Loading...
HomeMy WebLinkAbout20200845 Ver 1_Corps Comment Response_20210428West Neuse Interceptor Action ID SAW-2020-00564 April 26, 2021 Response to USACE Request for Additional Information Per the email of 7/21/20, the following provides each comment/question with a response (in bold italics) to each. Also attached are 1) Revised Impact Tables 2) Revised Permit Impact Depictions 3) Response to NMFS questions under the Section 7 Consultation. USACE Comments: 1) It is unclear if all the permanent wetland conversion impacts are addressed. It appears that in several locations that the new sewer line will be installed within forested wetlands that are within the existing easement but are currently not maintained and would result in permanent wetland conversion? a. In order to assist with the review please depict the proposed permanently maintained corridor. The attached revised impact sheets have been developed using current tree -line survey and the engineering design files to depict the permanent maintained corridor in forested wetlands, temporary wetland impacts in forested and non forested areas, and permanent (no loss) stream impacts. b. If additional conversion impacts do occur please update the PCN and exhibits accordingly. Impacts have been updated in the attached revised stream and wetland impact tables. c. In order to assist with the review please add labels showing the impact numbers on the impact exhibits. Impact labels are on the attached revised impact sheets. 2) Per Regional condition 4.1.11 use of rip -rap or any other engineered structures to stabilize a stream bed should be avoided to the maximum extent practicable. If riprap stabilization is needed, it should be placed only on the stream banks, or, if it is necessary to be placed in the stream bed, the finished top elevation of the riprap should not exceed that of the original stream bed. a. Stream impacts listed as temporary for bank stabilization appear to involve introduction of riprap stone within the stream channel and would be considered a permanent impact? All stream impacts are shown as permanent — no loss due to the placement of riprap below the bed elevation of the stream. b. Can you provide an explanation for why riprap is necessary for the proposed impacts? Black & Veatch, the project engineering firm, has reviewed the proposed stream impacts and stream crossing designs. Due to the velocity of the streams, riprap placement in the stream bed is required. The position of this sewer line adjacent to the Neuse River causes the crossings to be at the lower end of the streams where the channels are more incised and discharging at higher velocity into the river. Converting these crossing to more natural stream banks without addressing upstream/watershed controls would not lead to long term stability and may increase the amount of maintenance needed (and therefore temporary disturbances) within the streams. c. Will the proposed riprap be installed as to not exceed that of the original stream bed? Yes — please see the engineering details within the construction plan set that show a cross section of a typical stream crossing, with riprap at the bed elevation. 3) Section G. 5i. of the PCN is checked "Yes" that the project will involve blasting, and/or other percussive activities that will be conducted by machines, such as jackhammers, mechanized pile drivers, etc. a. Can you provide details to include type of percussive activity, purpose, duration, and the location of this activity on the property? Preliminary geotechnical boring locations along the line indicate that percussive activities will be required, but the exact location and extent will not be accurately determined until construction begins. The project is located within the Northern Long -Eared Bat range but Wake County is not shown on the USFWS Raleigh Office website as a county where this species is known to currently occur. In addition, NC Natural Heritage Program records do not indicate known occurrences within the specified % mile radius of the project. 4) In order to verify compliance with section 7(a)(2) of the Endangered Species Act please address the below questions. Note: the Permit area includes the waters that will be directly affected by the proposed work and the uplands directly affected as a result of authorizing the work. a. Does the permit area contain suitable habitat for Michaux's sumac? Some areas of potential habitat exist along the corridor where maintenance regimes allow for this species to survive. The project corridor was surveyed during the 2020 recommended window for this species and none were observed. b. Does the permit area contain suitable habitat for RCW? No. Limited pine stands are present along the corridor and those were of insufficient age or dominated by hardwood species. No known occurrences of RCW are recorded within the project vicinity. c. Note: Additional information may be requested during consultation with USFWS. Understood. 5) Will the existing pipe under the Neuse River be removed? If so will this be done using the same process as installation? Will it be done at the same time? The existing pipe under the Neuse river will be retained, but will not be in service. Having this pipe in place allows for temporary bypass of the proposed sewer line in the event future maintenance is needed, without disturbing the river. 6) It appears as though there is permanent impacts at the Neuse River crossing? a. It appears that permanent riprap is to be installed on the stream banks below the OHWM resulting in permanent impacts. i. Can you provide an explanation for why riprap is necessary for the proposed impact? Velocities in the river are extremely high at times, resulting in the need to stabilize the riverbed at the crossing in order to prevent disturbance to the bed and protect the proposed sewer pipe. Class 1 and 2 riprap is proposed to address this issue. b. It appears that the concrete pipe encasement meets the existing stream bed elevation of the Neuse River at one location? i. Can the depth/slope of the pipe can be altered so that the natural stream bed material could be placed to match the preexisting conditions? No — the proposed sewer line is designed at the absolute minimum grade to connect to existing infrastructure while allowing the sewer line to flow and prevent blockages. This is also why the river crossing is proposed for open -cut as subsurface technologies would not guarantee that the exact grade will be maintained. ii. As proposed the concrete encasement may be a permanent stream channel impact. A small permanent impact of 20 square feet of concrete encasement will be exposed in the river bed, but is too small to depict on the impact maps. 7) The location of the Neuse River crossing is located approximately 5000 linear feet upstream of NOAAs critical habitat designation and NCWRCs Anadromous Fish Spawning Inland Waters Area. The extent of these areas were limited to the Neuse downstream of the Milburnie Dam, which since has been removed. It appears that in order to verify compliance with General Condition 3 & 18 and Regional Conditions 1.1 & 1.3 coordination/consultation with NOAA and NCWRC will be necessary. a. I have attached the Section 7 checklist which will need to be filled out in order to consult with NOAA. Acknowledged — Section 7 Consultation with NMFS is ongoing and responses to their request for information is also attached. West Neuse Interceptor Action ID SAW-2020-00564 April 26, 2021 Response to NMFS Request for Additional Information 1. The copies of some of the plan drawing pages are very low resolution and are not legible even when zoomed in on screen. Please submit legible copies of pages G (C?)-02, G (C?)-03, D-04, D- 05, and D-06. Higher resolution plans are available at the link provided via email. 2. The project description mentions that coffer dams will be installed to dewater portions of the river during construction. Please provide the details on the construction and placement methods for these temporary structures (number and size of piles (if used) and how they will be driven into/ secured to the substrate for placement). The engineer doesn't typically dictate the exact method or type of coffer dam in contracts, but would expect that the Porta-dam system, or similar approach, may be used. This would not require piles. These are metal frames with a waterproof membrane (like a tarp) pulled over the frame. Additional information is available at the following link: Temporary Cofferdams, Flood Protection & Water Storage (portadam.com) 3. If the exact number of piles is not known, please estimate the number of piles to be driven per day (if used). See response to #2, if piles are used it is unknown how many may be installed per day, but none are anticipated. 4. The project description also mentions excavation of the substrate for placement of the pipes crossing the river, but the Section 7 checklist says there will be no dredging. Please estimate the amount (volume) of material that will be excavated. The checklist was filled out interpreting "dredging" differently from "excavation" while notifying NMFS of excavation that will occur. All volume of material excavated will essentially be equal to volume of the pipe and the concrete around the pipe. Excavation within the river would be approximately 950 cubic yards. All excavation is temporary, with river bottom elevations to be restored to pre -construction elevations. 5. If spoils will be stored temporarily on site, please describe how/ where it will be stored prior to replacement. Spoils will be stored in the construction easement away from the river prior to being hauled offsite for disposal. Stockpile areas will be secured with erosion control measures (silt fence etc.) to prevent sedimentation of adjacent waters during the storage period. 6. Please include how any excess spoils will be disposed of. Spoils will be disposed of offsite in upland areas with adequate stabilization. Wetland Impact TableImpactsFeature Type Impact no. Reason For Impact Impact Type Wetland Type Feature Name Forested? Y/N Jurisdiction Original PCN (acres) April 2021 (acres)Wetland W1 Utility Construction T Bottomland Hardwood Forest WAG Y USACE 0.546 0.550Wetland W2 Utility Construction T Bottomland Hardwood Forest WAH Y USACE 0.006 0.006Wetland W2 Utility Construction T Bottomland Hardwood Forest WAH N USACE N/A <0.001Wetland W3 Utility Construction T Bottomland Hardwood Forest WAF N USACE 0.024 0.023Wetland W4 Utility Construction T Bottomland Hardwood Forest WAE Y USACE N/A 0.040Wetland W4 Utility Construction T Bottomland Hardwood Forest WAE N USACE 0.079 0.040Wetland W5 Utility Construction T Bottomland Hardwood Forest WAD Y USACE 0.187 0.195Wetland W5 Utility Construction T Bottomland Hardwood Forest WAD N USACE 0.11 0.104Wetland W6 Utility Construction T Bottomland Hardwood Forest WAB Y USACE 0.038 0.038Wetland W6 Utility Construction T Bottomland Hardwood Forest WAB N USACE N/A 0.001Wetland W7 Utility Construction T Bottomland Hardwood Forest WAC N USACE 0.003 0.003Wetland W8 Utility Construction T Bottomland Hardwood Forest WZ Y USACE 0.114 0.101Wetland W8 Utility Construction T Bottomland Hardwood Forest WZ N USACE N/A 0.018Wetland W9 Utility Construction T Bottomland Hardwood Forest WAA Y USACE 0.163 0.157Wetland W9 Utility Construction T Bottomland Hardwood Forest WAA N USACE N/A 0.007Wetland W10 Utility Construction T Bottomland Hardwood Forest WY Y USACE 0.079 0.069Wetland W11 Utility Construction T Bottomland Hardwood Forest WX Y USACE 0.099 0.086Wetland W12 Utility Construction T Bottomland Hardwood Forest WBA Y USACE 0.020 0.020Wetland W13 Utility Construction T Bottomland Hardwood Forest WW Y USACE 0.071 0.062Wetland W14 Utility Construction P Bottomland Hardwood Forest WV Y USACE N/A 0.001Wetland W14 Utility Construction T Bottomland Hardwood Forest WV Y USACE 0.012 0.017Wetland W15 Utility Construction P Bottomland Hardwood Forest WU Y USACE 0.454 0.222Wetland W15 Utility Construction T Bottomland Hardwood Forest WU Y USACE 0.884 1.081Wetland W15 Utility Construction T Bottomland Hardwood Forest WU N USACE 0.368 0.420Wetland W16 Utility Construction T Bottomland Hardwood Forest WT Y USACE 0.364 0.434Wetland W17 Utility Construction P Bottomland Hardwood Forest WAZ Y USACE N/A 0.004Wetland W17 Utility Construction T Bottomland Hardwood Forest WAZ Y USACE N/A 0.021Wetland W17 Utility Construction T Bottomland Hardwood Forest WAZ N USACE 0.030 0.003Wetland W18 Utility Construction T Bottomland Hardwood Forest WS Y USACE 0.008 0.008Wetland W19 Utility Construction T Bottomland Hardwood Forest WR Y USACE 0.077 0.072Wetland W19 Utility Construction T Bottomland Hardwood Forest WR N USACE 0.068 0.072Wetland W20 Utility Construction T Bottomland Hardwood Forest WQ Y USACE 0.012 0.005Wetland W20 Utility Construction T Bottomland Hardwood Forest WQ N USACE N/A 0.007Wetland W21 Utility Construction P Bottomland Hardwood Forest WP Y USACE N/A 0.004Wetland W21 Utility Construction T Bottomland Hardwood Forest WP Y USACE 0.446 0.398Wetland W21 Utility Construction T Bottomland Hardwood Forest WP N USACE 0.235 0.282Wetland W22 Utility Construction T Bottomland Hardwood Forest WO Y USACE 0.023 N/A*Wetland W23 Utility Construction T Bottomland Hardwood Forest WN Y USACE 0.001 0.002Wetland W24 Utility Construction P Bottomland Hardwood Forest WM Y USACE N/A 0.004Wetland W24 Utility Construction T Bottomland Hardwood Forest WM Y USACE 0.22 0.154Wetland W24 Utility Construction T Bottomland Hardwood Forest WM N USACE 0.432 0.432Wetland W25 Utility Construction P Bottomland Hardwood Forest WL Y USACE 0.119 0.06Wetland W25 Utility Construction T Bottomland Hardwood Forest WL Y USACE 0.28 0.296Wetland W26 Utility Construction P Bottomland Hardwood Forest WK Y USACE N/A 0.008Wetland W26 Utility Construction T Bottomland Hardwood Forest WK Y USACE 0.035 0.042Wetland W26 Utility Construction T Bottomland Hardwood Forest WK N USACE 0.403 0.38Wetland W27 Utility Construction T Bottomland Hardwood Forest WAY Y USACE 0.02 0.018Wetland W28 Utility Construction T Bottomland Hardwood Forest WJ Y USACE 0.312 0.236Wetland W28 Utility Construction T Bottomland Hardwood Forest WJ N USACE 0.261 0.327Wetland W29 Utility Construction T Bottomland Hardwood Forest WI Y USACE 0.108 0.091Wetland W29 Utility Construction T Bottomland Hardwood Forest WI N USACE 0.278 0.295Wetland W30 Utility Construction P Bottomland Hardwood Forest WH Y USACE N/A 0.008Wetland W30 Utility Construction T Bottomland Hardwood Forest WH Y USACE 0.07 0.234Wetland W30 Utility Construction T Bottomland Hardwood Forest WH N USACE 0.323 0.142Wetland W31 Utility Construction P Bottomland Hardwood Forest WE Y USACE N/A 0.013Wetland W31 Utility Construction T Bottomland Hardwood Forest WE N USACE 0.069 0.29Wetland W31 Utility Construction T Bottomland Hardwood Forest WE Y USACE 0.529 0.294Wetland W32 Utility Construction T Bottomland Hardwood Forest WD N USACE 0.021 0.012Wetland W32 Utility Construction T Bottomland Hardwood Forest WD Y USACE N/A 0.009Wetland W33 Utility Construction T Bottomland Hardwood Forest WF N USACE 0.26 0.26Wetland W33 Utility Construction T Bottomland Hardwood Forest WF Y USACE N/A 0.025Wetland W34 Utility Construction T Bottomland Hardwood Forest WC Y USACE 0.35 0.374Wetland W34 Utility Construction T Bottomland Hardwood Forest WC N USACE 0.201 0.179Wetland W35 Utility Construction T Bottomland Hardwood Forest WB Y USACE N/A 0.08Wetland W35 Utility Construction T Bottomland Hardwood Forest WB N USACE 0.115 0.036Wetland W36 Utility Construction T Bottomland Hardwood Forest WA Y USACE 0.027 0.027Wetland W37 Utility Construction P Bottomland Hardwood Forest WAJ Y USACE N/A 0.003WetlandW37Utility ConstructionTBottomland Hardwood ForestWAJYUSACE0.0170.013Totals:Impact8.971 8.915*Impact removed due to reduced limits of disturbanceTemp Impact8.398 8.588Perm. Impact0.573 0.327 Stream Impact TableImpactsFeature Type # Reason for Impact Impact Type Type of Impact Stream Name Stream Type Jurisdiction Stream Width Original PCN April 2021Stream S1 Utility Construction P (No Loss) Bank Stabilization SN Perennial USACE 2 N/A 58Stream S1 Utility Construction T Bank Stabilization SN Perennial USACE 2 87 40Stream S2 Utility Construction T Bank Stabilization SM Intermittent USACE 2 55 56Stream S3 Utility Construction P (No Loss) Bank Stabilization SL Intermittent USACE 2 N/A 45Stream S3 Utility Construction T Bank Stabilization SL Intermittent USACE 2 67 20Stream S4 Utility Construction P (No Loss) Bank Stabilization SK Perennial USACE 2 N/A 31Stream S4 Utility Construction T Bank Stabilization SK Perennial USACE 2 106 74Stream S5 Utility Construction P (No Loss) Bank Stabilization SJ Perennial USACE 2 121 120Stream S6 Utility Construction P (No Loss) Bank Stabilization SI Perennial USACE 2 N/A 22Stream S6 Utility Construction T Bank Stabilization SI Perennial USACE 1 42 10Stream S7 Utility Construction P (No Loss) Bank Stabilization SH Intermittent USACE 1 N/A 42Stream S7 Utility Construction T Bank Stabilization SH Intermittent USACE 1 60 20Stream S8 Utility Construction P (No Loss) Bank Stabilization SG Perennial USACE 3 49 50Stream S9 Utility Construction P (No Loss) Bank Stabilization SF Intermittent USACE 1 46 45Stream S10 Utility Construction T Bank Stabilization SD Perennial USACE 2 42 43Stream S11 Utility Construction T Bank Stabilization SC Perennial USACE 2 14 16Stream S12 Utility Construction P (No Loss) Bank Stabilization SE Perennial USACE 2 60 58Stream S13 Utility Construction T Bank Stabilization SB Perennial USACE 2 44 52Stream S14 Utility Construction T Bank Stabilization Neuse River Perennial USACE 180 180 176Totals: Impact973 978Temp Impact697 507Perm. Impact276 471 WAJ/W37 WA/W36 WB/W35 W37: Temporary Wetland Impact (Forested): 0.013 acreW37: Permanent Wetland Conversion: 0.003 acreW36: Temporary Wetland Impact (Forested): 0.027 acreW35: Temporary Wetland Impact (Non-Forested): 0.036 acreW35: Temporary Wetland Impact (Forested): 0.080 acre April 2021 Wetland and S tream ImpactsPage 1 of 21 West Neuse In terceptorImprovementsWake County, NC010050Feet³Limits of Disturbance Pipe C enterline 2' Elevation Contour Permanent Wetland Conversion Temporary Wetland Impact Forested Wetland Permanent (No Loss) Stream Impact Temporary Stream Impact WC /W34 W34: Temporary Wetland Impact (Non-Forested): 0.179 acreW34: Temporary Wetland Impact (Forested): 0.374 acre April 2021 Wetland and S tream ImpactsPage 2 of 21 West Neuse In terceptorImprovementsWake County, NC010050Feet³Limits of Disturbance Pipe C enterline 2' Elevation Contour Permanent Wetland Conversion Temporary Wetland Impact Forested Wetland Permanent (No Loss) Stream Impact Temporary Stream Impact WF/W33 WD /W32 W33: Temporary Wetland Impact (Non-Forested): 0.263 acreW33: Temporary Wetland Impact (Forested): 0.025 acreW32: Temporary Wetland Impact (Non-Forested): 0.012 acreW32: Temporary Wetland Impact (Forested): 0.009 acre April 2021 Wetland and S tream ImpactsPage 3 of 21 West Neuse In terceptorImprovementsWake County, NC010050Feet³Limits of Disturbance Pipe C enterline 2' Elevation Contour Permanent Wetland Conversion Temporary Wetland Impact Forested Wetland Permanent (No Loss) Stream Impact Temporary Stream Impact SB/S13 WE/W31 W31: Permanent Wetland Conversion: 0.013 acreW31: Temp orary Wetland Impact (Non-Forested): 0.290 acreW31: Temp orary Wetland Impact (Forested): 0.294 acreS13: Temporary Stream Impact: 52 linear feet (104 square feet) April 2021 Wetland and S tream ImpactsPage 4 of 21 West Neuse In terceptorImprovementsWake County, NC010050Feet³Limits of Disturbance Pipe C enterline 2' Elevation Contour Permanent Wetland Conversion Temporary Wetland Impact Forested Wetland Permanent (No Loss) Stream Impact Temporary Stream Impact WH/W30 WI/W2 9 W30: Permanent Wetland Conversion: 0.008 acreW30: Temporary Wetland Impact (Forested): 0.234 acreW30: Temporary Wetland Impact (Non-Forested): 0.142 acreW29: Temporary Wetland Impact (Forested): 0.091 acreW29: Temporary Wetland Impact (Non-Forested): 0.295 acre April 2021 Wetland and S tream ImpactsPage 5 of 21 West Neuse In terceptorImprovementsWake County, NC010050Feet³Limits of Disturbance Pipe C enterline 2' Elevation Contour Permanent Wetland Conversion Temporary Wetland Impact Forested Wetland Permanent (No Loss) Stream Impact Temporary Stream Impact WJ/W28 WAY /W27 W28: Temporary Wetland Impact (Forested): 0.236 acreW28: Temporary Wetland Impact (Non-Forested): 0.327 acreW27: Temporary Wetland Impact (Forested): 0.018 acre April 2021 Wetland and S tream ImpactsPage 6 of 21 West Neuse In terceptorImprovementsWake County, NC010050Feet³Limits of Disturbance Pipe C enterline 2' Elevation Contour Permanent Wetland Conversion Temporary Wetland Impact Forested Wetland Permanent (No Loss) Stream Impact Temporary Stream Impact WAY /W27 WK /W26 W26: Permanent Wetland Conversion: 0.008 acreW26: Temporary Wetland Impact (Forested): 0.042 acreW26: Temporary Wetland Impact (Non-Forested): 0.380S14: Temporary Stream Impact: 176 linear feet (33,395 square feet) Neuse River/S14 April 2021 Wetland and S tream ImpactsPage 7 of 21 West Neuse In terceptorImprovementsWake County, NC010050Feet³Limits of Disturbance Pipe C enterline 2' Elevation Contour Permanent Wetland Conversion Temporary Wetland Impact Forested Wetland Permanent (No Loss) Stream Impact Temporary Stream Impact WL/W25 WL/W25 WL/W25 W25: Perman en t Wetland Con vers ion : 0.060 acreW25: Temp orary Wetland Impact (Forested): 0.296 acre April 2021 Wetland and S tream ImpactsPage 8 of 21 West Neuse In terceptorImprovementsWake County, NC010050Feet³Limits of Disturbance Pipe C enterline 2' Elevation Contour Permanent Wetland Conversion Temporary Wetland Impact Forested Wetland Permanent (No Loss) Stream Impact Temporary Stream Impact WM /W24 SE/S12 S12: Permanent (No Loss) Stream Impact: 58 linear feet (116 square feet) WM /W24 Impact to tals shown o n p age 11 April 2021 Wetland and S tream ImpactsPage 9 of 21 West Neuse In terceptorImprovementsWake County, NC010050Feet³Limits of Disturbance Pipe C enterline 2' Elevation Contour Permanent Wetland Conversion Temporary Wetland Impact Forested Wetland Permanent (No Loss) Stream Impact Temporary Stream Impact WM /W24 WM /W24 Impact totals shown on page 11 April 2021 Wetland and S tream ImpactsPage 10 of 21 West Neuse In terceptorImprovementsWake County, NC010050Feet³Limits of Disturbance Pipe C enterline 2' Elevation Contour Permanent Wetland Conversion Temporary Wetland Impact Forested Wetland Permanent (No Loss) Stream Impact Temporary Stream Impact WM /W24 SC/S11 SD/S10 WN /W23 W24: Permanent Wetland Conversion: 0.004 acreW24: Temporary Wetland Impact (Forested): 0.154 acreW24: Temporary Wetland Impact (Non-Forested): 0.432 acreW23: Temporary Wetland Impact (Forested): 0.002 acreS11: Temp orary Stream Impact: 16 linear feet (32 square feet)S10: Temporary Stream Impact: 43 linear feet (86 square feet) WM /W24 April 2021 Wetland and S tream ImpactsPage 11 of 21 West Neuse In terceptorImprovementsWake County, NC010050Feet³Limits of Disturbance Pipe C enterline 2' Elevation Contour Permanent Wetland Conversion Temporary Wetland Impact Forested Wetland Permanent (No Loss) Stream Impact Temporary Stream Impact WP/W21 WQ /W20 SF/S 9 W21: Perman ent Wetland Conversion: 0.004 acreW21: Temp orary Wetland Impact (Forested): 0.398 acreW21: Temp orary Wetland Impact (Non-Forested): 0.282 acreW20: Temp orary Wetland Impact (Forested): 0.005 acreW20: Temp orary Wetland Impact (Non-Forested): 0.007 acreS9: Permanent (No Loss) Stream Impact: 45 linear feet (45 square feet) April 2021 Wetland and S tream ImpactsPage 12 of 21 West Neuse In terceptorImprovementsWake County, NC010050Feet³Limits of Disturbance Pipe C enterline 2' Elevation Contour Permanent Wetland Conversion Temporary Wetland Impact Forested Wetland Permanent (No Loss) Stream Impact Temporary Stream Impact WR /W19 SH /S 7 WS /W18 SG/S 8 WAZ/W17 SI/S6 W19: Temporary Wetland Impact (Forested): 0.072 acreW19: Temporary Wetland Impact (Non-Forested): 0.072 acreW18: Temporary Wetland Impact (Forested): 0.008 acreW17: Permanent Wetland Conversion: 0.004 acreW17: Temporary Wetland Impact (Forested): 0.021 acreW17: Temporary Wetland Impact (Non-Forested): 0.003 acreS8: Permanent (No Loss) Stream Impact: 50 linear feet (150 square feet)S7: Permanent (No Loss) Stream Impact: 42 linear feet (42 square feet)S7: Temporary Stream Impact: 20 linear feet (20 square feet)S6: Permanent (No Loss) Stream Impact: 22 linear feet (22 square feet)S6: Temporary Stream Impact: 10 linear feet (10 square feet) April 2021 Wetland and S tream ImpactsPage 13 of 21 West Neuse In terceptorImprovementsWake County, NC010050Feet³Limits of Disturbance Pipe C enterline 2' Elevation Contour Permanent Wetland Conversion Temporary Wetland Impact Forested Wetland Permanent (No Loss) Stream Impact Temporary Stream Impact WT/W16 W16: Temporary Wetland Impact (Forested): 0.434 acre April 2021 Wetland and S tream ImpactsPage 14 of 21 West Neuse In terceptorImprovementsWake County, NC010050Feet³Limits of Disturbance Pipe C enterline 2' Elevation Contour Permanent Wetland Conversion Temporary Wetland Impact Forested Wetland Permanent (No Loss) Stream Impact Temporary Stream Impact WU /W15 WU/W25 Impact totals shown on page 17 WU/W15 April 2021 Wetland and S tream ImpactsPage 15 of 21 West Neuse In terceptorImprovementsWake County, NC010050Feet³Limits of Disturbance Pipe C enterline 2' Elevation Contour Permanent Wetland Conversion Temporary Wetland Impact Forested Wetland Permanent (No Loss) Stream Impact Temporary Stream Impact SJ/S5 W15: Permanent Wetland Conversion: 0.222 acreW15: Temporary Wetland Impact (Forested): 1.081 acreW15: Temporary Wetland Impact (Non-Forested): 0.420 acreS5: Permanent (No Loss) Stream Impact: 120 linear feet (240 square feet) WU/W15 April 2021 Wetland and S tream ImpactsPage 16 of 21 West Neuse In terceptorImprovementsWake County, NC010050Feet³Limits of Disturbance Pipe C enterline 2' Elevation Contour Permanent Wetland Conversion Temporary Wetland Impact Forested Wetland Permanent (No Loss) Stream Impact Temporary Stream Impact WV /W14 W14: Perman en t Wetland Con version : 0.001 acreW14: Temp orary Wetland Impact (Forested): 0.017 acre April 2021 Wetland and S tream ImpactsPage 17 of 21 West Neuse In terceptorImprovementsWake County, NC010050Feet³Limits of Disturbance Pipe C enterline 2' Elevation Contour Permanent Wetland Conversion Temporary Wetland Impact Forested Wetland Permanent (No Loss) Stream Impact Temporary Stream Impact WW/W13 WBA /W12 WX /W11 SK/S 4 W13: Temporary Wetland Impact (Forested): 0.062 acreW12: Temporary Wetland Impact (Forested): 0.020 acreW11: Temporary Wetland Impact (Forested): 0.086 acreS4: Permanent (No Loss) Stream Impact: 31 linear feet (62 square feet) S4: Temporary Stream Impact: 74 linear feet (148 square feet) April 2021 Wetland and S tream ImpactsPage 18 of 21 West Neuse In terceptorImprovementsWake County, NC010050Feet³Limits of Disturbance Pipe C enterline 2' Elevation Contour Permanent Wetland Conversion Temporary Wetland Impact Forested Wetland Permanent (No Loss) Stream Impact Temporary Stream Impact WZ/W8 WY /W10 SL/S3 WAA/W9 SM/S 2 WAC/W7 WAB/W6 WAD/W5 W10: Temporary Wetland Impact (Forested): 0.069 acreW9: Temporary Wetland Impact (Forested): 0.157 acreW9: Temporary Wetland Impact (Non-Forested): 0.007 acreW8: Temporary Wetland Impact (Forested): 0.101 acreW8: Temporary Wetland Impact (Non-Forested): 0.018 acreW7: Temporary Wetland Impact (Non-Forested): 0.003 acreW6: Temporary Wetland Impact (Forested): 0.038 acreW6: Temporary Wetland Impact (Non-Forested): 0.001 acreW5: Temporary Wetland Impact (Forested): 0.195 acreW5: Temporary Wetland Impact (Non-Forested): 0.104 acreS3: Permanent (No Loss) Stream Impact: 45 linear feet (90 square feet)S3: Temporary Stream Impact: 20 linear feet (40 square feet)S2: Temporary Stream Impact: 56 linear feet (112 square feet) April 2021 Wetland and S tream ImpactsPage 19 of 21 West Neuse In terceptorImprovementsWake County, NC010050Feet³Limits of Disturbance Pipe C enterline 2' Elevation Contour Permanent Wetland Conversion Temporary Wetland Impact Forested Wetland Permanent (No Loss) Stream Impact Temporary Stream Impact WAE/W4 WAF/W3 SN/S1 W4: Temporary Wetland Impact (Forested): 0.040 acreW4: Temporary Wetland Impact (Non-Forested): 0.040 acreW3: Temporary Wetland Impact (Non-Forested): 0.023 acreS1: Permanent (No Loss) Stream Impact: 58 linear feet (116 square feet)S1: Temporary Stream Impact: 40 linear feet (80 square feet) WAD/W5 April 2021 Wetland and S tream ImpactsPage 20 of 21 West Neuse In terceptorImprovementsWake County, NC010050Feet³Limits of Disturbance Pipe C enterline 2' Elevation Contour Permanent Wetland Conversion Temporary Wetland Impact Forested Wetland Permanent (No Loss) Stream Impact Temporary Stream Impact WAG /W1 WAH/W2 W2: Temp orary Wetland Impact (Forested): 0.006 acreW2: Temp orary Wetland Impact (Non-Forested): <0.001 acreW1: Temp orary Wetland Impact (Forested): 0.550 acre April 2021 Wetland and S tream ImpactsPage 21 of 21 West Neuse In terceptorImprovementsWake County, NC010050Feet³Limits of Disturbance Pipe C enterline 2' Elevation Contour Permanent Wetland Conversion Temporary Wetland Impact Forested Wetland Permanent (No Loss) Stream Impact Temporary Stream Impact