigation, e xplain why:
NC Stream Temperature Classification Maps can be found under the Mitigation Concepts tab on the Wilmington District's RIBITS website.
*** Recent changes to the stormwater rules have required updates to this section .***
1. Diffuse Flow Plan
1a. Doe s the proje ct include or is it adjace nt to prote cte d riparian buffers ide ntifie d within one of the NC Riparian Buffe r Prote ction Rule s?
For a list of options to meet the diffuse flow requirements, click here.
If no, e xplain why:
2. Stormw ater Management Plan
2a. Is this a NCDOT proje ct subje ct to compliance with NCDOT’s Indiv idual NPDES pe rmit NCS000250?*
2b. Doe s this proje ct me e t the re quire me nts for low de nsity proje cts as de fine d in 15A NCAC 02H .1003(2)?*
To look up low density requirement click here 15A NCAC 02H .1003(2).
2c. Doe s this proje ct hav e a stormwate r manage me nt plan (SM P) re v ie we d and approv e d unde r a state stormwate r program or state-approv e d local gov e rnme nt stormwate r
program?*
2d. Which of the following stormwate r manage me nt program(s) apply (che ck all that apply):*
Local Gov e rnme nt Stormwate r Programs *
Wetland A parking lot, bmp P Small-Basin Wetland Wetland A Yes Both 0.053
(acres)
0.000
0.053
0.053
E. Impact Justification and Mitigation
In designing the project, 0.018 acres of wetland were left to show minimization the impact.
Through construction the existing wetland will be marked in the field and protected with silt fence. Since the wetland is in the very back there should be
no construction activities in that area.
Yes No
The impact is 0.053 acres, much less than the 0.10 acre threshold.
F. Stormwater M anagement and Diffuse Flow Plan (required by DWR)
Yes No
No buffered streams in or adjacent to the property.
Yes No
Yes No
Yes No
N/A - project disturbs < 1 acre
Hint: projects that have vested rights, exemptions, or grandfathering from state or locally implemented stormw ater programs or projects that satisfy state or locally-implemented stormw ater programs through use of community in-lieu programs should answ er no
to this question.
Local Government State
If you have a local government approval please include the SMP on their overall impact map.
Phase II NSW
USMP Water Supply
Ple ase ide ntify which local gov e rnme nt stormwate r program you are using.*
Comme nts:
1. Environmental Documentation
1a. Doe s the proje ct inv olv e an e xpe nditure of public (fe de ral/state /local) funds or the use of public (fe de ral/state ) land?*
2. Violations (DWR Requirement)
2a. Is the site in v iolation of DWR Wate r Quality Ce rtification Rule s (15A NCAC 2H .0500), Isolate d We tland Rule s (15A NCAC 2H .1300), or DWR Surface Wate r or We tland Standards or
Riparian Buffe r Rule s (15A NCAC 2B .0200)?*
3. Cumulative Impacts (DWR Requirement)
3a. Will this proje ct (base d on past and re asonably anticipate d future impacts) re sult in additional de v e lopme nt, which could impact ne arby downstre am wate r quality?*
3b. If you answe re d “no,” prov ide a short narrativ e de scription.
4. Sewage Disposal (DWR Requirement)
4a. Is se wage disposal re quire d by DWR for this proje ct?*
5. Endangered Species and Designated Critical Habitat (Corps Requirement)
5a. Will this proje ct occur in or ne ar an are a with fe de rally prote cte d spe cie s or habitat?*
5b. Hav e you che cke d with the USFWS conce rning Endange re d Spe cie s Act impacts?*
5c. If ye s, indicate the USFWS Fie ld Office you hav e contacte d.
5d. Is anothe r Fe de ral age ncy inv olv e d?*
5e . Is this a DOT proje ct locate d within Div ision's 1-8?*
5f. Will you cut any tre e s in orde r to conduct the work in wate rs of the U.S.?*
5g. Doe s this proje ct inv olv e bridge mainte nance or re mov al?*
Link to the NLEB SLOPES document: http://saw-reg.usace.army.mil/NLEB/1-30-17-signed_NLEB-SLOPES&apps.pdf
5h. Doe s this proje ct inv olv e the construction/installation of a wind turbine (s)?**
5i. Doe s this proje ct inv olv e (1) blasting, and/or (2) othe r pe rcussiv e activitie s that will be conducte d by machine s, such as jackhamme rs, me chanize d pile driv e rs, e tc.?*
5j. What data source s did you use to de te rmine whe the r your site would impact Endange re d Spe cie s or De signate d Critical Habitat?*
6. Essential Fish Habitat (Corps Requirement)
6a. Will this proje ct occur in or ne ar an are a de signate d as an Esse ntial Fish Habitat?*
6b. What data source s did you use to de te rmine whe the r your site would impact an Esse ntial Fish Habitat?*
Town of Selma
G. Supplementary Information
Yes No
Yes No
Yes No
This is a small manufacturing project located in an existing industrial park. I don't foresee any additional development caused by this project.
Yes No N/A
Yes No
Yes No
Raleigh
Yes No Unknown
Yes No
Yes No
Yes No
Yes No
Yes No
Natural Heritage-List attached at bottom, Our site is basically a mowed lawn with no streams, no habitat on property and no impact.
IpaC- 1) Red-cockaded Woodpecker-No habitat on this property for the woodpecker. 2) Neuse River Waterdog- 3) Carolina Madtom-No stream on or
near out tract, no habitat no effect.
Yes No
7. Historic or Prehistoric Cultural Resources (Corps Requirement)
Link to the State Historic Preservation Office Historic Properties Map (does not include archaeological data: http://gis.ncdcr.gov/hpoweb/
7a. Will this proje ct occur in or ne ar an are a that the state , fe de ral or tribal gov e rnme nts hav e de signate d as hav ing historic or cultural pre se rv ation status (e .g., National Historic
Trust de signation or prope rtie s significant in North Carolina history and archae ology)?*
7b. What data source s did you use to de te rmine whe the r your site would impact historic or arche ological re source s?*
8. Flood Zone Designation (Corps Requirement)
Link to the FEM A Floodplain M aps: https://msc.fema.gov/portal/search
8a. Will this proje ct occur in a FEM A-designate d 100-ye ar floodplain?*
8c. What source (s) did you use to make the floodplain de te rmination?*
Comme nts
Ple ase use the space be low to attach all require d docume ntation or any additional information you fe e l is he lpful for application re v ie w. Documents should be combine d into one
file whe n possible , with a Cov e r Le tte r, Table of Conte nts, and a Cov e r She e t for e ach Se ction pre fe rre d.
*
· The project proponent hereby certifies that all information contained herein is true, accurate, and complete to the best of my knowledge and belief’; and
· The project proponent hereby requests that the certifying authority review and take action on this CWA 401 certification request within the applicable reasonable period of time.
· I have given true, accurate, and complete information on this form;
· I agree that submission of this PCN form is a “transaction” subject to Chapter 66, Article 40 of the NC General Statutes (the “Uniform Electronic Transactions Act”);
· I agree to conduct this transaction by electronic means pursuant to Chapter 66, Article 40 of the NC General Statutes (the “Uniform Electronic Transactions Act”);
· I understand that an electronic signature has the same legal effect and can be enforced in the same way as a written signature; AND
· I intend to electronically sign and submit the PCN form.
Full Name :*
Signature *
Date
None in Johnston County, no streams on the project.
Yes No
Website above, the project will occur within 1 mile of the Richard B Harrison School, this project should not cause any effect on the school.
Yes No
website above
M iscellaneous
Click the upload button or drag and drop files here to attach document
Airflow Package.pdf 8.68MB
File must be PDF or KMZ
Signature
By checking the box and signing below, I certify that:
Wyatt Brown