HomeMy WebLinkAbout20120712 Ver 1_Email_20130228RE: B -4488 Slocum Creek - Moratorium
, Page 1 of 3
RE: B -4488 Slocum Creek - Moratorium (C' veL�7
Ward, Garcy
Sent: Thursday, February 28, 2013 2:10 PM
To: Johnson, Jay B; Lane, Stephen; Steffens, Thomas A SAW (Thomas.A.Steffens @usace.army.mil)
Cc: Wainwright, David; Wilson, Travis W.; Carrillo, Sonia; Ward, Garcy
Jay,
This e -mail serves as authorization from DWQ to continue in -water work on Bridge 176 over Slocum Creek in
Craven County (B -4488) through March 8th of this year. The in -water work moratorium will begin on March 9th
and continue through September 30th. This supercedes condition 2 of the modification that was issued on
2/8/13. Please print out this e -mail to keep with the 401 Certification. Thanks.
Garcy Ward
Environmental Senior Specialist
North Carolina Division of Water Quality
Washington Regional Office
From: Johnson, Jay B
Sent: Thursday, February 28, 2013 10:15 AM
To: Ward, Garcy; Lane, Stephen; Steffens, Thomas A SAW ( Thomas .A.Steffens @usace.army.mi1)
Cc: Wainwright, David
Subject: FW: B -4488 Slocum Creek - Moratorium
Sirs, Requesting approval to move forward with the Bridge demo through 3/8.
From: Johnson, Jay B
Sent: Thursday, February 28, 2013 7:32 AM
To: Ward, Garcy; Lane, Stephen; Steffens, Thomas A SAW ( Thomas .A.Steffens @usace.army.mil)
Cc: Mcmannen, Brad T; Blankenship, Andrew; Bunn, Eddie J; Eatmon, Bryce E; Brame, Bill Jr.
Subject: FW: B -4488 Slocum Creek - Moratorium
Sirs, FYI. Travis granted extending in water work for bridge demo through March 8th. We can monitor their
progress on Tues. 3/5.
From: Wilson, Travis W.
Sent: Wednesday, February 27, 2013 10:44 AM
To: Mcmannen, Brad T
Cc: Blankenship, Andrew; Johnson, Jay B
Subject: RE: B -4488 Slocum Creek - Moratorium
i
WRC understands the contractor has run into problems that have delayed the removal of the old structure and
concurs with NCDOT's assessment that leaving the partially demolished bridge would be hazardous. Therefore;
WRC does not object to continuing in water work at this site through March 8 as requested.
NOTE: NEW PHONE NUMBER AND MAILING ADDRESS
Travis W. Wilson
Eastern Region Highway Project Coordinator
Habitat Conservation Program
NC Wildlife Resources Commission
1718 Hwy 56 West
https:Hmail.nc.gov /owa/ ?ae= Item& t = IPM. Note& id= RgAAAADMSzLcd9W2TJHI4 %2bm... 3/15/2013
RE: B -4488 Slocum Creek - Moratorium
Creedmoor, NC 27522
Phone: 919 - 707 -0370
Fax: 919 - 528 -2524
Travis.Wilson @ncwildlife.org
From: Mcmannen, Brad T
Sent: Wednesday, February 27, 2013 9:58 AM
To: Wilson, Travis W.
Cc: Blankenship, Andrew; Johnson, Jay B
Subject: FW: B -4488 Slocum Creek - Moratorium
From: Mcmannen, Brad T
Sent: Wednesday, February 27, 2013 9:45 AM
If you have any questions, please let me know.
Thanks,
Brad McMannen, PE
Assistant Resident Engineer
North Carolina Department of Transportation
209 S. Glenburnie Rd.
New Bern, NC 28560
(252) 514 -4759 (P)
(252) 514 -4716 (F)
Page 2 of 3
Email correspondence to and from this sender is subject to the N.C. Public Records Law and may be disclosed to
third parties.
To: Mcmannen, Brad T
Subject: B -4488 Slocum Creek - Moratorium
Travis,
Palmetto is currently working on removing the old bridge structure on Church Street over Slocum Creek.
Contractor has been saw cutting the bridge (deck, rail and caps) into pieces to remove with a crane. They have
been able to remove some of the pieces so far. Contractor has ran into several snags, which include containment
continuously needing repair, saws being sent to have repaired, guy wire on the east side was in the way and
crane not being delivered as scheduled.
The guy wire on the east side of the bridge was 35 feet from end bent 2. This location was in conflict with the
crane being able to function. Progress Energy was able to move the lines on Monday February 25.
The crane which was scheduled to be delivered this week from Edwards, has been delayed and will not arrive
until Monday March 4. The 2 cranes on site currently are not strong enough to remove this structure. This new
crane is much bigger and will be able to handle the loads.
If we stop work due the moratorium, the NCDOT feels that we are creating a hazard for the boating public.
https:Hmail.nc. gov /owa/ ?ae= Item &t = IPM. Note& id= RgAAAADMSzLcd9 W2TJH14 %2bm... 3/15/2013
RE: B -4488 Slocum Creek - Moratorium
Page 3 of 3
The NCDOT requests that the moratorium be extended to Friday March 8 for this project, at which time the
contractor will be completed with bridge demolition.