Dear Sir or Madam:
Attached is a copy of the inspection report which was prepared following an on -site inspection of the
subject site. This report is intended to provide you with information concerning the status of the site as
it relates to compliance with the North Carolina Sedimentation Pollution Control Act of 1973.
Please review this report carefully as it may contain corrective actions needed or comments which will
assist you in meeting the required performance standards of the Act.
It is our desire that any and all possible problems be discussed and resolved at the earliest possible time.
To facilitate this effort, please contact the named inspector at the address shown on the inspection
report if you have any questions.
Sincerely,
Land Quality Section
Mooresville Regional Office
North Carolina Department of Envcranmental Quality Division of Energy. Mineral and Land Resources
DE Mooresville Regional Office! 610 East Center Avenue- Suite 301 Mooresville. North Carolina 29115
jj.o_� 704-663-1699
• • •lI Stornmater Inspection•
North Carolina Department of Environmental Quality
Land Resources: 610 East Center Avenue, Suite 301, Mooresville, NC 28115 (704) 663-1699
County:-vlecklenburg Project: PNG-Huntersville Replacement
Person financially responsible: Piedmont Natural Gas Company, Inc. - Corey
90w4, Operations Supervisor
Address: 4301 Yancey Road, Charlotte, NC 28217
1. Project Location: Westmoreland Road, Cornelius
Pictures: No
River basin: Yadkin-PeeDee
Project #: NIECKL-2021-036
2. Weather and soil conditions: Sunny, Workable Soils Initial inspection: No
3. is site currently under notice of violation? No
4. Is the site in compliance with S.P.C.A. and rules? Yes if no, check violations below:
5. Violations:
6 is the site in compliance with NPDES Permit NCG010000 Construction Stormwater requirements? Yes
Describe:
7. Has sedimentation damage occurred since last inspection? No If Yes, where? (check all that apply)
Degree of damage:
8. Contact made with (name): No One Title:
Inspection report: Sent Report Date given -'sent: July 16, 2021
9. Corrective action needed:
10. Comments: Overall the site has sufficient permanent ground cover to restrain erosion, however there are
some remaining bare areas that need to be stabilized. No additional self -monitoring or
self -inspections are required. Project is in compliance and released under the SPCA.
Termination of coverage under the NPDES General Stormwater Permit for Construction
Activities (NCG01) must be requested by the permittee via a Notice of Termination (NOT)
unless permit approval date was prior to April Ist M9.
The NOT is available at: https:l 'edocs.deq.nc.gov?Forms/NCG01-Termination. Please note
that this correspondence must be uploaded as part of completing the NOT process.
Reported by: Jeffrey Chandler Others present:
Date of inspection: July 14, 2021 Time arriving on site: 10:00 AM Time leaving site: 10:20 AM
cc:
Sedil»elitation/ConstructiolI Stornilvater Inspection Report
North Carolina Department of Environmental Quality
Land Resources: 610 East Center Avenue, Suite 301, Mooresville, NC 281 l5 (704) 663-1699
County: Mecklenburg Project: PNG-Huntersville Replacement River basin: Yadkin-PeeDee
Person financially responsible: Piedmont Natural Gas - Jennifer H Ward. Project #•. MECKL-2019-029
Operations Manager
Address: 4301 Yancey Road, 4720 Piedmont Row Drive PO Box 33068, Charlotte, NC 28217
1. Project Location: Westmoreland Road, Huntersville
Pictures: No
2. Weather and soil conditions: Sunny, Workable Soils Initial inspection: No
3. Is site currently under notice of violation? No
4. Is the site in compliance with S.P.C.A. and rules? Yes If no, check violations below-
S. Violations:
6. Is the site in compliance with NPDES Permit NCG010000 Construction Stormwater requirements? Yes
Describe:
7. Has sedimentation damage occurred since last inspection? No If Yes, where? (check all that apply)
Degree of damage:
8. Contact made with (name): No One Title:
Inspection report: Sent Report Date givenisent; July 16, 2021
9. Corrective action needed:
10. Comments: Overall, the site has sufficient permanent ground cover to restrain erosion, however there are
some bare areas that need to be stabilized. No additional self -monitoring or self -inspections
are required. Project is in compliance and released under the SPCA. Termination of coverage
under the NPDES General Stormwater Permit for Construction Activities (NCGO1) must be
requested by the permittee via a Notice of Termination (NOT) unless permit approval date
was prior to April I st 2019.
The NOT is available at: https_`.'edocs,deq.nc_govlForms?7vCG01-Termination. Please note
that this correspondence must be uploaded as part of completing the NOT process_
Reported by: Jeffrey Chandler Others present:
Date of inspection: July 14, 2021 Time arriving on site: 10:00 AM Time leaving site: 10'20 AM