HomeMy WebLinkAboutNCC214398_ESC Approval Submitted_20210802ROY COOPER
Governor
ELIZABETH S. BISER
Secretary
BRIAN WRENN
Director
West Cumberland/United, LLC
Attn: Murray O. Duggins, Jr., Owner
P.O. Box 2888
Greensboro, NC 27402
NORTH CAROLINA
Environmental Quality
July 23, 2021
LETTER OF APPROVAL
Express Option
RE: Project Name: West Cumberland Apartments
Acres Approved: 6.15
Project ID: CUMBE-2022-006
County: Cumberland, City: Fayetteville,
River Basin: Cape Fear
Stream Classification: Other
Submitted By: Hagen Engineering, PA
Date Received by LQS: July 16, 2021
Plan Type: Express
Dear Mr. Duggins:
Address: Raeford Road/Hwy 401
This office has reviewed the subject erosion and sedimentation control plan. We find the plan to be
acceptable and hereby issue this Letter of Approval. The enclosed Certificate of Approval must be posted
at the job site. This plan shall expire three (3) years following the date of approval, if no land disturbing
activity has been undertaken, as required by Title 15A NCAC 413.0129.
As of April 1, 2019, all new construction activities are required to complete and submit an electronic
Notice of Intent (NOI) form requesting a Certificate of Coverage (COC) under the NCGO10000
Construction Stormwater General Permit. This form MUST be submitted and COC issued prior to the
commencement of any land disturbing activity on the above -named project. The NOI form may be
accessed at deq.nc.Rov/NCG01. Please direct questions about the NOI form to Annette Lucas at
Annette.lucaskncdenr.gov or Paul Clark at Paul.clarkkncdenr.gov. After you submit a complete and
correct NOI Form, a COC will be emailed to you within three business days. A $100 fee will be charged
annually until a Notice of Termination is issued. This fee is to be sent to the DEMLR Stormwater Central
Office staff in Raleigh.
Title 15A NCAC 4B .0118(a) and the NCGO1 permit require that the following documentation be kept on
file at the job site:
1. The approved E&SC plan as well as any approved deviation.
2. The NCGO1 permit and the COC, once it is received.
3. Records of inspections made during the previous 12 months.
E Q�� North Carolina Department of Environmental Quality I Division of Energy, Mineral and Land Resources
Fayetteville Regional Office 1225 Green Street, Suite 7141 Fayetteville, North Carolina 28301
NORTH CAROLINA -
oewnmwtoiEnviro�memalaual� /`� 910.433.3300
Letter of Approval with Modifications
West Cumberland/United, LLC
July 23, 2021
Page 2 of 2
This letter gives the notice required by G.S. 113A-61.1(a) of our right of periodic inspection to ensure
compliance with the approved plan.
Title 15A NCAC 413 .0118(a) requires that a copy of the approved erosion control plan be on file
at the job site. Also, this letter gives the notice required by G.S. I I3A-61.1(a) of our right of
periodic inspection to ensure compliance with the approved plan.
North Carolina's Sedimentation Pollution Control Act is performance -oriented, requiring protection of
existing natural resources and adjoining properties. If, following the commencement of this project, it is
determined that the erosion and sedimentation control plan is inadequate to meet the requirements of the
Sedimentation Pollution Control Act of 1973 (North Carolina General Statute 113A-51 through 66), this
office may require revisions to the plan and implementation of the revisions to ensure compliance with
the Act.
Acceptance and approval of this plan is conditioned upon your compliance with Federal and State water
quality laws, regulations, and rules. In addition, local city or county ordinances or rules may also apply to
this land -disturbing activity. This approval does not supersede any other permit or approval.
Please note that this approval is based in part on the accuracy of the information provided in the Financial
Responsibility Form, which you provided. You are requested to file an amended form if there is any
change in the information included on the form. This permit allows for a land -disturbance, as called for
on the application plan, not to exceed the approved acres. Exceeding the acreage will be a violation of
this permit and would require a revised plan and additional application fee. In addition, it would be
helpful if you notify this office of the proposed starting date for this project.
Your cooperation is appreciated.
Sincerely,
-�
Jodi Pace, EI
Regional Engineering Associate
DEMLR
Enclosures: Certificate of Approval
NPDES NCGO1 Fact Sheet
cc: Nolan Franz, Hagen Engineering, PA (electronic copy)
David Steinmetz, Building Inspector (electronic copy)
David Winstead, City of Fayetteville Permits (electronic copy)
DEMLR - Fayetteville Regional Office File