HomeMy WebLinkAboutSW1191201_Stormwater Report_20210719July 15, 2021 NARRATIVE / CALCULATIONS / MAPS/ SUPPORTING INFORMATION FOR STORMWATER REVIEW for project DPS - North Carolina National Guard Morganton Regional Readiness Center Phase II: New Construction SC0#16-14394-026 Site Address: 5155 Western Ave, Morganton, NC 28655 Engineer Timmons Group Attn: Frank Slinsky III, PE 5410 Trinity Road, Ste. 102 Raleigh, NC 27607 T: 919.866.4505 E: frank.slinsky(a)timmons.com Owner / Developer North Carolina National Guard Attn: LTC Rodney Newton 1636 Gold Star Dr., Suite 2600 Raleigh, NC 27607 T:984.345.6137 E: rodney.d.newton.mil(a)mail.mil TABLE OF CONTENTS Stormwater Management Permit Application (copy) Stormwater Management Major Modification Application (copy) Stormwater Narrative Wetland Memo — Original Permit Environmental JD — MOV Expansion Environmental Maps: ■ USGS Quad Map ■ NRCS Soil Map ■ FEMA Flood Map Property Deed Seasonal High Water Table Report Stormwater Management Mapping (Revised for MOV Expansion) Stormwater Calculations Wet Pond Sizing (Original Permit) Wet Pond Sizing (MOV Expansion) Pre -Post Development Hydraulic Routing (Original Permit) Pre -Post Development Hydraulic Routing (MOV Expansion) Storm Sewer and Outlet Protection Calculations (Original Permit) Storm Sewer and Outlet Protection Calculations (MOV Expansion) Wet Pond Supplement EZ (Original Permit) Wet Pond Supplement EZ (MOV Expansion) Operations and Maintenance EZ (Original Permit) Operations and Maintenance EZ (MOV Expansion) (Refer to Full size plan set for additional information) Stormwater Management Permit Application (copy) DEMLR USE ONLY Date Received Fee Paid Permit Number Applicable Rules: ❑ Coastal SW - 1995 ❑ Coastal SW - 2008 ❑ Ph 11- Post Construction (select all that apply) ❑ Non -Coastal SW- HQW/ORW Waters ❑ Universal Stormwater Management Plan ❑ Other WQ M mt Plan: State of North Carolina Department of Environment and Natural Resources Division of Energy, Mineral and Land Resources STORMWATER MANAGEMENT PERMIT APPLICATION FORM This form may be photocopied for use as an original I. GENERAL INFORMATION 1. Project Name (subdivision, facility, or establishment name - should be consistent with project name on plans, specifications, letters, operation and maintenance agreements, etc.): NCNG Readiness Center 2. Location of Project (street address): Western Avenue City:Morganton County:Burke Zip:27607 3. Directions to project (from nearest major intersection): At Salem Road and Burkemont Road. turn south onto Burkmont Road. In 1 mile turn left onto Western Avenue. The project is located at the end of Western Avenue in approximately 1 mile. 4. Latitude:35° 40' 45" N Longitude:81° 40' 57" W of the main entrance to the project. II. PERMIT INFORMATION: 1. a. Specify whether project is (check one): ®New ❑Modification ❑ Renewal w/ Modificationt tRenewals with modifications also requires SWU-102 - Renewal Application Form b.If this application is being submitted as the result of a modification to an existing permit, list the existing permit numbern/a , its issue date (if known)n/a , and the status of construction: ❑Not Started ❑Partially Completed* ❑ Completed* *provide a designer's certification 2. Specify the type of project (check one): ❑Low Density ®High Density ❑Drains to an Offsite Stormwater System ❑Other 3. If this application is being submitted as the result of a previously returned application or a letter from DEMLR requesting a state stormwater management permit application, list the stormwater project number, if assigned, n/a and the previous name of the project, if different than currently proposed, n/a 4. a. Additional Project Requirements (check applicable blanks; information on required state permits can be obtained by contacting the Customer Service Center at 1-877-623-6748): ❑CAMA Major ®Sedimentation/Erosion Control: 35 ac of Disturbed Area ❑NPDES Industrial Stormwater 0404/401 Permit: Proposed Impacts b.If any of these permits have already been acquired please provide the Project Name, Project/Permit Number, issue date and the type of each permit: 5. Is the project located within 5 miles of a public airport? ®No ❑Yes If yes, see S.L. 2012-200, Part VI: http://12ortal.ncdenr.org/web/lr/rules-and-regulations Form SWU-101 Version Oct. 31, 2013 Page 1 of 6 III. CONTACT INFORMATION 1. a. Print Applicant / Signing Official's name and title (specifically the developer, property owner, lessee, designated government official, individual, etc. who owns the project): Applicant/Organization:North Carolina National Guard Signing Official & Title:LTC Rodney D. Newton b. Contact information for person listed in item 1a above: Street Address:1636 Gold Star Drive City:Raleigh State:NC Zip:27607 Mailing Address (if applicablc):1636 Gold Star Drive City: State:NC Zip:27607 Phone: (919 ) 345-6137 Fax: ( ) n/a Email:rodney.d.newton.mil@mail.mil Please check the appropriate box. The applicant listed above is: ® The property owner (Skip to Contact Information, item 3a) ❑ Lessee* (Attach a copy of the lease agreement and complete Contact Information, item 2a and 2b below) ❑ Purchaser* (Attach a copy of the pending sales agreement and complete Contact Information, item 2a and 2b below) ❑ Developer* (Complete Contact Information, item 2a and 2b below.) 2. a. Print Property Owner's name and title below, if you are the lessee, purchaser or developer. (This is the person who owns the property that the project is located on): Property Owner/ Organization:n a Signing Official & Title: b. Contact information for person listed in item 2a above: Street Address: City: State: Zip: Mailing Address (if applicable): City: Phone: ( ) Email: State: Fax: ( ) Zip: 3. a. (Optional) Print the name and title of another contact such as the project's construction supervisor or other person who can answer questions about the project: Other Contact Person/Organization: Signing Official & Title: b. Contact information for person listed in item 3a above: Mailing Address: City: State: Zip: Phone: ( ) Fax: ( ) Email: 4. Local jurisdiction for building permits: North Carolina State Construction Office Point of Contact:Farouk Zaman Phone #: (919 ) 807-4095 Form SWU-101 Version Oct. 31, 2013 Page 2 of 6 IV. PROJECT INFORMATION 1. In the space provided below, briefly summarize how the stormwater runoff will be treated. Stormwater runoff will be treated in a new constructed wet pond SCM. 2. a. If claiming vested rights, identify the supporting documents provided and the date they were approved: ❑ Approval of a Site Specific Development Plan or PUD Approval Date: ❑ Valid Building Permit Issued Date: ❑ Other: Date: b.If claiming vested rights, identify the regulation(s) the project has been designed in accordance with: ❑ Coastal SW - 1995 ❑ Ph II - Post Construction Stormwater runoff from this project drains to the Catawba Total Property Area: 35 River basin. acres 5. Total Coastal Wetlands Area: 0 acres 6. Total Surface Water Area: 0.60 acres 7. Total Property Area (4) - Total Coastal Wetlands Area (5) - Total Surface Water Area (6) = Total Project Area+:34.4 acres + Total project area shall be calculated to exclude the following: the normal pool of impounded structures, the area between the banks of streams and rivers, the area below the Normal High Water (NHM line or Mean High Water (MHVv) line, and coastal wetlands landward from the NHW (or MHM line. The resultant project area is used to calculate overall percent built upon area (B UA). Non -coastal wetlands landward of the NHW (or MHW) line may be included in the total project area. 8. Project percent of impervious area: (Total Impervious Area / Total Project Area) X 100 = 46.7 9. How many drainage areas does the project have?1 (For high density, count 1 for each proposed engineered stormwater BMP. For low density and other projects, use 1 for the whole property area) 10. Complete the following information for each drainage area identified in Project Information item 9. If there are more than four drainage areas in the project, attach an additional sheet with the information for each area provided in the same format as below. Basin Information Drainage Area A Drainage Area _ Drainage Area _ Drainage Area _ Receiving Stream Name Hunting Creek Stream Class * C Stream Index Number 11-36-(0.3) Total Drainage Area (sf) 746,327 On -site Drainage Area (sf) 746,327 Off -site Drainage Area (sf) 0 Proposed Impervious Area** (sf) 570,010 Impervious Area** (total) 76.4% Impervious- Surface Area Drainage Area A Drainage Area _ Drainage Area _ Drainage Area _ On -site Buildings/Lots (sf) 64,267 On -site Streets (sf) 0 On -site Parking (sf) 465,306 On -site Sidewalks (sf) 33,389 Other on -site (sf) 0 Future (sf) 7,048 Off -site (sf) 0 Existing BUA*** (sf) 0 Total (sf): 570,010 * Stream Class and Index Number can be determined at: http2.aortal.ncdenr.or /wg eb/wq&s/csu/classifications Impervious area is defined as the built upon area including, but not limited to, buildings, roads, parking areas, sidewalks, gravel areas, etc. *** Report only that amount of existing B UA that will remain after development. Do not report any existing B UA that is to be removed and which will be replaced by new B UA. Form SWU-101 Version Oct. 31, 2013 Page 3 of 6 11. How was the off -site impervious area listed above determined? Provide documentation. H`1t — /I/O f#1 1'e �'A4 40-&-t'p.r I dL rf /t �w • S rd,'6C.r — _-- Proiects in Union County: Contact DEMLR Central Office staff to check if the project is located within a Threatened & Endangered Species watershed that maybe subject to more stringent stormwater requirements as per I5A NCAC 02B .0600. V. SUPPLEMENT AND O&M FORMS The applicable state stormwater management permit supplement and operation and maintenance (O&M) forms must be submitted for each BMP specified for this project. The latest versions of the forms can be downloaded from littp://portal.nedenr.org/web/wq/ws/su/bmp-manual. VI. SUBMITTAL REQUIREMENTS Only complete application packages will be accepted and reviewed by the Division of Energy, Mineral and Land Resources (DEMLR). A complete package includes all of the items listed below. A detailed application instruction sheet and BMP checklists are available from http://12ortal.nedenr-oEg/web/wq/ws/sulstateswIforms Iforms does. The complete application package should be submitted to the appropriate DEMLR Office. (The appropriate office may be found by locating project on the interactive online map athttp://12ortal.ncdetir.qM/web/­wil/ws/"`su/nia s.) Please indicate that the following required information have been provided by initialing in the space provided for each item. All original documents MUST be signed and initialed in blue ink. Download the latest versions for each submitted application package from htW.//12ortal.ncdenr.oi&ZwebZwg/ws/`su/statesw/forms docs. I 'tials 1. Original and one copy of the Stormwater Management Permit Application Form. 2. Original and one copy of the signed and notarized Deed Restrictions & Protective Covenants Form. (if required as per Part VII below) 3. Original of the applicable Supplement Form(s) (,,sealed, signed and dated), and O&M agreements) for each BMP. �/V 4. Permit application processing fee of $505 payable to NCDENR. (For an Express review, refer to hU://www.envheelp.org/napes/onesMogress.html for information on the Express program and the associated fees. Contact the appropriate regional office Express Permit Coordinator for additional information and to schedule the required application meeting.) 5. A detailed narrative (one to two pages) describing the stormwater treatment/managementfor the project. This is required in addition to the brief summary provided in the Project Information, item 1. - 6. A USGS map identifying the site location. If the receiving stream is reported as class SA or the receiving stream drains to class SA waters within 1/2 mile of the site boundary, include the'/z mite radius on the map. 7. Sealed, signed and dated calculations (one copy). 8. Two sets of plans folded to 8.5" x 14" (sealed, signed, & dated), including: a. Development/Project name. b. Engineer and firm. c. Location map with named streets and NCSR numbers. d. Legend. e. North arrow. f. Scale. g. Revision number and dates. h. Identify all surface waters on the plans by delineating the normal pool elevation of impounded structures, the banks of streams and rivers, the MHW or NHW line of tidal waters, and any coastal wetlands landward of the MHW or NHW lines. • Delineate the vegetated buffer landward from the normal pool elevation of impounded structures, the banks of streams or rivers, and the MHW (or NHW) of tidal waters. i. Dimensioned property/project boundary with bearings & distances. j. Site Layout with all BUA identified and dimensioned. k. Existing contours, proposed contours, spot elevations, finished floor elevations. 1. Details of roads, drainage features, collection systems, and stormwater control measures. in. Wetlands delineated, or a note on the plans that none exist. (Must be delineated by a qualified person. Provide documentation of qualifications and identify the person who made the determination on the plans. n. Existing drainage (including off -site), drainage easements, pipe sizes, runoff calculations. o. Drainage areas delineated (included in the main set of plans, not as a separate document). Form SWU-101 Version Oct. 31, 2013 Page 4 of 6 p. Vegetated buffers (where required). Copy of any applicable soils report with the associated SHWT elevations (Please identify elevations in addition to depths) as well as a map of the boring locations with the existing elevations and boring logs. Include an 8.5"x11" copy of the NRCS County Soils map with the project area clearly delineated. For projects with infiltration BMPs, the report should also include the soil type, expected infiltration rate, and the method of determining the infiltration rate. (Infiltration Devices submitted to WiRO: Schedule a site visit for DEMLR to verify the SHWT prior to submittal, (910) 796-7378.) 10. A copy of the most current property deed. Deed book: Page No:� 11. For corporations and limited liability corporations (LLC): Provide documentation from the NC 4//11 Secretary of State or other official documentation, which supports the titles and positions held by the persons listed in Contact Information, item 1a, 2a, and/or 3a per 15A NCAC 2H.1003(e). The corporation or LLC must be listed as an active corporation in good standing with the NC Secretary of State, otherwise the application will be returned. htW:/ /www.secretaKy.state.ne.us/­Corl2orations/CSearch-as2x VII. DEED RESTRICTIONS AND PROTECTIVE COVENANTS For all subdivisions, outparcels, and future development, the appropriate property restrictions and protective covenants are required to be recorded prior to the sale of any lot. If lot sizes vary significantly or the proposed BUA allocations vary, a table listing each lot number, lot size, and the allowable built -upon area must be provided as an attachment to the completed and notarized deed restriction form. The appropriate deed restrictions and protective covenants forms can be downloaded from http://portal.ncdenr.org/web/lr/state-stormwater- forms does. Download the latest versions for each submittal. In the instances where the applicant is different than the property owner, it is the responsibility of the property owner to sign the deed restrictions and protective covenants form while the applicant is responsible for ensuring that the deed restrictions are recorded. By the notarized signature(s) below, the permit holder(s) certify that the recorded property restrictions and protective covenants for this project, if required, shall include all the items required in the permit and listed on the forms available on the website, that the covenants will be binding on all parties and persons claiming under them, that they will run with the land, that the required covenants cannot be changed or deleted without concurrence from the NC DEMLR, and that they will be recorded prior to the sale of any lot. VIII. CONSULTANT INFORMATION AND AUTHORIZATION Applicant: Complete this section if you wish to designate authority to another individual and/or firm (such as a consulting engineer and/or firm) so that they may provide infonnation on your behalf for this project (such as addressing requests for additional information). Consulting Engineer:Francis Slinsky, PE Consulting Firm: Timmons Group Mailing Address:5410 Trinity Road _ City:Ralei Phone: (919 ) 866-4505 Email:frank.slin4@tinimons.com @timmons.com State:NC Zip:27607 Fax: (919 ) 859-5663 IX. PROPERTY OWNER AUTHORIZATION (if Contact Information, item 2 has been filled out, complete this section) I, (print or type name of person listed in Contact Information, item 2a) : certify that I own the property identified in this permit application, and thus give permission to (print or type name of person listed in Contact Information, item la) with (print or type name of organization listed in Contact Information, item 1a) to develop the project as currently proposed. A copy of the lease agreement or pending property sales contract has been provided with the submittal, which indicates the party responsible for the operation and maintenance of the stormwater system. Form SWU-101 Version Oct. 31, 2013 Page 5 of 6 As the legal property owner I acknowledge, understand, and agree by my signature below, that if my designated agent (entity listed in Contact Information, item 1) dissolves their company and/or cancels or defaults on their lease agreement, or pending sale, responsibility for compliance with the DEMLR Stormwater permit reverts back to me, the property owner. As the property owner, it is my responsibility to notify DEMLR immediately and submit a completed Name'/Ownership Change Form within 30 days; otherwise I will be operating a stormwater treatment facility without a valid permit, I understand that the operation of a stormwater treatment facility without a valid permit is a violation of NC General Statue 143-2I5.1 and may result in appropriate enforcement action including the assessment of civil penalties of up to $25,000 per day, pursuant to NCGS 143-215.6. Signature:. a Notary Public for the State of do hereby certify that before me this _ day of Date: County of personally appeared and acknowledge the due execution of the application for a stormwater permit. Witness my hand and official seal, SEAL My commission expires X. APPLICANT'S CERTIFICATION L (print or type name of person listed in Contact Information, item in) � orin t-i ). lilo certify that the information included on this permit application form is. to the bes of my knowledge, correct and that the project will be constructed in conformance with the approved plans, that the required deed restrictions and protective covenants will be recorded, and that the proposed project complies with the requirements of the applicable stormwater rules under 15A NCAC 2H .1000 and any other applicable state stormwater requirements. Signature: - —L3. zt- Date: `% M !-R Z o 1 `1 I, mee Iq La 1 12 e-Z a Notary Public for the State of #,, �� 1� County of do hereby certify that b t A N � u personally appeared before me this_, day of _ 1" C�. f'1 `� , and acknowIedge the ueC 'pn of the application for a stormwater permit. Witness my hand and official seal, ,f,kY +L Q v, Notary Public�v't= Wake = County Ei My Comm. EXP. A 01-20•2023 *,,p!^I 1CAR�Q SEAL My commission.expires: 01 l 2 d2 u 3. _ Form SW-101 Version Oct. 31, 2013 Page 6 of 6 Stormwater Management Major Modification Permit Application (copy) DEMLR USE ONLY Date Received Fee Paid Permit Number Applicable Rules: ❑ Coastal SW — 1995 ❑ Coastal SW — 2008 ❑ Ph 11- Post Construction (select all that apply) ❑ Non -Coastal SW- HQW/ORW Waters ❑ Universal Stormwater Management Plan ❑ Other WQ M mt Plan: State of North Carolina Department of Environment and Natural Resources Division of Energy, Mineral and Land Resources STORMWATER MANAGEMENT PERMIT APPLICATION FORM This form may be photocopied for use as an original I�e"9IL41aCAR a1U1101C405 KIN116301 1. Project Name (subdivision, facility, or establishment name - should be consistent with project name on plans, specifications, letters, operation and maintenance agreements, etc.): NCNG Morganton Regional Readiness Center 2. Location of Project (street address): Western Avenue City:Morganton County:Burke Zip:28655 3. Directions to project (from nearest major intersection): At Salem Road and Burkemont Road, turn south onto Burkemont Road. In 1 mile turn left onto Western Avenue. The project is located at the end of Western Avenue in approximately 1 mile. 4. Latitude:35° 40' 45" N Longitude:81° 40' 57" W of the main entrance to the project. II. PERMIT INFORMATION: 1. a. Specify whether project is (check one): ❑New ®Modification ❑ Renewal w/ Modificationt tRenewals with modifications also requires SWU-102 - Renewal Application Form b.If this application is being submitted as the result of a modification to an existing permit, list the existing permit number SW1191201 , its issue date (if known) July 27, 2020 , and the status of construction: ❑Not Started ®Partially Completed* ❑ Completed* *provide a designer's certification 2. Specify the type of project (check one): ❑Low Density ®High Density ❑Drains to an Offsite Stormwater System ❑Other 3. If this application is being submitted as the result of a previously returned application or a letter from DEMLR requesting a state stormwater management permit application, list the stormwater project number, if assigned, n/a and the previous name of the project, if different than currently proposed, n/a 4. a. Additional Project Requirements (check applicable blanks; information on required state permits can be obtained by contacting the Customer Service Center at 1-877-623-6748): ❑CAMA Major ®Sedimentation/Erosion Control: 35 ac of Disturbed Area ❑NPDES Industrial Stormwater 0404/401 Permit: Proposed Impacts b.If any of these permits have already been acquired please provide the Project Name, Project/Permit Number, issue date and the type of each permit: DPS NCNG Morganton RRC - Phase I DOC Facilities, BURKE 2019- 012, March 14, 2019, Existing Land Disturbance Permit NCNG Morganton Regional RRC Phase II: New Construction, BURKE 2020-013, March 6, 2020, Existing Land Disturbance Permit Is the project located within 5 miles of a public airport? ®No ❑Yes If yes, see S.L. 2012-200, Part VI: http://portal.ncdenr.org/web/lr/rules-and-regulations Form SWU-101 Version Oct. 31, 2013 Page 1 of 6 III. CONTACT INFORMATION 1. a. Print Applicant / Signing Official's name and title (specifically the developer, property owner, lessee, designated government official, individual, etc. who owns the project): Applicant/Organization: North Carolina National Guard Signing Official & Title:LTC Rodney D. Newton b.Contact information for person listed in item 1a above: Street Address:1636 Gold Star Drive City: Mailing Address (if applicablc):1636 Gold Star Drive State:NC Zip:27607 City:Raleigh State:NC Zip:27607 Phone: (919 ) 354-6137 Fax: ( ) N/A Email:rodney.d.newton.mil@mail.mil Please check the appropriate box. The applicant listed above is: ® The property owner (Skip to Contact Information, item 3a) ❑ Lessee* (Attach a copy of the lease agreement and complete Contact Information, item 2a and 2b below) ❑ Purchaser* (Attach a copy of the pending sales agreement and complete Contact Information, item 2a and 2b below) ❑ Developer* (Complete Contact Information, item 2a and 2b below.) 2. a. Print Property Owner's name and title below, if you are the lessee, purchaser or developer. (This is the person who owns the property that the project is located on): Property Owner/Organization: Signing Official & Title: b.Contact information for person listed in item 2a above: Street Address: City: Mailing Address (if applicable): State: Zip: City: State: Zip: Phone: ( ) Fax: ( ) Email: 3. a. (Optional) Print the name and title of another contact such as the project's construction supervisor or other person who can answer questions about the project: Other Contact Person/Organization: Signing Official & Title: b.Contact information for person listed in item 3a above: Mailing Address: City: State: Zip: Phone: ( ) Fax: ( ) Email: Local jurisdiction for building permits: North Carolina State Construction Office Point of Contact:Farouk Zaman Phone #: (919 ) 807-4095 Form SWU-101 Version Oct. 31, 2013 Page 2 of 6 IV. PROJECT INFORMATION 1. In the space provided below, briefly summarize how the stormwater runoff will be treated. Stormwater runoff will be treated in a new constructed wet pond SCM 2. a. If claiming vested rights, identify the supporting documents provided and the date they were approved: ❑ Approval of a Site Specific Development Plan or PUD Approval Date: ❑ Valid Building Permit Issued Date: ❑ Other: Date: b.If claiming vested rights, identify the regulation(s) the project has been designed in accordance with: ❑ Coastal SW - 1995 ❑ Ph II - Post Construction 3. Stormwater runoff from this project drains to the Catawba River basin. Total Property Area: 35 acres 5. Total Coastal Wetlands Area: 0 acres 6. Total Surface Water Area: 0.60 acres 7. Total Property Area (4) - Total Coastal Wetlands Area (5) - Total Surface Water Area (6) = Total Project Area+:34.4 acres + Total project area shall be calculated to exclude the following: the normal pool of impounded structures, the area between the banks of streams and rivers, the area below the Normal High Water (NHM line or Mean High Water (MHM line, and coastal wetlands landward from the NHW (or MH1O line. The resultant project area is used to calculate overall percent built upon area (B UA). Non -coastal wetlands landward of the NHW (or MHVv) line may be included in the total project area. 8. Project percent of impervious area: (Total Impervious Area / Total Project Area) X 100 = 46.7 9. How many drainage areas does the project have? 1 (For high density, count 1 for each proposed engineered stormwater BMP. For low density and other projects, use 1 for the whole property area) 10. Complete the following information for each drainage area identified in Project Information item 9. If there are more than four drainage areas in the project, attach an additional sheet with the information for each area provided in the same format as below. Basin Information Drainage Area A Drainage Area _ Drainage Area _ Drainage Area _ Receiving Stream Name Hunting Creek Stream Class * C Stream Index Number 11-36-(0.3) Total Drainage Area (sf) 746,327 On -site Drainage Area (sf) 746,327 Off -site Drainage Area (sf) 0 Proposed Impervious Area** (sf) 570,010 Impervious Area** (total) 76.4% Impervious- Surface Area Drainage Area A Drainage Area _ Drainage Area _ Drainage Area _ On -site Buildings/Lots (sf) 64,267 On -site Streets (sf) 0 On -site Parking (sf) 465,306 On -site Sidewalks (sf) 33,389 Other on -site (sf) 0 Future (sf) 7,048 Off -site (sf) 0 Existing BUA*** (sf) 0 Total (sf): 570,010 * Stream Class and Index Number can be determined at: http2.Z&ortal.ncdenr.or /wg eb/wq&s/csu/classifications Im ervious area is defined as the built upon area including, but not limited to, buildings, roads, parking areas, sidewalks, gravel areas, etc. Form SWU-101 Version Oct. 31, 2013 Page 3 of 6 11. How was the off -site impervious area listed above determined? Provide documentation. N/A - No offsite impervious area in this project Protects in Union County: Contact DEMLR Central Office staff to check if the project is located within a Threatened & Endangered Species watershed that may be subject to more stringent stormwater requirements as per 15A NCAC 02B .0600. V. SUPPLEMENT AND O&M FORMS The applicable state stormwater management permit supplement and operation and maintenance (O&M) forms must be submitted for each BMP specified for this project. The latest versions of the forms can be downloaded fromhttD://13ortal.nedenr.or-a/web/wa/ws/`su`/bmv-manual. VI. SUBMITTAL REQUIREMENTS Only complete application packages will be accepted and reviewed by the Division of Energy, Mineral and Land Resources (DEMLR). A complete package includes all of the items listed below. A detailed application instruction sheet and BMP checklists are available from htW://12ortal.ncdenr.org/web/wQlws/sulsta-tes-w/­fp-r—rnsdocs. The complete application package should be submitted to the appropriate DEMLR Office. (The appropriate office may be found by locating project on the interactive online map at http,/lportal.ncdenr.org/web/wq/ws/su/mays.) Please indicate that the .following required information have been provided by initialing in the space provided for each item. All original documents MUST be signed and initialed in blue ink. Download the latest versions for each submitted application package from http://portal.ncdenr.org/web/wq/ws/su- /stabes /forms docs. I "tiaas 1. Original and one copy of the Stormwater Management Permit Application Form. 2. Original and one copy of the signed and notarized Deed Restrictions & Protective Covenants Form. (if required as per Part VII below) 3. Original of the applicable Supplement Form(s) (sealed, signed and dated] and O&M agreement(s) for each BMP. 4. Permit application processing fee of $505 payable to NCDENR. (For an Express review, refer to http:I/www.envheII2.org/12agesAnestopexpress.html for information on the Express program and the associated fees. Contact the appropriate regional office Express Permit Coordinator for additional information and to schedule the required application meeting.) 5. A detailed narrative (one to two pages) describing the stormwater treatment/management for the project. This is required in addition to the brief summary provided in the Project Information, item 1. 6. A USGS map identifying the site location. If the receiving stream is reported as class SA or the receiving stream drains to class SA waters within 1/z mile of the site boundary, include the 1/2 mile radius on the map. 7. Sealed, signed and dated calculations (one copy). 8. Two sets of plans folded to 8.5" x 14" (sealed, signed, & dated), including: a. Development/Project name. b. Engineer and firm. c. Location map with named streets and NCSR numbers. d. Legend. e. North arrow. f. Scale. g. Revision number and dates. h. Identify all surface waters on the plans by delineating the normal pool elevation of impounded structures, the banks of streams and rivers, the MHW or NHW line of tidal waters, and any coastal wetlands landward of the MHW or NHW lines. • Delineate the vegetated buffer landward from the normal pool elevation of impounded structures, the banks of streams or rivers, and the MHW (or NHW) of tidal waters. i. Dimensioned property/project boundary with bearings & distances. j. Site Layout with all BUA identified and dimensioned. k. Existing contours, proposed contours, spot elevations, finished floor elevations. 1. Details of roads, drainage features, collection systems, and stormwater control measures. in. Wetlands delineated, or a note on the plans that none exist. (Must be delineated by a qualified person. Provide documentation of qualifications and identify the person who made the determination on the plans. n. Existing drainage (including off -site), drainage easements, pipe sizes, runoff calculations. o. Drainage areas delineated (included in the main set of plans, not as a separate document). Ma Z Form SWU-101 Version Oct. 31, 2013 Page 4 of 6 p. Vegetated buffers (where required). 9. Copy of any applicable soils report with the associated SHWT elevations (Please identify elevations in addition to depths) as well as a map of the boring locations with the existing elevations and boring logs. Include an 8.5"x11" copy of the NRCS County Soils map with the project area clearly delineated. For projects with infiltration BMPs, the report should also include the soil type, expected infiltration rate, and the method of determining the infiltration rate. (Infiltration Devices submitted to WiRO: Schedule a site visit for DEMLR to verify the SHWT prior to submittal, (910) 796-7378.) r II p 10. A copy of the most current property deed. Deed book: " b b Page No: [ l� 11. For corporations and limited liability corporations (LLC): Provide documentation from the NC Secretary of State or other official documentation, which supports the titles and positions held by'the persons listed in Contact Information, item 1a, 2a, and/or 3a per 15A NCAC 2H.1003(e). The corporation or LLC must be listed as an active corporation in good standing with the NC Secretary of State, otherwise the application will be returned. h www. ecretar .state.nc.us Co orations C arch.as x VII. DEED RESTRICTIONS AND PROTECTIVE COVENANTS For all subdivisions, outparcels, and future development, the appropriate property restrictions and protective covenants are required to be recorded prior to the sale of any lot. If lot sizes vary significantly or the proposed BUA allocations vary, a table listing each lot number, lot size, and the allowable built -upon area must be provided as an attachment to the completed and notarized deed restriction form. The appropriate deed restrictions and protective covenants forms can be downloaded from littp:llportal.ncdenr.org web/Ir/state-stormwater- forms does. Download the latest versions for each submittal. In the instances where the applicant is different than the property owner, it is the responsibility of the property owner to sign the deed restrictions and protective covenants form while the applicant is responsible for ensuring that the deed restrictions are recorded. By the notarized signature(s) below, the permit holder(s) certify that the recorded property restrictions and protective covenants for this project, if required, shall include all the items required in the permit and listed on the forms available on the website, that the covenants will be binding on all parties and persons claiming under them, that they will run with the land, that the required covenants cannot be changed or deleted without concurrence from the NC DEMLR, and that they will be recorded prior to the sale of any lot. VIII. CONSULTANT INFORMATION AND AUTHORIZATION Applicant: Complete this section if you wish to designate authority to another individual and/or firm (such as a consulting engineer and/or firm) so that they may provide information on your behalf for this project (such as addressing requests for additional information). Consulting Engineer:Francis Slinsky, PE Consulting Firm: Timmons GrQup Mailing Address:5410 Trinity Road City:Raleigh State:NC Zip:27607 Phone: 19 866-4505 Fax: (919 859- 663 Email:frank.slinsky@timmons.coxn IX. PROPERTY OWNER AUTHORIZATION (if Contact Information, item 2 has been filled out, complete this section) I, (print or type name of person listed in Contact Information, item 2a) , certify that I own the property identified in this permit application, and thus give permission to (print or type name of person listed in Contact Information, item 1a) with (print or type name of organization listed in Contact Information, item 1a) _ to develop the project as currently proposed. A copy of the lease agreement or pending property sales contract has been provided with the submittal, which indicates the party responsible for the operation and maintenance of the stormwater system. Form SWU-101 Version Oct. 31, 2013 Page 5 of 6 As the legal property owner I acknowledge, understand, and agree by my signature below, that if my designated agent (entity listed in Contact Information, item 1) dissolves their company and/or cancels or defaults on their lease agreement, or pending sale, responsibility for compliance with the DEMLR Stormwater permit reverts back to me, the property owner. As the property owner, it is my responsibility to notify DEMLR immediately and submit a completed Name/Ownership Change Form within 30 days; otherwise I will be operating a stormwater treatment facility without a valid permit. I understand that the operation of a stormwater treatment facility without a valid permit is a violation of NC General Statue 143-215.1 and may result in appropriate enforcement action including the assessment of civil penalties of up to $25,000 per day, pursuant to NCGS 143-215.6. Signature: Date:. I, . a Notary Public for the State of , County of do hereby certify that before me this _ day of personally appeared , and acknowledge the due execution of the application for a stormwater permit. Witness my hand and official seal, SEAL My commission expires X. APPLICANT'S CERTIFICATION 1, (print or type name of person listed in Contact Information, item 1a) S. certify that the information included on this permit application form is, to the best of my knowledge, correct and that the project will be constructed in conformance with the approved plans, that the required deed restrictions and protective covenants will be recorded, and that the proposed project complies with the requirements of the applicable stormwater rules under 15A NCAC 2H .1000 and any other applicable state stormwater requirements. Date:1 I, l V a Notary Public for the State of N - CCIA-OtLko a % , County of . WQI .P. , do hereby certify that personally appeared before me this LIL day of U l j , and acknowledge the due execution of the application for a stormwater permit. Witness my hand and official seal, � A 12ALd�fZZ _ •' n s EtW'■ NOTARY :lb PUBU+r���,�`{{'Oppp SEAL My commission expire Form SWU-101 Version Oct. 31, 2013 Page 6 of 6 Stormwater Narrative Narrative (Major Modifications in Red) 1. General Information a. Project Name: DPS—North Carolina National Guard Morganton Regional Readiness Center, Phase 11: New Construction b. Address: 5155 Western Avenue, Morganton, NC c. Total Site Area: 536.44 Acres (Parcel Area), 35 acres (Site Area) d. Disturbed Area: 34.33 Acres e. Wetland Area: 0 Acres (there are no wetlands onsite). f. Jurisdictional Streams and Stream Buffers: There is one jurisdictional stream on the property to the north of the site. There will be no impacts to the stream or stream buffer due to this project. g. Ownership: North Carolina National Guard h. Proposed Development: The North Carolina National Guard plans to construct a Regional Readiness Center (RRC) on the site of the former Dept of Corrections Western Youth Correctional Institution. The proposed project includes demolition of the existing buildings and construction of the RRC to be occupied by four National Guard units. i. Phasing: • This project includes two complete and separate "phases" which are publicly bid and constructed separately. • Phase I of the project included the relocation of existing Department of Corrections buildings to the CRV Correctional facility just south of the site of which Land Disturbance Permit BURKE 2019-012 was issued on March 14, 2019 (see attached). Construction of Phase I is underway and will be complete in February 2020 prior to beginning this project / Phase 11). • This project / Phase II will be bid in February 2020 after complete close out of Phase I project; Construction for Phase II is planned to begin February 2020 and end August 2021). — Construction is currently underway j. Existing Land Disturbance Permit (Phase I project): BURKE 2019-012 / Express Review Existing Land Disturbance Permit (Phase II project): BURKE 2020-013 k. Existing Stormwater Permit: SW1191201 I. NCDEQ Compliance Issues: None. m. Water & Sewer Service: This project will utilize water and sewer services through the City of Morganton. n. Historic Sites: N/A This is not a historic site and there are no historic features on this site. o. Public Funding This project is being funded through the state Connect NC Bond through the North Carolina National Guard. p. FEMA FIRM # 3710270000J, dated September 5, 2007 indicates that the site is outside the limits the 100-year flood plain. q. Soils on the site consist of predominately FaB, FaC, FaD (Fairview sandy clay loam) and Ur (Urban land). �. Pre -development BUA (On -Site): 6.36-ac s. Post -development BUA (On -Site): 21.04-ac Wetland Memo (Original Permit) Jacob Lewis From: Frank Slinsky Sent: Wednesday, February 12, 2020 6:10 PM To: Jacob Lewis Subject: FW: Morganton Regional Readiness Center 5155 Western Ave. Morganton, NC Attachments: _ags_df491 b9885a947a78e48b018f8e88f27.pdf Please use this for the submittal. Thanks. Sincerely, Frank Slinsky, PE, LEED AP Senior Project Manager TIMMONS GROUP I www.timmons.com 5410 Trinity Road, Suite 102 Raleigh, NC 27607 Office: 919.866.4505 1 Fax: 919.859.5663 Mobile: 919.830.8458 1 frank.slinsky(a-)timmons.com Your Vision Achieved Through Ours To send me files greater than 20MB click here. From: Robin Perez <Robin.Perez@timmons.com> Sent: Wednesday, February 12, 2020 4:55 PM To: Frank Slinsky <Frank.Slinsky@timmons.com> Cc: Lauren Norris -Heflin <Lauren.Norris-Heflin@timmons.com> Subject: Morganton Regional Readiness Center 5155 Western Ave. Morganton, NC Frank: To answer your question on the subject property: whether there were any past jurisdictional areas on the property as far back as in the 1940's — I first looked on the Burke County GIS website (http://gis.burkenc.org/ ) One must keep in mind that the soils maps are Level I surveys with only one soil data point per 500 acres and are only approximations based on extrapolation of topography, geology and that one soil boring observation point. The attached map from the Burke County GIS shows the soils, flood zones and blueline streams and the topo was viewed on the website but would not show up on the pdf. The aerial photography was available from 2009 -2018. The soils are mapped as Arkqua (AaA) 0-2% slopes, occasionally flooded along Hunting Creek in the darker reddish brown map unit, and as Fairview sandy clay loam, moderately eroded, (FaB2/FaD2) with 2 — 8% and 15 -25% slopes respectively, in the lighter brown map unit. The blue shading shows the flood zone for Hunting Creek. There is a map unit of Fairview coming onto the site from the northeast, with a crenulation that leads towards the small pond shown to the east. On the topographic map website, ( https://ngmdb.usgs.gov/topoview/viewer/#15/35.6793/-81.6835 ) there are maps as far back as 1905 (1941 edition) through 2019. The maps from 1905 through 1993 are labelled as National Historical Topographic Map Collection (HTMC) and the maps from 2010 through 2019 are USGS Topographic quadrangle maps. The accuracy improves as the maps get younger, and the maps were updated as mapping technology improved. Listed in order from the website: • 1905 (HTMC 1941 edition) shows the subject site located to the west of the stream (Hunting Creek) — which is I believe is an inaccuracy due to the age of the map. • 1956 (HTMC 1956 edition) shows the subject site located to the east of Hunting Creek, and no isolated pond to the east. • 1956 (HTMC 1966 edition) shows the subject site located to the east of Hunting Creek, and no isolated pond to the east. • 1956 (HTMC 1985 edition) shows the subject site located to the east of Hunting Creek, but with the small isolated pond to the east, similar to the map on the Burke Co. GIS map. • 1993 (HTMC 1996 edition) shows the current buildings and the small isolated pond to the east in purple (as a new edit), at the top of a topographic crenulation at 1200' elevation. • 2010 (US Topo) shows the small isolated pond to the east, but no topographic contours. • 2013 (US Topo) shows the small isolated pond to the east, but no topographic contours. • 2016 (US Topo) does not show the small isolated pond to the east, and with topographic contours • 2019 (US Topo) shows a blueline to where the small pond was, but no pond and with topographic contours. Given this information, I do not believe that there were any jurisdictional wetlands or streams in the immediate vicinity of the proposed improvements to the Morganton Regional Readiness Center. Relying on soil and topographic maps, especially older ones, does not accurately depict actual site conditions. I did note that the topographic crenulation leading to the small pond was at 1200 feet elevation, and the stream above the larger ponds to the south originated at approximately 1400' elevation, which might indicate natural springs ocurring between 1200 and 1400 feet elevations to the south and east of the subject site. Field verification by a soil scientist could verify the existence of any stream channel modifications that may have been done, as the soil profile would be disturbed in those areas. However, any such modifications were done well before any existing regulations and so should not cause concern from a regualtory perspective. Let me know if you have any questions. Best regards, Robin Robin Maycock Perez Environmental Group Leader TIMMONS GROUP I www.timmons.com 5410 Trinity Rd, Suite 102 1 Raleigh, NC 27607 Office: 919.532.3245 1 Fax: 919.859.5663 Mobile: 919.418.7645 Robin.Perez@timmons.com Your Vision Achieved Through Ours February 12, 2020 5161 Western ST, Morganton, Burke County, NCO 1,000 2,000 Owner: STATE HOSPITAL PIN: 2701118549 1 Feet 1000 S STERLING ST PIN EXT: 000 REID: 38843 MORGANTON, NC 28655 Property Value: $77,795,297 Property 5161 WESTERN AVE Acreage: 543.29 Address: MORGANTON 28655 Deed Book: 000000 Deed Page: 00000 PROPERTY DESC — Deed Date: 1/1/1900 1:00:00 AM 1:13,250 1 inch = 1104 feet A 4 -A Disclaimer. The information contained on this page is taken from aerial mapping, tax mapping, and public records and is NOT to be construed or used as a survey or7ega/description' Only a licensed professional land surveyor can legally determine precise locations, elevations, length and direction ofa line, and areas. Environmental JD (MOV Expansion) tw\ �`' �, 1 \ � '\ � �\ \\:r'., \`` it ,'� ,—/' ,' •\�'�_' l/�/� ' /' � I/ r' // 1 r/ � I \ \ \ \ `- 1 \r � \+ 1+. \ - 1 1 I •I ■ \' l ' � `/ 1 `` ' "1 ' ^ 1. /' 11 � /' // 1 / ' / � .' Ir '/ INS < \\ ` I \ 1 I \ \ \ ■ \ + `� `\ 1 p �\ r `©�.. i 1 r� / /'• ' 1 1 r' J / 1 / / / / rr 1\ �`� •\I 11 `I \\ 1+ II 1\ 1\ NIN . � ■ 1 / •1` \ �a 1 <. `'\ \ , _' \ 11 —' 1� 1 ,`\ _ � i .' � �� ' ,'1 � � // I I 1 I I/ /' ! 1/ A` 1\ \+ \; it ' \\ \ ` ` - ■ r. • `'` \' 1 \ ` ` \\ I ` '/ `. \ ` ` ; \ 1' / • • I / _ , 1 i ' / I ; I 1 / lo + 1 \ \ \ \ \ \ ,\ \ +1 ■ a` \ t 1 \1 /'/ `` , \ lil r' ' 1 \ 1 1 \ r I 1 1 � - 1 \ \ \ \ 1 \ ■ � \ { • \��y. 1� / I - 1 � � \ , \ r \ • \ +� / \ � / \ 1 1 1 I 1 r 1 \ \\ . \ \\ \ `- �\F \ \ \ � 1 ■ \ \ �_, I 1 \ / 1 r ' \ \ ti �, 1 f / I \ I I 1 I + 1 I \ � 1 \ \ 1 \ � \ .1 \ ` 1 \ \ • 1. \ \ \ � / 1 . Il,i I / I / I 1 1 1 1 / 1 I I I \ \\ '\ \;\�\ 1\ .\\ \ 1 \ .\ +\ ■ `\ `\ +\ \I \\ `� \ `\\ 'I; Ijli-- // rt, 'll� // I 1 1 / 1 1 I •r✓ I 1 1 ! `\ \. ■ ; \ r \ I `` 'I 1 — `r I `\ 111 \Ii I /' I/ \. \ ` 1 `\ \ \ \ ■ `\ , I �\ ` — _ \` J , ' \ c.1 1 III 1 1 I 1 / I I 1 I / \ I IN 1.6 ao \ N. I \ 1 \ \ \ \ \ \ \ 1 \ \ \ \ \ \ \ � ■\ \ l •I _ D aq / '. � 1' ■ it I I , 1 1 1 ' it IN IN e %\,. �• \�\\`' .��.�\\. \ `. `��..�•: �\ \ t°b�.7�lJ�'J'' :�f-� /� J '�� rlf .� / //'- '' I I I / 1 1 ` Environmental Maps USGS Quad Map NRCS Soil Map FEMA Flood Map ZUSGS U.S. DEPARTMENT OF THE INTERIOR U.S. GEOLOGICAL SURVEY ­Aw US Top MORGANTON SOUTH QUADRANGLE NOUN CAROLINA-BURKE CO. o 7.5-MINUTE SERIES Rom me ue SCALE 1:24 ODO 111­a? T= P=� N11 I N-1 11 11 . ........ . ` .15 xx, ­1� e I . .• .. . ..... MORGANTON SOUTH, NC UNTTFTJ ST ATFS DLP.',RTMENT OF AGRICULTURE "L RFSnTTRCFS MNSI RNWFICN SFRVICF BURKE COUNTY, NORTH C 4POLINA MORG,,NTON SOUTH QUADRANGLE SHFFTNUMBF11 12"F I,, ampkan T, �2 o.�aa��� ���.aaa���.d MORGANTON SOUTH, NORTH CAROLINA FEE: � av �ITI �e,��ae �a E��=aM�,9p�v�a e ����� .�oEx�����s���a�a.�e� LLa��a� National Flood Hazard Layer FIRMette O FEMA Legend 35°40'58.45"N 0 250 500 1,000 1,500 2,000 SEE HIS REPORT FOR DETAILED LEGEND AND INDEX MAP FOR FIRM PANEL LAYOUT Without Base Flood Elevation (BFE) Zone A. V. A99 SPECIAL FLOOD With BFE or Depth zone AE, AO, AH, VE, AR HAZARD AREAS Regulatory Floodway 0.2% Annual Chance Flood Hazard, Areas of 1% annual chance flood with average depth less than one foot or with drainage areas of less than one square mile zone x _Future Conditions 1% Annual Chance Flood Hazard zone x III, I Area with Reduced Flood Risk due to ITHER AREAS OF Levee. See Notes. zone x FLOOD HAZARD ��� Area with Flood Risk due to Leveezone D NO SCREEN Area of Minimal Flood Hazard zone x Q Effective LOMRs OTHER AREAS Area of Undetermined Flood Hazard zone D GENERAL ---- Channel, Culvert, or Storm Sewer STRUCTURES i i i i i i i Levee, Dike, or Floodwall e zo.z Cross Sections with 1% Annual Chance 17.5 Water Surface Elevation o- — — Coastal Transect -,,,, 513 ,,,,,,- Base Flood Elevation Line (BFE) Limit of Study Jurisdiction Boundary -- --- Coastal Transect Baseline OTHER _ Profile Baseline FEATURES Hydrographic Feature Digital Data Available N No Digital Data Available MAP PANELS Unmapped 9 The pin displayed on the map is an approximate 1� point selected by the user and does not represent an authoritative property location. This map complies with FEMA's standards for the use of digital flood maps if it is not void as described below. The basemap shown complies with FEMA's basemap accuracy standards The flood hazard information is derived directly from the authoritative NFHL web services provided by FEMA. This map was exported on 9/27/2018 at 5:49:34 PM and does not reflect changes or amendments subsequent to this date and time. The NFHL and effective information may change or become superseded by new data over time. This map image is void if the one or more of the following map elements do not appear: basemap imagery, flood zone labels, legend, scale bar, map creation date, community identifiers, FIRM panel number, and FIRM effective date. Map images for unmapped and unmodernized areas cannot be used for regulatory purposes. Property Deed No. BB —RECORD OF DEEDS STATE OF NORTH CAROLINA COUNTY OF BUMM TE1S DEED, Made this the lat, day of September. A.D., 1945, by Ben X. Leonard and wife, EvIa Leonard, of Burke County, State of North Carolina, parties ofthn First part, to The State Hospital at Morganton, a Departmental Corporation of the State of North Carolina. party of the second part: W I T N R B 8 E T H r THAT TER SAID PANTIL'S OP THE FIRST PART, in oonaiderationaf the Sum'of Sixteen Thousand Dollars, to them paid by the pety of the Sam nd part, the receipt of Which is hereby acknowledged, have bargained and sold and by these presents do bargain, sell and convey unto the said party of the Seo aid part, its suceeesors and asaigns, all those certain traeta or parcels of land lying and being in Morganton Ttirnahip, Durke County, State of North Carolina, adjoining the lands of S,W. Roylar, Shuping and others and bounded as follows: viz FIRST TRACTr a Chestnut sapling, now a eboatnut stump, the ❑rglnal corner of the.old-aurvsy, sod, runs North 42 degrees Wast, [non North 40 deg. Wost) 1700 feet to,a stake in the ❑reek= Usnoo down the meandera of the Croak the. XDllonieg courses and distances; North 35 dogr000 Beset, 200 feet; North 45 degrees East, 165 feet, to the Mouthy of a small branch; thence up the meanders of the shall branch the follaeing coursoa and dIatanoee; North 80 degree Pleat, 140 feet, North 16 ddgraes, West, 06 feet; North 63 degrees West, 120 feet,• North 77 degrees, Went, 115 foot; South 75 degrees Waist 60 feet; North 66 degrees West, 159 feet to a stake In road, over bri4p; thence North 57 degrees best 110 feet; thence North 26 degrees West, 100 feet; thence North 70 degrees West, 100 fast; thonca North 60 degroos West.90 feet; thence North 48 degrees hest 100 £eat• thence North 31 degrees West 139 feet; tbonca North 44 degrees Want, 15� feet; thence North 54 degrees Wo st, 1Z4 Peet to a -stake ip o-.Sna11 branch on or in the old line; thence North 42 degrees East {now. North 45 degrees L4ast), to Shuping line, 987 feet to a atone; 3hupingls comer- thence . same course North 45 de oes East to Carswell's line, 380 rent to an Iron pipe; the old corner; thence North 70 degrees East with Carsuell}a line. 276 feeE to a stake and pointers,• old ljatt and Carswell, oorner; thence South 71 desg. East with the old marked line, 4106 feet to a atone, the old corner; thanoe South where the old m rner, stood; thence North 88 d egroea Wast 4375 feet to the BEGINNIND ---Containing 309 acres, more or least Being the same land conveyed by W.R.Uullis to B.d.Loonerd, by dead dated September, 20th, 1943, andragistorad in Office of Register of beads of Burks 0ounty, In Book No. 57, page 123; also name land by B.M. Leonard and wifo, Eula Leonard to W.R. Mullis by deed dated Ap2-11, 22nd., 1943, and registered in Book No. 57, page 14, Also being same land conveyed by Charles T. Leonard and rife, Minnia Leonard to B.H. Leonard and wire, Zile, Leonard by deed dated November, 11th, 1942. and registered in Book No. 54, Page 553--�urther reference is made to the chain of title set out in the above referred ocnveyancast SECOND TRACTr M W 1 , 16F a Maple at the head of a d 1tah, the old corner, and runs South 15 degrees West with the line of Lot 'a lloe, 3, and 4, 300 foot to a stakel thence South 70 degrees 30 Minutes East with the line -if Lot No. 3, 558 feet to a stake, In the creek; thence up the meanders of the creek the folloeing couraee and distances; South 6 degrees 30 Minutes West, 165 foot; South 42 degrees Mat, 1i18 foot; South 47 degrees West, !}83 feet; South 67 dogrooa Vest, 100 feet, Nortb 75 degrees Went, 90 feat; South 15 degreeg Wast, 135 feet to a ild pho-tu tree, the Northwest corner of lot No. 5; thence North 71 degrees 'seat with the old marked line, 2050 feet to a stale In the edge of the field; thence North 71 degrees East, vdth the old line, 21}67 feet to the point of BEGM, IN0 Containing 46 acres, more or 1083t--Balne the same tract of land conveyed byS. W. Royler, Ouardian for Va being -ale Caroviall Hale, to Ben Lcarts of Lot Honard, deed dated 2nd. dap of September, 1yM and Lot 16. , and 6pas.��, and J, as oat out in R� port of Commineionore in Special- Proceeding re—orayq n Book Number 20, of gpeofal, proceedings Pages 5, to 15, to :which referance in madet STAMP: $2q.60 TO HAVE ANT) To ROTD, the sforeaaid tracts or parcels of i8nd,and all privileges and appurtenances thsrounto belonging, to it, the said party of tba second part, its successors and assigns ferovert And the parties of the First part covenant with the party of the second part that they are seized of said premises in fee and have the right to corrveythe same in fee simple; that the same are free from all encumbrancos; and that they will warrant and defend the title to the same against the claims of all persons whomsoever, IN TES'P,DONY ;r'EEREOF', the said parties of the first part have hereunto set their bands apd.seala, the day and year first above written: Ben i:. Leonard SEAT, Eula Leonard SEAL 92 No. 66—RECORD OF DEEDS NORTH CAROLINA BURKE COUNTY I. J.F.Bowera, Clerk Superior Court of Burke Coun y, do hereby certify that Ben M. Leonard and Eula Leonard, his wife, pereonally appeared beforo me this day and acknowledged the due execution of the foregoing d ad of conveyance. Let the insturment, together with the certificate, be registereds WITNESS, My hand, this the Is t, dap of September, 11945: i i S.F.Bowers Clark uper or 15ourt, ur a. .a. Filed for registration the 5th. day of September, 1945, at 11:30 AM, and registered this the llth. day of September, 1945, at 1:30 PM DS. NORTH CAROLINA BU COUNTY THIS EED, Made this the 31st, day of August, 194% by O.Lee Horton, and wife, Mozelle K. H. ton, of Parke County, State of North Carali , parties of the First pert, to Ben M. Leo rd, of Burke County, State of North Carcli a, part of the Second part: W I T N E S S E T H: i THAT 71,1.1AS, On January, 17th, 1941, Paul M- b le D. Lee Horton, Truatee the land hereinafter deecr recorded in roe ffo. 49, page 139, in office of Re that thereafter d on same day 0. Lee Horton conv Carswell Dale, whi h eaid deed is recorded in Book of Deeds, and that either of said deeds set out a to perform and that a wife of the said O.Lee Hor conveyance, as afores d, and some question has be dower, and whereas, t said parties of the First in or to said lands by ■eon of the matters and t matter whatsoever: and wife, Vassie Dale, eonveyed to bed and other land, w eh deed in ;later of Deeds for a County, and �ed the same Lands t Vassie }6, Page 140, O'fio of Register ,y powers and dutl for said trustee on did not join the said n raised as to r inchoate right of ,art, claim no ht, title or interei zings set out ova, or in any other NOW, THEREFORE, the partied of the Fi*rat part, for ardin con ""ration of the sum of one dollar, to them in hand id , the receipt oP hioh 1. ereby aoknowledged, have remised and released and by t ee presents do remi e, ral set and forever quitclaim unto the party of the Second p and his heirs an asei s all right, title , claim and the of the said partle of the first part in a to a certain tract or parcel of land lying and being in the ty of Burke and Stay* of North Carolina, in Horgantcn Township, and adjoinimg the ]e nd of S.W. Hoyle, ry Leonard, and others, and bounded go follows: 13B3INNINO, On a wild CherXEast, on bank fearner of Lot No. 5, and h nee wi tccurees and distances; Noree Eaiseat, 90 feet; North 76 dst, feetfeet; North 112 deg. East et; rth 8to a stake in line of Aot; t oe wit70 dog.30 Min. West 558t a s eke ithe line of Lot No. t, Sodeg. at,BEGINNIN[i-and containacres, morBeing pare of Lot No. 4,.ot No. 5, of"Vassie Carswell Dale, ets. Charli CBook of Special Proceedin20, Page 6 the Creek, the Northwest a creek the following t 135 feet; South 75 deg. North 47 deg. East 483 eg. 30 Min. Saab, 195 feet the line of Lot NR. 3, North line of lot No. 61 thence with 200 feet to the ppint of or less: Special Prodeeding , entitled rswell at al. " Recorded In TO HAVE AND TO HOLD , the afo said '.tract or parse of land and all privileges them ant belonging to him the said ps y of the Second part and his heirs and assigns free and discharged from all right, itle, claim, or lnter0 of the said parties of the First part, or any one claimin y', through or under them - IN TESTIMONY WHEREOF, id parties of the First ca t, ve hereunto set their hands and Seale , the day and ar first above writtene 0 Lee Horton SEAL Moz&ile K. Horton g' NORTH CARD A BU RKE CO I, J.F wera, Clerk of the Superior Court of Ber a County, do roby certify, that Q.Lee Orton, and Mozelle K.Horton, his wife. per Onally appeare before me this day and cknowledged the due execution of the S Pogo�,t,,a,'a,'1,,.,,nnoxed do d of conveyance for th pur;oses therein expressed. Let the inaturme ther with by certificate, be r istered - Witness 241 hand , this the 10th. dayof September, 194 : S.F.Bowere_, Clerk Superior Court, Burge Co. Frank Slinsky From: Smith, Mike M <michael.smith@ncdenr.gov> Sent: Wednesday, November 14, 2018 11:30 AM To: Frank Slinsky Cc: Aiken, Stan E Subject: RE: [External] FRO Form Signature and Letter of Consent Frank, After reviewing the correspondence below and although the State Hospital remains the deeded owner of the property (1945), there is no need for a letter of consent from DHHS. Clearly, the use of this property has been allocated from DHHS to the North Carolina Department of Public Safety (NCDPS, 1969) and then from (NCDPS) to the North Carolina National Guard (NCNG, 2018) for use as a Regional Readiness Center. This correspondence will serve as the original owner's consent form. On line 9 of the Financial Responsibility Form (FRO) required for the erosion and sediment control plan submittal, I recommend leaving the State Hospital listed as the owner of the property as it now appears on the form. A signed authorization to disturb will be required from North Carolina National Guard for the Financially Responsible Party (the company who performs the work) to (1) submit an erosion and sediment control plan, and (2) to conduct the land disturbing activity. Thank you for the time and effort spent obtaining this information. Michael Smith Assistant Regional Engineer Land Quality Section North Carolina Department of Environmental Quality 828 296-4500 main 828 296-4621 office r n ichaei. sm ith@ ncd en r. gov_ 2090 US70 Highway Swannanoa, NC 28778-8211 ho- - -- . 'Nothing Compares Email correspondence to and from this address is subject to the North Carolina Public Records Law and may be disclosed to third parties From: Frank Slinsky <Frank.Slinsky@timmons.com> Sent: Wednesday, November 14, 2018 9:04 AM To: Smith, Mike M <michael.smith@ncdenr.gov> Subject: FW: [External] FRO Form Signature and Letter of Consent Mike, This is in reference to the NCNG Morganton projects we discussed of which you are reviewing Phase 1 of the project. See correspondence below. I also attached the deed for the project. I assume we do not need a letter of consent from the DHHS now? This issue seems to have gone to the top with regards to State properties. If nothing else, maybe these emails can serve as their consent? Thanks. Sincerely, Frank Slinsky, PE, LEED AP Senior Project Manager TIMMONS GROUP I www.timmons.com 5410 Trinity Road, Suite 102 Raleigh, NC 27607 Office: 919.866.4505 Fax: 919.859.5663 Mobile: 919.830.8458 frank.slinsky@timmons.com Your Vision Achieved Through Ours To send me files greater than 20MB click here. From: Krotoszynski, David<david.krotoszvnski@dhhs.nc.gov> Sent: Wednesday, November 14, 2018 8:51 AM To: Frank Slinsky <Frank.Slinskv@timmons.com> Cc: Hoff, Luke <Iuke.hoff@dhhs.nc.gov> Subject: FW: [External] FRO Form Signature and Letter of Consent Morning Frank, The NC Department of Administration, State Property Office, has confirmed that the DHHS has no role nor need to participate with the planned DPS project along 5161 Western Avenue, Morganton. Regards, David Krotoszynski Chief— Property Acquisition, Disposition & Risk Management Division of Property and Construction North Carolina Department of Health and Human Services 919 855 4872 office 919 733 5711 fax David. krotoszvnskir2a dhhs.nc.aov 2104 Umstead Drive 3026 Mail Service Center Raleigh, NC 27699-3026 Entail correspondence to and from this address is subject to the North Carolina public Records Law and may be disclosed to third parties. Twitter YouTube Unauthorized disclosure of juvenile, health, legally privileged, or otherwise confidential information, including confidential information relating to an ongoing State procurement effort, is prohibited by law. Ifyou have received this e-mail in error, please notify the sender immediately and delete all records ofthis e-mail. From: Moser, Mike Sent: Tuesday, November 13, 2018 11:00 AM To: Cox, John <iohn.cox doa.nc. ov>; Krotoszynski, David <david.krotosz nski dhhs.nc. ov> Subject: RE: [External] FRO Form Signature and Letter of Consent David, You are correct, this property was allocated to DPS in 1969 and they have complete control. Mike Mike Moser General Real Estate Manager State Property Office Department of Administration 116 West Jones Street Raleigh, NC 27603 919 807 4680 office mike. moser doa.nc. gov NC Department of Administration Email correspondence to and from this address is subject to the North Carolina Public Records Law and may be disclosed to third parties From: Cox, John Sent: Tuesday, November 13, 2018 8:19 AM To: Krotoszynski, David<david.krotoszynski@dhhs.nc.Rav> Cc: Moser, Mike <mike.moser@doa.nc.gov> Subject: FW: [External] FRO Form Signature and Letter of Consent David; I am forwarding your request for verification to Mike Moser the Manager of General Real Estate. Thank you, John John Cox Facilities Information Section Manager State Property Office NC Department of Administration (919) 807-4674 office J_oh n. Cox@doa. nc.gov 1321 Mail Service Center Raleigh,NC 27699-1321 s swvf el ti. ae NC Department of Administration Email correspondence to and from this address is subject to the North Carolina Public Records Law and may be disclosed to third parties. From: Krotoszynski, David Sent: Tuesday, November 6, 2018 11:27 AM To: Cox, John <iohn.cox@doa.nc.gov> Cc: Mulligan, Jeff <jefF.mulligan@doa.nc.eov>; Hoff, Luke <luke.hoff dhhs.nc. ov> Subject: FW: [External] FRO Form Signature and Letter of Consent Morning John, The DHHS Division of Property and Construction was contacted in regards to a DPS NC National Guard construction project. Please review the forwarded email thread along with the attachments and supply your office's opinion on the issue. In review of the parcel at 5161 Western Avenue, Morganton, via Google Earth, DPS has two (2) facilities in operation on the parcel in question. The reallocation between DHHS and DPS occurred in February 1969, see plat and deed PDF, and the issue seems to be a listing error at the Burke County Register of Deeds GIS that lists the State Hospital. DHHS is of the mind, that the reallocation occurred in 1969 and that DPS is the steward of the property since full execution which would lead the DHHS no role in the upcoming construction project or required documentation. Regards, David Krotoszynski Chief— Property Acquisition, Disposition & Risk Management Division of Property and Construction North Carolina Department of Health and Human Services 919 855 4872 office 919 733 5711 fax David.krotoszvnski car dhhs.nc.eov 2104 Umstead Drive 3026 Mail Service Center Raleigh, NC 27699-3026 Entail correspondence to and -from this address is subject to the North Carolina Public Records Law and may be disclosed to third parties. 4 Twitter YouTube Unauthorized disclosure of juvenile, health, legally privileged, or otherwise confidential information, including confidential information relating to an ongoing State procurement effort, is prohibited by law, Ifyou have received this e-mail in error, please notify the sender immediately and delete all records of this e-mail. From: Frank Slinsky <Frank.Slinskv@timmons.com> Sent: Tuesday, November 6, 2018 10:59 AM To: Krotoszynski, David<david.krotoszynsk1@dhhs.nc.gov> Cc: Hoff, Luke <luke.hoff@dhhs.nc.gov> Subject: RE: [External] FRO Form Signature and Letter of Consent Yes sir, attached are overall plans of both projects occurring on the DoC portion of the site. Phase 1 has been approved for Bidding by the NCSCO and will be advertised this Sunday November 11, 2018 and Phase 2 is the DID review process at the NCSCO. Phase 2 will begin after Phase 1 is close out. I also attached the document from February of 1969 where 97 acres of this site were allocated from the State Hospital for use by the Department of Corrections. In April of 2018, 85.6 acres were transferred intra-agency by mutual consent between the Adult Corrections and Juvenile Justice (ACJJ) and the North Carolina National Guard (NCNG). Hope that helps. Thank you! Sincerely, Frank Slinsky, PE, LEED AP Senior Project Manager TIMMONS GROUP I www.timmons.com 5410 Trinity Road, Suite 102 Raleigh, NC 27607 Office: 919.866.4505 1 Fax: 919.859.5663 Mobile: 919.830.8458 1 frank. slinsky_atimmons.com Your Vision Achieved Through Ours To send me files greater than 20MB click here. From: Krotoszynski, David <david.krotoszynski @dhhs.nc.pov> Sent: Tuesday, November 06, 2018 10:27 AM To: Frank Slinsky <Frank.Slinsky@timmons.com> Cc: Hoff, Luke <I_uke._hoff@dhhs.nc.gov> Subject: RE: [External] FRO Form Signature and Letter of Consent Morning Frank, In the review process, it would be quite helpful to have a schematic of the proposed construction project in order to better understand the entire situation. Could your office please provide a project schematic via email? Thank You, David Krotoszynski Chief— Property Acquisition, Disposition & Risk Management Division of Property and Construction North Carolina Department of Health and Human Services 919 855 4872 office 919 733 5711 fax David.krcitosz nski(&,dhhs.nc. ov 2104 Umstead Drive 3026 Mail Service Center Raleigh, NC 27699-3026 Email correspondence to and from this address is subject to the North Carolina Public Records Law and may be disclosed to third parties. Twitter YouTube Unauthorized disclosure of juvenile, health, legally privileged, or otherwise confidential information, including confidential information relating to an ongoing State procurement effort, is prohibited by law. If you have received this e-mail in error, please notify the sender immediately and delete all records of this e-mail From: Hoff, Luke Sent: Monday, November 5, 2018 1:50 PM To: Krotoszynski, David<david.krotoszynskiC)dhhs.nc.gov> Cc: Axtman, Rodney <rodne .axtman dhhs.nc. ov> Subject: FW: [External] FRO Form Signature and Letter of Consent David: Please verify that the attached site is the financial responsibility of DHHS. If so, then should Landowner(s) of Record be revised from State Hospital (at Morganton) to the NC DHHS on the attached Financial Responsibility Form? Any issues with the attached forms and me signing them? Luke Luke O. Hoff, P.E. Director Division of Property and Construction North Carolina Department of Health and Human Services 919 855 4870 office 919 618 7553 mobile 919 733 5711 fax Iuke.hofl dhhs.nc. ov 2104 Umstead Drive 3026 Mail Service Center Raleigh, NC 27699-3026 Email correspondence to and from this address is subject to the North Carolina Public Records Law and may be disclosed to third parties. Twitter YouTube Unauthorized disclosure of juvenile, health, legally privileged, or otherwise confidential information, including confidential information relating to an ongoing State procurement effort, is prohibited by law. If you have received this e-mail in error, please notify the sender immediately and delete all records of this e-mail. From: Frank Slinsky <Frank.Slinsky@timmons.com> Sent: Monday, November 5, 2018 1:07 PM To: Hoff, Luke <luke.hoff@dhhs.nc.gov> Subject: [External] FRO Form Signature and Letter of Consent Mr. Hoff I am working on site plans for the DPS North Carolina National Guard and the DPS Dept of Corrections on the State Hospital site located at 5161 Western Avenue, Morganton NC 28655. Construction Plans for the project were approved by the NC State Construction Office and they will be distributed for Public Bid this Sunday Nov 11, 2018. According to Burke County GIS and the attached deed provided by DPS, the site is currently owned by the State Hospital and in February of 1969 State Hospital allocated this portion of the site to the Department of Corrections for their use. For plan approval NCDEQ plan reviewer is asking that you all: 1) sign / notarize the attached Financial Responsibility / Ownership form as land owner (State Hospital) Part B. bottom of Page. 2) put the attached letter on your letterhead and sign it. We apologize for the short notice of this request as it was just brought to our attention. I would be happy to meet you with the forms at your convenience as we would like to finalize the review process with the DEQ this week prior to bidding if possible. Thank you for your assistance and please call with any questions. Sincerely, Frank Slinsky, PE, LEED AP Senior Project Manager TIMMONS GROUP I www.timmons.com 5410 Trinity Road, Suite 102 Raleigh, NC 27607 Office: 919.866.4505 Fax: 919.859.5663 Mobile:919.830.8458 frank. slinskyCc�timmons.com Your Vision Achieved Through Ours To send me files greater than 20MB click here. Email correspondence to and from this address is subject to the North Carolina Public Records Law and may be disclosed to third parties by an authorized State official. Unauthorized disclosure of juvenile, health, legally privileged, or otherwise confidential information, including confidential information relating to an ongoing State procurement effort, is prohibited by law. If you have received this email in error, please notify the sender immediately and delete all records of this email. Email correspondence to and from this address may be subject to the North Carolina Public Records Law and may be disclosed to third parties by an authorized state official. Seasonal High Water Table Report TIMMONS GROUP YOUR VISION ACHIEVED THROUGH OURS. January 25, 2017 Frank Slinsky, P.E. Timmons Group, Inc. 5410 Trinity Road Suite 102 Raleigh, NC 27607 5410 Trinity Road P 919.866.4951 Suite 102 F 919.859.5663 Raleiqh, NC 27607 www.timmons.com Re: Seasonal High Water Table Investigation for NCNG Readiness Center Located off of Western Avenue, Morganton, Burke County, North Carolina Mr. Slinksy: At your request, Timmons Group, Inc., has completed an investigation of seasonal high water table (SHWT) depth for the NCNG Readiness Center, located off of Western Avenue in Morganton (PIN.- 2701118549). At your direction, this investigation was limited in scope to the proposed stormwater BMP locations on the site, as illustrated on the attached drawing. The investigation was completed on January 14, 2017. Depth to SHWT was determined using accepted soil science practices. A hand auger was used to advance vertically into the native soil until redoximorphic features (often mistakenly called "mottles ") with a chroma of 2 or less were observed. True mottles that meet this color criterion that are the result of parent material coloration are ignored, as these are not indicative of the seasonal high water table. Four hand auger borings were advanced in the locations proposed for the stormwater BMPs per the drawing referenced above. In borings 1 and 3, chroma 2 redoximorphic features indicative of the SHWT were not observed in the borings to a depth of 168 inches below the soil surface. In boring 2, auger refusal was experienced at 118 inches below the soil surface. In boring 4, auger refusal was experienced at 72 inches below the soil surface, The table below lists the observed SHWT depths below the existing soil surface. Boring ID Auger Refusal inches SHWT Depth' (inches) SHWT Elevation (approximate 1 N/A > 168 < 1198.00 2 118 N/A < 1222.17 3 N/A > 168 < 1198.00 4 72 N/A < 1216.00 Depth below existing soil surface 1 CIVIL ENGINEERING I ENVIRONIIIFNTAL I SURVEYING I GIS I LANDSCAPE ARCHITECTLIRF j CONSTRUCTION SERVICES Thank you for the opportunity to assist you with this seasonal high water table investigation for this site. Do not hesitate to call me if you have any questions regarding this investigation or if you need any additional information. Sincerely, $OIL �Q . Scott Mitchell, PE, LSS �� y NC Environmental Practice Group Leader �7 f Justin Milstein, SSIT Environmental Scientist CL ) _ (!>\ \o §5} /� ■ , Q § (\ 2\;[ 0 \\\\ ± ))}§ o oo 2 / ()\k ) / \ �� \ g /66 © \\\/ a IM rM / \ %\/ �i\j e0 <z /z�� EE LLJ z\/a 0 Im <\ (D // < /f\/ ^ // O©o± m0 >S>E \ 7 0 Ck °2 �< Stormwater Management Mapping (Revised for MOV Expansion) a / // _ \ \ \ \ \ \ \ \ \ \ \ \ \ /✓/ram—� //k /�i //�i / //i/ /// //l /// / r / \��_ � \ - // / / //i�i //i/ / ///�'—_—_—__ \ \ \\ \ \� \\ \\\\ \ \— — — — \_ \ \ \ --, / �- �\ \ \ \\�\\`` \\ _ mac` ,, // // / - \\\ \ \�\r \ \\\\ \ \ \ \ \\ \\ \ \ 1 ✓/ �� \ \ \\ \ \\\ \ �/ = \ \ / / /1, / l / l / l / / I - if 1 „ I / l / /, / ✓ �` aN RL�Tl!�N _ f / / / / - - - - — �\ \ \ \ \ \ - - - \ \ ' `' y �/ l / 11 �z l l 11 /l( �/ //// // % ///' ` ! - - s �`,� _ -/ / ///// / / / /' / -_- - — - \ \ \ \ - \ /, I \ \ \ \ `\ \ ��ii„� \\ / / 111 I 1 / /// / /� - y1 - ` _\\�\ __ _-� �� �j _/_i,/'//// /// /// / // / ' / -- �\ \ \\ \� \ \\\\ \ \\ \ \ \ --_ \���`� 1 l L l \ \ '-/ '/ _ \\ \ \ \ \ ` '\\\ \ \� Y 1 / 1 / / / �1 vomDs \ \ \ \ \ \ \ I \ \ / \ \ \ \ \ \ \ vT �/// // / / \\\\ \ v\ \ \\\ \ \ \ / - \ \ \ \ / / / / \ \ \ 4 / I _- \ \ \ \ - l �� �' 1 / / �/ / I ` - \ - - - - r i / / - / / //// / // / / - _ _ - \ \\\ \ ✓" \ \ \\ \ \\ \ _ \ 4 _ ^ - \ \ \ \ / / / \ \ _ \ \ \ - = _\ _ -1 ` �i 1� / / / / / / ��c l , I I I 1 ! / / / / / / \ _ - \ \- > _ - _� _ - / / / / / / / / / / - - _ \\ ,' \\\\ \ ) I l \\ \\ \ \ \ - _ - - - _ \ \ \ \ / / / \ \ \ \ \ \ \ \ \ \ Y YI / l l l l I I / J _ oIIs'/ , -/// / // / / / / / / _ _� \ \ \ \\\ \\\ \\\ \ _ \ \ \ \ \ \ / \ 1 \ \ \ — — i — / \ \ \ \ \ — \ �\ \ / / / \ \ \ \ \ �,' 1�\ � ' I I I I1 l� �� I I 1 \ \\ I ♦ / � �� �\ _ __, ////// / // / / -\ \ \ \ \\ \\\ _ \ - // = ll ; \ \ (, I 1 'IIIII '� 1 I I I►' I I 1 \ \\ \\ \ \ , _ _ _ , - i ; _ _ _ / / , / / / - �, , \ \ \ \ \\ \ \ \\ \ \ _ _ _ _ _ \ I \ '' _ = /// / / / / / I / / / _ - -� \ \ \ \ \ \\\\ \ \ \ \ \ _ _ _ - _ \ \ \ \ tiST / _ \ \ \ \ \ I \ - / // / // / / - - - \ \ \ \\ \1\ \ \ \-, \ \ / \ \ �/ /-- \ \ \\ . II III ! 1 �� 1 \ \\ \ \ \ \\ �� \ I i \ \ /c /'%' _/ / / // // \ \ \\ - \ \ \\ \ co \ \ \ - /_-_l�\ car 14 I I 1 11 I I \\ I � . \ `\ I r \\� \\ 1 1 11 \\ \ I 1� \ /�- - // l c. t' \\ \ \ \ 1 \ \ \ \ _ - \ \ iTs '-__--- \ \ \ \ / /" / \\ \ 1 \ Ill \ \\ \ \ _ - \ \ \ 11 I 1 / �l Iy l l LI•I ,1\, \ \\ r!\I \\ I - \\ 1)��\ / /'/---_/i'// / // / ///I 1.�� �1.1 1�1 I'"` \1� \\ \1 \\\\ \\ \ ♦\ \ -\ \ \ \ \ \ / \\ \ \ X- I` r 111 IIII 1/ 1 1 IIII ' \* \\ C\\ \ I 1I✓ ,_- \- �/ / / J/ /I \ \ \1 \ IIIII \\\ \ \ \\ \\\ \\� \ \ I _ ---- \ -\ \\ \ - ,/ /' • , �„ I c l t%l I 1 I )) III 1 / - \- %- - - / _ - / -/ ,'/- \ \ - - l -\\ \ \ \\ I I I 1 I 1 I \ I 1 \ \ \\ \ \ \ \ \ '\ \ \ - \ / '?1 / I z1 I I 1 , I� I I I 1 , 1 1 / I I I I , \ - - - - / _ -/11 / / / I I I 1 \ \ \ \ \ \ ♦ \ - \ 1 \ \ � - , • \ \ \ \ \ \ \ \ o Il 1 1 1 , I I 11 / I 1 / \ -/ - -// ' 1 1 I I I I I I I \ \ \\\\ \ \\ \ \,1 �.. ♦ \ _ \ \ \ - - _ \ - \� \ \ \\\ \ \ 1 HP I I1 \ , l I 111 1 I 11I I I I I,/I / l l I I 1 ( / \---/\- s-- f - -/ /-- 1 I I I 1 l ! I , 1 \ \ \ \ \ �- \ I \ \ \ - \ \ \ - ����bl I ,IIIIIIII �11 /l 111 1 /---- _-_ /' 1 , 1 1 1 I / I ,I \�\ \\\ \\\ \ \\ \ _ _=\\\\ - - \\ �\ 1 \ \ \ \\ \\\ \ \ \ • \ • t - \ \ \ \ • \ y L- - - \ - � — - \ \ \ / ) ! I I / 1 � l I I I I I / / / / / / I / / , 1 , I I I ` \ \ \ / ' I \ \ \ \\ \ \ \ \ \ \ \ �■ ,�,�__ _ �= \ \ ' \ - \ \\ \ \ . \ \ POST -DEVELOPMENT STORMWATER QUALITY CONTROL PRE -DEVELOPMENT ONSITE IMPERVIOUS SURFACES = 6.36 ±ACRES POST -DEVELOPMENT ONSITE IMPERVIOUS SURFACES = 21.04 ± ACRES (INCLUDING FUTURE BUILDOUT) IMPERVIOUS AREA REQUIRED TO BE TREATED = 14.68 ±ACRES IMPERVIOUS AREA TO BE TREATED = 12.94 ±ACRES (WET DETENTION A) IMPERVIOUS AREA TO BE TREATED = 3.76 ±ACRES (WET DETENTION B) r - \~ / 1 III I I I I 1 / / - I I 1 \ / I I I \ \ `.1��' \\\ \ \ \\ \ \ \ \ \- - - _ _ $ - \� Z \' / _ \ \ - %/J '- \ \\ , Illll l II , I I HP II 11 I(/III( / / / _\-/� - ' ' / I I I I \ \ \ \ \ 1 I \\ �\``_` \ \ \ \\\ ---- --�- \ \ V -- \ \ \ \ \ / / / - \\ 1. , \ , , I I III , I I , � / _ - / I I ` _ _ - - I I \ \ \ \ \\ \ \ \ \ `\ _ - _ _ -_ _ __ - _ �G= ; \\ �� , \ \ / - _ _ - \ \ \ \ PRE -DEVELOPMENT STORMWATER QUANTITY CONTROL \\ \ �� I , I I 1 I I - / / / / I I I _ 1 I I \ \\\ \ ----- - - _ /� \__�\_ \ \\ /\\\\\ - \ \ \\� \ \ \ ' I I I I , 1 I b I III I / - �� _ __ -_ -=-_ _ I J \ \ - - - _ _ __ , \ fJ//,'- \\�\\\�/ .\ ,,II 11 I I 'l l ' �� � / / ' / / / / - ---------------I \ \ \11\ , \\ \\ �_� ---___ _===�/L` \� \-^ , �'' --� ^\ \ \ \ \\ J ��/ a /~\\\\\\\\ / �! I III I IIIIII I , IIII III I 1�\ \ = _ _ _�_ ' / ���i �--__- _-___-__ -__- _\\_�\\\\\\\11 \\\\�� -- _ _f/___ \��\\\� \\ \ , \= \ I 1 I I _ ��-�i=��=�/ice ��� �_-� ---==__----_____- II 1 - - - - - __ _ \ _ \ ^� / /,� �'/ \Q\\ 4 \\kl / I I I I I I I I I I I I I I I I 1 1 \ \ \1 \ - - _ _ _ - _ - _ _ _ _ _ = __ — _ --_ -- _-_-_---__ ____-_-_-_ - - - - = = = = = - - - - _ _ - _ ' ' _ - _ _ - - / / \ \ r h\ I III 1 I 1\I I \ ~ \ ^ \ _ -_ - - - - - - _ -. - -_ _ - - - J J) \ 1 - - - - - - - - - - - - - - - - -_ _ - - �\� \ `\\� \\ \ \ \ ` \ r /r 0\\ II I I I I I s 11 I I 1 I I I I I \ \ \ \ \ �\ _ -��� .-- _ - =="f-- - mac_ ` ` - - - - - � - - \\\\\\\ \ \--_ \ \ \ \ \ [ \ \ t -\\ \ \ - / \ \ \ �/ - \ \�/ \X I I I I I� \ \ \ \ --/ _ _-- ---- e----------- — - \\\\ \�\\ \ / \ \ \ \ _J / - \\\ \�\ \ i I I I I I ,IIII 1 I I I I 1 I 1 1 1 \ \ / - � -- _--- ---- --t�=_ � - - \I'I \\�\ \ \\ 1, - \\ \ \ \ \ \ \ \ ) \, / r �\\ \ / \ I I I I I I I I I I I /, / -/1 ---_ �\ \ \\\\\\ �\ \ \ �/ / //,\Q \0\ \` \ / I I I I ' I I I I I I I I I I I I I I 1 1 \ \ �/ / _ - _ _ \ t\ \ \ \'\\, , \ \ -_ - / - i�\ \ \\ \ \ \ \ \\\\ \ \\ - \ ~� I /� /\Q \ (\! J/ 11 I' I 1 I'I I I I I I I I I I I I I 1 1 \ \ �/ I \ \ \ \--- _-- \ \�\\\ \ \\\�\� \\\ \ \ \// \\\ \\ \\ \ \\ \ \ \� - \ / / f/\�\\\\\\\ \� / \ , I I I I I I I I I\�I I I I I I I , \ \ /. / - - _ _ _ _ _ - \ \ \�\ \ \ \ --� < J / 1' , \\ \\\\ \ \ ) I I I I I I I I I I I I I I I I I \ \ / / \max- - x - - _ x x x -max- _ - - \ \ \ \ \ \ \ \ \ \ \ \ \ _ 1 L // / ��\\\'\,\ ��f \ \ I I I I I III 11I I I I I I I I� I I I I I I \ ` \ \ \ \ \ I 1 / \ \ -- - -- - _ _—� - - \ \\\\ \\\ \ \\\ \\\ // / \ \ \ \ \ \ \ _\ \ \ C x- .�--x x- -x-x \\ \ \ \ / _ \ \ \ \ \ \ \ - \ \ 1 / �� \\�\\\ \\ , / I I I I I I I I I I I I I \ \ \ \ I I / I ' \ I l'- / / / �F—x� 1 \ \\\\ \ lt\\ \ \l i \ \ \ \ \ \ \ \ \ \ \ \ - �\ PRE -DEVELOPMENT DRAINAGE AREA (Acres) (CN) Q1 Q10 Q100 ANALYSIS POINT A 26.38 85 76.00 171.35 283.62 ANALYSIS POINT B 28.27 80 44.11 144.18 200.56 ANALYSIS POINT C 7.25 78 6.48 17.85 32.31 / / / / �/ \\\\\ \ l / I I I I I 1 1 1 1 1 I 1 I 1 \ \ \ / \ \ \ \ / II \ 1 \ \ \ > \ I _ _ \ \ r // / /, \\\\`\ Q\\\� / r�/ /, 1 I 1 I I I I 1 vl 1 \ \ \ \ \ I \ \ \ I , I \ / ^, / , \ 1 \ ,\, \\\ 1\111�- ^- - \ \\\\ \ \ \ \ + ��, / \\\\\\ - I I I 1 I I I 1 I �� I 1 \ \ \ \ x \ -r / / - - _ ` - 1 , 111 - - \ \ \ \ \ NOTE: POST -DEVELOPMENT FLOW IS LESS THAN PRE -DEVELOPMENT FLOW AT ALL ANALYSIS POINTS. / I f / / \ ( \. / / \ 1 I I I I\ \ \ \ \ / 1 \ \ \ \ _ _ _ I _ _ _ / \ 1 \I 1 1 \ t / _ - _ - \ \ \ \ I /� \ \\\\ ie. t \ I I I I I I I I I I I I I I P I \ \ \ \ \ \ V I \ I _ _ _ - �- _ _- _ _ _ _ - _ _ _ - _ - - - _ _ - - _ - - _ , ) l \ I I 1 1 1 , , , 1 `1�/ I / - - \ \ \ \ \ \ \ ,>�\ REFER TO CALCULATION BOOKLET FOR ADDITIONAL INFORMATION. // (I/ /0\\\��\\/. \ ( II I 1 I I I I 1 \ \ . 1 / , y \ \ i _ - z = l� ,I, \ /• \ \ \ \ \ \ " \ Jr / / / \ \\ / , I I I I I I I I I I I I I , 1 I \ \ \ \ \ I / \ \ \ ✓ / - / \ - \ \ /� I I ��I , , I i 1, t ✓ 1 - �- - - \ \ \ \ \ \ \ \ \ / /' , \ PRE -DEVELOPMENT IMPERVIOUS AREA AND WATER QUALITY TREATMENT / f) rl\\�\\\a\ ) I 1 I 1 1 1 I I I I I I�\I , \ \ \ \ \ \ 1 \ \ \ \ / _ -\ \ _ \ \ / I II t I I _ _ _ \ �\ \ \ \ \\ J /// 1 1 \\\\\\\1�\\\\\ ( \ / 1 1 I 1 1 I I I I I 1 I 'I I I \ \ \ \ \ \ I /1 \ \\ \ \ // ` I \ I / -- \\-� \� I 1 I I//II 11 tl\I I / \ \ \wO DS\ \ \ \ \ \\ "f\ \\\\\ III , I \\\\ \1 . c\ I I I I I I I I I I I I \ \ \ \ 1I I\ \ - - \ ) i \ , I I 1 I II / \ \ \ \ \ \ l \ t \ I\ \\�111\\\� G', \ J/ / % 1 1 1 1 I I I 1 1 1 1 1 1 1 1 1 1 1 1 \ �\ \ \ \ \ \ \ I I I \ rl \ \ \ \ / \ \\ \ \ I I I ' IIII I1I1 \\ L \ \ \ \ \ \ \ \ \ \\ \ \\\\\ \\\ a I I I I I 1 \ s \ \ \ \ I / \ x 1 ^/' I \ \ _ - - _ \ I I I I I I I , 1 / \ \ \ \ \\ \ \ I) I I I I I I I 1, ,1 \vim \ \ \ I8_241\ \ \ \ / \/\ \ I \\ \ \ \��\\�\\11 \I ( \ / / I I 1 \ \ \ \ _ _ _ _ - \ \ - \ \ \ EXISTING IMPERVIOUS \ \ 1 x1 Ix I I I I I 1 I J/ - . \ \ \\ \ \\ \\ \ \\\ \ ♦ \ \ \� \ \ \ --- \ \ \ \ 1' I iI I I111II1�1,�\t \\^ \ \ \ \ \ \ \\ \\ \\\ 1\\ \\\ / I 1 I , \ \ \ \ r 1 - - \ \ \ \ \ \ \ \ \ \ "I i, 1 \\ �, / l l I I I ( I I I I I 1 1 1 \ \\ \ 1 1 I I 1 1 1 1 1 \ \\\ \ \ \ \\ I � \ \\ -, \ \j\\-\`\\\\\\ I I I I , , \ \ 06 11 I/ - - I \ , � � � DRAINAGE AREA ��\'' \ \\-\ 1 I i I I I ,I' 1 I I 1 1 \ \ \ \ \ \-,u\ \ II I 1\ `\� \ \ \ \\ \ \ �, \\ \\ --11,111111\, \I I I I I 1 1 1 I I \ \ \ \ � \ ( I 1 \ \ \ \ I I I 1 1 \ \ \ I I \\\ \\\ \\\ I I I1.� I 1111I,1\\\ "� \�~\ \ \\ \ \\ \\ \\ \\ \\\\\\\\ \ \\I \I _ \ \ \ \ \ 1 \ \ III\\ \\ 1 I I I 1 1 1 I \ \ \ \ ^ \ ^ \ f U\ \ \ \ \ I 1 I I I \ \ '� \ \ \ \ \ - \\\ \ I I 1 , I I I I I 1 1 \ \ \ ` -1 \ ) \ \ r - \ I I 1 1 \ \ \ - 1 \ - \ \ 1 \ \ r \ \ \\I \ \ I 1 ' , I I 1 \ \ \\ \ \ \\ I ' \ x \ \ \ l \ \ \ ' x I" I I 1 \\ \ \ z_ \ \ \ \ 1 �� \�- ��\\\\\\ I \ \ I I I 1 \ \ \ 1 ' / \ \ \ \ \ \\ _ \ I I 1 I I 1 \ �-` ) \ \ \ \\ \ \ 1 \ " - \\J\\ \ \ l \` \ \ , 1 1 1 I I I I I 1 I 1 1 \ \ \ \ \ \ \ I III \ I \ \ \ \ 1 I 1 1 \ \ \ \ \ \ \ \ \ \ _ _ - \ \ 1 1 , \ \ ` - \..,\\\ \ ) y* I 1 I \ \ \ \ ��\ \ - �' I I 1 \ \ \ \ \ \ \ \ \ \ \ I 1 1 1 1 I 1 \ \ \ y\ \ �? a \ \\ ��_ \ \\ \ - - -- - \\ 1 -- THIS DRAWING IS FOR AGENCY REVIEW ONLY - NOT FOR CONSTRUCTION �t_�� \�\\ �� \11' I\ I , I I I I 1 '1 1 1 \ \ \ \ \\ \\ �\ \ ,I o \\ \� � \ \ \ \ \ \ \ \ \ \ \ I I 1.1 I I I I \ \ \ \^\�\ ! \ \t Z \_ "A \\\\--- \\ \ \ - __ r �b \ � I \ \ \ \ - � \ \ 1 I I \ \ I \ 1 ( \ \----- \ \ \ r - ^ _\ \ • 1 1 I I I I 1 1 \\ \ \ \ \ \ \ \ , I II \ \ \ \ \ \ \ \ \ I \ \ \ I i.1 I \ \\ \ r \ \ \ \ \ \\\\ \ \ H I I I I 1 1 \ \ \ \ \ II� \ \ \ ��--�• J\\\\I \�\ \ \ \ \ \ \ \ \\ \\ \\\ \\ \` \�__ 1 II \\ x \ � -\ �X 1 \ \ \ 11 x I 1 I \ \ \ \ \ �\ ^�t� \\ \\ \ _ \\\\\\ \ \ - �\ , /II 1 x \ WETLANDS IN THE PROJECT AREA HAVE BEEN IDENTIFIED AND CONFIRMED BY - _ ' \ _ \ \ / 1) ( ( � - - �- ` _-� I II \ \ \ \ \ \ \ \ \ \ l I I 1 \ ti � ~ \ \ ' \ ACOE AND NCDEQ. NO IMPACTS ARE PROPOSED. '� , \ - \ - \) / \\ ( I I '1 '1 I 1 1 I I f \ <oAr ' _- — - - _ 4I 1 \i , - \ S \ \ \ \ \ \ \ \ \ \ \ \ 1 I' I I e \ \ \ \ �c\w�c ROWFH\ \ 1 \ \ ; `1 t I 1, \ \ \ - \\ \ -, \ �\ I 1 I I I I / ,t / / / - ' - X�' 1 h r \ I \ \ \ \ \ 1 \ \ I I ( I '�O\ \ \ V \ \WO__ _ AND \ 1 1 / \ ( \ -\ \ \ ( I I I I 1 I I I l , / 1 , \ \ I \ I' I \ VE TA\TVN \ \ f '/ 1 \ r ` ) I -, r 1 I /\ // h I I I\ \ \ \ � \ \ \ ?! I I 1 I I / / \ \� x \ I \ 1 \ \ 1 I \ \ \ % I \ \ , -\\\^ \ , \ I 1 I I I / \� I / �� _ \ \ 1 \ I \ I 1 x x I \ l \ \ L \ / !` I _ \\ `'\� \ \ I I I I I I I I I 1 / /\ � / � / �- \ \ \ \ \ 1 I 1 \ I I \ \ .\ ) � \, I / t l y l� I 1 �1v\\\- \ `'� \) 1 I I ' I I I ' I / I --- \\ 1 °^ `� \ \- - \\ I I I / I \\ , I' I 1 1 \ \ I\ \ \ v\\ \ \ ' ` // \ I 1 1, \ \ I \ \ I ' 1 I I 1 / / _ \ \ l : \ -; \ , I \ , 1 , I , \ \ \� t \ t ) / r 1 1 I \ - \ \ ) �\ 1 I I I I I I I I I + \ \ I -_<_ \ \ 1 I I \ \ I / \ \ � /� \ l � -\\\ \ \\1 p tt) �\ I I I I I 1 I I , I 111/� /� � 1 I , / ! \ \\\\� 1 1 / / t // \ \ I \ I I I\ 1 1 \ \I. � \ \\ t. \ 1 I / ) 4 r ' \ \ \ \ I \ C' \ ,\I �� I I ' I I 1 I I I 1 I I I I I / -' 1 1 -7 // 1p l_ _ - // J ) , / - - - ( r - I\ GRAS�F/E D \ I i I \ I I \ °\ \ \R \ ) 1 \, \ .4 (\ 0 t 1 \ \() � ( \\ \ II / \` I I l I I I ( ( I \ \ I I I \ I I 1 \ 1 1 , •'\ \ i I l \ .,\ \ l l I� \ \\ \\�` \) �1\ I I I I I I I I I I I IrI � � '1 I I \ 1 I x \ \ I \ I 11 J I I _ \/ \,\\ \r\�\ ,I\11 \ I I I 1 1' I I I f ]I l I r I I I 1 \ \ \ l \ \ \\1 11\ \ \`1 I 1 I I I I I I I I x 1 \ II 71. 05 I I l \ , I I 1, I I \ 11 a> \ i \ \ , ` 1 1\ ; i l ! r l \ ^ \� I` S I \ \ \ \\ , 1 I I III 1 1 1 I I I 1 \ \ \ I I I 1 \•�. \ \ I ) . I r \ \? \4, \\ I\ r \ I I I I I j 1 1 ® \ \ �lltlt+l 1 I ' I ' I I I I' I' I I 1 l / 93.28' I \\ \ 1 I I , \ \ \ \ I \ I 4 / ( \' J ` f f 1 7 ) \- , ll\ \`\\ I � l ' I I I I I 1 III 1 I 1 1 \ \ 15 , i, , 5 1( I 1 ! I \ �I \ -_ \ I I I I I , \ I I 1 \ \ \ \ \ \ \ \ \ \ II i I x \\ \ \ \-(,� �\ \ \ '\ \ ,7 I 11 I / � ," J / t % J r> / � � > r )III\\ \Ill; ( �\ I I , I I I I 1 I I I ' III I \ /�/� , , \ \ \ \ 1 , \ \\ \ l'� i `I `) , ) , D/ 1 f � �,' ; ) � 1� ; ; 1 1 1 ( 1 II 1 I 1 172.68' I \ \ ' \ \ - �� \ \ \ ( l 1( \ 1 ? // `I , - 1, J / ( 5 , \ I !\ / 1 \ i \\ \ \' \ 1 / I ^ / f • / I i' 111 \ l I I I r I \ \ 11 `� V \I \ � � \ RASS - > 1 I I !I )I / I tI \ � \ � , \ I/ _ �` t / \\\,1 I\\ I I I ' I 1 I l l I I 1 53.63 \ / ) \ \ i \ \ \ \ \ \ \ \ f s c- / / / \ \ t 1 \ �► ` `� ✓ r� 1 // (IIII\(�, O ` I I I I I I \ I I I l 11 /// J \ l f I! I l 1 \ � 1 1 1 1 I I \ r r/ \ -� - I \ I I > 1 1 \ l \ I / Y \ \ J ( I / / 1, \\�',\ I � I I I 1 I , 1 I _228'. 1 8 z 228.36 � I \ I I ° \ \ \ \ I (' x, Ix 1\ 1\ ( \ I) I I 1 I i ! 1 ( f 1, �/ 1 1 1 l ;� o I ,(% \ ' `\Y ` h L ) '1 / : y / - v \\ ( / N� I I I \I \ I I , / I 1 1 11 I ` \ I I \ \ - o� \ I , , �. \ j ( f I' ) � j ( l I I I , I I \ t ' \ 1 1 '129. 1 I I I \ � \ \ I 1 , � \ \ � ` \ \I / 1\ , , ) � /( /J I Il 1 s � I 1 / \ I 1 1 ) ` ( I / / \ I I \ 11 I �1 / ) / \ I > > / , I\`, \\ , G)1 \ \ I,I��I I I T \ \ (. I \ �\ \ I ( II t, 1 � I I � r / < N I \��I ( k ` � I I,, \ l v \ 0 l/ / , 11\ r IIll I �\ \ \ I \ \ \ .I \ \ k ( ,1), 1\r/ \( I \�� / ` / ) (( I ) <�of 1 \ \ I%� r l / /1 / // / % / 111 1 1 ,-, \I I \\ I I I I I' I I I I ( L 1 I / �� \ ( IIII 11�I / I I I I I 1 I I / 1* 1 �x i \ \ \ ,I \ \ I .\1 \ I ) /�) ) IL 1 � / / -\ ( L` ) I J / � I r �) ) � \+ ) II / / i ) //y ,_ r / I / /r -\ I( 11 I I I I - -L l / - \ / J I / r / / \ /! I 1 )1 I / " / f ! C / / 1 / h o ( ( , ' 1\\ 11�1 1 1 l I 1 I I I I I I, Ic x �x� \ ) < I -_M f l ! ( \ r v/ 2 1 J / t t.r/ I I ) // / / / - \ , / / J I l / / I 1 / 1 I !! / / J U \ 1 I / I I1\� IIII\ �\ ` 1 I I 1 I I ,I ( \ ( \1 I \ \ I / / \ \ \ ( �� / 1 / I \' \ \ 1 , / I / ) r I I t a \ l l / \° \ / / / / / / / / v ♦ / \ 1 I 1 / _ - ^ x— \ \ \ / \ 1 \ ) I r l I 1 \ / (_ 1 I I I / S / > �/ I � 1 < ( ) < l I / / i / I / '' t - \ ) Ill((I�\1,t) I I I I I I , I I I, , ( \ . - I 1 \ ; i , 9 , `. -1�/� I r J ) / , _ 1 \ (( , i I \ \ \ I 1 I i \ \ _ ` ,x \ I 1 ( ) < 1 ( I I 1 I I / / l 1 / / // \\ 1 1 ,1 I f- \ I / / \ \ \/1 l Il 1 ( \\ \ 111+ \ r / ) �� / I / / / / / / \/ / f f //� r - _ J\ \ (11\I \) 1 1 1 1 1 1 1 1 I I , - _ 1 G 9. I \ I ) -�) 1 \ ?� - � r /) / r 1 / 1 I I J , '{\ (r t ) / / , / r / / / , \ \ I � > , ( 1. / JJ \ / r _ \ \ \ I , I l / I l I \ \ \ _� I I 1 1 ♦ \ ( -) I I I I I T /� / / - / / ' ' f / i / , ( , J ! I , \ / / / / ' / r / /' /' / \ II ` / / / / / / °/ / / J 1 r �- _ ^ / I 1\) I I \ I I \' 1 \ \ ` I I I \ ' '�► I 1 I I � 1 1 \ ( \ ( ) / ,l / , / ( o / , , / ^ \ _ t- 1� I)I III ( \ \ 1 _G ) t \ / / / r / r / / ( / r / / II 11 II ( \ / ♦ \ \ \ / / / ` Ji \-- I l II 1 ( / ) / // / // // / /✓ / / ✓ J z/ r-; -, \ _. \ 1 - � � ) J % \ x I ` � 1 I x \ � 1 \ \, I I I � r / / / / l / r / I � r _ \ -IIII I,, \ t / / � ` = � = � a / /� I I / / \ \ \ I I r I I e, r '- / / / ~ / � / Il I l v / / J \ ) / _ / / / - l l / I --,--\--J/Il(/\\ - - . `11 1 _ _ �I\, 1'I tii,��--- /1\ti\ t ---- �� / ♦ /' r /'t 1\ J / - / - // I ' +') 1 _ �r /--✓ ///�I 1 1 �- / / / - / / 1 _ � 1 __ / y - � .' � / �X� , '� r� .� / i/ ✓ / G Y �•CONSTRU N LIMfL� --_ �� �//- - �i /� ��� iS���f�1 #`/����� ��♦��.� ����'!1/'�°��� � � fir/ �//f ���,,� �/ / ,` fl/ � r pj �11 - r/ r/ /� % � %; '%' � m �/ FA ,� ���� r I ���, I I I I/ I / - I .j \ \ I ^ IJ /1////l I ) I' / \ / I I ' — \III , I I I / ( ( I I SEE ABOVE \— 1 I / / \\0 r I / / \ , \ T - IIII' I I I I, II I ,I / \ ( ( (. / ^-` - 11\\N I I I 1 / \ -„ I f I I I � ...., I'l /' -\ I 1 I I I 1 I - - --\1\\\\,I , 'I I \\ \\ I/ ' -\\\ \\\I I / ) I /- / \\\\\\\\1 ; \ \, \ r I earl j —/ 1 / )I / \ \ \\ I ,� \ \ - / r \\\\\'\\"\\\ \ \ \ \ \ r ( \\ \\\\ , \ \ \\ \ \ " \ \\ I \ \ \\ \\\- - \� - \ � I 1 \ � '_ \\\ \ - \\\\ \ l \ ) \\ — \\\ � ~ L o \ / \ \ \ \ \ \ \ `_ ` _— - _ � � \ \ \ \ \ \ _ � --` \\_ _ n - - - \ \ - \ \ \ \ \\ \^ - - _ �---�/-- -- \\\\\\\ \ \ \\�\\\ \\ \ \- ��-`��`��� __ \ — \ \\\ ,�—_ — — — -- — -- \ \ \ \\\ \ \ \ \ — — — " --=—�—=--- --- \ \ \ \- \ - \ \ \ \ \\ \ \\ \ \ \ - - \ - _X \ \ \ \ \ - ._ - - \\ \ \ \` � - - -\�\\ \\ \ \\ � - ,- _ \ \ - \ \ \\ \ \ � \` \ \ \ \\ \ - \ \- \ \\ \ \ - - \ \ - \ � \ \ \ \ ,� / - - \ - \ _ \ �`�\ \ � \ \ `\\ \ \ \ \ \ \ \ \ I 1 � I 1 \ _ � \ - '� � \ \ � \ \ - _ \ \\ \ \ \ � \ \ \ I / / ✓ \ \ " \\\\\\\ \\\' \ \ -� \\ \ \\ \ \\ \ \ � \ '\ \ \ I , / \ �\ � \ \' \\\'\ \ \ \\ \ \ \- \ \ \ \\ \\ \ \ \ \ \ \ \ \ \ \ 1 I I / / I / / / ��J � � �a� Jti qP \\�\\\ �\ \ \\ \\ \ \\ ", \\ \ \ \ \ 1 I I 1 / / / / / / / /' INSET'A' 79' r� /1 i \ , - ---_-' I \ - I I \ \ I I I I I % - r/ / / <ti // / ✓ / r r/ / r / J - / 5 .62 I / I A `\ \ I \ ))1 I I I { I/ I- t t/ ov f- / /� ( / I'I I r % / 1 I / / / .,/ / / , o / / r /\ \ �I _ / \ \ 1 / ( ) t \ �1111I I I I ( / ' r ✓✓� �� , / / )/ /� , , ( I r °l/J I1 r N/ J / /_� fJ S 1 v' ,I - - -- ( \ \ I \ \ I \ l\1l I I I I Il/// ,/// /"t- / f J'/ - / / , 1 ( r ) I , I / // I S /r ) ° / J O# \ x r 2d \ ) \ ( I 1 11, l 1' I 1111/I / / ' ' ' �/ /r/ / / // 1-� l^ ) r / / ) / l / Fox A / \ ) I t I l \ / I / / ' X / ' /` / / l / ✓ I / t \ ( I ( / / 1 \ A \ \ I, ------- 1 \ I \ ( / / ) I I111 t),t /r I /✓ / / /-//- / / ` f \ Itf . ( // I ( l I I 1 )r / rJ- \ \ ® ® \ \ /--------\ I \ ✓) 1 ) r f I f I III("" /'I ft // - -� / / Al , / ) 1 I 1 � % ) a I -� I \ I \ ----- / I ) + I I 1/ ,/ / / r r ✓ / rl^( �r/ �/ (' , ,! I Al / / ) , ( ) ) l 1 _ A \\ \ - - - - — - _ _ - - \ I I I /I- '`' I 1 I 1) IIIII f I I I I ( I I I/I/ r,/ 1 r �- r r ' r1/ ,I~ /1'n l I /( ,1 ,/ ,f /)11 ` (n.\� / ,_ o f fl- x _ _ \ \ / ' \ e \ \J \ , J 1 I I ' I I I t / I ( : i / r f (/ < . I _/ / I - Il \ I //I1 1 / > I / / / ) I/ r I STORM PIPS II - ----\ \ \ / I s / ! / III I I / \ f / / ( / t r r / I -/ ) `` II\ / - \ \ s , I I I I I !/) 1111I 1 I I f / � (1 / I r / \ I ( f ) / F /� / / r / d/ FENC1 III -\ \ '\ __--_ --\ \ - 1 r I I ))/ 1 /, III) III 'I I I I ,/ ; %t- . ( / (\ / / / / / /'/ ^ \ I I r \ ) 1 / , J , , r((J \ , / PAINTED GA �II\ \ \ -- / - \ \ / ( ,II/ // )) //))IIII( 1)1 I ' �, �1 // o '/ I ( E,b II \ \ \ \ \ 1 I 'f I , / / I I < )1 ) / 1 ! I ) / / f / ✓ 'i / " \ )PAINT P II 120"4/' / / \ \ \ \\ \ r III ) ( / / /(I1//)// //lI/r/))/r1 r ) / / I I (v % J\\/�r\C A I I 1 r t ,r f / ,,/ I G \ )P�AL L �II \ /� x \ \\ \ \\ i I I I I� *-O I / t J I/ )I/IJf 1 ( I 1 1 ,/ 11/ 1 \ t Il 1 ♦ \' `�jal / / / / ( ` \` ~ �.�AfJyTE[� ( I 1 t / ) f I l / ' - //'f // \ 65.28' % I \ \ \ \ I I(. I I ( l l r(/ I I I I I I I I I I I I \ I/ r I > / ( `/ z_ 1 1 r 1 ../ `) ( \, r f-�C�}d0�1 E > r \ \ \ \ I I I \ I \ I // 1 1( I I ) I l l 1 1 1 ) I I I , ) 1 ( / // /�I J / � l \ 1' 1 11 \ I t I ll I I I ) I I I I I It , I C , /� Z \ _j ✓I l x I / / ) I / I ! I) c 1 / a /f r 1 / / ( 1 I ��/ �, �'rr � \ L4�HT POLE V I) \\ I I I I 1,/x 1\ 1 11 / I I / ) I I I III I J ) Il 1 1) 1 j / n( 1 (� ) ) 11 , 4 I I 'i / I �� ) t \ \ � ✓' x / I \ I 1 I \ I / / I I l 1 J (( ) l 111 / 1) 1 I t I / r , i ) 1) /1 (� / / I 1 / / /1 ✓ / \`=J,J� \ 1 \ ` SITE WSJ\ LA \ / I 1 I , \ I \ I I , ) 1 I , , , 1 I I � ) I I I ) / % / / 1 / / * / / I / / .v /� r./ ✓ \ \ - _ __� \ / I I I I I \II 0) I ( t! l) it /1/ /III)//IIII ( / / , 4 1 , ,t,I 1, / J • J- / \ J __el `\ \- -\-` \\ =� \ - - x- x- L -x x �-1x / 1 1 I> J 1 , ( 1 /I I / I I I 1 1 r I I 1 I ! ( I / / ./ / / / / JJ� / - 1 � ` \ r - __' "-� - / _ _ _ - / t, �-4 1 1 I \ l / 1 / I! / / / / ss f / /( J /l ( L / 1 / / ) r < J �''% \r \ l ' \ / �7__ � / J / _ �/ _, -^-,rJ ,\% ) // I/ ) I 1 1 k � ) I I >1 ) /// I/ /////I // ( I 'f' S / I ) 1 )♦) ) r/ /1 J / r� l \ 1 // I, �//: \ --, \ \ \v \ �� ---mac_—"'_; -�- � � �__�_�--I PIL-M ��— �??�� ��' _ \ 1 I I / / , 1 / I I/ , ), I I I t 1 ) > .f 1 ' I I ^� �, �• /ci /__--- __\ \,--------.-__/--__-, �'------1--.- /- - Z�'S �cfil• - � r 1 \ l I1 / )III,) I/ I/ I / /,(J t I I / > I / / / 1 \ \-\ - - '�tI r---- -"/r- -----1 —�� I I- I /1 I ! /r 1\ I 0* ( 1 //l/It II/, (IIII ,/�� /rrl/I ( !' -JI1( I I( \, /lI ) D 1 I /eo\/ I _\ \\ \l\ \ / . / �r ( \ < ) �) t I I ) II l / // II / ( ' ( { I / \ I ) 1> I �> � \ �� � v. / � , \ \;\t1 "/1 //I/ II (I, I/ //II..", t' ) / ( I1 / S/ / / a \ I a <rI ` --\1 \ ` - �/ �( 1 x 1 \ I I I 1/ / / I J I I `` l \ I I ) > 1 -- t ` '� / Ill (! // I/ I / // / / ) \ ) I l ) I / ) r / / /) ,\-__ \ \ '� < / x ( \ ._'I�/I, IJ /////I /! (I, l / /I/ /-�I `r I / _1 I// l .-' \ •_ � \ I! 1 I ', I llr lI✓ r - ✓-/,�/ 11 / ! ) \ 1 I J / - __-� \ -l-- `' ---. _/ -, I I / I . I / / II I I f l I / /%( // /I-'r .i r _. / Jr / I r � <\ / I I� \ \ \ - \ � - - \ - � _ I \ / l l l l l l l / / / , \ ( , �r) r ) 1 II 1 1 y r/` ""\.- -\ -\\-� \ I I '' 11 / l I 1 /l ) l/ l / � \ I I� 1 ' 1 1 111 I / l l,l l / ,/ , 1 ,J I I'l1 r , \ I / \ I r 1 \ ` \ \� -._, \ ^ - _ - - - \ \� r ll' 1 \ t� 1 I /II III/////III//! I/I( 1 �/I /I ( t .I, r� JJ I ) ( �\ \ �vr1 /\ /_/ �-A- �- ~ ` - _��-^ < I l S (" x� I ! I I I I I / l / 1 \ , I ) / l t \- ( t 1 / \ ✓ \ �-- .� \ \ - - t� III II l 1 1, I l I\ r 1 f r - `- "- r / ) t `I ) / I I !f' / I I I A I 1 \ \ / / / /^ /-,'_\,-- -_ — � _t � I I l 1, f \ l 1 I �^ # / r , �/ / \ .� \/ _-/ _ \_.-_ � �1 9 ( / �I , 1I III 1 / I! l ! l )/ 1 / I r I I ) 1 °, 1 , /./ �. _ _ - - f i ® I °°' J t , t' IlI 1 111/l/I'Ill /Il 1 '' ! l l rl '// I J ( ' ✓ �l r \ - -' ^t ,''-..".- -� _- ---\_ ��_-�,\ ® I ( / / ( 1' I I \ I I I I I l l 1 � ( I I / 11, 1 \, 1 1) i I (' I f' �% 1 1 ,' (I / �t:' \L o t `� / I ` , / / -' - / i /^/ � - - - --- _ � - \ f < ,I/ % I j x III( II r)/,/(III I I I I, I I, ( 1 1I 1 1 ( / 1 \ \ \Y / -\\v/ -\/ ,- ✓ J -`_\ .� ,� - t 11t {� / I 1� 1�11111111111 I1f 1 ,1( 1//)/, , , / �.♦ �� ) / i l \y ^% // r� r L , �lr_";_--\` \`_ 1 ..r &- I I ( < kI\ I I I I I I , I I I 1 1 , / l / / / J► \ \ \ 1 L. \_� , �- \ ' / ✓ - � _ _ _- - ^ ` I I I ')11 I I\\, 1, I I I / r o '`� l /" -/ , r~-- .~\-\ l ( 1 f IL ti� / III I I , ) I I I I /, / ♦ \ I - j ) \ / / - — �- \ r _ - Ix I I ! rI 1 r,I� I I w , I I I 1 I I I I / /, I f/ � J // l \ \ \ O � , - \ \ ► ) ... r - J .-- /' ✓ - , _ S -o- - - -1 / ,\ "` \ - _ - I J . I �1 ) x ,, (If 1' I I\ II (II II I )I It/ ✓ /f ( � �� .r 1\, ^--'J✓-/'✓- ---',.'�,..--�'_^- _ \.- —~ \,, ' `�9 ' I 1 III IIIII\ /IIII I If II �♦ v, rr�� _" � /I ,^ / '/-' /f- --/_� -- - \ -\\ ? , ■1 II I iI! I I, , L 1, i \ \ \�_t�� I I - / _ / \. -\-_ l_� I I I } S 1 ( 1 ) 1I I,'II..10 1, 1•(-"I I .J ( \ `_ , I1 -�I / //- //_ �� ," _� - -�_ __ -- I I f / S �>�) (/ 1 I I I I I \ I I I\ � \ I I \ , , ,V/I 11�1 l I I /' I I r - ( \ I l // / / - / � i _, _/ - �` r � � __% \ � \ \ - ' / � //III \ I I J S-' ! � ) /I / /� I ` , \\ , I II I I, / - r-�-/" / /, /-f / / ��-/` _-\ �-. - \/"_ \ \ \ e j, I \ \ I I I 1 / r / / / i' / /'1 L 1 I t ,'� II 11I I\ \\ \\ \ �� I I I I I \ _ r '/ / / // ri / -�//--��--- �-= \^-_-` \- �'\ �\\�\--`D --�� It J / J ) \ \\ \` \, \\I I III111II\ II l /\!' iy \y �, \!\\li \!' \!' //i \\�/ //� /// /,� , /-/^ ---- \_ \ _ j / l - \ 1 \ \ 1 \ 1 �� �- / I / / ` _\ --� \ / r�� �'-�- - _ - - - - - _- - - - - - - - - - - - - __- - - - _ _ _ / �� ,- /t / \ \ \ 1 1 I 1 l I \ I I I 1 I \I• \I ( w \!' \! v\1, / /. .- / / / ./ - ✓ - - - ✓ \ '-\ ` \ / `__ - -- -- --_ ------ + \ \\ \ \ 1 1 > \,,\\i, \L, \L' Z-\Irw-\D _ / / _. \� -\ r�/\ \�`� / �'m - v � �- 7- -�1• y�� X= _I/ 1 -\1\\ \\\II\\1,\0\\\, III111'I I\ \Y\\1�WETLANDS& r-'\\\\/ �' �/ ///�/1-/ /�._ \�� ` \1 --\- -\\/ T r _ - - - ,/ 1 \ 1 11 1 I 1 1 I 1 r / // - / / _ _ \ - r \ \- �- ` L i ,� >® - ' fix-" x x x - x x= - - _ _ _ ^� _ \ -six 1 J / \11 \ 1 1 1 \ I \\I \ I ) l\ .' II l I \ \ \ �\ �\`��I 1- STREAM \v\'\t' / - \\\ \ / �/J / / / / Jr ' ,- _ - ^ - _> _ \ �. \ -f \ \ ' )// 1 I 1 \ 1\ 1 1 1 I `I' W /W \\ /~ / / J// - _ � - ✓I- \ ✓ \� / ' / \ Il \1 1 I I1I,I III I\ I1 1 \ \ y ��\1°�(\l,�y \l \! \r 11 I 1L / / / / ✓/ // / / /r'`-\--- '^ \-'-'/1ti 1 -- \ - ��\\\-1 ` - , .�/ �. 1 1 t I\ \I 1 \ I 1 1, \ l� \\ �- \\ , , / /// / `\ \-, \ '\' '� \ - _ / - / / / \ I 1 I I 1 \ 1 1 I III , \ \ \ \li \l \i \li \l� ,r I \ / / / / / / / / r / / i ./ ^ � 1 - --�\-"� `- -s _\ / �' \ - - - �� u -/--r __ t __ �__'i/'� \ I I I I III 111 1\III,I11I \\ \ \` \\ ^ -/- rf ( \r ,/ //,//�/ / /� r`- '� /1 \ ^ \ f - / \\� - - -- __ ', - _ ✓-----___�-_-_-_ --- - -_-- — ---_ --'' \ II I 1(1\III ) II ,1 \\\ \\ \ �\_ --^ ) \` '/ ///�/ /// Ji- /- - . \ \ \\ \^ - -' -- --- __ \ w - -- �-'- _----------� \\� II \II1`1\f IIf 1I11III\\ \\ \\- \ _ r/ r ' /I// / J //� / -/\.- (' ^\ \�\ \J ` / ` ------------ /-' � - �� -� • , ----_____ t-=_-_-_�_ - _ �- _ \ I 1I \\ I III \ I I 1 1 \ \ \ �✓/\-/ � / _, -/, // / / , /' \ - - ` / /-` --,L ------ --- / � "Z ^\- t---- _---�o�.___---------- `--- -- --- \ \ \ \ I III I I I I I(i IIIII\ IIII IIll1,\ \ \\ \ \-`_- \- '' //J,/ / �'/ /� JJr// /� r/V /_ � \_\_ \ � .^ \_-ram -\ / "/- _\ - / - // - - _ ----� - \ \ 1 I If I 1 II ,II I I I 1 \\ \ \ - - / / / / - -\ \ \ �- \ f / ./ �- __ -------------------- ///-- -_- - -\^\ \\'I IIII\I III )II III,' I 1 \\ \ y\\ - -� / " / ✓/ ^ / �^ r`N .� \ - -----_ \\ I I I \ \ \\ _/ / / ///// / r / \ / --___ J / - _ / -\-\ ,I \ \ III, IIII I II III )II 1 I\\\\ \\\\ \ `/ / /�// // ,✓�, _ \- � _ - r \ - - ( \ I I I I I I 1 I I I ), \ \ \ \ \ - / .� --/ t- - - - - - ----- - '� - l//'- \\ \�\\\ \ \ ) \ I I 1I I, l ll,I 111,IIIII III// )� \ \\ \\ \ \` \\ \- -' / ,-//- //'IIII^ // IIII -) -�` \ _� \\ \\ ` -^\ r� ��---\\�-------_ _- / ✓ '\- - _-_ ^Y-__-= ___-__-- ---- �_-=___---` �JII,l1/ \-\\ \ \ \ \I I I,- I I I I \\ III 11I�III�II J Il IIIII( l I \ \ \\-\ \ f� - - IJ-/// ',' ' t '/ ✓ - `^- o --- ` ' ` \- ---- '\ - -- - - - \ / J \/--- \ \ \ I t l 1 I I , 1 1 I\\\ I I 1 I IIIIII \ \ \ \ \ \ \ \ � _ / r / - // - / r / i/ -� \ -\` / %gam __ ------ _ /_ _, - - �� 1-�1f^.►, l/ - \ \ \ \ 1 I \ I \ I 1 I 1 I I I 1I1I(II I 11) III/\ \ \ \ \ "\ \ // / /I / / ,// JJ / /_ --^f ,- \ ^ / �. - - -�__' - / ' - --_ `. /II'/ ` v \ \ \ , I I , \ ) I � I , \ \ \ \ \ - / / , , / , / / .j \\ \' _ , ----- 1 �--------------- -- / ~\ \ \ ) I \ 1 I I 1 1 II I I ), III) \ -\ \ L. \ \ \\ - / / 1 (// IIII/ - / - /' -_.' - r- _ / - _- -_-_ - - ` \- /1 / \ 1 1 I \ \ ( l I I I \ \ f I )I, )I II III I \ \ i \ \ \_ --_ / !� / / / / % / / \ - /- - \ _ ° ,� ' _ - - - - - - - _ /I \ 1 I IJ I f' I I 1 1 1 11 \ \ \ ' - ` \ / �/ -14 / \ / / r e- '-- `\ �' /" ---- -----_------- - I, /- 1 \ \ , f I ) I I ! I, 1 ) I I 11 I I I 11 \\\\\ \ \ � \\ _-` _ �� / - (/ - l _r ,^'I 1 -\ \ -- - \' _ t-._ --\ ` J � I / _ - - �_-- __ _ Ill/ \� \ \ I / I / I / �l I / I I) 1 I11� It\\ \ \\ ~ --\ -\ \ �. ) / //-/J f i / // '�-� - \ - / - / ^ - - - \ - \ - - \ _ 1 " / ' - / - / _ - - - - - _-- =_ - - -� - __-__ _ - - - \ / I I I I I , f / I 1 I) 1 / I 1 / r 1 I I , I \ \ \ \ \ - _ \ _ _ t I / `/ , / - / / r __ _ �- , \ - -- \ - \ \ -- - - - 1 -\\r _\ - \/ _= M-��_��_ _- 1\\ 11{/\ r /I) 1 ) I Il/I I/I!1\II((/III\111,1t1\\\\1\I\\\ter_\�\� \//J///r��/- / J,/r/ ✓ \ I-J� 1 _ _ / a ✓- -_\\ \-\_`_ -� -� � -/' J \ (- \, ^\ \ \ I, ' ' //I I I1/' �� I I1I'I\/t\\ \\\\\i--^\_�\\�`-^\//�//!/! // I//// ^' / /✓ ��r1 \-� v\ ~`�`'~�` 11 I� a /'--- — �(/ (\�_ - -�� = _- ' J / / / / \ \ \ \ I i / , / / J // SEE INSET B SHEET C4.9 ) I 1 f \ \ ` v - _ - _ - \ - _ - , - // //' / t ( ( ,' / �' / `� f y - - f� �t ' Y --- -- -_- ��\\\/ — __'� - -----' / I ' 1 ) \ \ i \ \ / -- -\ \- "". "/ // / -) / % /._/ --/ \- \ J - _ / - _ \\\\\ IIII/// / / _ - _ �_ - / / - - - \ _ \ . \ / / , , / / / / / / l / I I l ' I 1 \ \ \ \ - - \ - _ _ �\ \ \ _ \ - / l ✓ / J % I - ( ✓ \ \ \ _ - , r _ \ - / / / \ -\\ \\�� /// IIII __ �- ' ' \ \ \- - \ - // / / / / , l 1, \ \ �`� \ \-_ -- \ _ \ - \_/ / / / / / / \ / I r �% �- \/ r✓- / -\- \ \\ /"/ - ---- _-^----_ / \ / r , \\I / I / /// / I ( I I \ \ \ \ - - \ \ \` ^✓ r r / \� I / \/ 1,� -/` / \ - � // - '_ - i` — _ _ — _ ._ _ \ / -.� , \ \ \ I I r \ I / / / / / ) / _ j , ) 1 \ - \ �/ � \ \ \ \ .� / / / / / � - ^ / \ / �1 _� \ \ // / ''i ' _�-_ _ - - - - - _ - - - \ / \ \ _ \ - \ \ / / / / - \\ I / -� .) ✓ v ✓ ^ \ r i c JI'r . l'. \ \ _ \ \ - ,- 1-1 - 1 \ \ \ \ _ ✓ / / \ / / i > \ v / \ 1 __- r \ \ I I I / f ✓ L f V \ \ - " / /'/ - ' - _ - _ _ - _ - - \ _ \ \ \ I ( / I l l l , ^� \ ' \ - - \ ` - - - - - - \ \ _ \ , / _ 1 f / / f '/ �� h Si✓A E 1' 60' / / J / / \ ^ - - - 1 / // '/ _ - - _ _ _ - �- - - \ \ ✓\ - - ` — _� - = \ \ (/ /, ) 1 1 I I I \ \ ` \ - - ^ / / , r / / J ti 1� _ `- ' ' \ •/ / / ��/'�'� _- __� --- -_` \ \-_- f -\ \ \ \ I III /! // IlI 1 I ��< s -\ \-\ /\_- / /- �,% - J /^ / / - ..� \ � / / /, // / / _ \ \� \ �. \ l Y - / i _ � \ \ \ 1 ( I I / .r \ \ - \ `- - \' \ - ,� �-. - .1 o [ - _ ~ _ / f r' C 1 / - J / - / - - \\\v / /// '- _ - _\ \ - \ \\ " - - - - - - \ I I I I I / III l (I � 1 \ I \ \ \ \ \ \ - - - - �\ _ - \ - / f / ✓ J - �/' � / / / ///// \ \\\---------- I I r // 1 I \ - / r ' / // /- ✓ // /j, / / / \ \ \ \ \ -�-- --___- , \ 1 I I I J� 1 1 I 1 \ \ \ \\\\ \\ \ \\\\\ -\\-_- � �\ ,\ \( I/ \ \ l -) // ✓ // / 00 1-\ \ r I � / - -� - / / / / I \ \ �_ / /_ -^� _ _- - __ _ - - \ \1 I I I I I I / 1 I f / I 1 1 l I 1 \ - \ \ \ _ \ \ \ _ \ _ _ _ _ - / \ \ _ - _ _ J / I O ✓� 1\ / // // // /�// / / / I \ \ /// -. _ _ --\- \ \\\1 IIII Ill l\// /, I II \ \ \\\\\\ \ \ \\ \ 4 \-`\-_ \\ ' \ -\ -\_ __~ // /'-/r- / -1 gyp. J --1 _ L✓ / / / \\` /� -\ \\ ` II, ) Ill/ \ \ \ \ \ \ \ \ \ \ \ \ - \ \ \ -- / /-✓ - CQ' / \.._ �I-1 / - / - - `1 / / /, /� / / ` , /^ \ \ 2 - \ 1 1 � /� I1 ( \ I/ \ \ \ \ \ \ \ \ \ \ - - -- \' - J/� \ -- \ - \ - \ / _ '' ,� / / I " r \ 1 / / , l I \ \ I, < \ \ 11 111 I )If ///1, \ \ \ \ \ \ \ \ \ \_- \ \ -_ ( /' / \ _ \, / /� -/ / �/r Irl SEE INSET 'A' I \ \ \ /II 1 -\ I \II,If1111I Ilt�/%I/ /!II 1 Itr 1 \� \ \� \\\\\\ \-\ - `- r `\^- ` \_ \-- /- -/ '-�' J /-- r lc\ �J - / r / / I \ I 1 ,IIII IIII `�_ I)IIl(I 11 I I I \ \_ \�\ \\\\ -\\\- \ \\-/ _\I r\ \-\\ \ - /J L r --./ I' /-\) r, / r/ ��� \ -^''- I ^ / / r /^Il 1 t 111 (- J ' -) I 11, I IIII I IIII , \ \ \ \- \_\ \ \\\� \_ \\ \\\-\\\- -\ --\ \ \`\ \\ \--•--- __rvr-/_\- J / rr/✓ `� Q r �r ✓ — -/"/✓ - ' - \ %�� ��%//`/ri I (I O E � 00 m y n v ro > U � N Q z m Y X a; LA rO .s �D -C _ N Q M � o0 Q O Z: . i (v o CL v U) C Vc M ♦-1 . i C UV L °� M � M n N o � O - N �� - i , U �~w a� o m cn o N • W= Q y N co,r (0 0 z O . N (0 � O a w 2 V5 °° -m • • 0 zU c.EZ-oR f; W C p •L - a) (� > U o�H tmairn ¢ J E • • O 'F, C o U.9�Z TI= cx H 3 z�Qu>Ira� NOT FOR CONSTRUCTION MCA RO�/,''', .``���O�.\H �� ? ��FESS/p� ?'-9 Q = SEAL 033612 .c► FNGINEE, ����:I '��l�'q�p�S S LINS �`��` SD/DD REVIEW /� CU w Z Z O CU CU Z 0. W C) O. Z W � CU IV •/ / J V/ Q w O Z z U O 0 L Ln � Q 0) 00 Q w O N z � U z Q J � Z Q Z o � JZ = O cu O 0)'tO f1/ V_ Q U m2 � = Z C) � a) �O �GQ M N � �a L O Oa) ZQ�c'_0 I `J � z a) ��//�� � *O� VJ O J Lo O Q 2 vJGLo Revisions No. Date OR #2 2021 JULY 09 Project Number: 1711-B Date: 2021 J U LY 15 Drawn by: FS PRE -DEVELOPMENT STORMWATER MANAGEMENT PLAN Sheet Number: ■ ��� -\\\ \\\\\\ \ \ \\\\� \ \� \ \ \�\ \\\ \ \ \ _ \ \ \\\\ \\ \ \ _ \ \ \ \ - _ \'� 1 r - - \ \\ \- \ \ \ \ \\\\\ \\ \ \ \\ \\ \ \\ \ \ _ _ _ - \ \ \ \\ \ - \ - �1 _ - - / _ \ \ . \ \\ \\\\\� \\\\\\\\\\, \� \\ \ `------ ___ \\\ \\\\ \ \, \ \\ \)_r--� \` I- \ ` \ \ \� \ \\ _ \\\ \ \ \ \ \ \ _ + ^ _\ \ \ \ \ / /i -/ 1 /// / X // / /// /// / //// / i-�� \\� ��_�_� \ �� _�� / /,- �fl /� // // �_� - _-_ \\\�\\\\\\\'� \\\\\\\ \\\ \\ \ \------ \\ \\ \\\\\\\ \ \\ \1�--/ /7 �' \ _~ �i \ \\\ \ �\\ \\\\\ // / �.� /kI / �////�// -/// /// /j/�// /////////��� \\� - -- \� � `' ' / // / �\ \\\� \\\\f \\\\ \ \ \\ \\�\ \ \ \\ \ \ \ \ \, //' // r ` / \ �\ \\\� \ \\ ii/-'-.ice -=\ / \/ / K l IIII r / l /// /j/ / •- -�� '( w� / / / / / / / -\ \ \\\\\ \ \ \ \ \ \ \ \ \ _ I \ \ \ \ \ \ \- �� / / �- \\\ / / / / l/ l I I1111 /l //// / - \� �_ ( FS�I CTIDN'_ i'i - //////// /--_-_---- \ \ \ \ \ \ ---- - \ / \\♦ \ `\\ \\\\ \\ \\ \\ �/�i�--\ - //l/ / l /1 1/l /// /// / / /_ -- \ \`-�'-' - f� / ///f/T7-7� , /-----=-rw DS \ \\ \\\ \\�\\\\\\\ __ --- \\ \ _/>' I \ \ \ 1\' , -/ / `\\\\ \ \ \ a \\ \\\ -\\ 11 lO / / ��� \`- / / /-r--�---__- \ \\ \ \ I \ \ / / / \ \� \ \ / / \ \� \ - - \ 4 / I i / \ \ \ \ & IV l 1'I1/ �l / / / // _ _ _can�zi iv%%� _ /� I , / �_--_ \ \ \ \\\✓�) \\\\ \ \ \ \ --__ _-(^ �l 1 \ \ \� o\ \ =-` \ \ / l c / 111 ( !/// /// /\\\ I /~ e'�''T-�R \ \ _ t - /// /i/// / /- _� \ \ 1 \ \ \ \_ \ \ / / r/ .\ \ \\ \ \ / // / / / / / / \ \ -- --\ \\ 11 I I/II/ 1 \ - - -. \ \ \\ \ \ \ - __- \\- \ \ \ \\ \ \\\\ / / _ \ \ \\ - I I I \ - - - / \ \ \ \ \\ \ \\ \ \ \\ 1 \ \ \ - _ _ \ \ 1 I ' I / / I I I \ \ \ \ \ \ \ r -/ - - i - - / / / / / / { / / / / / - \ \ \ \ \ \\ \ \ \\ \ \\ - _ \ \ \ \ / /r / _wooers \ \ \ �\ \ \ \ /i -=(1 \ (, 11 1 I I I 1 \\ \\ 1 -_ \ � � -/ - / //,///// / / / __- \ \ \ \ s\ -- - \ \ \\ \\ \ \ \ \ ' '/ \, \\\ \ \� \ / / / / / \ \�\ \ , \ \ \ / \ \ - z /"---1�\\\\ �.-I`II /III l ♦ II111\\\\ \\\\ 1\\ i'�\\ I _\ \\\\, �,c`� - -//// /// /// / / /�- \ \ 1\\�\\ 11 \\\ \\\\-___\___ \\\\\\\\\ \COSRU / / / \\\ -\ 1- \\\ \\\ / 1 \l \ _/ / / 1/ / / // [ \ \ \ \C&E 1NGciiT -\ \ \ ♦„ I --- \ \\� \\ '� / I /1 /�/ I I \\ \\ \ I \ // // �/ l c r' \\ I\ 1 1 \ ifs\, \ \ \ \ \ T-_ \ \ \ \\ \ \ I 1 1 / -. �)I ,\ \ \` \\\\\\ \ I � I ' .i \� -� -- - - _ / /I � / i \ 1 , \ I \\\ \ l\ \ \ \�� � - \ \\ \ \ 90 s , L \ \�\ \I \ ``1 • � II I 1 / � 1 //'lam r I\ \ \ I I \\`\ _/ / / /I I I \ \ 1 ,11 \ \ \ \\ � \� \ - \ - ---- ` - \\ \ / - \ �\ \ /��1 / 1 �I I I I I / I / I , , , I I I I I I I / �/r j J / / I I I 1\ \ I I \ \ \ \ 1� 19 - \ \ \ \ \ /-- \ I 1�✓, l I I I 1 I I r / r r � _ ���\�� 1 .l�/ / l j 1 1 1 III / / / // // / , I I I / \ \ s s• -. // \ i I I I \ \ \\ \ \ \\\ \ \ ♦ \ \ \ , t • \./ 5 � \ \ \ \ \ \ . I l / - - 1 I 1 \ 1 I I I I I 1 \ \ \\\ \\ \\ \ \ \ \ �0 r * I I I I I I I I l l / / l � 14 / '•.•� - - / / / / II / 1 1 I I I \ \ \ \, / I ) I\ \ \\ \\\\ \ \ •\ • _ \ \ \\\ \ \ % \\ 1 / I�II�II��II�I III/�`/ / /// //// / /'//l/l II ' 1 1 i `\ \\ \ \ \`\- - ' II/ / 1111�11\\\\\\ \��\\ \ \\\\ \\\ \ �_--- - - 1205 \\��� \ \ \\\\ /, ~/ ~ \\\\\\\\\ / ` I I I I II \ \\I` \\\ _ = �\`„^� __ _ _ / / /- / - / -/- � __ -/- _-_-_ _ -_-_ _� \ \ j 1 \\ `- _ _ _ _ - - 2t0 \ \= \� \J. 1 I 1 \ / /// �% \\\�\\\�\\ / I I I I I I II 1 \ I\ _ _:,.:fT - - \ \ \ \ \ 1 2 \ \ \ \\\\\\ \ ) / / /�\\ \\\\\ I I I 1 1 :: > : \ \ \ \ \ \ I . - \\\\\0\ I I 1 \ \ I. .•. - - ---- -------------- -- s-- \ \\\ \ \ - \ \ \ \ \\ \ �,/ \\ I I I 1 - - \ \ - \ \ \ \ r\ \ \ \ I I - I \ f \ \ 1 \ / I r � ( \ \ I \ I r / I \ \ f \\\ I \ I / \ I ( / I J / \ f/ \ 1 I / I \ \ \ I \ r I 1 \ \ \ I \a I \ \ I • I \\ 1 \ ) \ c /I I \ 1 I I 1 \ a 11 1 \ /1 1 \ I I \ I \ \ I \ \ \\ a \ I \ i 1 \ \ 1 I 11 \ \ u \ \� I 1 1� \ \ \ I \ \ 1 \ \ \ I \ \ 1 I \ \ 1 111 I \ 1 \ 1 I 1 \ 1 1 \ \ 1 \ \ I \ l L \ 1 \\ 1 I \\ \ I \ `� I � - L. I' \ \ \ 1 t I \ I _ -� I \ \1 \ 1 \1 1 \ -, f 1 - \ 1 I \ \ \ I \ \ Y \ 1 \ \ \ i \ \ ) \ \ 1 1 I I \ h t I r \ 1 \ \ \ \ � 1 \ I \ / \ '1 ) l l l C 1 \ \ e I r I I \\ r 1 / 1 / � 1 ) r 1 1 Y 1 1 1 J ♦ \ ✓ 1 i \ r 2 I ) O L Y \ / a� 1 11 / I 1 I \ r v 1 1 \ -- I 1 1 \ - 1\ l 1 1 - 1 1 J I I . \ I I _ I I I \ _ ---j ,11 - / - - ) \ _ J r h / J - / 1i / i- / �V / I / / / /' / ,/�- r ,, 4 � / - � /� iJ_ / __-^ \ I yam% � � J __ /1 ___ , � / J � T / f / _X� / /� . / �� \ --i1, / ,% // ////%////�///'i -_ 'rjj�= � � ��-_--- -- ----\_ \\'/�i'/'i'' / //- I //// Irk � \ / � / / /j 1l // /// /// /', / / / / � / / � _ - - - -_- - - \ \ \ - - - / / / / / // // \ /�/ / / __ _ \ - - -_ _ �\ - - / / / /- A� / I i i I I '1• z \ :r : i .ti . t•i .1• :.r: I I •t• r I 1 • •l. I : 1• I I : �: t \ t• f .�j I i I "... �.: .,: j �•. \ _ t �• :t: \ .1• t :; \ I a -- - f: \ \ \ I .�: ; L;: I I :1= .:. :i: :t. \ I \ \ \ :a: ..-: �G� I I :<: I• \ •1 _ I C• ��pp Y� ia �: • ti::::::::::.:.:. •� .7: \ :F:I: :=: •�• •� ' I 1 .TES . =k* * - :=Z;: I \ I •� �j�'"'"- •t 1 A?p• . t . I I 1 '� . I: I• F 7 1 \ :t:= .�:�:•:- •fit.• : �;:•:•:-:-:•:•:-:-:;c;:-:-:•:•:-:-:•:�:=:=:�:�:=:=:�:�:•.•.• :}:"-•:-:.•.•. �3� "• t \ • :R \ ���// :.. - 1 _ 1 \ ' :•. ..•.•.- 1 F -� \ 1 t :t:•• 1 h' �� .•t . \ 1 I 1 •t - I . 1 I �: 1 \ � •1• :�S ti;� 1 '- I •t• y, I -i=• 1 .h. ,�'-,I: :•i� •{S _ \ r 1 a \ _ -: 1 \ •I: :\: :�: I 1 \ •I •x•:•••• \ _ \ 't•. \ 1:• _ � ti \ •\• _ r• _ •I \ :�: •t• _ I 1 1 \• \ .� .� 1 1 _ \ '�; :,: - .�: :�:�. �:.:-1 _ 1 :1 .. - t \ :}• :�: j \ l :� _'�' _ - �•�•� \ \ '1:• .. :. -. .-.- .� .-�-. . :� f :�. {- •G :-�:-. :�:• .��. ! I •.� - a: :�:�: �: _.�... r a=: :\= ;�;: :�;• •D :h:�' t \ �13PJ�t70X � 9$$6#0 : �� � � • • x" N •+Z I l • a'� • it €)F. Fi •© :� C ;�;:;:•. :* :�:• }: :.: :Y t I .� �. • . .fi •� • :-:-. t-• =1= :nMtf 3 J�[�tD3 i7 #:•=:. =:i: I I •`�. - I I I :is :4 I. •4- :F ::: =�:: :-...... .�: .>: :I :.. •I \' :� f c .'a /1 .. •h I ��� I :a •=.- I •t ::� :` CO I y 6' l I �:�: \ I .'�:�'� •.%. �; . -. r =.� �f.•. •t \ :I: l :I: : .1. =l = .� . 1 I 1 :�••.1"1: . •. = "1 1 :'G F _ _ + \• __ I 1 •a J . I. J � 1 /1 •C• I . �/: l l I •.� •k�: E .�-, �. . h :�:� j� 1 :- I :�I. :•� i .y.. I :� �t a •I. .: J t / N jj J z� , I \-.:{:- s / �. i. �3�. _ \ 1 �.::�:' \ 4 r I r I z. I: I ., r t I l•� I �J�� :�: I •� I / j •�•. I \ ••i ✓ t I 1 •� !•• / 1 •k: M I •t•. r 1 I :}: =a' 1 1 �I. .j: .t. :L / :f: _ I l ( I 1 1 I I :) 1 I I 7 J j l I J.l.•. ( S •r�. •1: �F� •l J I I \ / = l I :1- ( I �1� Y- J 1 : \ .n - 1 I I r I 1 I \ I 1 \. :7: I i •C• I: \ I � I I 1 I I - f � �t� l :tip :F: I \ \ \ r \ :a• I I I � / I \ : �: " :,: 1 I _ \ I :h \ 1 I \ I / 1 I _ _ Wit.-T=�:��=�=�����=�=�������=�����=�=�����=�=�� :ti:. - =1 I ::T:: :•.•. ) \ I ,'1 �1� s r \ / \ '.tr. ( J ( \ \ \ =i- 1 \ / �./1 S 1 .� }':�( •:k: ::i::• 1 I r y. / =l= . �= / 1 .// �SS ,{/.�� e / I :I E 0 1 1 / 1 r1 .c. _ I s 1 "Y: •:�: I I r 1 _ I I 1 • }} J I / _ 1 :�s�•�. 1 I 1 J I :I - is =�: :4� L :x: POST -DEVELOPMENT STORMWATER QUALITY CONTROL PRE -DEVELOPMENT ONSITE IMPERVIOUS SURFACES = 6.36 ± ACRES POST -DEVELOPMENT ONSITE IMPERVIOUS SURFACES = 21.04 ± ACRES (INCLUDING FUTURE BUILDOUT) IMPERVIOUS AREA REQUIRED TO BE TREATED = 14.68 ± ACRES IMPERVIOUS AREA TO BE TREATED = 12.94 ± ACRES (WET DETENTION A) IMPERVIOUS AREA TO BE TREATED = 3.76 ± ACRES (WET DETENTION B) TOTAL TREATED IMPERVIOUS = 16.70 ± ACRES (A+B) IMPERVIOUS AREA OVER -TREATED = 2.02 ± ACRES POST -DEVELOPMENT STORMWATER QUANTITY CONTROL DRAINAGE ANALYSIS POINT A AREA (CN) Q1 Q10 Q100 (Acres) POST -DEVELOPMENT 17.13 92 23.16 42.85 47.56 Al WET POND A POST -DEVELOPMENT 14.20 84 32.83 82.30 142.92 A2 BYPASS POST -DEVELOPMENT 31.33 45.69 123.31 186.95 Al A2 COMBINED ANALYSIS POINT B POST -DEVELOPMENT 4.63 93 2.80 6.87 32.44 B1 WET POND B POST -DEVELOPMENT 26.15 80 40.80 105.62 185.52 B2 BYPASS POST -DEVELOPMENT 30.78 43.56 112.49 215.84 B1 B2 COMBINED NOTE: POST -DEVELOPMENT FLOWS ARE LESS THAN PRE -DEVELOPMENT FLOW FOR THE 1-YEAR AND 10 YEAR STORM EVENT AT ALL ANALYSIS POINTS. REFER TO CALCULATION BOOKLET FOR ADDITIONAL INFORMATION. POST -DEVELOPMENT IMPERVIOUS AREA AND WATER UALITY TREATMENT Q 000000 � � ►♦ww♦♦♦w ----,g!� PROPOSED IMPERVIOUS BYPASS POST -DEVELOPMENT IMPERVIOUS TREATED IN SCM � � DRAINAGE AREA DRAINAGE AREA BASIN INFORMATION BUA TYPE DRAINAGE AREA Al DRAINAGE AREA B1 PROJECT AREA ON -SITE BUILDINGS SF 64 267 2 219 EXISTING 66 486 ON -SITE STREETS SF 0 5 045 5 045 ON -SITE PARKING SF 458 962 61 657 520 349 ON -SITE SIDEWALKS SF 33 389 0 33 389 FUTURE SF 37 048 BLDG 94 865 PVMT. 131 891 TOTAL IMPERVIOUS SF 593 666 163 786 727 452 TOTAL DRAINAGE AREA SF 739 983 201 625 941 608 THIS DRAWING IS FOR AGENCY REVIEW ONLY - NOT FOR CONSTRUCTION J� D g- / /' ww� --- --- - �` ` 1 �, / �= ��1 it///�`' ��,��.4::♦fin. \.�.•�' +, / : ` -�/� - - �� ---- iii- ��,� -' / -�i�� =�j IIIi .«- .O � ^ � {'♦�, / ' d! � •• ,.�/ - _ _ _ . .fir . ,/•I1', �. u / CJ - • ' +. �w�I raj,. �� _ _ t ,._ Ir I i� / / J �,�j , /j� 01 %� '�'I /�/ / I I// I 1 / ` • �_i ♦ 1 / I �� 1 u / - s n� A 'y,.. pin�Z �! i �'j I .. \ �♦♦♦,�i♦+, ♦-,4-0 ►�`!�-- `'���V0.0440MA�i '►'V./1'� >-icV.-V �sfii►wc � 9-�� `yam - - - b�>b' �� arKLM.ripl �♦♦♦-Q►♦O♦/i♦♦.+o�►O♦♦♦♦♦!��O♦w♦5,� '�N�'.',1►�►1�►�►�►1*G♦♦^►COS♦�f►♦�♦tom♦O♦t♦7♦.1��♦wCw�O♦G♦♦C♦�;�:m _ .�. � i 'A .i- "��� ��►♦c♦♦�.��ww�•.�WAAA441W 0.w♦I��ww���'w�,��1.� ►w-��cw�we,;w.we♦�•��w♦♦o♦� -.1 • - � � --' _.___.__ www♦♦., e�-- - - = �w♦, a ►♦ ._e iw©ese ♦♦♦,.�w♦♦♦wwwww♦♦ems♦♦.��♦` ► n .�' , ��7`�♦��♦♦s�o ♦�;��♦`♦0r1♦��♦♦♦I � �I ��♦�♦�w�,►w♦w♦w!,1•�w♦♦w♦w♦w4w♦♦� ►F,A11A�♦♦♦♦`! ����I, ���♦v.' `. ♦'V< ��'q►�Ii►� ■ �1� .���� 1•♦���I�;��♦`!`\��LEr�►/♦♦♦♦♦♦♦♦♦♦♦j�♦+i♦w♦♦♦j♦w♦jwj♦♦♦�i��r'-;��♦♦♦♦w♦♦♦♦♦��001 ,►w♦♦w♦www♦� A♦♦wwws♦s♦vw♦ww�h I►w♦♦�♦�♦v�li♦c�t��♦w♦♦♦♦♦w♦♦♦� I�♦♦♦r♦i� I �, fl �►�o�i`♦. od �j ►I , ..� ,►w♦♦w♦1 ���� �:� - i1♦♦♦w♦ ► 1 ♦w♦♦` ►♦w♦♦♦w♦w♦ww♦ww�♦♦♦♦ww♦www♦ww1►►�♦w♦♦ww♦w♦ww� y��♦w��w♦` -t �'i I .�1 1 . �� O♦w♦ww ► ww♦..♦7ww / 0 �� ♦wwwww 1 ► ♦♦♦♦♦ • ,�. �����i �a9w♦.1sf1�1►'1►♦♦♦♦♦1 ♦♦♦♦♦�♦♦1 t!=.!►��►. ,►♦♦♦♦♦1 ► ♦♦♦♦♦♦ ♦♦♦♦♦♦♦1 .♦♦♦♦♦♦w0 ►♦♦♦♦♦♦/ ►�►♦♦♦� 1� ww♦., ww♦,,...��.♦ww♦♦wa.♦_♦,�♦_.,♦_�w ► s� w♦w♦♦w 1 ►w♦♦♦♦4 ►ww♦♦♦♦w w♦♦♦♦♦w.1 ww♦♦w♦w _ wwww �������� ►'�♦♦♦/.��fi,.I�w♦♦♦♦1'..��., .►�' Y 1; vs► Aww♦♦♦/ / w♦♦♦♦.i._��� ♦w♦♦♦w♦1 ►♦w♦♦w♦0�► ►w♦w♦♦♦1 ►1►��w�w� �� f � I ►'�♦♦ram'_ :.a :►w♦♦w♦�-♦�l���91� . ♦♦�. ►w♦♦w♦/ / ♦♦♦♦♦w / ♦♦ww♦♦♦1 ,♦♦♦w♦♦w�► ►♦♦ww♦w1 ►'►��.♦w� ►� ':�: �) 71� �. . �- >♦w� u.'♦e,%:U205k4 ♦♦ww- v1►. ___� __�!e�,111.,►♦1� 'w♦ww♦w 1 ♦♦♦w♦1 / ►,♦♦♦w♦♦w �►w♦w♦♦ws� www♦w♦w �.;♦ww� I,�i a ♦0�1� i'w�<►�)..1r►♦'►♦♦♦1 .eti.s�..��7G,. ���1♦��� 0♦♦♦♦♦�. ► �w♦♦♦♦♦ 1 ♦♦♦♦♦♦♦��o��������-v♦♦♦♦♦♦��► ►♦♦♦♦♦♦� /;►�1w♦♦� I / .�� l ;II' www♦w�T�,fgLv" w♦w♦w♦w♦w�i` r0V A_ ���= w♦�1 .�.w♦w♦1/w� ►♦w♦www♦w♦ww` / ♦www♦w♦w♦` / ��♦w♦w♦www♦w♦ww` 1 7w♦w♦w♦w♦w♦w♦wi�� www♦w♦w♦w♦w� �,�w♦,►♦w♦w4 �� ,�♦w, �'♦w♦�iAi ��'♦♦♦♦♦♦ �►w N►www♦♦♦ ►♦♦♦♦. ♦♦w♦♦♦ 1 ► ►♦♦♦♦♦d / ►♦♦♦♦♦♦♦ ► ♦♦♦♦♦♦♦♦1 ♦♦♦♦♦♦♦ 1 w♦♦♦ ►ram ®� ;� 1 �d .!o���� �.�♦w��..!r.:`s♦♦♦w♦1� l��r►,�'v♦/►♦w♦� ♦♦��.w.� Fw♦♦♦♦� ► / w♦♦♦♦w' / w♦♦♦♦w♦� ►♦♦♦♦♦♦-��► ►w♦♦♦♦w� ►' �♦♦w� ►� ♦ Z Ii •►w♦w♦`►'! ":- 4 ►w♦♦jw♦w♦♦j�! I►��i��1i�♦w♦w/�♦w♦w♦w1 �w♦wri�� GKOK♦w♦w♦`. - - ������ 7wwwwwwwwww� / ♦w♦w♦w♦w♦w♦w♦1 ► 7w♦w♦w♦w♦w♦twwt,� �w♦w♦w♦w♦w♦w� �A��,zQn /� w�w��� i�►w♦w���ilt':'u.l ���♦♦♦♦��'/►♦-':OOww�i�`�.�►�♦r0� w♦♦♦♦i ���1 ► ►♦♦♦♦♦/������� �t�w.�® II`r,go, ♦♦w - w1 G♦��l.G_.���w�� 1 ��� �♦ �w♦♦w♦� 1 ♦ww♦.; / ♦♦w♦♦w♦1 / ww♦♦w�♦w ►♦♦w♦♦w� / .. �.♦ . � ��www♦w1 - ►� y,,t��s.�i����w.w.�/��.!w�w1 �►♦w� '♦w♦w♦w♦w♦wt � � �♦w♦w♦w♦w♦� 1 �♦w♦w♦www♦w♦w♦� ► ;►w♦w♦w♦w♦w♦w►w`� �w♦w♦w♦w♦w♦w� ♦♦1 �wr ►�♦�I ►wZw-♦��.w�w-♦�G �w� �� w♦w♦♦w ►vw♦♦w♦� / ►w♦♦w♦♦w' ► ♦♦--- w♦w♦w♦w 1 d►♦we ;'��♦��a .� _mow ♦ ►♦♦♦♦♦� ► Iw♦♦♦♦w 1 ♦♦♦♦♦♦♦�i 1♦♦♦♦♦♦♦�► ►♦♦♦♦♦♦� / '✓� �w♦i1 i���Ow<--J������ �c ��������A��� ��w♦wwwww♦w�■1 ►�A�,�A-A' �►♦w♦�►ww_t► �wA ���� �I - .-...-. .- ---- ♦w♦�♦w♦ice ►♦♦1 ►.4������� w-M,S �`w♦w�w�w♦���� �♦w♦w�� ►♦www♦w♦www♦w♦w♦www♦w♦w�w�w♦ww � . ��i�♦��i' ►��� www♦�������������♦�♦w♦w♦w♦w♦www♦ww♦c 1♦O♦w♦w♦� ►w♦w♦�►♦w♦w♦w♦w♦w♦w♦w♦w♦�1w♦w`wt�fw:��♦,w♦w♦`� '�wiw♦ww� •wiwi��!!•!•!•!•!•!•wiw_�'�.wi,�i�w���i�wwiwiwi"i -www♦w♦� �o♦ww� 1♦I1c14�!!¢ j�►�ni�,��y��w♦w♦ww•♦ ♦w� wwo /♦♦♦w♦♦♦♦♦♦wwwwh ♦♦ ►♦v1 ♦♦♦♦♦♦♦♦♦♦♦♦♦♦♦♦ ►w ,w♦. ♦♦ww♦w♦♦w♦♦wwww♦w �1 1♦♦� /♦♦♦♦♦♦♦♦♦♦♦♦♦♦♦♦♦. ♦ w♦w, ♦♦♦www♦������������. �'♦♦� ♦♦w♦♦w♦ w♦ ► k1; �w♦w♦w� �w♦w♦w♦w♦w♦w�� �w♦1 ►<� `� �♦ww♦wA �♦w♦w♦w♦w♦w♦� �w♦w♦w� �♦w♦rw ►1 w♦ ♦♦ww♦w♦ ♦♦♦ ►ww� 1#� �w♦o♦w� �w♦w♦w♦w♦w♦w� �►♦o♦w♦1 ►www♦w� ♦' pw♦+♦♦�w♦w♦♦w�♦w♦w♦� ►w♦w♦w♦w1 �� ��w♦.♦w♦\ w�♦www♦� www♦w♦ww�. ��1 ��www♦ww+►♦�� ►♦w♦ AL ALwwwww♦w♦w♦w♦w♦w♦w♦www♦w♦w♦w♦www♦w♦w♦w♦� ►w♦www♦w♦.� �� ���w♦www♦w♦�� ��ww♦www♦w♦w♦w♦www♦w♦www♦w♦www♦w♦w♦w♦www♦w♦www♦� ►�♦�♦�♦�♦�� ►w♦w♦w♦we!►♦w♦w♦www♦M► 1i wwww♦�i��-♦10VA-1 w♦www♦� ♦♦♦♦�►♦♦♦♦♦1'♦♦♦♦♦1►♦♦♦�'♦♦�►♦♦♦♦. ���w�♦♦�i►♦w♦w♦wwwA!►w♦��w♦w♦wwwww��♦w♦w.w��♦ww�►www♦�w�,�!w. ��w�w��♦��. ♦�V. INSET'A' / )1 1 / /i-^ - / .f I 1:4"• •�•� / I / I J ( ) \ \�/ � � -� - fr /�"- /--� ----- ----\ /� /� I - --- f i ® I \ I t "�:": . ' 1 r 1 / / `� �C ,;, , 't- / ^-_ --- - /� - r• _"- _ --__ `-. /\\ \ / /' / _ _ - \ I .4 I It 1 ' I •: F;• ':�.• I� ♦ /'J► �\ , / I , \y �\ ^Iu / r / t- /.' _ 1 - - _ _ _ - \ - - � \ _ - 1 .r . / _ ' / // ' - - I I j W I I I I / / rI/ '`�, \ \ 1 1 I� ` \ / / \ ' ' - � / � �/ - - _ � \ - _ - � \ V / /�/ / -\ 1 \ I I I.11�0 / / ♦ rx.4lPvd I ` - ) .1` 1 \ / / // -� S - .� _ �-\I -- / J ® 1 f* J .i TOP 6F PIA€='V00.9Z' I ) ..- r / - / - \ - - ) �� f� I �_` 0 \�` I Ix I( I ( / \ \ l� �� . �/ \ \( -J /�, J- ^ � //---,/\\�� -,\ \/ -/ 33 �I --� \ \ �_-� I x I ` I Il I1 I (( l \\II / / e' /f ( L c, -- \1/ / � //-r - --/ /�/-1\- -\ \1, `\, 12 / �I \ I `� 1 III 11 I�\ I', �♦ V, rc�� i /I //- /fr��-/- __ \� J \ /1 \ \ \ I I/ I (1 I II I L / � \ \ \---fir 1 / --- / _ - ^ �' \\ _\\- _ (- I I 1 - ^\ \\ \ \ \ \ i / I 1 11 �) I I) I I 1 \ \ 1 � I I I IIII l � � I / ) (I I r \ - - f 1 � I �' / " -- " ^ ' � � / -� � � ' - r . - J �.�/ - \ ` � \ - I / � \\\\\\\=\- v�-_- -�✓ ✓///11 \\�\\ I x 1 /I I/(��1 \\ 1\� 1 I III 11 II( I� I � / �/( -1 J/,, //v / / r �� �� J /�� - - 1 ` --�,�cJ'/// _ N \ \\ - - \ l _ _�_� ' , 1 \ \ \ 1 u �� I I 1 I ' �1 \�_\_\,_\_�\ I )1\\ \ 11 I I III I I \ r _ - \ rr / / \ r / / // , / / / 11 - i ' _ - ` \ - ``` �\ \ _ r - _ \ / \ - o / t r�4 \ 1 ) \ 1 I \ I , 1 ( ,v w ,v ,t w ,v / / J / % / \ _ - \ \ (. I / / ® _ - _-/ =_ -__ _------------_-_-- ---- - +� 1c/ \ \\\\ \\ \ \,1 \1, 1\1 I II I 1 I I \v �1 w ,,v ,v v�, r\ / J / - / _-- �. \ ` /- / \ r / t 1E w_ f i-r _ - ' / I \ \ \ 1 \ \ \ j \ 1 \ \ I I I 1 \ 11 1 I ( ) pv w\ w � � �> , ,f �w -;D/ _ � r / \ \ / / /� / / / /� ' / r J, '� - \ 1 _ \ ` _ y \ \ / r\ \ - ® - _ - J r � `�� �_ _ _� _ - _ - ��-= X- , - _ _ `_" / / ^ \ 1 \ \ 1 1 1 \ 1 I 1 1 I \ ^� ,L <k ✓,1 �L- ,L -� - - \ / / / / / - / - / y ^ \ - 1 \ \ T.... - - --_ - ` 1/ 1 1 1\ 11 \ 1 IIIII I \\ \ \l \V .'i,, '� r \ r/ // // // / -/ /'_/�^�� /�„ \_ _- 1\-\ \ �. ` fix- p x x x ^� _ \ x x= s1�x ) J / 11\\\ 111 \\I �(\11 \ 1 III I \ 1 �\\!,\'\ �(✓�-�-��� - /- \\ / /// //�_/r �r -r _ -\ - I- \ \ - I \ ^® ® \ ` � " I/ \ \ \ 1 1 1 I \I\ III 1 1' 'I1 I \ \ \ \ \L \y v\L ,li /�L. \lam 1 \ \ / / / / / ' / - - - - \ > - f - ^ - - J - � , �~ - - f// 1 I 1 11\ 111 1 11\ I 1 `Y / \\ 1 / / // / / / //-� �� � ✓ram \ \ y �� .,- % 1 I , \ , l \ I \ 1 I I I I I ) I II I I \ 1 1 � ` \ �\1% sl (� ,1 yr \ r \ \ - / .1 / / / / / �� / - \ \ \ - \ -� _ \� _ � _ _ _ 1 - / \ I I I I' 1\\ 1\' 1 1 III' \ ` \ \ \ ^,y `,r (I /%// /'�� ./ '\ ,/ -\ - _ _ _� , -� _ u _ ---- __ - ( �_^--/ /--n \ I I II I I 1 \ f \ // /// i / / ) \ -- / _* - \�_-- _ -_-- __ ^� � __ -- \-----__�-=_J --=----•- - I'--- _=_ -___- -\\ IIII(I \I1\11I1) I)I) \)� \` \\-- _- -r- / r1 \ rJ /�////// / //�Il- /- r \ I \\ -\ r ^`- ,- _ __ \ w. .\, -'-/---------- \ I I \1, 1 `1 , ( 111 I I \ \ \ \- -'' / `/ // / / / / / / / �- c' ^_\ �\ \J / ,- _ - - - ��I - \ , � - - t - _ _ _ _`_ � _ \ I , ► \ \ \ III \ I 1 ) \_ .r r \ _ / / / _ / - / , / / r / / / , - - \ - y- ` - _ - - �` � / \ i � - - t - . - _ _ _ - _ v - - - ;`,_ _ _ _ - _ _ _ 1 \ I I I I I I \ I I I I \ I I I I I , ` ,I / / / / / � / / // / / / r �J/ \ \ `"� . ^ \ - - r- \ / . ' - / _ _\ - - - - _ _ - / �` `� �o� _ _ _ - - - - - - - - - - - // - 1- - - - - - - - __ __ ^ \ \ \ 1 I I I , I ( I I I I I I I 1 III I ' I I , 1 \ I \ - - - - / - '� / / / / //' f / / / ./ - / - \ ,\ \ - -, - - _ \ /^ ,� -, � ____---\�---------------------------- ///- -_--_- � \ \ \ \ \ \,I I I II \1 III I`II.1 (I I III\ y\\ --/ // //-1 ////'/'/ //r/-/ / \, \/ --_ - Y ~ `` // �- ��`-� I,J //�\ _ _ - - - - - i, //- __` __ \ -\ 1 I \ \ I I1 I I I II I II I11( II1�)I1 \\IIII\ \\ - \\ \_�,../ / / /-�/ // / / / //-/ / -- - -- \ \� -_ __ r 1 \ - \ 1 I I \ \ - / // / / / ✓ / I / \ \ \ !_ _� � �, __� I - ------ rl-\ ////- \ \ � ( \ 1 I I ( I IIII II I 11 III II I /I\ I \ \ \ \_ \ \ -/--- / / // / / / - / / r- .-- --k �\ - \.-,,\/I- -\ _ _r - - - - i-- ----- _ \ ` \ \ ) ) \ I I l I 11 II )11 I II,I(/ ) \ \\ \ \ \---- / .-�-// '/ / // / / -/ �` \ \\ \\ \ - /r _ --- -- - - l / -\ \ I I III \ \ \ \ \ / // / -� r-_--_---_A / - - - - - - - - - - - - - - * - _ - _ _ - - _ - - _- - _ - - - - - - /�/(/ - \ - \ \ \ \ I I I I I \ \ 1 1 l I I III (I / Ill l l \ \ \ \ - \ \ /-� - - / ' // // i / // / ' / J ✓ ~ - - - - ^ - o \ \ , - _-_ - - - ..✓ - _ _ - \ 1 \ \ \ 1 \ 1 1 1 \ I 1 J 1 (` l l I I \ \ \ \ \ / / / / / / r '� \ �` / \--\ - \ _ _ _ _ / �\/-- \ \ / ) 1 I 1 \\ I / III I I I \ \ \ \ \_ � _ , / - / -- / / / /-e -_ - \ '1 \-- / ---- - -- - - - - 1-�1..-�--- � // -\ \ \ / / \ 1 I ( I I 1 ` \ \ \ - \ --- / / ✓ , r / % - - ^ - \ _^- -IL-7 __ _____ �- - - \ \ 1 I 1 1 I I I II II I I 1 I, / \ \ \ \ \ \ -� / ! / / / / / ti / - �. ---- i � _ - - y_-- J � - --_ `. �/I// v \ \ \ I I I I \ 1 I\ I ) , \ \ \ \ \ - / / / / / / • / / �• \- , ~ - I ---------------- _- / �\ \ \ I \ 1 I I 1 1 11 IIII II III) \ \\\ �. \ \\ - / / 1 (// /r//, - / /� .` - r^ ,i/r_ --i_ `-\ �1--\_-_-- `�J � �' � _-' -------------- \- lIl/ \ "\ \\ \ I \ \I 1 \ I ) ( \11 (II I111 III,II111 I \\i \\\ \_-\ \-- - /--' /� l' f' / I/ ' %-/ /' J\_- -^-\ -r� _ -//- - �� � °`, _- / I l ) I ( ( I I ) Ill\ � \ \ \. \ \\ \ / �/ � / / l / I \' - \^' - ^ - - � r _ - - . l / - \ \ I I ) I / / I I ` I I I I I I 11, I \ \ \ - � / r ( / - / _' - / \ \ _L �" -; , - I- / - _ _ - - - - - - //� l \ \ ( 1 / 1 ) 1 I I I I \ \ \ \ - \ \\ \ ` �- ' / - .J - / / / r '� � \ \ � 1i __ II / �' / \- ) 1 1 \ / I / I1✓I / I11111 I III\\\ \ \ \_ - \_ ,f / I// / f I / ' � \- \- -/--/^---V -- \--\_ -\ _ N / L /-/- ---- - - _�-= = -- - -1/I / / 1 ( I 1 f / I ) I / l I l I 1 // I III,,1\ \ \ \ \ \ \ -- -\/,'r / '// / /, / , / r _ - -/ - \\ \/- --_- - _, _\\- � - \� - .� - _--_ _ _ = -___-- ==r- _ -\ \\ 1 \ r / I I I ( / 1 1/ 1/ \ I ) I I\� I I \I \\ ! ( \ \ter\ \ �•• .1 \. `\. ` \// // r /~l/ / �/ -/ .. \_ 4^ -� / -\, -- � - __ --- /- /-% -I- --'r+�--- r- f -.-� - \ I f I 1 ! I i I I I I 1 \ \ ti \ -\ -- -- �-\ / // ( � 1 / / � .�r - v \_' \ -- ® \`_\�` - ` - -�� // \ c r. ^^\ I ) I / / I I \ \ \ - -\ \ \/, / / / r / �/ / ■1 \ .J �. ) �_ 1�-a _� ,-% • - \\I( I = _ - _ _ - /r /� / I ~ / \ `\ \ \\ I / I / // / /1 /� SEE INSET'C' SHEET C4.9 I 1 I / \ \ \ v � - - \ _ - \ _ -_ - _ - /i /// / / / / ✓ / ✓/ , - 1 J ` ry , _ - f / - \ 1 / / I / /r \ % /-- " -- -\�\ / / / / / I I \ -\ \ - - \/ - , � t \ _/ / ' _ - - - ' i ' \ - I \\L �\ / - J ��/ //// / / r / / \ \ // / / / / / / � � / / / / I l ) 1 ` ` \_ _ -�'- - _ \ 11 ` \ / / // / ./ % / '7 r / / \ \ ^ , � i - , _ IIII\ /////// / -- _ -- - \ /- \ _ \\ l / /, / / / / / I I - \ ` - �` \ \- \- / l / / J / ( ✓ \\ \ _- r / \ % I ) ` \ / - - ,\/-\ \\\ \��_�_/j//i/ __ - -/ __ -\ \ -\-\ \ \ _� \ r /// ///�/,// �/1/�II11 /\\\\•' �\\\\'_\-- -�\\\\ \-1 r"I /J// r ✓ r- \ / r �, ._" \r �✓ / /- \ \` `ter//� - -- - - - _-_ \ \ ) I I r- \ l / / / ) / l 1 \ \ \ \ \ J / t. /\/ f! 1 V --! \ \ - /' / r /''-/ - _ _ - - - - - - \ / \ \ \ _ ~ ) / //// �\ I I I / -, .J\,� r ; ^\ ^�, e �. �l \ \ - _ - - - - v I - -/ 1 / ( \ ,/ `�J' err // / \^♦-_- \ //� / ///-- �_-- _-_� ___- `_ --� \ \- �\ ` = _\= _ \ \ ( ( / // /1 IIII / I _- \ \�`\ \ _- / ^/ / ` r -/ /� / •I/ _-1, POD /i / - -� - _ / / - \ //, % i '/ - ------ �- \\ - \ - _� '\ \ \IIII // // ,l1 1 // s \ ` -� :32;_ v��_ �. `\� \ /\_ /' / / rl �/� �/ / --L ^ti / / -- -\ &/�/ /// //- _7 !- \\_\\\\\A -\N \------\\\�\\ \1 1IIII // 11/Ill( \1)\ I - \ \ .�\ 7- \,� ac _ \ ___� %\ f I / C / - / /- ' // // \\\\ /---_-----_ _\\ 1'II1111I \�� ljll cl \ \ \ v- I/- 1\ / r �\ J , // / / , / \ \ \-- _ \ \ I I ) \ \ I \ \ \ `\ - \\ \ � � ` / j -r-/ / r/ '� lam\ � // / / r-~�- / / // / /� I \\ \1_//-_--_--------\ \1 111 I I �I / �II III I ( I \ \ \-\ \\\ \` , _ --`__ \/ / \ r\ -� _- JI , )- "�,; / / / / ` \\ ` / - - _ _ \ \ \ ` IIII , I / I I \ \ \ l \ \ \ \ \ \ \ - \ - \ _ - - - \ � / -\ \ - \ - \ \ - -' / '/ ' - - / r / \ _ / 7 ..LE 1 / 60 // /r -/' -®- /')//// // // / � ( /^\ \\ 2// - _ -\- \ \\ `I 111\\// I(11)I/ \\ \ \ \\ \\\\\\ - - -\ \ //\ `\ - r _ r / r / Jf1 - / / / _ r _ / / / , 11 \ I r \ \ \I II I - /�// I I \ \\ \ \ \ \ \ _ - _ ' \ / \ - -' \ - / / o \ �^ 6fl - - -"1�0 / / r J 1 1 , 1 I I I I/1l / //, I I \ \ \ \ \ \ \ \ \ \ \ 1 /- r / \ ' \ ^ / i I I \ \ \ \ \ - \ / /\ - �- / / __ I�► SEEINSET'A' 1 \ \\ /lI/J -\ I \1\IIIIII I II\�/%�/,/1 \ Ilr- ) \� \ -\\� \\\\\`\\\\ `- �. __ -�\ `_ \ \-- v`,���/_. --\/ / Ir plc- �- - � I / / - - - - / � ( ^ -\ / \ / I I I I I Ib - / I i I ( \ \ \ \ \ \ - \ - \ _ _ \ J r / / - I/ / -� / / / \ ) \ IIII / 1 (/// ' \\\ \ \ \\ \\-/ \ r \ \\ \ � ---� I' _ ` // r r/ 0 \ ✓�- /� / / /^\\, ` I /I/ 1 (_ - I ) I \III I IIII I I ,IIII I ,\ \I� \ \- \_\ \\\\ \\ \\\-\\\--• _� --� \ \�\ \\ -_• _- /,.r-/_\- - .) /rr-// <4 4r -fir ✓ / -/w ��]] r i O E � 00 M y N � O > U N Z r. } X a; 0, rO .s U,, 0O oo6 Z �0 _C ONO N Q a o w . i (Q o CL v ._ U) C V c 4-1 . = - VV N L V M a 0 N O u N o o U i a) fY W ._ �7 w rl � • 0 00 . cn o W Vi � M Y -a O ZW z o i\ • u - N a W O (Y ao L O cn U z rn • Y ao c• o Z - Z c _rn W ai C i L - U o H 0 a� rn E• J C • O ' a� c E - o x U � � ca o ca - N H z�Q�nfra� NOT FOR CONSTRUCTION 11111 1 , 1 / 1 I / NC A R o l O 2 S F ES O '9 O �9 Q - SEAL = = 033612 = _ I Nc► F . N �G G E IN ,q N C S S SL I N SD DD REVIEW /� U W Z z O CU CU z W 0 z Q W CU V �U) vJ Q W � z z O O 0 L Ln Q U) 00 Q W o N z � U z W- z Q Z o z � _ J O C5 O 0�O V r ��� W Q U m�� = Z q � �O �GQ ce) N � •� L O �O" ZQ 1 0-�) I `' J ,_ z a) �//)� O. * O V- O O J_ Ln 0 2 cn � Lo Revisions No. Date OR #2 2021 JULY 09 Project Number: 1711-B Date: 2021 J U LY 15 Drawn by: FS POST -DEVELOPMENT STORMWATER MANAGEMENT PLAN Sheet Number: ■ \ / /,/�/ / ��/// /JI I I I 1 `-\ \ \\'-- ``~- ��\\-- \\ / - l ///-( ( / I - 7 r/ I N \\ \_ \` � `-\-\'\ -- \ �///// //,'/ //IJ/III( J\\\,�\ \\\/ f\\ \_ \�//^ // ///r) / \ !( I/ \ �.1 \ \ \ \ \ / �1 ' l / // / ! / � l ( I ' \ `\ -\ \\ ! --- - \ \-`-- / )I / "/ rY i / _/ t.\ ,`.. \ \ \ 1 1 ' �- � - \\I / / / / I I /f I �/ I I I I \\ \ \``\ / -- \ \ \ \ / r r I \\ I �I '` \� \ I / ( , I r - \ l / / _ I J ( l ) ) \ \ V r �' 1 \ \ \ - _ - , l - -/ / / / / \\/ � / 1 - / j \ o f \\ \_ \_ \_ �\ I / / /,- \\ IIII / //J\\`f;�^\✓��"-f __ , vL-I" \- `�_� \\�-__ - _ �--� ) \\\\-\_✓ - J/ _/ _/ 1 / (�/ \ / // i �- ! I-\ \ - \ \ I ( I /�/I J1�,111'/ I �`\� \\ \\ \r - /` / / ` / // /Ir / �el \ �'` � - \ \ \ I I I I I / / / l l 1 ) l J ` _ ` \ ` - _ , \ _ ^ l / / �,% 4 � \ � � -+;`\ \ \ I III I� // J�111 (1 \ 1 1 I I I I \ \ \ \\ \-- \`-----_--� \/\ \ \ -- \)-\-/ I l / / /� \/ / /�/ JJ�_ ^ \\ \ I I (I I \ // I I 1 aI I 1 \ \ \ \ ` \ - - \ v \ -- r / / / v - \ 1 I I �/ 1 ` \ - \ \ \\ \ \\ _ \---- ` \\ /\ ( I/ \ / --J r l I�-\ _�~�\\1 III( III��) / II'I'/I I 1 ( I \ \� \\`\, \ -\\ \\_ \- \ 7' `- \- '\ /---/~//--`I I 11 \ _\- \\IIII IIII I )II \ /"/1/I I \1/ \\ \ \\ 11 \ \\\\ \\l" \ \--- \ -\ //` \ \ \-\\--- \ -// // /' ^ ./ -/ /✓ /I/✓ r` _ \ \ 11 1 11 I ►III - I/II \ \ \ \ \ \ �\ \ \ \ \ - � _ \ \ - _ (- , r '\ - \ 1 1 \IIIIIII 11 \.- / / I \I \ \\\\ \ \\\ \ \ \\ -`-_ ` - /` �. `\ -`� \---/ / --/ ✓/ /\/-� t, r\� ) \ I 1 1I\ II 1 ��^1 IIII( I I I \ \ -\\\ \\\ � - - r \\_\\ \1 - �J -:= .._,../ I/ _ �) // r,-/ 1 d \- II\ II ( I� I I I I \I \� \_ \\ \ -SEE SHEETC4.7 �__\ 1 -___,_ - ---� ) r `� a� ~1 I I 1 I III II II III \\\ \ \ \ ---\ \ - _ /�\- _ / r/ r I` I \ /' I I _ --- _ / 1 \\\IIIII II III, I(Il \\\Iv \\ -\-\, ` \\`'\\\\\\\ \\ ---IIII �\ �\\\-\� ^`--'f/-__ _/`-----'r / - "�.)�\+-ter ( I 1 1 \\\ lr \_ \ \ \ \ \ \\ - -\ \ � ,_ ^ _ r / I 1111I\ ,,((\ \ \ \ \ / \ - \- ,\ -\\` \\ - -1 - �-\ -, \ --' - - - -_ -� /a /�- /^ ^-�-° IIIIIII �^ \` \ IIII\ Ir - -- -`\`- \\\ -\ \\-\ \ \\--`_--`- ` \ /\\ \- \\_ �. �.�.�i �'/\�-�� -/- _ - -( \I IIII II \ \ \ \ \\ ` --- -\ - \- \ \ \\ \ \- - `\ \\- \- - -/ __ _ - - _ -,__/ �-`/\"\ �_ lIIIIIIII \ \ \ \ \ \ \lam - _ , ` \ \ \ \ - � - - - \ - - -\ -'\ \ ^ - - - - - - _ r - f - - ` / - / v - - - - - - - ,- I IIIIII ��\\ \\ \ 1/ _ _� IIII\ `\\\ \�� \ �� 1 \_--` - =\ `�+�-� - -"- ^- --/-`` -. _- \. -- I \ \\ \ -\ `; \ \ \ \ \ - - - \ - - -- II III �= \ \\ \� \ \\\ \ � � !^ - -- ---- -- /--__,_��_ --_ - \- \ II I I// \ \ \ _\ \ \-- _ \ `-\ -� --`-----'-^ __-\- -� �/� II III////r\ \�\1` \�, \ \`I- ~\� ��-�`�\\ --\_ /r\ \---_i-/\ J '- \ �- y ` _ -,_-- - ; I IIIII' // 1 ` \\ _ \\ - \ -� m - - \ _---- �� �_- /I IIIII �J I//�\\\�\\\r \\`\ \- `\-`\� ° l \- -//-_ --\_--\,-__-_-/ - - \ - / lI I I ( I / \11 - - \ \ 11 \- 1 /� \-_ \-,--- /�- ---- - \- _/ r '^\ - 4 ' I/ II/,I ////%-\\ \` -\�\" ' � -_\ __-\, \\ \ \\\\ _-\ _--- -i_ - _-- -_- -` - -_\ ._ _- \- / / ////(I// //lI/ \� \ -\ IIII\\ \ \-\ \ \ IIII\\ \\ ` \ \�_=_ � i^�-'r---^--_-�\�_i \-__\ \ ��\` / // /J/ //I �\\ \ _11 \ \ \ \ - \ \ \ \- \ \\ \ -.-_ J- r-A-/ --\--- _ ✓ -_ _ / / _ --� _ ` ` _ ` ' i /// / / // / _ \ / �\ \ \ \ \ \ \ - \ \ \ \ \ \ \ \ \ ^ �` - i I _ _ _ _ - _ _ - - - - - - \ - �\ - - - \ ` \\ //i \ \ - \ \ \ - _ - _ _ _ _ _ \ /� �� \- _ \ \ \ \ \ \ \ \ \\ \\ \ \ \\-_ / /-_ _/ / _ _ ---_ - --\� / �- \ J� _ \ - \ /�_-' _ \ IIII \ \ \ � \- \ \ \ \ \ - - _/ r -/ - ---- -_ � - �_ - _ \\ \ v\ --� _ / _ \ \ \ \ \ - \ \ \ _ - \ \ \ \ \ \ \ - \\ - IJ - / ^ - - - - - - - - - - __ - - �- - \ \ \ \ ,�'� - _ - - - \ \ \ \\ - \ - \ \ - \ \ \ \ \ - / ' / -' / - - - - - - - _ _ - -j � - -\ \\ \ \\ \ ---�� _--/l-- \ \\\\ \ \ \ \- \\ `- � \ \ \ \ \\ \ \ \\ /_ / _� - -/ _ r� - ~+-- = J-- - \ \\ ~ \\ - - 1 \ - - ^ \ \ of -_ ` - J / / J �- \ - - - - - / - _ - _ _ _ _ ` \\ \ \ \ \ \ \\ \ \ - -\ - _ _ n 41 f - Cn \ \ c \ _ / r - _ / / / _ _ \ \ \ \\ - \ \ \ - \ \ \ \ \ \ \ \ / / ! \_ �__ _ -\ \\ \ / J \ - - ` - - \\\ \ ` \ \ - \ - \ \- \ \ \ \\ \ \ \\ \ \ \ - _ / / / / / - / / / 1 �• / / / '� / ��- _ _ - \\ - \ \ \ \\ -\ \ \ \ \ \ / // --_ __ --- -`+ \ \\ \\\� - \ "-\\ \ \ \ \\\ \ \ -_-� // / --//- --� / �/ // `_ _�`�1 \ � `IIII\\\\\ \\ \ I✓ / \ \ _ \ \ \ / - / / _ \ \ \\ \ \ \ \ // /- \ \ \ \ \\\\ �\ -, \� \\\-� .- `- \ \\ IIII---__ \- ) I\ `I / / ( , / r '/ ////� �'^��- \\ \ ��\\~\\�\\\\\ IIII\ / / _ \ \ \ \ - \ \ \ \ \\ - \ - - - \ \ - \ / / / / / \ \ - \\\ \ \ \ / / r /. --- \ -\ \ -\\ \ - - \ \ \� \ \ _' ` ` \\\� \\ \\---- _ __ \ / �/ l S 1 ) r// I-/'////// 1 /\\� \\� �� \\\\\\\\ \\\\\\\\\\ \ - - \ \ \_ \ \\ \ - _ / / I / / \ \ - \ \\ \�\ \\\ \\\ / / - - - \ _ - \ \, \ \ \ \ \\ � \ \ \ \ \ \ ` I + � - \ \ \\ \ - - - - _ �' / / I / I / / I _j + \` - -\ \ \\ \\ \\ \\ \\ \\ \ / i//-/�-- \ \ -- \\-\\ \ - \ - \ \ \ - � - � - \ \\ - - _ _- \ // / I ( \ 1 I , ( / C3 I;.---\\\\\\\\�\\\\\ \\\ / _ �- -\-\ \ \\ ` -_ \\ - \ \ \ - _- - \� - -- _ �/ ` \ -1-Z-_ _-\\ \ IIII \ \ / / /'/'_'� �-� _ IIII \ \\ \\ 1 \\ \ \ 1 _--- \\\-- - �/ J / /- r _- -� ` \4�� \\ I ( \\\\�\\\\\\ \\ / _ _ _ - \\ \ i / '� \ \\- -\ -\ -� - -� \ `-_ -_\- \ _� \\ \\ \ -� _-_� /� \ __ -/ /---- _%, � ` I 1 1 \\\ \\\\ i//'/ / �-_ \--\\- - -\_ \` \` \\ \- ,, \ "-�, - " ~ -'ti -\ \ -'\---__,- / I / --_ l ) J I I IIII >�) \ _ /// r _ \`_-\_+ \\ -\ \ \ -\ -- \ � \\\ \ \_\\ \\\� � � _ _ _\// \\~ \� /\/ J/ /' /'"��`' '"'_ \ \\ \ I� I ( \ J ( \ \\ / � - � - - - - - -\ ` \i - - \ - _ - \ `\ - \ _ ` \ - \ \ \ - \ \ \ \ \ - ,�\ _\ , \ \ \ \ \ \ ,� �-� i / - / / / / / / / \ , \ \ \ \ \\ \ \\ \ j / - i - / �- - 1 ` - _ ` - \ \ -\ \ - \ \ ` - - \ \ - \ - ` ` \ _ \ \ - - \ \ \ \ \ \ _ _ r / I / / / \ \ \ \ \ \ \ ) \ I `1 - - -, - \ \ \ \ \ \ - _ \ \ - \ - \ - - / / I J \ l 1 \ �/_-'/-�-------+"-\�\- \ __\-`\� \\--\- \\\�\- \\\ \\\�\\ \ / / /I I \\1 1�/\(`I\��11\ _ _ - -^ - \ \ \ \ \ _ - \ \ \ - \ \ \ \ -� / ) / d / y I l /i i-'- -� �'-_ -\`= �- -�� \ \ \\ \ � \-\\\-\\\ - \ IIII \\\ _\\_\\\ \ \\ \\\ _\`_ -/ //J,- ./ '✓1 I 11 )((" II I\ '✓'�_'-- ----_ - �`� �_\ \ \\-IIII \_ -�-\�, \\\ \ \ \ \ - \ \ \\ \ \ \-_ - // /' \ / I 1/ l II \ ���- - _-_ __ -- _\`\ \- \\-- \ -_ -\- \ -\- \ \ \ \ - \ \ \ \ -\\ \ \\ \ \\ \ \- -_- \ \ 1 I / I I1 11 II, I � \\ \ \ \ \ \ \ \ \ . \ \ \ - / 1 f I I 1 I - - ,--,-\-\ \ -\-, � _" \ ,= `\\ \ \�\\ \\- : \ \ Z \; �,\\: \~ ~� `- _ �_/�/ ,--- k I -) I 1 I ; I\I l I \ I 1 - - -'--- \---- � - ` \ \ __ - \ - - \ �- \ \ \ \ \ - \ `\ \ \ � - f __ \ 1 / I I II I I I ( \ - \ \ \ \ \ \ ( 1 1 I I %--- -� - \\- \ - -\ \ \ - \ \ " '\ \ \\� \ `^ \ \ \ \ �� \-1 - --\----_- r--\ \ \ \ 1 1 , I I' J I ) %/'- = -- _ ` `' ---� - , �, -_' � \ \ \\� � � - '`� � \ - \ r\-\ \\ ` � \ \ - __. � -\ �\\\ \ 1 \ I \ I , IIII / � //`i _ - - - �� - _ \ - _ - _ _ \ - \ \\ \ \ \ _ \ \ \ _ ,\ \ \ \ _ \ I , I \ \ \ \ I 1 III , / -\ -_� \-_IIII\-\,�\\_\\\ �\ \ , ,\ ,((� , / _ ' ` � - \ - _ - - _ -IIII \ \ \ - \ \\ \ \ \ - \ \ \ \ \ \ \ \ \ \ - \ \ \ \ \ \ \ ( \ i/- - _ \ \\__ 1 r Z_ ��\\ - - -_ � -- � \-� -, - \� \ \ -\\ \\ \ -_\---'^\_`- \ \ \\ 1 1 l I1111 II \�I / - ;-- -�-\ --` __-- _ \\ \\\�\ \�\\�\� \+� _ \-� �\ -\\� ` \�- ---_ -� \\ \ I \ (1 \I \11) 1 IIIII 111 \ 11 \ I / j-`_� \=- �_ \\ -\\ \\` \+\ \\\\� \ \ - `� \ \ \\ \ _ `_ 1 ~__- \� \ 1 (J I rl III I I 1 IIIII \ /"_� -_ _-�\\\ \_ _ - ,\` �` \\ IIII\\-\\�� ~ \ 1\ �\'� \�� ��`\\I\\I IIlIIIIII/ I1IJ II)111IIl�1(' //,/ -!--_ �� ___ _ - \� .- \,, -� ;-��-� \� \\\\\� IIII - �� �`� \\ \ \ l� \ I i II 1 J l / 1 III J I ( \ \ l/ _ -` -- -\ _ _ \ \ \\\ `\ \ \ \ \ \ /1 O (I /( r //(/l //' /I /J JIl JJ ) I' \( // _ \\ \ \ \\ \ \ \ \ \ - \ / / / / / / / / ) 1 / / / � _ \ ` _- __ -. =- - _ 1 \ \\ \ 1 \ \ \ -, \ �. \ \ \ \ \ \ l 1 ) I ^ J / // / , //, / � /,I / / // / l / I �/ '- = --_ _ -- ��\\ �- _�� \\ \ \\ \\\�\\�� IIII _ �`\ \\ \\\ l \ �J I/ I I /, J/ // / / !r//// /�i/r,� j /- �/ j /� // //- - _�+ - �� ` � -\- -\\ IIII \ \\ \\ \\ - \ \ \ \ \ \ I )/J J / / // �/ / / !/ /// / //�/ / �// / I/ /' /- -_``- �\� _ _ \\\ \\- \�\ \\\ \ ��\ \1 11 / // // ////i/ //////�i// �� ///J/f -cram / �'i r -_ 'I/1/'', ----- ----_ -- ` -:-;- ; = \`�\\ � \\ \\1\\\\\ IIII /f///l/ r //i// // ///////// // / r ///I / /r/��//�///'//�/ llll//!, f - _ r �. _ \ \ _,- _ _ - _\- _ - \~ \_\ \ \ \\ \\ \ \\ \ \\ \ I \ I I J // // / 1 / //// % ///// j /-i /�i// / // /..� j / �j // ��/ / / jl I /' _----- -__� -- =\` \\_` �_ \\\ \ \ IIII \ \ 1 ( /// I/ // / / ., / r l ram// r ( r / / // /I /l,//// , -_-_-= -_ _ �-`\-\-\_-- _� \\_ \\\\ - N \\\ I �// / // rl r/////,/�/„ // f 11 I1 / ( ) / / J ' // / - _L. _ -��� `\�� `�\� \\ '\\\\\\`\\\ � \\� ( \\1) IJ/r Il/ /I/ / 1 \1// // / / / /I (/ J/ / / // / (/r_ \�ll( , �11 ) )l( ��/////// // -1 .i _ - --= ���_- '_ -\`\ `� \- \\ � \ \\ \\' \r1 \ /�l I J //�//r�/l 1 /�I(III/1 / / l / �< ( I / < ( 1 11/� r I��, _ �\ _ \ - \ � �\ ,\\\ \ \\ �� I \II\/ / / J J// I J� (� // / ( r ( / I I ( l \ - l'l// (/ //// - _--- -- - -\`\\ \\ \�\ ,1\\ ` \\\ , \\ \ \\ , / / /� )I ( I \ \ )\ 1 1\ I II! ` \\\ -a ( / r (I///I � ' --=_ _ �-__ �__ _-Z_-+ \ \_ \ \ \ \ 1 )'If/III/III II /-% �I , I, I \ ' \� 1 \ ( ^ II I/ /� / - i = - �_ - --_- = -\\\� � \- \_\\\ \ \\ \\\ 1 ) I I /I�I1/ //l//// �r/// r�/%/ I \ 1 r�/r/�G�- \ \ \\`_�� -�\ = ( i�� 1 /J/// --- - _ -_ \ _ --\ \ \\ \\ \ \ �II II 1 f /I I / (I\ 1 \l - \ -. �\- I�'^ \IIIIII/ ///i-_i_ ___ ,�� ___�___�+ \\\� \\\_�\ \�\\\\ IIII\ ll (I%I l lJ//J/ IIII/ / /c 1 1I \- \\� `-��`\� - �_�.\ \-� \\`^ \ I I J I J I /! / // / / - - _ _ � 1 - _ - ` _ -� �` \\` : \ \ \ I I ( / l l) 1 /) I '1 / �/ l r / I I ` ` 1 \ , \ _ _ \\- _ _' .=�� \\\\ �__ ` J 1I I I - _ _- - \ _ \ \ \ ` \\` II ,I' 1 / /// , / )l/ Il\ \ ,I / \� - - -\ - \\ I II////// //�- - _ --__-_��� _ - \ \ \\\ \\ \\\ \\ \ \\ 1 III If/) III )ll l !� ((l I J \ \ �_ �= _+=�1` \_ t-==� ��-\�\\��� /III)I' ( //,/ / __ __ =f= -_ - - __ �__ � _ \\ � \ \ \ \ \ \ \ \\ `\ II ( I IIJJ I l / /I ( ( ( \() o, --- - - - - N -�� I I(l I IIII/ / - �� ` _ �\ \ \\ `\\ IIII IIIII II I1j1IIIJI'/) lll)lIII ( I\I (\ I \ _�=, �? - _ _� �� _- - \\\ �\ \�\� `III III(/ / /// -� - - _ \ \\\�; \\� V ��\ l 1 11 II III 1 I I /IIIII (Il� / ( II I \ �_ �.-� _ _ _ _ ;� �� ^ ��� 1\-- ,, \ IIII\\ _\) 111I I // /� _ _- -_---- _ _ _ ,. _Z _`\ - \ - \ \\ \1 I I II1111II/(1 , 1 ) \I \ __ --- __ _ _ -- \\) 1/If)/ /// / - ti = _ \ \\\�•\ \\ 1l I ( IIII I( I I IIIII► _-_-�--�- - - - - \\\�=�\\\ \�\ \ \\� \.J\I > Ifl////- /�� ---' ---- = -= \ `� \\\ \\\ \\ �\�`I> 11 II 1 II (II111I1 )1 I\\�1\ Ili _- ---_-�_\� �� \- _ �_ \ \\ \\\\\ \\ -\ \\ (/// / f/ / -/�"i -_-- ---- - - � -\\ - - \\ \\ \\' �I I ll II 11 I II I\III ( I� /--_- _ - - - �_-- - \ \_\� _ -� \\� \ \ \\ \\ \ :� \\ IIII/ // // /_ / _ ~ -�� \- -\ \\ \\ ,\�\\\ I\ 11 I 1 IIII j1 I IIII I I I \ \\ 1 J /_ _. --_--- - - - �� , _ -- \ \\ �_ \- IIII\ \ \\ \ \ \- �\ \\ ,J ! ) lI / / / /_ _ � -\ � - \ \\ \\ \ \ 11 \1� ((I II II 1 I 1 1 \ I - - - _ _ - _ _ _ _-_� _- _� _ � \\� _\ \ \ ,, \ \\ \\ \\� \ IIIIII J/// -_/ - - --_ = _ \\\� \?\\\ \\\ \\ IIII 11 I I II111'I \I l \IIII^- --- - _ =ti-\\_- --\ \ \ \\-\Q\ �) I I / I / / / = �_ _ \ _ �.r = _ \\ \ \ \ \ 1 1\ i1 1\ \ \ I I 1 _ _ __ �`` \ \ \` \ \ \ / /-_~ - - \\ \\ \ \ \ \ III 1I\ 1 II f _ _ �_�_ - ^� \_-\ -\\ " \ \ \ \\\ \ IIII\ \\III II (/ //� / --_ = _ -� - \ \ \ IIII\ \\ 1 \ 111 I\1 II \ 1\�--__--__- = - - -\� \\\ \ �\ \\\` \- \ \ \ I // '--_� _ - - \ \ \ \\ \\ 1 1 I I III l - _ --_J - - - \ / / / - - - - \ 1 1 - r-- _ - - \ \\ \ \ \ / - - - \ 1 \ _ �- - _ \ \ \ \ - - \ 1 \ ,\ - - - \ - \ \\ \\\ \\ I' I1 / // / / �_� ----- - �_ IIII \ \\\ \ 1\ \ `1 1\ (I I \ iJ- -�- _ - __+_ - - � _- \\ \\ \ \ IIII \\ �� \\\ \\\ I ( _ - - - - - - - \ \ \\ \ 1 \ \ \\ - - - \\\ \ - 1 // // / --- -- - _ \ \ \ 1 \ \ -- \\\\\ - IIII /// _ ---- - _ \\ \ \ \ 1 \ \ \\ \ \I \11 \ I /-=-- - - \ ^` \ \ \� �` \ - \ \ \ \ \\ \ �\\\\\\ / \ \\ IIII / /�►/- ^_ - - - - - - �_-_ - -\\ \ \\ \\ \\ \\ \ \\ \ \\ �\\ ( III ``11 1 \ , � / - - _ \ - \ \\ \ \\� \\\ I I 1 \ / / - _ - - - - - - - - - -\ \ \\ \ \ \ \ \ \ \ \ \ \\ 1 1 \ \ =i '� '= Y l - � ti� \ -\ ti \� `\ \ \ \ \\ I\ 1 1 �\ \\ \\ _ = j11 ( I l / /i_ '_- - - - - - - - = - 1 \\\ \ \ \\ \\ \\ \\ \\ \ �\ 1\ \\ \\\ I 1\ \ \`\ _ `_-_"- \ - ` - � \- \. \ \ \ 1 I I I IIII `\� - / / ------ - - \ \ \ \ \ \ \ \ \ \\ \ 1 \ \ /� �� \ \� �� = _�\� �\ ~ \�ti�\` \11 l �\ \ \\ 'I)�Ir /i/ _ --+_ _�\\ \ \ \ \\\ \\ \\ \ \IIII\ ��/ �- - - 1- \ \ \ \ \ 1 f' - - - \ \ \ \ \ \ \ 1� / s \ \ \ \ 1 \\\ \\�\ ; - _ - III I /, /// / / - ; _ ; - - - - - - _ - - -- \ \ \ \ \\ \\ \\ \ \\\ \\ 1\ \ \I 1 \ \\\,\\\ I\ / /, / -\ ^ = = _ =_� �= ; \\ - _ \ \\ \` l I 11 �\ \ 1\ 1\ \ \ \\\ \\ \'�-� `=_ J I I / / / , _-_ _ti - - - _ \` \� \ \ \ \\ \\ II II \ \ \ 1 (\\ \ \ \ \ \ \ �� /� / / - / - - _ \_ � , - \ �\ \ \ \1 \ \ \\\ \ - / I / - -� -` \ \ \ \ \ \ \�1 l IIII \ �r - _� _-_ - _ \= �_ \` \- \- \ \� \ \\ \\ 1 \ I / - 1 \ / \ �\\ \\ \ __- _ //IJ /� / //// _---_ ___ _-_ - \\ - \\\ \\\ \0 IIII\\ \\�\\ \�\\ \\ 1\ \\\\ \ \��/� �� / - = ��- \\�\ -\ \`\\\\ \ \\ IIII\ \\\\S \ \\ - - I r/ �/ / / / r / / / /i - - _ \ \ \\` \\\ \\\ \\ Q\ \\\ \\\ \\ \\ \I \\\ 1\\ \\ \\\ \ IIII\ _ /% �- E _ = �t _ -\ \\ �\ \� -- _\ \` \ \\ \ \\ \ 1 1\ I I \\ \ \ \� \_ `_` ✓/ l / / /i /i - - - _ - - - - _ I \� \� \ \ \ \ \ \ \\ \\ \ \ \\ \\ \\�\\ //ii ��- _ - - - =~ ' -- ; - __ - - � \ \\\ \ 1 1 II \ - \ \ \\� \\\ _ /// / / // / - _ _ - = - - -\ \ \ \\ \\ \\ \1 \ \\ \� \\ A\ \\ \\ IIII\ \\ \ _ /// /i/ _ - - �- - ` \\ \\ \ O \ \ I ,1 I \\ \ \ \ _ \ / / / // x - - - \ \ \ \ \\ \ \� \ \ \\ \ \ \ \ \ - /i - - \ - \ \\ I \ 1 \ / - \ \ \ \ \ , \\ / - - - \ \ \ \\ - _- ; \\ / /!/ / , X // , / / - _ - _ - _ \ \\ \\ \\ \\ \\ \\ \\ \� \\ 1\ 0\\ O \ \ ////'' - =- - �- _ / �\ \` \ \ \ \\ \ 1\ 1 \ II ( \ \ / - \ \ _- _ - 1 \ _ _ __ _ 1 1 \ _� \ \ \ \ \ \ \ / // - \ \ \ \ \ \ \ \ \ \\ \ �\ /i/ 1 1 - - _ \ \ \ \ \1 1 I \ _ \ ��\\ - \ \ \ \ \ \ \ \\ \ N /// / _ - � . 1 \ / / / i - \ \ \ \ \ \ \ / - - - - - \ _ \ \ 1 / _ \ \ - \ \ - \ \\ \ / / / / / / \ \ \ \ \ \ \ \ \ \ \\ - 1 /. - - - - \ \ �\ \ 1 1 \ \ \ /-J-_JI\�\ \ \ \ \ \\ \ \ \ \ / - - _ \ p�y7\ \ \I _ _ _ / // / / / / \ \ \ \\ \ \ \ \ \ \ � \ \ \ \ \ // - - - _ _ _ \_ \ \ \ \ \ I \ i - \ _ _ \ \ / _ - \ \ \ \ \ \ \ _ \ \ \ I _ \ / - - '\ \ \ \ \ / _\'_ \ 1 \ \ \ / / \ \ \ \ \ \ \ \ \ \ - \ \ \ 1 1 \ _ \ \ / \ \ \ \ \ \ \ / - - - - \ \ I \ _ \ \ \ 1 1\ / / \ / / - �\_ 1 \ / _ \ 1 II \ / / - \\ \\ \ \ \ 1 \ \ \ \ \ \\ // ��� s =_ - _ - - ` = _ �\ IIII IIII \ \ \\ \ 1 1 1 \ - \ / \ \ _ \ \ \ \ \ \ _ - - _ \ / \ \ / \ / /i / \ _ \ - 1 1 \ r / \ \ \ \ \ / \ \ \ \ \ I `\- _ ` \\ \\ \\ - / / / / / / / / ✓ - \ \ \ \ \ \ \ \ \ \\ \ \ \ \ \ \ \ \ \\ \ / /ice - -�^ _ _�� + - _ - \\� \- \ \ \ \ \\\ 1 \\ ( \\ _ i -\ _~\ \ \\ \\ \\✓//� / / / / /�/ // - _ \\\ \ IIII\\ \\ \ \ \ _ \ \� \\ \ \ \\\/�/-/r/�` ---\ =� -\_\ \\\\ \ \\ \ \\ 1 \ \`- •� \\� \\ \\ J // %/ /// / /i /i / j __ - -� \\ \ `� IIII \\\ \\\ \\ \ + ... \� \\ \ \\ \ \\ \�/ /i / �� �' ,� -' .�� - \\1 ` _ -" ` \\\ \ IIII\ \ \ _ _ _ - '\ ` - \\\ �\ \\� / / / // ///i i i -\ \\ \\ IIII d \ \ \\ - \ \ \\ \ IIII\\\ // /'���_ _--__ \ _/ / / \ \ \ \ / - \ - \ / / /i // // �= � \ �\ \ \ \ _ \\ \ \ � IIII / / -- _ �+`'-`-\�._�-+ \\ \ \ \ , \\ �=- \ \ \ \ 1 \ / _ \ _ - 1 \ \ \ _ \ \ \ \\ � // � / / , ! - / _ \ \ \ \ \ \� \ � \ \ \ � \ � \ \ �\ \\ \\ \ / / / � - _ � �; \ \ .,; - - _ � _ \ IIII \ \ \ \ \ \ - ✓ / - - \ \� \ _ IIII \\\ \ / �/ /// // / ' i _ �-� _ - \ � \\\ \ \ \ \\ \ � .- � - � \ \ \\ / /✓ � � � = - \ _ - \ \ 1\\ \\\ \ ,� / - - �_ \\ \ \ \ _/ / / /i// /i/i / /�� \ \ \ \\ \ \ s \ \ -\ �\ \ \ IIII \\\� ///�/i_ �_� \ �= - -\ \� I \\\\\� 111 IIII\ \ `_//'�=� \� \ \\\� \�\ \� / / / i / �� /r �� - - \\ \\ �\ \ \ \ \ � - \ \ \ \ \ \ \ \ 11 I� / // /i �,,,� �.�: \ - - \ ` )\ \ IIII\ \\ \\ �� ,/_ � _ -- - INSET'B' PRE -DEVELOPMENT STORMWATER QUANTITY CONTROL PRE -DEVELOPMENT DRAINAGE AREA (Acres) (CN) Q1 Q10 Q100 ANALYSIS POINT A 26.38 85 76.00 171.35 283.62 ANALYSIS POINT B 28.27 80 44.11 144.18 200.56 ANALYSIS POINT C 7.25 78 6.48 17.85 32.31 NOTE: POST -DEVELOPMENT FLOW IS LESS THAN PRE -DEVELOPMENT FLOW AT ALL ANALYSIS POINTS. REFER TO CALCULATION BOOKLET FOR ADDITIONAL INFORMATION. PRE -DEVELOPMENT IMPERVIOUS AREA AND WATER QUALITY TREATMENT EXISTING IMPERVIOUS DRAINAGE AREA POST -DEVELOPMENT STORMWATER QUALITY CONTROL PRE -DEVELOPMENT ONSITE IMPERVIOUS SURFACES = 6.36 ±ACRES POST -DEVELOPMENT ONSITE IMPERVIOUS SURFACES = 21.04 ± ACRES (INCLUDING FUTURE BUILDOUT) IMPERVIOUS AREA REQUIRED TO BE TREATED = 14.68 ±ACRES IMPERVIOUS AREA TO BE TREATED = 12.94 ±ACRES (WET DETENTION A) IMPERVIOUS AREA TO BE TREATED = 3.76 ±ACRES (WET DETENTION B) TOTAL TREATED IMPERVIOUS = 16.70 ± ACRES (A+B) IMPERVIOUS AREA OVER -TREATED = 2.02 ± ACRES THIS DRAWING IS FOR AGENCY REVIEW ONLY - NOT FOR CONSTRUCTION *WETLANDS IN THE PROJECT AREA HAVE BEEN IDENTIFIED AND CONFIRMED BY ACOE AND NCDEQ. NO IMPACTS ARE PROPOSED. \ / ////, / /// // /I/ / I I I i -�-\ \ \��-_-_ ��\\\ \\ / // / ///-f ( / J I - ' �/ I11 \\ \_ ,`\ \ � � -\\\ l\ -- \ / f////// ///,'// / )/ /II I I / \ \\,� \-\\\/- - _'\\ `_ \ '/ / / / //rJ / 1 \ J /! I./ l �� .- _ ` \ / \ \ ` \ \ _ \ \ I \ I / / / / / l ( I \ ` \ - + \ \ \ ! - _ - - - - _ _ \ - - - �' / ) / ^� t l / / j •\ / : \ \ \ ) 1 ' �- \\I / / / / I /// / �/ I I I I \\ _ \--- / ---- \ \ \ \ � / ,, r 1 I \\ I -I / �) \ 1 / ( I I r - \ l / / _ I / 1 l J , \ \ V y� �' 1 \ \ � - �• „f -� ✓ / / / / \\J � / � � / `J \ ? I -\ \ \_ \_ �\ I / / //-�\ 11I1 / I�, ,--.r^\'//\.,,• ,- r-- t-I^ \ -` --, \\�-__ �-- _ i--�. \ \\\\ \_✓ - JI _/_/ I / I1/ \ / �/ f `` ) !.� \ -- \ \ ' ( I I II )I�IIl1'1 ! - - `\`\� \\ \__\-'--^r- / / / // /� / �� _ \ h - \ \ \ \ I,I /J // /lI ) / \~,` J `_ V `\ `- /\_^ / / J A `-\ �� -� --__`- \ \ I III I � // /IIII t, \ 1 1 I I I I \ \ \ \\ \-- \`-------- \/\ \ \ -- \, -\_/ I -,I / / /V ,/ / /� . J)�_ - ---- \\ \ I I (I I \ /// 1 ,a1 I 1 \ \ \ \ -\ \ - \ v \ \ � / / / / V -, � --__ _\ I,I , I I 1/ Ill/ \ _ \ , \\ \ . _ \_--Y � \\ /- / I/ \_ \ / ./!) r , / f ,' )-- --_�-\\\1 I III IIII) // III I I I I 1 \ \ \\`\\\ `\ \ -\\_ \_ ___^-\ �' `\ \_ -\ /_ /~/ / �\ \ Il 1 I \ \ \ \ \ _ _ / / -- / / / I _\ \ \ _ \ \\ \ II I I Ij1 � I/I I I \\ \ \ \,_ \ \ \\\\ \1\ \ \__- \ `\ ^ \^ �\ \_ // / /� -/ ✓ / \ \ \ IIII IIII w/ �' ///I ( 1I/ \ \ \ \\ \\ \\ \ \ \ \ _ -� -`- \ \\ -\-- \ ,_ (- ./ / // / �•' \ 1 1 IIIIIIII l( �. / J I I \ \\\\ \ \\\ \ - \\ - -` - /\- _ -\ -`k. \---/ / � ,`/ ✓/ /\/ o r-\� \ / I II ( I I k///- lI Il I 1l \ \ \ \ \ - \ \\ \ \\ I \ _ \ _ - - v ` r _ , ! /' - / / _V /t <- \ I \ I(\ I� 1 �I,- IIII ( 1 I I \ \ -\`" \`\ � \ - / \\-\\ \ - �J ��.�•-_.._,..� 1/ - `) // r,-/ , d \- � �) 1 1I�\III1I1(1 `� IIIIII I I\ \I/- \ \� \_\ \ \\\ \\ - SEE SHEETC4.8 `\ 1 ^\-\ \\`-_- -_/-r---- J)- /rr11 `� a� 1 I \ \ _ . _ \ \\IIIIII IIII II IIII (I ` \\\\Iv \\ - -\-\, `\\`'\\IIII\ \\----\\\\_ \ �\ \\--- \--f- ^ _/�---/----^-r / ✓ \_,-�_P_ I \ - - - ^� ( III l \\ \I \-_ \ \ \- \ -, \ \ \\ \ - -1 \- - \\ `- \ -/- - i_ \_ - !^ ? ^ -/^ten N I � I III\ 1Ii\ \ \ I \ \ / -_ `--.` -_ \ - -\ \-`_ \\ �- _-\ \ \ _� �- � _ _ .- / / - \ I I I I ` \ \ \ \ I r = _ - - - _ - _ `' \ \ \ - \ \ \ \ \ \ `� - - ` 1 / \ \ \ - \ \ _ \.` �' - _ / \ - ` / - -. - J \I IIII 1 \\\ \ \ \ \\` -� - -\ -1 \\\ \ -- \ \- ~ - +\\ \ - -__/ `�`� - '- - --- /_` / IIIIIIII \ \\\ \ \ ll� --` \ \\ - \ ` \ \\- -"--\ ---\ -'\ \ ^ -----` _-f--- ---/-/ --- -- I IIIIII \\ \\ \ I/ _ _� IIII\ -\\\ \�� \ �� � -__�- _\ `\_--- - _- - --/--� .� \. -- _ I \ \\ \ -\ `� \ \ \ \ \ - - _ ` - -- --r-,_- 1 1 I I I )- \ \\ \\. \ \\\ \\ '__ - - r - - - - - - / - - - - � \ - / / I I I I -- - \ \ \ _ ` -• - ' \` ` \ \ \ -" \ - \ \ - _- - - _ / \ ' _ ' 1. ^ \ - '-- -� - -• ` \-' J- ' _ �- � \ �- �. _ /) )IIIII J I/,�\\\\\)\/ \\-\ \- -\-`\� ° l \-^//-- -\_- -\.-- ---/ - `\ - / // II / I / \--\\\� - \ \ --\ \- 1 / \-_ ~\_/--- /'---- -`--_- v\-_/, --`\ - I I ll l I I // _, \ \ \ / \ \ \ - \ - - _ ~ \ \\ \\ \ - \ -\ J - ,/ - J v ` -•- - _ _ _ / _ - \ - \ \ / ////II/, //lI/ \� \ 1\ ~\ IIII\\ \ \•\\ � \ \\\\%\ \\ , \ / \ \� _ i " /_ -___- - -/- -__ I---\ 1 \-\--�\`'' / // /)/ //I � �\\ \ -\\\ \ \ \ \ _ \ \ \ \\ \\ \ -.-_ J- ^`/ _\-^ -- � - _ -/ l _ --� - ` , � _ ^ -_ / /�� ///// / //- \\^ \- IIII \ \ \ \� \ \ \ \ \ \\ ` ) \ \ - _- ' .r_ �- '` /- _�- ` ` \ - \ //i \ \ - \ \ \ - _ _ _ _ _ \ _ _ C //� i / i i - \ \ \ \ \ \ _ \ ^ \ \ \ \ \ \ \ I - _ • _ - _ _ .r �- - _ _ / - ~ - - '- -_ - \ ^- - \ --=--�_ -- \ \ \ \ \\ - \ -\ \ - \ \ \\ \ _r' /�-' /-----�� ---_ _-� �_ �-\\\ \\ \\ --_n----_/----�-\ \\ - \ \ \ \- �� � \ \ \_- \\ \ \ \\ /- r / -/ �, - --- - � - - \ \\ \ �__ _==� \ -- - ^\ of __ `_) / -^/ -- / _ -- -�_\`\ IIII \\ ~\\ \ _ _ _ _ _ _ _ ` \ �_ \ \ \ ti - - - - - - \\ _ - -- \\ ` e 41 - G \ \ c r • - - r I // / / ✓ - / ^ / _" _ ` _- - � \ -� \\ \\ \ \ - \\ / - \ - - \ , \ - ` \ _ \\ - - \- \ \\ - - --~ -� - - \ \ - \ � \ \ \\ \ \ ` - J- / ^ - J/ / i / - /- /`^ �- _' '� _ - - l� - _ _ -- ` \ ^ \ \ \ \\ \ \ \ \ \ \ - \\ \\ \ \\ \ / / ! \. _-- - \\\ \ --- _ ��--�_ - \ \ \ \~\ \ \ - \ \ - \ \ - \ \-_ _- /� / / �_- �, '_^�'�- \- \\ -, \ \\ \\\` \\ /'- ---� _~_ 1`- - �X\\\� \��`-� \,�\\\` 11 \\-, \\\\ \--- --//// //// J///1-,-�i-- /�/�-`_- -� \\\ti � � \\.\\=\\\\ \\\\\\\ // -- - -_-- \ \-\\\\\�\-\\�-\\\ `-_`\\\\\\\-_-----\- )I1rI// (� ////,-1- � �- -\-\1\\\~\\\IIII\\�\\\\ / / - , - _ \ \ \ \ \ \ \ \ \\ \ _ \ - -� _ - _ ` ` \\ \ \ \ \ \ _. - - ` - _ \ / I I o ✓ - / / / / J _ / .--_ _� � ~ - \ - \ _ \ \ ', \~ \ \ \ \ \ \ \ / _ _ - ... .- - \ ` - - \ \ \ \ \ \ \ \ \� \ \ _ 1 \ \ \\\ \ ` - �� - _ \ _- I / ( / / / / �/ / / // ...- \ \ \ ~ \ \ \\\ \ \\`\ \\ \\\ \IIII \ \ / / _ � - \ _ \ \ \ \ \ \ \ \ \ \ _ - � \\ - \\ III I- - \ - Z - J I ( I / I / / / ,- / / \\ \ \ \\ \\\\ \\'\ \\\ \ / / / / -` `\ \ \ \ \ \ \ \ \ \ \ �\ `� \-_ \ - \ \\ \ \ ---• / / / / �/ / J \ \ \\\-\ \ \\\\\\\\ \\\\IIII\ / / r / - - - \ \ \ \ ,-\ - I- - \_ \ \\ \\ ___\\ -- 1 I ) / I 1 / \ \ 1_ \ \ \ / /' _ \ \ \ - \� \ \ \ \= _\\ - _ \ \- --- - / I r / (II/I- �/'I I/ // \ \`_\\\\\\\\\\\\\\�\\\\\ / - �� _ \ 1 \ \ \ \ \ \ _ / / j/ _ _ -- \ - \ , \\ \- \\\ \ \ \ \\ \ ti ` _ \_ \\\ - ---_ _ "i //✓ I / / I ( / I r -./ - A\\� -\\ \\\\ \\\\ \\\\ \ / i//-/�_- \\ -� \\'\\\ - \ - \ \ \ -, -_ -_ - \ \-- ---_-- \ // / I ( \ ` / I l 1 / G� Z. �--\\\\\\\\�\\\\IIII / �'� / I _-- � � � - N - `t \ -, " \~ ", \� -, �` _�-- " \- - \--� - - , \\ -` / 1 •"✓ \\ /\ (\` ` \\ =\ \ `\.l \ ~ \ \ \\\�\\ \\�\\ IIII \ \\ /// // __ �. -- \ - \ \\ ` \\ \ \ `- \ " \1_ \`\ �- - - ` `� -\ �.- - _ ✓-_ \_ r / '~/--__-_� �_�/y�, 11` \ �\ \\\ \ / j -_ _ - \ \ \\\ _ \ \\ `_ \ " - -__`__\ \\-\ \\ -, 11 --_�- `' \ \ \ /^ ``-.` tR% J/ I Il l 1 \\`\\\\�\\\\\ i / : - _ \ \ \ - \ - - - 1 - - \ \ - - - _ ` - _ \� , �\ \ - -_ - - _ _- - - - /� \ - - ~/ / - - - - �%, � ..� ` I ) 1 \ \\ \\\\ // / / ' / _ \ \ -, - - - - - \ - _'- \ ` \ \ \ \ -_ _ = + \ \ \ \ \ ' - \ \ ter• - - - - \ _ , _ \ ./ / / - / � ) \ \ I _ _ /// r _ - - \`---+ \\ -\ \ \ -\ -_ \ � �\\\ \_\\ \\\�� _ ---\I/ \\~ \� /\/ J // / ^^-`. -- \ `\ \ `1 1 \ f ( \\1 / �.� 1 _ \ = \ \ _ \ \ \ \ - �� '` '� A - - - - _ \ \ ` 1 \ \ - �\` _ " " \ \ \ _ \ - \\\ \ - - , \ \ \\ " \ - ~ \ \ \ \ \ \ \ \ \ \ \ \ `� __ 1. / / / / / 'I 1 ( / ) r �' I I l l \ // =� r _ - _-\` \ _: -\ \ \ - \ \� 11 � \ -_ `-� \ \\ \ \ \ \\ \ \-` - \ \ \ \\ \ \ \\ -\ -/ "I I- r� ✓1 1 l ) I� l ! I I I I I \ \ \ - \ \ - \ \ \ \ \ \ = \ \ \ \ - \ - \ \ \ \ - - \ - - __ _ -- \I- \ -\-1 �`� � - `\� \ \�\\ \ \\- \ \ \ \ \ IN. �,\\ \ \\~ ~� -` /�/ I v)1 I \ I\I l I \ 1 i - - \- - - \ \ \ - \ \ - _ - - \ - - \ � - \ \ -, \ \' \ \ \ � \ \ \ -- - J - - \ 1 / I 1 1 1 I I I ( _ _ _ - - \ - - - \ \ \ \ \ l 1 I I 1 % i ! �� - - _ -_ _ _ + _ \� _ \ - _� _ � � - �- ` ` \ , , , 1 \ \\\ \ \ - ` ^ \ \ \, \ �� \ � - \ _ \ - - _ -_ - _ r - - \ \ 1 \ i \ , I I I J J 1 1 / - - _ ' \ \ - - \ � - \ -, � \ _ \ - \ _ " -, ' - \ � \ � � � � \ � ,` ^ \ - - - _ , _ _ \ \ 1 1 ` \ 1 I l l ( ) 1 1 � 1 / J J //� -_-_ _ - ` �---`-_- � ,z �\,� \ ` --' ` \ \- \ \\� \�-\�`� \- \ \� \\\� �_ \ -_' ` \ \\\ \ \ I 1 )I I )If I ( I -- - --- - _ \ \_ \\ \ �' - - - \ - \ \ \ ` \ - \` \\- - - - ---- \ -, , I \ , I ) ) ( 11 I '/%---- t --� \\ \-� \ - \\ \ \ \ \ _ \ \ - \ \\ \ \ \ _ \ ) ( I ) \ \\ \ I I III / / /// �_- �- \\- _ - \ --- -` \ \ -� \ \ \ - _ \ - \ \ \ _ `- \ \� \ \ `�-__- -- ---- - \ \ \ \ \ I _ - -`---_\~__�-\ ��--- �\ _\\\-\ -\-,\ \-\ --____ \ \ �\ \\\I ,\ ((Ir Ili ; / 1% - - ` _ _\ _ _ - _ `_\\ � , � � _`� \ ` �� � - - _ � \ \ � -, � \ � \ \ - -\, - _ � _ \- \ \-\\\ \� \ , \ I \ (( //IIII I l l / :--- _ ---�`\ - - -_\\- IIII\\-` \�\\\ \ \ _ \ \\\- \-- ` \-- _"\ \ \ 1 \ 1 (�\II 1 IIII I 1 \ l I 1\ ,- �- - - �. - �� - \ - -` - ^ - - - + _ - - ` \ _ - \ - - - 1 \\ \\ \\ \ \ \ _ `. \ " \\ _ - \ - - _ - - \ I I 1 I I I I I I I ) I I I I I 1 I � I ( ) � //� -_ - - _ -� - \ _- -_- - -_- �_ _ � - `\\ `�� ; - `\ \\ \\\ \- \ \ \ � \ -\ \ \ \ - \ _ \ ` _ \ - \ \ \ \ ` I / / I / 1 I 1 I I , \ /// \ - -_ - - _ _ _ \ \\��\\\` � �\ =�` � -,\ , \ \1\ \\ - � \\� � \\ \ -� \ -\ - - ^ \ #0\ I \ I 1 l I I I I I I ( III I I 1 1 I l t \(' \ \ \ \ \\ - \ `� \ \\�- � I I 1 )l J JI I I1 J I I I ) l/ / � - / = \ -� \ . -1 \ _-_ - -_- _ _ `-\� \\ \ _ _ \ \ \\ -\\ \\ \ \ IIII - , \ \\ - \ - \ I ( / � /I / , // l .I / / /�/ /%'� / / J!1 J J 1 1 I ) I I I / / / / ter/ �- _� \- _ - '- - - _- --. -• - -\ - \ + - - - \\ \\\ \ \ \ \ \ \ \ \ \ \ \ \ \ \ \ \ \ \ \ / / / , / // / / / / / / J I 1 /// � _� „�- _ _ - _ _-- � =�� \ ` z - � -, - � \\\ \\ \\ - \\� IIII - �`\ \\ \\ \ \ \ �1 I l I ,/ / J / J�// // / , r -I-, , i ///�, �/ / %/'� 111/� l '//' - - - - - - _ `` \ \\ "\ \ -\ \1 \\\ �\, \\\ � \\ \ I / I // / / /// / // /,� // /' ////// - J/,- f // I / _,/ ,- //� I // _ / \` 1 / // / /i/ / / / / i I // // - - - - _ - _ _ =_ - - \ - _ ` \ - \\ - - \\ \ \\ \ , IIII I I l / /// /l , / // / / /� / / /i //�// %/ l /r // /J / // i / I // _-- -- --_ --_ - \ _ _ _ \ \ \ \ \ 1 - 1 / / / // / / / / /// // / / / ./ / -_ JlllI / _ \ \\ _ _ \`` - ` ` - \ \\ \\ \ \\ \` �\ \ \ _I 1 / / / // / / / / /� /ice // i.% / / / l ////I% --! - --_ _-_-�_�_- `�`�`-\�` \- � � �\-`\\-\\\\ �\ \ \ \ 1// 1/I/ / II/ //////�/ ' r // // / / 1 /�i /// / _ - - - - \ - `\\ , \ \ \ _� \ \ \,\, II II \N \\ \ \\�� I ( I J / // �// ( l 1/////� ,/ / // // /!( r l 1 I I I ��(/ fIJ / / i /�%-J �� ( / / /'/� / -- r--_-= - _- __�-_� `-- "��� \� \\\\\)�\\, ��\\ IIII I//!////' ///i'/ ) \I/� //// ////� // I // / / )/ J (/r- \� 1(( /-, ( / ) 1l/ i��// /// /// l �., _ - _ _-- - ==~�'- ��� \� `\\\� \\` \\'I � \ II \/J�J // / //�//X, 1 / IIIII//J/ / I / / ///�< ( I / f„ / ( 1 11/fr/' J I�rc-/) / , / - -_ -_ _ _ _ -_ _ _ -_ _- �� \ _ \ \\ , � \1 �\ � I I\ / / )/ ) J� / ( � ( I ( I \l// - ( ( \ s / / (/ /// / - - _- - - ( 1 / ( / r 1/I(/ /// / // - - - - \\ \� _ \ =ti\ \ ` \\ \` \\\ \ \\ 1 1 ( )'I f /III / III/ /l /( /_ l / /�✓ �11) I I I I l \ \ 1 \ \ \l l l l I f I I I I / � i _ __ - - _ - _ - = _ � = � '__�� \ � � � ,- -\ \ � � \\ \\\ � (1 1 I I I /) II II/ J // l //// J J r / /� ( \ \ 1 r � /� � � \ \ ` \\ �-IIII �` � / ��� \ / \ \ \\\III I / /// ___ / -�� -__ \`\`~ \_\\\\�`\ \\\\\�\\\\\ \\\ \\IIII 1111/Ilf(rIJI�J/J/J/ //Ili%/��//cl'( \ f )1,\I\ \_\-- ~ �_`\\\,\--- __- ":Z - ,,c^�\ IIIIIII,/I/1 ///��'►_-__- 1 --� 1_ -_ �_ \\-\\ `-\\,z \\ \�\� \1\\\\1\ l)'I�I/j1I111f)I(I /l//l(1 /ll/l/( l\�\ , J l\, \ _- \\ ��`\\ �\,�� I IIII//// // i �= - _--_ -_ _-��_�_ - � \_ \ \ -\\\\� \�\ \\\\ 1 I III(I(/ 11IIII 11 /l /I J ( / (1 )() L \\_� ��- - �\`` `-_ - ``-\\ \Z ^ )► / - - -- --- _ _ -\ �\ \ \ \ \\\ � II I 11 // \ I(\1 \ \ \ _ - ` -JI IIII l 11/I////; 'i --� _� _ _ \ - \\\ \ \ \\1 I (II 11'l 1/I l 1 I I )I \ `� :- �'? - - �_ � ---_ \- \ X \\ /IIII / -' - -- - _ - \- \_\; \ \ \\ \ \\ \\1 IIIII IIII I �II lI� / I III \_ _ _, _\ \ -� - _\ \\` '\ 1111I111/ / / ///N _-- - '-_ `'- \` _ \ \ \ \C\ 1 I 1 1 1f , I \ l I \___ ;`_�� ^�`�\\ \\\\��� Il / /Il /// �" -_ i = --- - _ _ _ _ `�� �;\\� \ \ \ �\\\\l\\ 111 ,IIIII II IIIII I j1/l 11/, )Jl I I I//f - _ _� _ - - _ - \ \ \ \� \ 11( ((II //I/ i _ r.. _ _ -= ti = _ - _\ \- \` \�\\ �� 1 1 \ 1 I II 1) I )11 /Ill (\ 1 - -= Yam_ �� - _ _ - \�\\\\� _ == \\ \\\ �\ \\\\\\\�. \\\,1 1 /f IIII/=/--- -_- =� �`�\_ _\ \\ ��`� 11 I( (IIII 1 IIII III \\� )//c_ - _ _ \ _ - �\\\\\\\` \\ \- IIII /// // , /,� i/_ _ - ' _ �- _ -- = _ - - - _ - �\- -\� \ \\ �� \\ 11 I n „I1 II I I, II (\ ►, / =_-=- _ - _=� - _ - � �\`-`�_�__ = , \N \ \\ \ \ \ ', \ I l/ //I / %_ - = _.� - \` � - \\\ \\� \ , I I\ 1 11 II 111 11 IIIIII 1 \ \\ I = = - - -- _ _ _ - _ _� =_ , - -�\\ \\ \\ \ \ \\\ \\�\\\\/1 f // / / '� -_ \�_Z _ _ _ - - \\ \\ \\\ \ `\\ ,I 1 II l\ IIII I III f ----=��_ _ --^ E \--- mac- \\ \ \ \ \ \\ \\ \\\\� �11(I I I / I)/� // /�___�_-----_- - - - \\- \\\ \\\ \\ \\ 11�1 Il 1I1 111 III)l\ I1 ---___==- - �- -_ __ -�\\` _ - - \ \\\ IIII IIII \\\ \\� I' // / / / / // / - _� _- � �� \\- \ \\ \\ \ \\ \\ 11\ \\ 111 \ ll 1 \I I I II I I\ I 1 l ` ,\ - - -�-' = = \\ - _\\ �\- ��\ \\ \\ \\\ \ \ \\ \ \\\ .\ \\o\\\I III // /'�/ i_ �_ - - - ` = - IIII\\ \ \\ \\ \\ 1�1 1 \ \ 1 \ 1 11\ \ �� J'- - - _ -\-� \ \ \ \\\ \\ \\ \ \�O\\ II11 1 (( ,/ _ - ---_'_�___- �_�- \\ \\ ` I l \I 11 I \\ 1-�/�� _-- - =-___ \� -, - `\ \\-� _-\ \\ \\\ \\\ \ \\ \ IIII\ \\\ / \( I I/// /! // �/ - -= - \\- \\\ \\\\\\\�\\\1\I``\\\\1\\\\\`\\ \1\11 I\III I\\ /` -/ _ _- ____ \ \ - -� \-\+ \�� \\ IIII IIII \\\\\\\\\ -JI\ \11I // //_ _--_ _ - �_�_�� �`;�C-\`\\ \\\ \\\ \\ \ \\`\\ \\II \ IIIII rl-`i,�-= = ___ \`- _ \\\ - %--, \-\\� \� \\ \\\\ \\� \x\\\_ \\I I/// -_---- = _ --_\\\ \ \ \ \ IIII \1 \\ \ \l \\11 1 1 . ~\\~�_ ~`- \` - \ \ "\O \\� \ 1 \ \ II ( / / / /i%� - _ - \ \ \\\ \ \\\ \\ \\ \\\1 \\\ \\ \ (k \1 1 11 1\ I� \/ _ _^ \ `� - -- �\ , \ �� �\ \ IIII\ IIII\\\\\ \ \\ \�\\.\ \`\ ,)1 ` , (I / , , _ - - - - --� _ _ - _ \\ \ \\ \\ 0 0 \\\ \\ \\ \\ IIII \\ \, ,\ \I\ \, \\ \� \ , /� - _� r \ \ ` __ - - = - \ \- \- \\ \ \ \\ \ \\ 11 , l .\- \�\\Q�\\` � �i I1) 1 1 /j ( /�// / / i _ - _ _ _ - _ _� = -\ \\ - \\\ \IIII \\\� IIII IIII \\\ \\�\\ \\ \\ \ \\ IIII \ \\ \\ \ 1� // i/ = `' " ' - - - = _ = \� \\ \\ _\ \ \ \ \ \ \ \( \\\ `\\ ,1 \ \\ IIII+ J )1 / / - _ - _ \ \ \ \ \ \ \ \\ \ \ \ 1 I\ \ \ \\\\�� /// /� _ -/ --- �_ �_---� --\\- \ � \l \\\\\lI\\ 11 \ IIII �\ \-� ✓ / I 1 // / / / _ - _ _� _\ \ \ \ \� \\ \ \ \ \\ \\ 1` l Il \ \\ \ \\ \ = �� = = - / '� _- - - -\ \ \ \- \ _ - \ \ � \ , \ \I \\ \ - // /// _-_- - - -\\ \ \ \\ \ \A\\\\ \ \ \\\ -�/ IIII --\\ \\\ \ \\ \\ - - ; I I I/ // i / / �_ = - - -- = \ \\ \\ \\\ \\ \I \ \ \ IIII \ \\\ / , , - -_ _ _ - _ \ \ \ 11 \ \\�`\\ _- - � J (/ / / // / / _ - _- _ ` - " .-\ \ \\ \� \ \\\ \ \ \ \ \ 1 \I \\ \ \ \ \ \\ /// �� ^ - ` _ �� - - \ \ \ \ \\ \ \ \ 1 1 I \\ \ \\ 1/ / / / - _�- \ \ \ \ \ \ \ \\\�\ l\ \ \ \\ _ - \� _ -\ - \ \ \ 1 \ \- \\ -\ _ 1\ / / // / / // , / �i= ==~ -� - - \ \\ \\ \\ \\ \\ \\ \1 \\ \\\�\A \ �\ \\\\�\ \\ �\\- /// /ii - _ _ _ _ _ 1- __- _ - -- ` \\ \ \ _- \\ \\ \\ \ \\I I I 11 1 \ -�\\\� �1- _ �i l/ IIII// / // - __-- =_-- \- \ \ \\ IIII \\, IIII \\ \ \� \��\�\ \�\ i//i✓- - -- ` _� --\ � _� \\ IIII\\ \ \ \1 II IIII 1 \ \ \\�\_\\� l //� / - - _ -- - \ \\ \ \ \ \ \\ \ \ \\ \ \\ \\ \�\\�///�-r�s-=-= _-- �\ /\-\-� \\\ _\ _-\ \ \\ \\\ \\ \ (11 I IIII`\\_ / - _ _ y� \ \ \ \ \ \ \ �\\\ _\-- _ /,,// / ////,/ / �\ \ -- � \\ \\ \\ \\ \ I \\ \ �\ , \\ \\ \\ % _ _ - _ _ �\ -`-� \ - \ \\\\\ \ \\ 11 I Il \( \ �\ _-\- \- \i / / /, // /, / j //! _� _ �ti+\ .\\ \\ \\ \\\ \\\ \\\ \\ \\ \\ \ \ \� \� \\ \�\��/ / // /i - - = _ - - - \� �.\ __ _ \ \� - \\\ \\ \\ \ \ \\\ 11 IIII\ - \\- _ _� \\ \ // // / / / / / // / _ - + \\ \ \\ \\ \ \ \ \\ \\ \\\ \\ \ \� � \�\ \� // _ - '� = - _ _ _ ^ -�_� \ \- \ IIII \\ \\ \I \ \I 1 \ --\\\ "\ \\\\\//// / / IIII/, / /: =�Z-Z �\\ \ \ IIII IIII \ \ \\ Q ��\ \ \�1j�i� _ - _--- -- -� `\ -\ - \� � \\�\\ \\IIIII\I 1 \\ �': - -\ `\ - \ / / / / // /i // // N� ` - \\ \\ \ \ \\ \ \\ \ \ \ \\ \ IIII\ \\\ L� //// _ _ -` - -- \\ -- ` _ \ \ \\\ \ \I \\\ 1 \I\ \` \ / / - \ \ \ - \ \\\ --_ \, --- \\` \\ \� / / // /�/ / f% /// // / //// - _ - \ 1\� \\\ \\\ \ \\ \\\ \�� \\\ \\\ \\\ \\\ \\\ \� \\ \ ��\ . i //% _-�` _ _ _Z` �_� \� �`-\\ IIII \\\ \ \\ 11\ \\I I\II \ ( (I I \` ` __' \\ \. / / / �- - \ - \ \ \ / - - \\ \ \ \ \ / i = \ \ \ \ \ \ `1 - \� _ 1\� \� \///// //// ///i / _ �/'-- _\�� IIII\ \\\ \\ \ \ \\ \ \\ \ _- -. \ O �O \ \// // - _ _ _ `_- __ - _"� _ � \ \\- \ \\ 1 \ //, IIII � \ -\\\ \\ \ - // / '/ /i // / _ _ `, \ \ \ \ \ \ \ \\ \\ \\ \ \ O\ \O \Q \\� / / __�; _ _ - _ �� - _ �- ` \_\� ��\� \\ IIII \\\ I \\\ \I\ 111 II \\ - ^=_ ._ - Z \ \ // / / /r // /// ✓ ^/ ✓ _ ` \ \ \ \\ \ \ 1\ \ \\ \\ \ - \ \\ \\ \\ _ /✓ ' - - _ �_ _ �.-- - Z �-` \- \ IIII \ , , \ \\\ \ \ \\ 1 111 \\ �i i - \� `. �\ \\ \\ \ / // // IIII// � j � -\ \ \\ \\ �\ \ \\ \\ \\\ \\\ \ \ \\ \\ \\\\ \\ / ,// / ,- - _ 1-_ ` _� _ _ - �.- _ \ \ \ \ `\ � \ •A ., \ \\` % __ = �- �` \\ �\ \\ \\� / / /� %/ //� // / /i i ' / _ _- \\ \ \� \ \\\ \\ \\ \ \ _ ` �\ \\ \\\ \\\ \ \\ \ /f/ �- / r /�` - - _\� +_\ _ _ `` \\�\ \\ \ IIII \ \ \ \ / _ . � � \� \\ /� j , IIII II II / " - _ \\ IIII �� \\ \\ \\\ \\\tea � \ \ \� \ IIII\ \\\ �///,// / - _ _ _ -��_�_ III I\\ \\ \ \ � _ \��\\\\\ \\`\ / /i//i ii / /� _ / -_ - -- \\ \\ \\ \\ \\ \\ \ \ - � �\ \ \\ \\ \\\ \\ \\/////// -r _ r - �_- \\ _ _ - __ \- -\ \\\ _ - _ - ` _- � - \ \ \ \\ \� �� �/ /// / IIII / i_ - \\ \\ \\ \IIII \ \ \ \\ . . \\ \\ �\ \ \\\ \- // , ,� ter_ - - - \ - --_"' _ \ ti\\ \ \\ \ \ \\ i i - / ri _ \ \ \ _ \ \ \ _ \ \ /i / \ \ \ \ \ \ _ - \ -�\ \�� \ \\� - � /// � / � /_ �/ �- _ \\ \ \ \\ \\ \ \\ \ � _\� - � � \\ \\\ \\ IIII /ir��=---�_= _ - \� \\ - - \` \\\-\ \ \ \ �\ \ /// /� // /� ii // // /j /- �'�_ 1 _ \\ \\ \ \� \\ \ \ _ _ \- \ `•� \\\ IIII \\ �-/ /// / _ ' - _ _ �'^ -`� \ \ -- .^ ` I\ \ \\ IIII 1\ \\\ \\ \\ \\\ ✓ / i - \ � \\ \� \\ \\� // � /i /i / /� / !- / - - \ � \� \\ \ � \ \� \\ � ; \ _ � \Q \ \ �\ \\ IIII\ \ ////i � - -` �..: �, \ \\ \ .: - � � \\ \�\\ \\ \ 1 \\ \\ \\ \\ - _ / _ - �\ \ \ \ - / / / /i/i /i i/� \ \ \ \ \ - \ ` _ \ � \ \ \ \ \ / /// i � � _ \ - -- � \ \ � � \ IIII � \ \\ \ - _ � '�� .`__ IIII \ \\ \ \ �/ // i _ /i /�✓ - \ \ \\\ \ \� \\ \ \\\ A\ /�///// �.i _ = _ - \� \ �\ \\ )\\ I' \ \ \\ //'i�_ _ \ \ \\\ \\�\: / ,�� /� / ��_ i-�-- \\\�\\ \�\ \ \ \ -�` � \ \ \ \\IIII 1" /,�✓ /_� �,�;����-� _ \ \,. )\\ \\rn.\ �\\\\\ ,\��/�/-_ - \\ \ \ � \ � \ \ \ \ \ IIII , \ 1 .�// / _ --\ - \ \ \ - ./ INSET'C' POST -DEVELOPMENT STORMWATER QUANTITY CONTROL DRAINAGE ANALYSIS POINT A AREA (CN) Q1 Q10 Q100 (Acres) POST -DEVELOPMENT 17.13 92 23.16 42.85 47.56 Al (WET POND A) POST -DEVELOPMENT 14.20 84 32.83 82.30 142.92 A2 (BYPASS) POST -DEVELOPMENT 31.33 45.69 123.31 186.95 Al+A2 (COMBINED) ANALYSIS POINT B POST -DEVELOPMENT 4.63 93 2.80 6.87 32.44 B1 (WET POND B) POST -DEVELOPMENT 26.15 80 40.80 105.62 185.52 B2 (BYPASS) POST -DEVELOPMENT 30.78 43.56 112.49 215.84 B1+B2 (COMBINED) NOTE: POST -DEVELOPMENT FLOWS ARE LESS THAN PRE -DEVELOPMENT FLOW FOR THE 1-YEAR AND 10 YEAR STORM EVENT AT ALL ANALYSIS POINTS. REFER TO CALCULATION BOOKLET FOR ADDITIONAL INFORMATION. POST -DEVELOPMENT IMPERVIOUS AREA AND WATER QUALITY TREATMENT PROPOSED IMPERVIOUS (BYPASS) POST -DEVELOPMENT IMPERVIOUS TREATED IN SCM � � � DRAINAGE AREA DRAINAGE AREA BASIN INFORMATION BUA TYPE DRAINAGE AREA Al DRAINAGE AREA B1 PROJECT AREA ON -SITE BUILDINGS (SF) 64,267 2,219 (EXISTING) 66,486 ON -SITE STREETS (SF) 0 5,045 5,045 ON -SITE PARKING (SF) 458,962 61,657 520,349 ON -SITE SIDEWALKS (SF) 33,389 0 33,389 FUTURE (SF) 37,048 (BLDG) 94,865 (PVMT.) 131,891 TOTAL IMPERVIOUS (SF) 593,666 163,786 727,452 TOTAL DRAINAGE AREA (SF) 739,983 201,625 941,608 O E � 00 m U N U > r, a ¢ Z ro Y X N LA M s �0 -C 0000 N Q rn 00 ¢ o .� .. i (v o CL v Cz NOr c V� c 0a -1 i � UV n N 0 LO O (0 N 1= 0 , O 0 U i x W - • o m a in o x z =.E 0F�LO • O a W 2(gWNaorn • 2 ZU c-Z-°O W C N'C _rnrn > U o�H tmairn = J E • • O '7D C 0 U . N � � cxa H>. zFZQLnWa� NOT FOR CONSTRUCTION MCA R pZi,,-�' .``���o�'.�H �� ? ��FESS/p� ?'-9 Q = SEAL 033612 - ` .o FNGINEE� ��� `�. '�.I�Iq�p/S .� % INS ,,, S L �� SD/DD REVIEW /� CU W z z O CU CU z 0. W C) O. Z W Z) CU V V ) V ) Q w O Z z O 0 L LO � Q U) 00 w � N Q O z � U CU Z J � _ Q 7 Z z 0 Z � = J C5 O o) O L � r� � O V 0- o a� U m � � N � = z N �� -O 1 > M � N �� L O COL_ z< ��� I `J ,_ z a) �//)� O. " 0 V- O J Ln 0 2 cn � Lo Revisions No. Date OR #2 2021 JULY 09 Project Number: 1711-B Date: 2021 J U LY 15 Drawn by: FS PRE & POST -DEVELOPMENT STORMWATER MANAGEMENT PLAN Sheet Number: ■ Design Calculations Wet Pond Sizing (Original Permit) Wet Pond Sizing (MOV Expansion) Pre -Post Development Hydraulic Routing (Original Permit) Pre -Post Development Hydraulic Routing (MOV Expansion) Storm Sewer and Outlet Protection Calculations (Original Permit) Storm Sewer and Outlet Protection Calculations (MOV Expansion) Wet Pond Supplement EZ (Original Permit) Wet Pond Supplement EZ (MOV Expansion) Operations and Maintenance EZ (Original Permit) Operations and Maintenance EZ (MOV Expansion) 11-Feb-20 Original Permit CNG NC Drainage Area, (DA) = Impervious Area c=0.95 Pervious Area c= 0.30 Cc = CN= Permanent Water Quality Pool % Impervious = Permanent Pool Design Depth = SA / DA Ratio = Required Surface Area = Permanent Pool Volume Req.= Temporary Water Quality Pool Design Storm Rainfall Runoff Coeff. (Rv = 0.05 + 0.009 (% Imperv.)) _ Required Volume (design rainfall)(Rv)(DA) = Surface Area Provided: Permanent Pool Max. Depth = Area of Pond Bottom (Above PSS) _ Area Bottom of Shelf= Area of Permanent Pool= Area Top of Shelf= Perm. Pool Volume Provided= Avg. Perm. Pool Depth Provided (Eq. 2)= Surface Area at 1" Storage Volume= L TIMMONS GROUP 17.13 ac 11 Pre= 4.6 in/hr 13.09 ac CcPre= 0.52 4.04 ac Q1 Pre= 40.97 cfs 0.80 11 Post= 4.6 in/hr 92.0 Q1 Post= 62.78 cfs 76.4 % 3.00 ft 2.77 (from Tbl. 1.1) 20,692 sf 62,076 cf 1.00 in (Typically 1-in) 0.74 in/in 45,874.13 cf 4.50 ft 11,663 sf 19,192 sf 21,548 sf 21,548 sf 71,664 cf 3.33 ft 32.107 sf 1" Storage Volume Provided= 45,890 cf Temp. Storage Depth above Dewatering Hole = 1.60 ft Diameter of Dewatering Hole = 3.50 in Detention (Draw -Down) Time = 2.4 days T days=(Temp. Storage Vol Req / (0.6' A(2'g'(h))11/2)' 86400 (where h = one third temp. storage depth measured to centroid of orifice) Max Drawdow Rate= 0.39 cfs Permanent Pool Volume= 71,664 cf Forebay Volume Required = 14,333 cf Forebay Volume Provided = 11,876 cf 16.6 % Tahle 1 1 (EL= 1197.0) (EL= 1201.0) (EL= 1201.0) (EL= 1202.0) > 62,076 OK > 3.00 OK (EL= 1203.1) > 45,874 OK (2-5 days Required) > 62,076 OK SA / DA Ratios 85 % TSS efficiency Permanent Pool Depth (ft) % Impervious 3.0 4.0 5.0 6.0 10 0.51 0.43 0.37 0.30 20 0.84 0.69 0.61 0.51 30 1.17 0.94 0.84 0.72 40 1.51 1.24 1.09 0.91 50 1.79 1.51 1.31 1.13 60 2.09 1.77 1.49 1.31 70 2.51 2.09 1.80 1.56 80 2.92 2.41 2.07 1.82 90 3.25 2.64 2.31 2.04 s:\1319\0001\talcs\PondSize-Wet Pond-piedmont-90 tss printed: 2/11/2020 2:01 PM Page 1 of 2 Main Pool Permanent Pool Volume Stage (ft) Elevation Area (sf) Storage (cf) -4.00 1197.00 11,663 Top of Sed. Stor. in Main Pond -3.00 1198.00 13,476 12,570 -2.00 1199.00 15,333 26,974 -1.00 1200.00 17,242 43,262 0.00 1201.00 19,192 61,479 Inside of Shelf Elev. 0.50 1201.50 21,548 71,664 Normal Pool Elev. Outside of Shelf Elev. Forebay Volume Stage (ft) Elevation Area (sf) Storage (cf) -4.50 1197.00 753 0 Top of Sed. Stor. in Forebay -4.00 1197.50 1,291 511 -3.50 1198.00 1,828 1,291 ssm -3.00 1198.50 2,136 2,282 -2.50 1199.00 2,444 3,427 -2.00 1199.50 2,792 4,736 -1.50 1200.00 3,140 6,219 -1.00 1200.50 3,514 7,882 -0.50 1201.00 3,887 9,732 Inside of Shelf Elev. 0.00 1201.50 4,687 11,876 Normal Pool Elev. Total Pond Stage / Storage Detail 0.00 1201.50 26,296 0 Normal Pool Elev. 0.50 1202 29,027 13830.75 1.50 1203 31,814 44251.25 45889.671 Water Quality Elevation 2.50 1204 34658 60158.25 3.50 1205 37559 45889.671 Anti -Floatation Invert of Riser: 1,196.00 ft Crest of Riser: 1,203.10 ft Inside Width of Riser 4.00 ft Inside Length of Riser: 4.00 ft Riser Wall Thickness: 8.00 in Volume of Riser: 201.96 cf Volume of Riser Walls: 88.36 cf Weight of Concrete: 150 Ibs/cf Buoyancy Force: 62.4 Ibs/cf Weight of Riser Walls: 13,253 lbs Buoyancy Force of Riser: 12,602 lbs Weight of Riser minus Buoyancy Force 651 lbs Width of Anchor extension 6 in Thickness of Anchor extension 6 in Weight of Water acting on anchor extension 5169 lbs Weight of extension required (concrete) None lbs Safety Factor (SF) 1.3 Weight of extension required with SF 0 lbs Anchor Length: 6.33 ft Anchor Width: 6.33 ft Volume of Anchor: 20 cf Weight of Proposed Anchor 3008 lbs Is Anchor sufficient? YES Total Downward Force: 21,430 lbs Total Boyancy Force: 12,602 lbs Total Safety Factor: 1.7 Original Permit s:\1319\0001\calcs\PondSize-Wet Pond-piedmont-90 tss printed: 2/11/2020 2:01 PM Page 2 of 2 15-Jul-21 M OV Expansion INCNG Moraanton 139004 1 nton. NC Drainage Area, (DA) = Impervious Area c=0.95 Pervious Area c= 0.30 Cc = CN= Permanent Water Quality Pool % Impervious = Permanent Pool Design Depth = SA / DA Ratio = Required Surface Area = Permanent Pool Volume Req.= Temporary Water Quality Pool Design Storm Rainfall Runoff Coeff. (Rv = 0.05 + 0.009 (% Imperv.)) _ Required Volume (design rainfall)(Rv)(DA) _ Surface Area Provided: Permanent Pool Max. Depth = Area of Pond Bottom (Above PSS) _ Area Bottom of Shelf= Area of Permanent Pool= Area Top of Shelf= Perm. Pool Volume Provided= Avg. Perm. Pool Depth Provided (Eq.1)= Surface Area at 1" Storage Volume= GWF .r-6 TIMMONS GROUP 4.63 ac 11 Pre= 4.6 in/hr 3.76 ac CcPre= 0.52 0.87 ac Q1Pre= 11.07 cfs 0.83 11 Post= 4.6 in/hr 93.0 Q1 Post= 17.63 cfs 81.2 % 3.50 ft 2.67 (from Tbl. 1.1) 5,375 sf 18,812 cf 1.00 in (Typically 1-in) 0.78 in/in 13,124.27 cf 4.00 ft 1,245 sf 4,408 sf 5,502 sf 6,919 sf 19,358 cf 3.52 ft 9,410 sf 1" Storage Volume Provided= 13,132 cf Temp. Storage Depth above Dewatering Hole = 1.56 ft Diameter of Dewatering Hole = 1.50 in Detention (Draw -Down) Time = 3.6 days T days=(Temp. Storage Vol Req / (0.6' A(2'g'(h))11/2)' 86400 (where h = one third temp. storage depth measured to centroid of orifice) Max Drawdow Rate= 0.07 cfs Permanent Pool Volume= 19,358 cf Forebay Volume Required = 2,904 cf Forebay Volume Provided = 2,968 cf 15.3 % Tnhl,- 1 1 (EL= 1207.0) (EL= 1210.0) (EL= 1210.50 (EL= 1211.0) > 18,812 OK > 3.50 OK (EL=1212.06) > 13,124 OK (2-5 days Required) > 18,812 OK SA / DA Ratios 85 % TSS efficiency Permanent Pool Depth (ft) % Impervious 3.0 4.0 5.0 6.0 10 0.51 0.43 0.37 0.30 20 0.84 0.69 0.61 0.51 30 1.17 0.94 0.84 0.72 40 1.51 1.24 1.09 0.91 50 1.79 1.51 1.31 1.13 60 2.09 1.77 1.49 1.31 70 2.51 2.09 1.80 1.56 80 2.92 2.41 2.07 1.82 90 3.25 2.64 2.31 2.04 s:\1319\0001\calcs\PondSize-Wet Pond-piedmont-90 tss-GWF printed: 7/14/2021 10:33 AM Page 1 of 2 Main Pool Permanent Pool Volume Stage (ft) Elevation Area (sf) Storage (cf) -5.50 1205.00 1,245 Top of Sed. Stor. in Main Pond -4.50 1206.00 1,815 1,530 -3.50 1207.00 2,500 3,688 -2.50 1208.00 3,053 6,464 -1.50 1209.00 3,718 9,850 -0.50 1210.00 4,408 13,913 0.00 1210.50 5,502 16,390 Inside of Shelf Elev. 0.50 1211.00 6,919 19,495 Normal/Outside of Shelf Elev. Forebay Volume Stage (ft) Elevation Area (sf) Storage (cf) -5.00 1205.50 160 Top of Sed. Stor. in Forebay -4.50 1206.00 219 95 -4.00 1207.00 364 386 -3.00 1208.00 543 840 ssm -2.00 1209.00 754 1,488 -1.00 1210.00 998 2,364 Inside of Shelf Elev. -0.50 1210.50 1,418 2,968 Normal Pool Elev. Total Pond Stage / Storage Detail 0.00 2010.50 6,919 0 Normal Pool Elev. 0.50 2011 8,123 3760.5 11.56 2� 9,410 Water Quality Elevation 2.50 2013 10,700 22583.5 3.50 2014 12072 33969.5 4.50 2015 13502 46756.5 5.50 2016 15000 61007.5 Anti -Floatation Invert of Riser: 1,202.00 ft Crest of Riser: 1,214.00 ft Inside Width of Riser 4.00 ft Inside Length of Riser: 4.00 ft Riser Wall Thickness: 8.00 in Volume of Riser: 341.33 cf Volume of Riser Walls: 149.33 cf Weight of Concrete: 150 Ibs/cf Buoyancy Force: 62.4 Ibs/cf Weight of Riser Walls: 22,400 lbs Buoyancy Force of Riser: 21,299 lbs Weight of Riser minus Buoyancy Force 1,101 lbs Width of Anchor extension 12 in Thickness of Anchor extension 12 in Weight of Water acting on anchor extension 18970 lbs Weight of extension required (concrete) None lbs Safety Factor (SF) 2.3 Weight of extension required with SF 0 lbs Anchor Length: 7.33 ft Anchor Width: 7.33 ft Volume of Anchor: 54 cf Weight of Proposed Anchor 8067 lbs Is Anchor sufficient? YES Total Downward Force: 49,436 lbs Total Boyancy Force: 21,299 lbs Total Safety Factor: 2.3 MOV Expansion s:\1319\0001\calcs\PondSize-Wet Pond-piedmont-90 tss-GWF printed: 7/14/2021 10:33 AM Page 2 of 2 Hydraflow Table of Contents Pre -post calcs with helipad.gpw Original Permit Hydraflow Hydrographs Extension for Autodesk® Civil 3D® 2019 by Autodesk, Inc. v2019.2 Monday, 03 / 2 / 2020 Watershed Model Schematic...................................................................................... 1 Hydrograph Return Period Recap............................................................................. 2 Year SummaryReport......................................................................................................................... HydrographReports................................................................................................................... Hydrograph No. 1, SCS Runoff, Pre Development.................................................................. Hydrograph No. 2, SCS Runoff, Post Development -Bypass .................................................... Hydrograph No. 3, SCS Runoff, Post Development-BMP........................................................ Hydrograph No. 4, Reservoir, BMP Routing............................................................................. PondReport - Wet Pond...................................................................................................... Hydrograph No. 5, Combine, Post Development-Total........................................................... Hydrograph No. 6, SCS Runoff, Analysis Point B Pre -Development ..................................... TR-55 Tc Worksheet................................................................................... Hydrograph No. 7, SCS Runoff, Analysis Point B Post -Development ............. TR-55 Tc Worksheet................................................................................... Hydrograph No. 8, SCS Runoff, Analysis Point C Pre -Development .............. TR-55 Tc Worksheet................................................................................... Hydrograph No. 9, SCS Runoff, Analysis Point C Post -Development ............. TR-55 Tc Worksheet................................................................................... 10 -Year 3 4 4 5 6 7 8 9 10 11 12 13 14 ..................... 15 ..................... 16 ..................... 17 SummaryReport ....................................................................................................................... 18 HydrographReports................................................................................................................. 19 Hydrograph No. 1, SCS Runoff, Pre Development................................................................ 19 Hydrograph No. 2, SCS Runoff, Post Development -Bypass .................................................. 20 Hydrograph No. 3, SCS Runoff, Post Development-BMP...................................................... 21 Hydrograph No. 4, Reservoir, BMP Routing........................................................................... 22 Hydrograph No. 5, Combine, Post Development-Total.......................................................... 23 Hydrograph No. 6, SCS Runoff, Analysis Point B Pre -Development ..................................... 24 Hydrograph No. 7, SCS Runoff, Analysis Point B Post -Development .................................... 25 Hydrograph No. 8, SCS Runoff, Analysis Point C Pre -Development .................................... 26 Hydrograph No. 9, SCS Runoff, Analysis Point C Post -Development ................................... 27 100 - Year SummaryReport ....................................................................................................................... 28 HydrographReports................................................................................................................. 29 Hydrograph No. 1, SCS Runoff, Pre Development................................................................ 29 Hydrograph No. 2, SCS Runoff, Post Development -Bypass .................................................. 30 Hydrograph No. 3, SCS Runoff, Post Development-BMP...................................................... 31 Hydrograph No. 4, Reservoir, BMP Routing........................................................................... 32 Hydrograph No. 5, Combine, Post Development-Total.......................................................... 33 Hydrograph No. 6, SCS Runoff, Analysis Point B Pre -Development ..................................... 34 Hydrograph No. 7, SCS Runoff, Analysis Point B Post -Development .................................... 35 Hydrograph No. 8, SCS Runoff, Analysis Point C Pre -Development .................................... 36 Hydrograph No. 9, SCS Runoff, Analysis Point C Post -Development ................................... 37 OFReport.................................................................................................................. 38 1 Watershed Model Schematic Original Permit Hydraflow Hydrographs Extension for Autodesk® Civil 3D® 2019 by Autodesk, Inc. v2019.2 1 2 3 ED CD CD 6 7 ED CD Leaend Hvd. Origin Description 1 SCS Runoff Pre Development 2 SCS Runoff Post Development -Bypass 3 SCS Runoff Post Development-BMP 4 Reservoir BMP Routing 5 Combine Post Development -Total 6 SCS Runoff Analysis Point B Pre -Development 7 SCS Runoff Analysis Point B Post -Development 8 SCS Runoff Analysis Point C Pre -Development 9 SCS Runoff Analysis Point C Post -Development Project: Pre -post calcs with helipad.gpw Monday, 03 / 2 / 2020 Hydrograph Return Period R��� Original Permit y ra o Hydrographs Extension for Autodesk® Civil 3D® 2019 by Autodesk, Inc. v2019.2 Hyd. Hydrograph Inflow Peak Outflow (cfs) Hydrograph No. type hyd(s) Description (origin) 1-yr 2-yr 3-yr 5-yr 10-yr 25-yr 50-yr 100-yr 1 SCS Runoff ------ 76.00 101.42 ------- ------- 171.35 ------- ------- 283.62 Pre Development 2 SCS Runoff ------ 32.83 45.51 ------- ------- 82.30 ------- ------- 142.92 Post Development -Bypass 3 SCS Runoff ------ 63.63 80.39 ------- ------- 125.26 ------- ------- 196.39 Post Development-BMP 4 Reservoir 3 23.16 38.82 ------- ------- 42.85 ------- ------- 47.56 BMP Routing 5 Combine 2,4 45.69 80.91 ------- ------- 123.31 ------- ------- 186.95 Post Development -Total 6 SCS Runoff ------ 2.856 4.069 ------- ------- 7.610 ------- ------- 13.55 Analysis Point B Pre -Development 7 SCS Runoff ------ 1.591 2.433 ------- ------- 4.987 ------- ------- 9.472 Analysis Point B Post -Development 8 SCS Runoff ------ 6.484 9.375 ------- ------- 17.85 ------- ------- 32.31 Analysis Point C Pre -Development 9 SCS Runoff ------ 1.676 2.570 ------- ------- 5.290 ------- ------- 10.07 Analysis Point C Post -Development Proj. file: Pre -post calcs with helipad.gpw Monday, 03 / 2 / 2020 Hydrograph Summary Repo rlydraflowHydrographsExtension for Autodesk® Civil 3D®2019bbylAuodelskk,,Inc. v 019.2 Hyd. No. Hydrograph type (origin) Peak flow (cfs) Time interval (min) Time to Peak (min) Hyd. volume (cuft) Inflow hyd(s) Maximum elevation (ft) Total strge used (cuft) Hydrograph Description 1 SCS Runoff 76.00 2 716 153,965 ------ ------ ------ Pre Development 2 SCS Runoff 32.83 2 718 65,895 ------ ------ ------ Post Development -Bypass 3 SCS Runoff 63.63 2 716 134,263 ------ ------ ------ Post Development-BMP 4 Reservoir 23.16 2 724 131,779 3 1203.68 66,330 BMP Routing 5 Combine 45.69 2 720 197,673 2,4 ------ ------ Post Development -Total 6 SCS Runoff 2.856 2 728 10,081 ------ ------ ------ Analysis Point B Pre -Development 7 SCS Runoff 1.591 2 744 9,811 ------ ------ ------ Analysis Point B Post -Development 8 SCS Runoff 6.484 2 738 32,551 ------ ------ ------ Analysis Point C Pre -Development 9 SCS Runoff 1.676 2 754 12,409 ------ ------ ------ Analysis Point C Post -Development Pre -post calcs with helipad.gpw Return Period: 1 Year Monday, 03 / 2 / 2020 4 Hydrograph Report Original Permit Hydraflow Hydrographs Extension for Autodesk® Civil 3D® 2019 by Autodesk, Inc. v2019.2 Monday, 03 / 2 / 2020 Hyd. No. 1 Pre Development Hydrograph type = SCS Runoff Peak discharge = 76.00 cfs Storm frequency = 1 yrs Time to peak = 716 min Time interval = 2 min Hyd. volume = 153,965 cuft Drainage area = 26.380 ac Curve number = 85* Basin Slope = 0.0 % Hydraulic length = 0 ft Tc method = User Time of conc. (Tc) = 5.00 min Total precip. = 3.15 in Distribution = Type II Storm duration = 24 hrs Shape factor = 484 * Composite (Area/CN) _ [(8.300 x 98) + (18.080 x 79)] / 26.380 Q (cfs) 80.00 70.00 40.00 20.00 10.00 Q (cfs) 80.00 70.00 50.00 40.00 30.00 20.00 10.00 0.00 0.00 0 120 240 360 480 600 720 840 960 1080 1200 1320 1440 — Hyd No. 1 Time (min) Hydrograph Report 5 Original Permit Hydraflow Hydrographs Extension for Autodesk® Civil 3D® 2019 by Autodesk, Inc. v2019.2 Monday, 03 / 2 / 2020 Hyd. No. 2 Post Development -Bypass Hydrograph type = SCS Runoff Peak discharge = 32.83 cfs Storm frequency = 1 yrs Time to peak = 718 min Time interval = 2 min Hyd. volume = 65,895 cuft Drainage area = 14.200 ac Curve number = 80* Basin Slope = 0.0 % Hydraulic length = 0 ft Tc method = User Time of conc. (Tc) = 5.00 min Total precip. = 3.15 in Distribution = Type II Storm duration = 24 hrs Shape factor = 484 * Composite (Area/CN) _ [(3.840 x 98) + (10.360 x 74)] / 14.200 Q (cfs) 35.00 '••• 25.00 20.00 15.00 10.00 5.00 Q (cfs) 35.00 30.00 25.00 20.00 15.00 10.00 5.00 0.00 0.00 0 120 240 360 480 600 720 840 960 1080 1200 1320 1440 1560 — Hyd No. 2 Time (min) 6 Hydrograph Report Original Permit Hydraflow Hydrographs Extension for Autodesk® Civil 3D® 2019 by Autodesk, Inc. v2019.2 Monday, 03 / 2 / 2020 Hyd. No. 3 Post Development-BMP Hydrograph type = SCS Runoff Peak discharge = 63.63 cfs Storm frequency = 1 yrs Time to peak = 716 min Time interval = 2 min Hyd. volume = 134,263 cuft Drainage area = 17.130 ac Curve number = 92* Basin Slope = 0.0 % Hydraulic length = 0 ft Tc method = User Time of conc. (Tc) = 5.00 min Total precip. = 3.15 in Distribution = Type II Storm duration = 24 hrs Shape factor = 484 Composite (Area/CN) _ [(13.090 x 98) + (4.040 x 74)] / 17.130 Post Development-BMP Q (cfs) Hyd. No. 3 -- 1 Year Q (cfs) 70.00 70.00 60.00 60.00 50.00 50.00 40.00 40.00 30.00 30.00 20.00 20.00 10.00 10.00 0.00 0.00 0 120 240 360 480 600 720 840 960 1080 1200 — Hyd No. 3 Time (min) Hydrograph Report 7 Original Permit Hydraflow Hydrographs Extension for Autodesk® Civil 3D® 2019 by Autodesk, Inc. v2019.2 Monday, 03 / 2 / 2020 Hyd. No. 4 BMP Routing Hydrograph type = Reservoir Peak discharge = 23.16 cfs Storm frequency = 1 yrs Time to peak = 724 min Time interval = 2 min Hyd. volume = 131,779 cuft Inflow hyd. No. = 3 - Post Development-BMP Max. Elevation = 1203.68 ft Reservoir name = Wet Pond Max. Storage = 66,330 cuft Storage Indication method used. Q (cfs) 70.00 -1 •• 40.00 20.00 10.00 Q (cfs) 70.00 •• •11 50.00 40.00 30.00 20.00 10.00 0.00 -1 0.00 0 240 480 720 960 1200 1440 1680 1920 2160 2400 2640 2880 3120 Time (min) — Hyd No. 4 Hyd No. 3 Total storage used = 66,330 cult Original Perm o (D O O O O O O O O O O O O O O O O fD O O 0 v 0 �W Crn w < o CD o Do �� < (DN O N O ( Si W O O mo m 6 <o I(/)N-O Z W 7 (D O O- (n O rF O� mm <o N 0 � O � 60 D OQ 3 C W O O (D O O O _. N r WCL v n q O m ( Q 0 Q (n o _m � (p) L O N A o 0 o o o CD N � I O 0 l (D 0 C N O tp Q Z O rl �F O 0 CL Pond Report Original Permit Hydraflow Hydrographs Extension for Autodesk® Civil 3D® 2019 by Autodesk, Inc. v2019.2 Monday, 03 / 2 / 2020 Pond No. 1 - Wet Pond Pond Data Contours -User-defined contour areas. Conic method used for volume calculation. Begining Elevation = 1201.50 ft Stage / Storage Table Stage (ft) Elevation (ft) Contour area (sqft) Incr. Storage (cuft) Total storage (cuft) 0.00 1201.50 26,296 0 0 0.50 1202.00 29,027 13,824 13,824 1.50 1203.00 31,814 30,407 44,231 2.50 1204.00 34,658 33,223 77,453 3.50 1205.00 37,559 36,095 113,548 4.50 1206.00 40,515 39,024 152,572 5.50 1207.00 43,529 42,009 194,581 6.50 1208.00 46,599 45,051 239,632 Culvert / Orifice Structures [A] [B] [C] [PrfRsr] Rise (in) = 24.00 3.50 Inactive 0.00 Span (in) = 24.00 3.50 10.00 0.00 No. Barrels = 1 1 3 0 Invert El. (ft) = 1196.00 1201.50 1203.30 0.00 Length (ft) = 50.00 0.00 0.00 0.00 Slope (%) = 10.00 0.00 0.00 n/a N-Value = .013 .013 .013 n/a Orifice Coeff. = 0.60 0.60 0.60 0.60 Multi -Stage = n/a Yes Yes No Stage (ft) 7.00 AM AM 4.00 ►41I17 M Weir Structures [A] [B] [C] [D] Crest Len (ft) = 16.00 10.00 Inactive 0.00 Crest El. (ft) = 1203.10 1206.50 1205.00 0.00 Weir Coeff. = 3.33 2.60 3.33 3.33 Weir Type = 1 Broad Rect --- Multi-Stage = Yes No Yes No Exfil.(in/hr) = 0.000 (by Wet area) TW Elev. (ft) = 0.00 Note: Culvert/Orifice outflows are analyzed under inlet (ic) and outlet (oc) control. Weir risers checked for orifice conditions (ic) and submergence (s). Stage / Discharge Elev (ft) 1208.50 1207.50 1206.50 1205.50 EW11,16 `W11616 % 1202.50 0.00 ' ' ' ' ' ' ' ' ' ' ' 1201.50 0.00 10.00 20.00 30.00 40.00 50.00 60.00 70.00 80.00 90.00 100.00 - Total Q Discharge (cfs) Hydrograph Report 9 Original Permit Hydraflow Hydrographs Extension for Autodesk® Civil 3D® 2019 by Autodesk, Inc. v2019.2 Hyd. No. 5 Post Development -Total Hydrograph type = Combine Peak discharge Storm frequency = 1 yrs Time to peak Time interval = 2 min Hyd. volume Inflow hyds. = 2, 4 Contrib. drain. area Post Development -Total Monday, 03 / 2 / 2020 = 45.69 cfs = 720 min = 197,673 cuft = 14.200 ac Q (cfs) Hyd. No. 5 -- 1 Year Q (cfs) 50.00 50.00 40.00 40.00 30.00 30.00 20.00 20.00 10.00 10.00 0.00 0.00 0 120 240 360 480 600 720 840 960 1080 1200 1320 1440 1560 Time (min) — Hyd No. 5 — Hyd No. 2 Hyd No. 4 Hydrograph Report 10 Original Permit Hydraflow Hydrographs Extension for Autodesk® Civil 3D® 2019 by Autodesk, Inc. v2019.2 Monday, 03 / 2 / 2020 Hyd. No. 6 Analysis Point B Pre -Development Hydrograph type = SCS Runoff Peak discharge = 2.856 cfs Storm frequency = 1 yrs Time to peak = 728 min Time interval = 2 min Hyd. volume = 10,081 cuft Drainage area = 2.100 ac Curve number = 79* Basin Slope = 0.0 % Hydraulic length = 0 ft Tc method = TR55 Time of conc. (Tc) = 20.20 min Total precip. = 3.15 in Distribution = Type II Storm duration = 24 hrs Shape factor = 484 Composite (Area/CN) _ [(2.100 x 79)] / 2.100 Analysis Point B Pre -Development Q (cfs) Hyd. No. 6 -- 1 Year Q (cfs) 3.00 3.00 2.00 2.00 1.00 1.00 0.00 0.00 0 120 240 360 480 600 720 840 960 1080 1200 1320 1440 1560 — Hyd No. 6 Time (min) TR55 Tc Worksheet 11 Original Permit Hyd. No. 6 Analysis Point B Pre -Development Hydraflow Hydrographs Extension for Autodesk® Civil 3D® 2019 by Autodesk, Inc. v2019.2 Description A B C Totals Sheet Flow Manning's n-value = 0.240 0.011 0.011 Flow length (ft) = 300.0 0.0 0.0 Two-year 24-hr precip. (in) = 3.83 0.00 0.00 Land slope (%) = 7.00 0.00 0.00 Travel Time (min) = 19.03 + 0.00 + 0.00 = 19.03 Shallow Concentrated Flow Flow length (ft) = 301.00 0.00 0.00 Watercourse slope (%) = 6.66 0.00 0.00 Surface description = Unpaved Paved Paved Average velocity (ft/s) =4.16 0.00 0.00 Travel Time (min) = 1.20 + 0.00 + 0.00 = 1.20 Channel Flow X sectional flow area (sqft) = 0.00 0.00 0.00 Wetted perimeter (ft) = 0.00 0.00 0.00 Channel slope (%) = 0.00 0.00 0.00 Manning's n-value = 0.015 0.015 0.015 Velocity (ft/s) =0.00 0.00 0.00 Flow length (ft) ({0})0.0 0.0 0.0 Travel Time (min) = 0.00 + 0.00 + 0.00 = 0.00 Total Travel Time, Tc.............................................................................. 20.20 min Hydrograph Report 12 Original Permit Hydraflow Hydrographs Extension for Autodesk® Civil 3D® 2019 by Autodesk, Inc. v2019.2 Hyd. No. 7 Analysis Point B Post -Development Hydrograph type = SCS Runoff Peak discharge Storm frequency = 1 yrs Time to peak Time interval = 2 min Hyd. volume Drainage area = 2.690 ac Curve number Basin Slope = 0.0 % Hydraulic length Tc method = TR55 Time of conc. (Tc) Total precip. = 3.15 in Distribution Storm duration = 24 hrs Shape factor * Composite (Area/CN) _ [(2.690 x 74)] / 2.690 Q (cfs) 2.00 1.00 Analysis Point B Post -Development Hyd. No. 7 -- 1 Year 120 240 360 480 600 720 840 960 Hyd No. 7 Monday, 03 / 2 / 2020 = 1.591 cfs = 744 min = 9,811 cuft = 74* = 0 ft = 49.90 min = Type II = 484 Q (cfs) 2.00 1.00 0.00 1080 1200 1320 1440 1560 Time (min) TR55 Tc Worksheet 13 Original Permit Hyd. No. 7 Analysis Point B Post -Development Hydraflow Hydrographs Extension for Autodesk® Civil 3D® 2019 by Autodesk, Inc. v2019.2 Description A B C Totals Sheet Flow Manning's n-value = 0.410 0.240 0.011 Flow length (ft) = 200.0 177.0 100.0 Two-year 24-hr precip. (in) = 3.83 3.83 3.83 Land slope (%) = 2.00 5.65 2.00 Travel Time (min) = 34.86 + 13.59 + 1.11 = 49.56 Shallow Concentrated Flow Flow length (ft) = 20.00 0.00 0.00 Watercourse slope (%) = 2.00 0.00 0.00 Surface description = Unpaved Paved Paved Average velocity (ft/s) =2.28 0.00 0.00 Travel Time (min) = 0.15 + 0.00 + 0.00 = 0.15 Channel Flow X sectional flow area (sqft) = 1.23 0.00 0.00 Wetted perimeter (ft) = 3.94 0.00 0.00 Channel slope (%) = 7.22 0.00 0.00 Manning's n-value = 0.013 0.015 0.015 Velocity (ft/s) =14.12 0.00 0.00 Flow length (ft) ({0})146.0 0.0 0.0 Travel Time (min) = 0.17 + 0.00 + 0.00 = 0.17 Total Travel Time, Tc.............................................................................. 49.90 min Hydrograph Report 14 Original Permit Hydraflow Hydrographs Extension for Autodesk® Civil 3D® 2019 by Autodesk, Inc. v2019.2 Monday, 03 / 2 / 2020 Hyd. No. 8 Analysis Point C Pre -Development Hydrograph type = SCS Runoff Peak discharge = 6.484 cfs Storm frequency = 1 yrs Time to peak = 738 min Time interval = 2 min Hyd. volume = 32,551 cuft Drainage area = 7.250 ac Curve number = 78* Basin Slope = 0.0 % Hydraulic length = 0 ft Tc method = TR55 Time of conc. (Tc) = 39.10 min Total precip. = 3.15 in Distribution = Type II Storm duration = 24 hrs Shape factor = 484 * Composite (Area/CN) _ [(6.370 x 79) + (0.880 x 73)] / 7.250 Q (cfs) 7.00 . Me 5.00 3.00 r •• 1.00 Q (cfs) 7.00 9.1 •• 5.00 4.00 3.00 2.00 1.00 0.00 1 1 11 1 1 1 1 1 10.00 0 120 240 360 480 600 720 840 960 1080 1200 1320 1440 1560 — Hyd No. 8 Time (min) TR55 Tc Worksheet 15 Original Permit Hyd. No. 8 Analysis Point C Pre -Development Hydraflow Hydrographs Extension for Autodesk® Civil 3D® 2019 by Autodesk, Inc. v2019.2 Description A B C Totals Sheet Flow Manning's n-value = 0.240 0.011 0.011 Flow length (ft) = 300.0 0.0 0.0 Two-year 24-hr precip. (in) = 3.83 0.00 0.00 Land slope (%) = 1.33 0.00 0.00 Travel Time (min) = 36.98 + 0.00 + 0.00 = 36.98 Shallow Concentrated Flow Flow length (ft) = 183.00 0.00 0.00 Watercourse slope (%) = 1.10 0.00 0.00 Surface description = Unpaved Paved Paved Average velocity (ft/s) =1.69 0.00 0.00 Travel Time (min) = 1.80 + 0.00 + 0.00 = 1.80 Channel Flow X sectional flow area (sqft) = 1.23 12.00 0.00 Wetted perimeter (ft) = 3.93 20.00 0.00 Channel slope (%) = 15.50 11.11 0.00 Manning's n-value = 0.013 0.026 0.015 Velocity (ft/s) =20.72 13.57 0.00 Flow length (ft) ({0})142.0 180.0 0.0 Travel Time (min) = 0.11 + 0.22 + 0.00 = 0.34 Total Travel Time, Tc.............................................................................. 39.10 min Hydrograph Report 16 Original Permit Hydraflow Hydrographs Extension for Autodesk® Civil 3D® 2019 by Autodesk, Inc. v2019.2 Hyd. No. 9 Analysis Point C Post -Development Hydrograph type = SCS Runoff Peak discharge Storm frequency = 1 yrs Time to peak Time interval = 2 min Hyd. volume Drainage area = 3.380 ac Curve number Basin Slope = 0.0 % Hydraulic length Tc method = TR55 Time of conc. (Tc) Total precip. = 3.15 in Distribution Storm duration = 24 hrs Shape factor * Composite (Area/CN) _ [(3.380 x 74)] / 3.380 Q (cfs) 2.00 1.00 Analysis Point C Post -Development Hyd. No. 9 -- 1 Year 120 240 360 480 600 720 840 960 Hyd No. 9 Monday, 03 / 2 / 2020 = 1.676 cfs = 754 min = 12,409 cuft = 74* = 0 ft = 63.20 min = Type II = 484 Q (cfs) 2.00 1.00 0.00 1080 1200 1320 1440 1560 Time (min) TR55 Tc Worksheet 17 Original Permit Hyd. No. 9 Analysis Point C Post -Development Hydraflow Hydrographs Extension for Autodesk® Civil 3D® 2019 by Autodesk, Inc. v2019.2 Description A B C Totals Sheet Flow Manning's n-value = 0.410 0.240 0.011 Flow length (ft) = 300.0 177.0 0.0 Two-year 24-hr precip. (in) = 3.83 3.83 0.00 Land slope (%) = 2.00 5.65 0.00 Travel Time (min) = 48.21 + 13.59 + 0.00 = 61.81 Shallow Concentrated Flow Flow length (ft) = 52.00 214.00 0.00 Watercourse slope (%) = 2.00 8.88 0.00 Surface description = Unpaved Unpaved Paved Average velocity (ft/s) =2.28 4.81 0.00 Travel Time (min) = 0.38 + 0.74 + 0.00 = 1.12 Channel Flow X sectional flow area (sqft) = 1.23 13.00 0.00 Wetted perimeter (ft) = 3.93 27.00 0.00 Channel slope (%) = 6.23 8.80 0.00 Manning's n-value = 0.013 0.026 0.015 Velocity (ft/s) =13.14 10.42 0.00 Flow length (ft) ({0})146.0 34.0 0.0 Travel Time (min) = 0.19 + 0.05 + 0.00 = 0.24 Total Travel Time, Tc.............................................................................. 63.20 min 18 Hydrograph Summary Repo rlydraflowHydrographsExtension for AutodeskOCivil 3DO2019gyi9'fodelsNn'C V%19.2 Hyd. No. Hydrograph type (origin) Peak flow (cfs) Time interval (min) Time to Peak (min) Hyd. volume (cuft) Inflow hyd(s) Maximum elevation (ft) Total strge used (cuft) Hydrograph Description 1 SCS Runoff 171.35 2 716 358,388 ------ ------ ------ Pre Development 2 SCS Runoff 82.30 2 716 168,404 ------ ------ ------ Post Development -Bypass 3 SCS Runoff 125.26 2 716 276,630 ------ ------ ------ Post Development-BMP 4 Reservoir 42.85 2 724 274,122 3 1205.10 116,964 BMP Routing 5 Combine 123.31 2 716 442,526 2,4 ------ ------ Post Development -Total 6 SCS Runoff 7.610 2 726 26,276 ------ ------ ------ Analysis Point B Pre -Development 7 SCS Runoff 4.987 2 744 28,409 ------ ------ ------ Analysis Point B Post -Development 8 SCS Runoff 17.85 2 736 86,559 ------ ------ ------ Analysis Point C Pre -Development 9 SCS Runoff 5.290 2 752 35,931 ------ ------ ------ Analysis Point C Post -Development Pre -post calcs with helipad.gpw Return Period: 10 Year Monday, 03 / 2 / 2020 19 Hydrograph Report Original Permit Hydraflow Hydrographs Extension for Autodesk® Civil 3D® 2019 by Autodesk, Inc. v2019.2 Monday, 03 / 2 / 2020 Hyd. No. 1 Pre Development Hydrograph type = SCS Runoff Peak discharge = 171.35 cfs Storm frequency = 10 yrs Time to peak = 716 min Time interval = 2 min Hyd. volume = 358,388 cuft Drainage area = 26.380 ac Curve number = 85* Basin Slope = 0.0 % Hydraulic length = 0 ft Tc method = User Time of conc. (Tc) = 5.00 min Total precip. = 5.67 in Distribution = Type II Storm duration = 24 hrs Shape factor = 484 * Composite (Area/CN) _ [(8.300 x 98) + (18.080 x 79)] / 26.380 Q (cfs) 180.00 160.00 140.00 120.00 100.00 80.00 60.00 40.00 20.00 0 00 Pre Development Hyd. No. 1 -- 10 Year Q (cfs) 180.00 160.00 140.00 120.00 100.00 80.00 60.00 40.00 20.00 0 00 0 120 240 360 480 600 720 840 960 1080 1200 1320 — Hyd No. 1 Time (min) 20 Hydrograph Report Original Permit Hydraflow Hydrographs Extension for Autodesk® Civil 3D® 2019 by Autodesk, Inc. v2019.2 Monday, 03 / 2 / 2020 Hyd. No. 2 Post Development -Bypass Hydrograph type = SCS Runoff Peak discharge = 82.30 cfs Storm frequency = 10 yrs Time to peak = 716 min Time interval = 2 min Hyd. volume = 168,404 cuft Drainage area = 14.200 ac Curve number = 80* Basin Slope = 0.0 % Hydraulic length = 0 ft Tc method = User Time of conc. (Tc) = 5.00 min Total precip. = 5.67 in Distribution = Type II Storm duration = 24 hrs Shape factor = 484 * Composite (Area/CN) _ [(3.840 x 98) + (10.360 x 74)] / 14.200 Q (cfs) 90.00 80.00 70.00 60.00 50.00 40.00 30.00 20.00 Post Development -Bypass Hyd. No. 2 -- 10 Year Q (cfs) 90.00 80.00 70.00 60.00 50.00 40.00 30.00 20.00 0 120 240 360 480 600 720 840 960 1080 1200 1320 — Hyd No. 2 Time (min) 21 Hydrograph Report Original Permit Hydraflow Hydrographs Extension for Autodesk® Civil 3D® 2019 by Autodesk, Inc. v2019.2 Monday, 03 / 2 / 2020 Hyd. No. 3 Post Development-BMP Hydrograph type = SCS Runoff Peak discharge = 125.26 cfs Storm frequency = 10 yrs Time to peak = 716 min Time interval = 2 min Hyd. volume = 276,630 cuft Drainage area = 17.130 ac Curve number = 92* Basin Slope = 0.0 % Hydraulic length = 0 ft Tc method = User Time of conc. (Tc) = 5.00 min Total precip. = 5.67 in Distribution = Type II Storm duration = 24 hrs Shape factor = 484 Composite (Area/CN) _ [(13.090 x 98) + (4.040 x 74)] / 17.130 Post Development-BMP Q (cfs) Hyd. No. 3 -- 10 Year Q (cfs) 140.00 140.00 120.00 120.00 100.00 100.00 80.00 80.00 60.00 60.00 40.00 40.00 20.00 20.00 0.00 0.00 0 120 240 360 480 600 720 840 960 1080 1200 — Hyd No. 3 Time (min) Hydrograph Report 22 Original Permit Hydraflow Hydrographs Extension for Autodesk® Civil 3D® 2019 by Autodesk, Inc. v2019.2 Monday, 03 / 2 / 2020 Hyd. No. 4 BMP Routing Hydrograph type = Reservoir Peak discharge = 42.85 cfs Storm frequency = 10 yrs Time to peak = 724 min Time interval = 2 min Hyd. volume = 274,122 cuft Inflow hyd. No. = 3 - Post Development-BMP Max. Elevation = 1205.10 ft Reservoir name = Wet Pond Max. Storage = 116,964 cuft Storage Indication method used. Q (cfs) 140.00 120.00 100.00 40.00 20.00 Q (cfs) 140.00 120.00 100.00 40.00 20.00 0.00 0.00 0 120 240 360 480 600 720 840 960 1080 1200 1320 1440 1560 Time (min) — Hyd No. 4 Hyd No. 3 Total storage used = 116,964 cult Hydrograph Report 23 Original Permit Hydraflow Hydrographs Extension for Autodesk® Civil 3D® 2019 by Autodesk, Inc. v2019.2 Monday, 03 / 2 / 2020 Hyd. No. 5 Post Development -Total Hydrograph type = Combine Peak discharge = 123.31 cfs Storm frequency = 10 yrs Time to peak = 716 min Time interval = 2 min Hyd. volume = 442,526 cuft Inflow hyds. = 2, 4 Contrib. drain. area = 14.200 ac Q (cfs) 140.00 120.00 100.00 40.00 20.00 Q (cfs) 140.00 120.00 100.00 40.00 20.00 0.00 - - 0.00 0 120 240 360 480 600 720 840 960 1080 1200 1320 1440 1560 Time (min) — Hyd No. 5 Hyd No. 2 Hyd No. 4 Hydrograph Report 24 Original Permit Hydraflow Hydrographs Extension for Autodesk® Civil 3D® 2019 by Autodesk, Inc. v2019.2 Monday, 03 / 2 / 2020 Hyd. No. 6 Analysis Point B Pre -Development Hydrograph type = SCS Runoff Peak discharge = 7.610 cfs Storm frequency = 10 yrs Time to peak = 726 min Time interval = 2 min Hyd. volume = 26,276 cuft Drainage area = 2.100 ac Curve number = 79* Basin Slope = 0.0 % Hydraulic length = 0 ft Tc method = TR55 Time of conc. (Tc) = 20.20 min Total precip. = 5.67 in Distribution = Type II Storm duration = 24 hrs Shape factor = 484 Composite (Area/CN) _ [(2.100 x 79)] / 2.100 Analysis Point B Pre -Development Q (cfs) Hyd. No. 6 -- 10 Year Q (cfs) 8.00 8.00 6.00 6.00 4.00 4.00 2.00 2.00 0.00 0.00 0 120 240 360 480 600 720 840 960 1080 1200 1320 1440 1560 — Hyd No. 6 Time (min) Hydrograph Report 25 Original Permit Hydraflow Hydrographs Extension for Autodesk® Civil 3D® 2019 by Autodesk, Inc. v2019.2 Monday, 03 / 2 / 2020 Hyd. No. 7 Analysis Point B Post -Development Hydrograph type = SCS Runoff Peak discharge = 4.987 cfs Storm frequency = 10 yrs Time to peak = 744 min Time interval = 2 min Hyd. volume = 28,409 cuft Drainage area = 2.690 ac Curve number = 74* Basin Slope = 0.0 % Hydraulic length = 0 ft Tc method = TR55 Time of conc. (Tc) = 49.90 min Total precip. = 5.67 in Distribution = Type II Storm duration = 24 hrs Shape factor = 484 * Composite (Area/CN) _ [(2.690 x 74)] / 2.690 Q (cfs) 5.00 4.00 3.00 1.00 Analysis Point B Post -Development Hyd. No. 7 -- 10 Year Q (cfs) 5.00 4.00 3.00 2.00 1.00 0.00 0.00 0 120 240 360 480 600 720 840 960 1080 1200 1320 1440 1560 — Hyd No. 7 Time (min) Hydrograph Report 26 Original Permit Hydraflow Hydrographs Extension for Autodesk® Civil 3D® 2019 by Autodesk, Inc. v2019.2 Monday, 03 / 2 / 2020 Hyd. No. 8 Analysis Point C Pre -Development Hydrograph type = SCS Runoff Peak discharge = 17.85 cfs Storm frequency = 10 yrs Time to peak = 736 min Time interval = 2 min Hyd. volume = 86,559 cuft Drainage area = 7.250 ac Curve number = 78* Basin Slope = 0.0 % Hydraulic length = 0 ft Tc method = TR55 Time of conc. (Tc) = 39.10 min Total precip. = 5.67 in Distribution = Type II Storm duration = 24 hrs Shape factor = 484 * Composite (Area/CN) _ [(6.370 x 79) + (0.880 x 73)] / 7.250 Q (cfs) 18.00 15.00 12.00 M M 3.00 Analysis Point C Pre -Development Hyd. No. 8 -- 10 Year Q (cfs) 18.00 15.00 12.00 M . �� 3.00 0.00 120 240 360 480 600 720 840 960 1080 1200 1320 1440 1560 Hyd No. 8 Time (min) Hydrograph Report 27 Original Permit Hydraflow Hydrographs Extension for Autodesk® Civil 3D® 2019 by Autodesk, Inc. v2019.2 Monday, 03 / 2 / 2020 Hyd. No. 9 Analysis Point C Post -Development Hydrograph type = SCS Runoff Peak discharge = 5.290 cfs Storm frequency = 10 yrs Time to peak = 752 min Time interval = 2 min Hyd. volume = 35,931 cuft Drainage area = 3.380 ac Curve number = 74* Basin Slope = 0.0 % Hydraulic length = 0 ft Tc method = TR55 Time of conc. (Tc) = 63.20 min Total precip. = 5.67 in Distribution = Type II Storm duration = 24 hrs Shape factor = 484 * Composite (Area/CN) _ [(3.380 x 74)] / 3.380 Q (cfs) 6.00 5.00 4.00 3.00 rM 1.00 WITIN Analysis Point C Post -Development Hyd. No. 9 -- 10 Year Q (cfs) 6.00 5.00 4.00 3.00 2.00 1.00 EFIVIT21 0 120 240 360 480 600 720 840 960 1080 1200 1320 1440 1560 — Hyd No. 9 Time (min) 28 Hydrograph Summary Repo rlydraflowHydrographsExtension for Autodesk® Civil 3D®2019bbylAuodelskk,,Inc. v 019.2 Hyd. No. Hydrograph type (origin) Peak flow (cfs) Time interval (min) Time to Peak (min) Hyd. volume (cuft) Inflow hyd(s) Maximum elevation (ft) Total strge used (cuft) Hydrograph Description 1 SCS Runoff 283.62 2 716 612,484 ------ ------ ------ Pre Development 2 SCS Runoff 142.92 2 716 300,479 ------ ------ ------ Post Development -Bypass 3 SCS Runoff 196.39 2 716 446,987 ------ ------ ------ Post Development-BMP 4 Reservoir 47.56 2 724 444,463 3 1206.60 177,689 BMP Routing 5 Combine 186.95 2 716 744,941 2,4 ------ ------ Post Development -Total 6 SCS Runoff 13.55 2 726 47,308 ------ ------ ------ Analysis Point B Pre -Development 7 SCS Runoff 9.472 2 742 53,636 ------ ------ ------ Analysis Point B Post -Development 8 SCS Runoff 32.31 2 736 157,277 ------ ------ ------ Analysis Point C Pre -Development 9 SCS Runoff 10.07 2 752 67,837 ------ ------ ------ Analysis Point C Post -Development Pre -post calcs with helipad.gpw Return Period: 100 Year Monday, 03 / 2 / 2020 29 Hydrograph Report Original Permit Hydraflow Hydrographs Extension for Autodesk® Civil 3D® 2019 by Autodesk, Inc. v2019.2 Monday, 03 / 2 / 2020 Hyd. No. 1 Pre Development Hydrograph type = SCS Runoff Peak discharge = 283.62 cfs Storm frequency = 100 yrs Time to peak = 716 min Time interval = 2 min Hyd. volume = 612,484 cuft Drainage area = 26.380 ac Curve number = 85* Basin Slope = 0.0 % Hydraulic length = 0 ft Tc method = User Time of conc. (Tc) = 5.00 min Total precip. = 8.63 in Distribution = Type II Storm duration = 24 hrs Shape factor = 484 * Composite (Area/CN) _ [(8.300 x 98) + (18.080 x 79)] / 26.380 Pre Development Q (cfs) Hyd. No. 1 -- 100 Year Q (cfs) 320.00 280.00 240.00 200.00 160.00 120.00 80.00 40.00 0 00 320.00 280.00 240.00 200.00 160.00 120.00 80.00 40.00 0 00 0 120 240 360 480 600 720 840 960 1080 1200 — Hyd No. 1 Time (min) 30 Hydrograph Report Original Permit Hydraflow Hydrographs Extension for Autodesk® Civil 3D® 2019 by Autodesk, Inc. v2019.2 Monday, 03 / 2 / 2020 Hyd. No. 2 Post Development -Bypass Hydrograph type = SCS Runoff Peak discharge = 142.92 cfs Storm frequency = 100 yrs Time to peak = 716 min Time interval = 2 min Hyd. volume = 300,479 cuft Drainage area = 14.200 ac Curve number = 80* Basin Slope = 0.0 % Hydraulic length = 0 ft Tc method = User Time of conc. (Tc) = 5.00 min Total precip. = 8.63 in Distribution = Type II Storm duration = 24 hrs Shape factor = 484 * Composite (Area/CN) _ [(3.840 x 98) + (10.360 x 74)] / 14.200 Q (cfs) 160.00 140.00 120.00 100.00 40.00 20.00 Q (cfs) 160.00 140.00 120.00 100.00 40.00 20.00 0.00 0.00 0 120 240 360 480 600 720 840 960 1080 1200 1320 — Hyd No. 2 Time (min) 31 Hydrograph Report Original Permit Hydraflow Hydrographs Extension for Autodesk® Civil 3D® 2019 by Autodesk, Inc. v2019.2 Monday, 03 / 2 / 2020 Hyd. No. 3 Post Development-BMP Hydrograph type = SCS Runoff Peak discharge = 196.39 cfs Storm frequency = 100 yrs Time to peak = 716 min Time interval = 2 min Hyd. volume = 446,987 cuft Drainage area = 17.130 ac Curve number = 92* Basin Slope = 0.0 % Hydraulic length = 0 ft Tc method = User Time of conc. (Tc) = 5.00 min Total precip. = 8.63 in Distribution = Type II Storm duration = 24 hrs Shape factor = 484 Composite (Area/CN) _ [(13.090 x 98) + (4.040 x 74)] / 17.130 Post Development-BMP Q (cfs) Hyd. No. 3 -- 100 Year Q (cfs) 210.00 210.00 180.00 180.00 150.00 150.00 120.00 120.00 90.00 90.00 60.00 60.00 30.00 30.00 0.00 0.00 0 120 240 360 480 600 720 840 960 1080 1200 — Hyd No. 3 Time (min) Hydrograph Report 32 Original Permit Hydraflow Hydrographs Extension for Autodesk® Civil 3D® 2019 by Autodesk, Inc. v2019.2 Monday, 03 / 2 / 2020 Hyd. No. 4 BMP Routing Hydrograph type = Reservoir Peak discharge = 47.56 cfs Storm frequency = 100 yrs Time to peak = 724 min Time interval = 2 min Hyd. volume = 444,463 cuft Inflow hyd. No. = 3 - Post Development-BMP Max. Elevation = 1206.60 ft Reservoir name = Wet Pond Max. Storage = 177,689 cuft Storage Indication method used. Q (cfs) 210.00 180.00 150.00 120.00 Q (cfs) 210.00 180.00 150.00 120.00 30.00 0.00 - 0.00 0 120 240 360 480 600 720 840 960 1080 1200 1320 1440 1560 Time (min) — Hyd No. 4 Hyd No. 3 Total storage used = 177,689 cult Hydrograph Report 33 Original Permit Hydraflow Hydrographs Extension for Autodesk® Civil 3D® 2019 by Autodesk, Inc. v2019.2 Monday, 03 / 2 / 2020 Hyd. No. 5 Post Development -Total Hydrograph type = Combine Peak discharge = 186.95 cfs Storm frequency = 100 yrs Time to peak = 716 min Time interval = 2 min Hyd. volume = 744,941 cuft Inflow hyds. = 2, 4 Contrib. drain. area = 14.200 ac Q (cfs) 210.00 180.00 150.00 120.00 Q (cfs) 210.00 180.00 150.00 120.00 30.00 0.00 - 0.00 0 120 240 360 480 600 720 840 960 1080 1200 1320 1440 1560 Time (min) — Hyd No. 5 Hyd No. 2 Hyd No. 4 34 Hydrograph Report Original Permit Hydraflow Hydrographs Extension for Autodesk® Civil 3D® 2019 by Autodesk, Inc. v2019.2 Monday, 03 / 2 / 2020 Hyd. No. 6 Analysis Point B Pre -Development Hydrograph type = SCS Runoff Peak discharge = 13.55 cfs Storm frequency = 100 yrs Time to peak = 726 min Time interval = 2 min Hyd. volume = 47,308 cuft Drainage area = 2.100 ac Curve number = 79* Basin Slope = 0.0 % Hydraulic length = 0 ft Tc method = TR55 Time of conc. (Tc) = 20.20 min Total precip. = 8.63 in Distribution = Type II Storm duration = 24 hrs Shape factor = 484 * Composite (Area/CN) _ [(2.100 x 79)] / 2.100 Analysis Point B Pre -Development Q (cfs) Hyd. No. 6 -- 100 Year Q (cfs) 14.00 12.00 10.00 8.00 6.00 4.00 2.00 0 00 14.00 12.00 10.00 8.00 6.00 4.00 2.00 0 00 0 120 240 360 480 600 720 840 960 1080 1200 1320 1440 1560 Hyd No. 6 Time (min) Hydrograph Report 35 Original Permit Hydraflow Hydrographs Extension for Autodesk® Civil 3D® 2019 by Autodesk, Inc. v2019.2 Monday, 03 / 2 / 2020 Hyd. No. 7 Analysis Point B Post -Development Hydrograph type = SCS Runoff Peak discharge = 9.472 cfs Storm frequency = 100 yrs Time to peak = 742 min Time interval = 2 min Hyd. volume = 53,636 cuft Drainage area = 2.690 ac Curve number = 74* Basin Slope = 0.0 % Hydraulic length = 0 ft Tc method = TR55 Time of conc. (Tc) = 49.90 min Total precip. = 8.63 in Distribution = Type II Storm duration = 24 hrs Shape factor = 484 * Composite (Area/CN) _ [(2.690 x 74)] / 2.690 Q (cfs) 10.00 Were . UX 4.00 r w Analysis Point B Post -Development Hyd. No. 7 -- 100 Year Q (cfs) 10.00 N. We 4.00 r w 0.00 120 240 360 480 600 720 840 960 1080 1200 1320 1440 1560 Hyd No. 7 Time (min) Hydrograph Report 36 Original Permit Hydraflow Hydrographs Extension for Autodesk® Civil 3D® 2019 by Autodesk, Inc. v2019.2 Monday, 03 / 2 / 2020 Hyd. No. 8 Analysis Point C Pre -Development Hydrograph type = SCS Runoff Peak discharge = 32.31 cfs Storm frequency = 100 yrs Time to peak = 736 min Time interval = 2 min Hyd. volume = 157,277 cuft Drainage area = 7.250 ac Curve number = 78* Basin Slope = 0.0 % Hydraulic length = 0 ft Tc method = TR55 Time of conc. (Tc) = 39.10 min Total precip. = 8.63 in Distribution = Type II Storm duration = 24 hrs Shape factor = 484 * Composite (Area/CN) _ [(6.370 x 79) + (0.880 x 73)] / 7.250 Q (cfs) 35.00 'G • • 25.00 20.00 15.00 10.00 5.00 Q (cfs) 35.00 30.00 25.00 20.00 15.00 10.00 5.00 0.00 1 10.00 0 120 240 360 480 600 720 840 960 1080 1200 1320 1440 1560 — Hyd No. 8 Time (min) Hydrograph Report 37 Original Permit Hydraflow Hydrographs Extension for Autodesk® Civil 3D® 2019 by Autodesk, Inc. v2019.2 Monday, 03 / 2 / 2020 Hyd. No. 9 Analysis Point C Post -Development Hydrograph type = SCS Runoff Peak discharge = 10.07 cfs Storm frequency = 100 yrs Time to peak = 752 min Time interval = 2 min Hyd. volume = 67,837 cuft Drainage area = 3.380 ac Curve number = 74* Basin Slope = 0.0 % Hydraulic length = 0 ft Tc method = TR55 Time of conc. (Tc) = 63.20 min Total precip. = 8.63 in Distribution = Type II Storm duration = 24 hrs Shape factor = 484 * Composite (Area/CN) _ [(3.380 x 74)] / 3.380 Q (cfs) 12.00 10.00 M M 4.00 r M� Analysis Point C Post -Development Hyd. No. 9 -- 100 Year Q (cfs) 12.00 10.00 M . �� 4.00 r M� 0.00 120 240 360 480 600 720 840 960 1080 1200 1320 1440 1560 Hyd No. 9 Time (min) Hydraflow Rainfall Report 38 Original Permit Hydraflow Hydrographs Extension for Autodesk® Civil 3D® 2019 by Autodesk, Inc. v2019.2 Monday, 03 / 2 / 2020 Return Period Intensity -Duration -Frequency Equation Coefficients (FHA) (Yrs) B D E (N/A) 1 52.0631 11.7000 0.8619 -------- 2 66.4941 12.6000 0.8713 -------- 3 0.0000 0.0000 0.0000 -------- 5 0.0000 0.0000 0.0000 -------- 10 71.9699 12.4000 0.8031 -------- 25 66.3798 11.3000 0.7470 -------- 50 59.6913 10.1000 0.6967 -------- 100 55.6813 9.2000 0.6564 -------- File name: Morganton.IDF Intensity = B / (Tc + D)^E Return Period Intensity Values (in/hr) (Yrs) 6 min 10 16 20 26 30 36 40 46 60 66 60 1 4.60 3.67 3.07 2.65 2.33 2.09 1.90 1.74 1.60 1.49 1.39 1.31 2 5.47 4.40 3.69 3.19 2.82 2.53 2.30 2.11 1.95 1.81 1.69 1.59 3 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 5 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 10 7.26 5.93 5.04 4.41 3.93 3.55 3.25 2.99 2.78 2.60 2.45 2.31 25 8.25 6.76 5.77 5.07 4.54 4.12 3.78 3.50 3.27 3.07 2.89 2.74 50 9.01 7.38 6.32 5.57 5.00 4.56 4.20 3.90 3.65 3.44 3.25 3.09 100 9.76 8.00 6.88 6.08 5.48 5.01 4.63 4.32 4.05 3.82 3.62 3.45 Tc = time in minutes. Values may exceed 60. Precip. file name: R:\333\39004-NCNG MORGANTON RRC\Calcs\Stormwater\Morganton.pcp Storm Rainfall Precipitation Table (in) Distribution 1-yr 2-yr 3-yr 6-yr 10-yr 26-yr 60-yr 100-yr SCS 24-hour 3.15 3.83 0.00 4.43 5.67 6.79 7.70 8.63 SCS 6-Hr 2.06 2.48 0.00 3.11 3.60 4.35 4.98 5.66 Huff-1 st 0.00 0.00 0.00 2.75 0.00 0.00 0.00 0.00 Huff-2nd 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Huff-3rd 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Huff-4th 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Huff-Indy 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Custom 0.00 0.00 0.00 2.80 0.00 0.00 0.00 0.00 Hydraflow Table of Contents Pre -post calcs MOV Expansion-GWF.gpw MOV Exr)ansion Hydraflow Hydrographs Extension for AUtodeskS Civil 3DO 2019 by Autodesk, Inc. v2019.2 Wednesday, 07 / 14 / 2021 Watershed Model Schematic...................................................................................... 1 Hydrograph Return Period Recap............................................................................. 2 1 -Year HydrographReports................................................................................................................... 3 Hydrograph No. 1, SCS Runoff, Pre Development.................................................................. 3 Hydrograph No. 2, SCS Runoff, Post Development -Bypass .................................................... 4 Hydrograph No. 3, SCS Runoff, Post Development-BMP........................................................ 5 Hydrograph No. 4, Reservoir, BMP Routing............................................................................. 6 Hydrograph No. 5, Combine, Post Development-Total............................................................ 7 Hydrograph No. 6, SCS Runoff, Analysis Point B Post -Development ...................................... 8 Hydrograph No. 7, Reservoir, Wet Pond 2............................................................................... 9 Hydrograph No. 8, SCS Runoff, MOV Pre Development....................................................... 10 Hydrograph No. 9, SCS Runoff, MOV Bypass....................................................................... 11 Hydrograph No. 10, Combine, MOV COMBINED.................................................................. 12 2 - Year HydrographReports................................................................................................................. 13 Hydrograph No. 1, SCS Runoff, Pre Development................................................................ 13 Hydrograph No. 2, SCS Runoff, Post Development -Bypass .................................................. 14 Hydrograph No. 3, SCS Runoff, Post Development-BMP...................................................... 15 Hydrograph No. 4, Reservoir, BMP Routing........................................................................... 16 Hydrograph No. 5, Combine, Post Development-Total.......................................................... 17 Hydrograph No. 6, SCS Runoff, Analysis Point B Post -Development .................................... 18 Hydrograph No. 7, Reservoir, Wet Pond 2............................................................................. 19 Hydrograph No. 8, SCS Runoff, MOV Pre Development....................................................... 20 Hydrograph No. 9, SCS Runoff, MOV Bypass....................................................................... 21 Hydrograph No. 10, Combine, MOV COMBINED.................................................................. 22 10 -Year HydrographReports................................................................................................................. 23 Hydrograph No. 1, SCS Runoff, Pre Development................................................................ 23 Hydrograph No. 2, SCS Runoff, Post Development -Bypass .................................................. 24 Hydrograph No. 3, SCS Runoff, Post Development-BMP...................................................... 25 Hydrograph No. 4, Reservoir, BMP Routing........................................................................... 26 Hydrograph No. 5, Combine, Post Development-Total.......................................................... 27 Hydrograph No. 6, SCS Runoff, Analysis Point B Post -Development .................................... 28 Hydrograph No. 7, Reservoir, Wet Pond 2............................................................................. 29 Hydrograph No. 8, SCS Runoff, MOV Pre Development....................................................... 30 Hydrograph No. 9, SCS Runoff, MOV Bypass....................................................................... 31 Hydrograph No. 10, Combine, MOV COMBINED.................................................................. 32 100 - Year HydrographReports................................................................................................................. 33 Hydrograph No. 1, SCS Runoff, Pre Development................................................................ 33 Hydrograph No. 2, SCS Runoff, Post Development -Bypass .................................................. 34 Hydrograph No. 3, SCS Runoff, Post Development-BMP...................................................... 35 Contents continued... Pre -post calcs MOV Expansion-GWF.gpw MOV Expansion Hydrograph No. 4, Reservoir, BMP Routing........................................................................... 36 Hydrograph No. 5, Combine, Post Development-Total.......................................................... 37 Hydrograph No. 6, SCS Runoff, Analysis Point B Post -Development .................................... 38 Hydrograph No. 7, Reservoir, Wet Pond 2............................................................................. 39 Hydrograph No. 8, SCS Runoff, MOV Pre Development....................................................... 40 Hydrograph No. 9, SCS Runoff, MOV Bypass....................................................................... 41 Hydrograph No. 10, Combine, MOV COMBINED.................................................................. 42 OFReport.................................................................................................................. 43 Watershed Model Schematic MOV Expansion Hydraflow Hydrographs Extension for Autodesk@ Civil 3D@ 2019 by Autodesk, Inc. v2019.2 ED C 8 9 6 5 10 Project: Pre -post calcs MOV Expansion-GWF.gpw Wednesday, 07 / 14 / 2021 Hydrograph Return Period RI MOV Expansion y ra o ydrographs Extension for Autodesk@ Civil 3D@ 2019 by Autodesk, Inc. v2019.2 Hyd. Hydrograph Inflow Peak Outflow (cfs) Hydrograph No. type hyd(s) Description (origin) 1-yr 2-yr 3-yr 5-yr 10-yr 25-yr 50-yr 100-yr 1 SCS Runoff ------ 76.00 101.42 ------- ------- 171.35 ------- ------- 283.62 Pre Development 2 SCS Runoff ------ 32.83 45.51 ------- ------- 82.30 ------- ------- 142.92 Post Development -Bypass 3 SCS Runoff ------ 63.63 80.39 ------- ------- 125.26 ------- ------- 196.39 Post Development-BMP 4 Reservoir 3 23.16 38.82 ------- ------- 42.85 ------- ------- 47.56 BMP Routing 5 Combine 2,4 45.69 80.91 ------- ------- 123.31 ------- ------- 186.95 Post Development -Total 6 SCS Runoff ------ 17.71 22.22 ------- ------- 34.28 ------- ------- 53.42 Analysis Point B Post -Development 7 Reservoir 6 2.804 4.367 ------- ------- 6.876 ------- ------- 32.44 Wet Pond 2 8 SCS Runoff ------ 44.16 62.28 ------- ------- 114.30 ------- ------- 200.77 MOV Pre Development 9 SCS Runoff ------ 40.80 57.55 ------- ------- 105.62 ------- ------- 185.52 MOV Bypass 10 Combine 7,9 43.56 61.91 ------- ------- 112.49 ------- ------- 215.84 MOV COMBINED Proj. file: Pre -post calcs MOV Expansion-GWF.gpw Wednesday, 07 / 14 / 2021 3 Hydrograph Report MOV Expansion Hydraflow Hydrographs Extension for AUtodeskS Civil 3DO 2019 by Autodesk, Inc. v2019.2 Wednesday, 07 / 14 / 2021 Hyd. No. 1 Pre Development Hydrograph type = SCS Runoff Peak discharge = 76.00 cfs Storm frequency = 1 yrs Time to peak = 716 min Time interval = 2 min Hyd. volume = 153,965 cuft Drainage area = 26.380 ac Curve number = 85* Basin Slope = 0.0 % Hydraulic length = 0 ft Tc method = User Time of conc. (Tc) = 5.00 min Total precip. = 3.15 in Distribution = Type II Storm duration = 24 hrs Shape factor = 484 Composite (Area/CN) _ [(8.300 x 98) + (18.080 x 79)] / 26.380 Q (cfs) 80.00 70.00 50.00 40.00 30.00 10.00 Q (cfs) 80.00 70.00 50.00 40.00 30.00 20.00 10.00 0.00 0.00 0 120 240 360 480 600 720 840 960 1080 1200 1320 1440 — Hyd No. 1 Time (min) Hydrograph Report 4 MOV Expansion Hydraflow Hydrographs Extension for AUtodeskS Civil 3DO 2019 by Autodesk, Inc. v2019.2 Wednesday, 07 / 14 / 2021 Hyd. No. 2 Post Development -Bypass Hydrograph type = SCS Runoff Peak discharge = 32.83 cfs Storm frequency = 1 yrs Time to peak = 718 min Time interval = 2 min Hyd. volume = 65,895 cuft Drainage area = 14.200 ac Curve number = 80* Basin Slope = 0.0 % Hydraulic length = 0 ft Tc method = User Time of conc. (Tc) = 5.00 min Total precip. = 3.15 in Distribution = Type II Storm duration = 24 hrs Shape factor = 484 Composite (Area/CN) _ [(3.840 x 98) + (10.360 x 74)] / 14.200 Q (cfs) 35.00 30.00 25.00 15.00 10.00 5.00 Q (cfs) 35.00 30.00 25.00 20.00 15.00 10.00 5.00 0.00 0.00 0 120 240 360 480 600 720 840 960 1080 1200 1320 1440 1560 — Hyd No. 2 Time (min) 5 Hydrograph Report MOV Expansion Hydraflow Hydrographs Extension for AUtodeskS Civil 3DO 2019 by Autodesk, Inc. v2019.2 Wednesday, 07 / 14 / 2021 Hyd. No. 3 Post Development-BMP Hydrograph type = SCS Runoff Peak discharge = 63.63 cfs Storm frequency = 1 yrs Time to peak = 716 min Time interval = 2 min Hyd. volume = 134,263 cuft Drainage area = 17.130 ac Curve number = 92* Basin Slope = 0.0 % Hydraulic length = 0 ft Tc method = User Time of conc. (Tc) = 5.00 min Total precip. = 3.15 in Distribution = Type II Storm duration = 24 hrs Shape factor = 484 Composite (Area/CN) _ [(13.090 x 98) + (4.040 x 74)] / 17.130 Post Development-BMP Q (cfs) Hyd. No. 3 -- 1 Year Q (cfs) 70.00 70.00 60.00 60.00 50.00 50.00 40.00 40.00 30.00 30.00 20.00 20.00 10.00 10.00 0.00 0.00 0 120 240 360 480 600 720 840 960 1080 1200 — Hyd No. 3 Time (min) Hydrograph Report 6 MOV Expansion Hydraflow Hydrographs Extension for AUtodeskS Civil 3DO 2019 by Autodesk, Inc. v2019.2 Wednesday, 07 / 14 / 2021 Hyd. No. 4 BMP Routing Hydrograph type = Reservoir Peak discharge = 23.16 cfs Storm frequency = 1 yrs Time to peak = 724 min Time interval = 2 min Hyd. volume = 131,779 cuft Inflow hyd. No. = 3 - Post Development-BMP Max. Elevation = 1203.68 ft Reservoir name = Wet Pond Max. Storage = 66,330 cuft Storage Indication method used BMP Routing 1 1 1 --- I---------- 1 1 1 11 1 1 :1 1 •.1 11 1 Ol • 1 •1 11 . 1 ::1 1 Hydrograph Report 7 MOV Expansion Hydraflow Hydrographs Extension for AUtodeskS Civil 3DO 2019 by Autodesk, Inc. v2019.2 Hyd. No. 5 Post Development -Total Hydrograph type = Combine Peak discharge Storm frequency = 1 yrs Time to peak Time interval = 2 min Hyd. volume Inflow hyds. = 2, 4 Contrib. drain. area Post Development -Total Wednesday, 07 / 14 / 2021 = 45.69 cfs = 720 min = 197,673 cuft = 14.200 ac Q (cfs) Hyd. No. 5 -- 1 Year Q (cfs) 50.00 50.00 40.00 40.00 30.00 30.00 20.00 20.00 10.00 10.00 0.00 0.00 0 120 240 360 480 600 720 840 960 1080 1200 1320 1440 1560 Time (min) — Hyd No. 5 — Hyd No. 2 Hyd No. 4 8 Hydrograph Report MOV Expansion Hydraflow Hydrographs Extension for AUtodeskS Civil 3DO 2019 by Autodesk, Inc. v2019.2 Wednesday, 07 / 14 / 2021 Hyd. No. 6 Analysis Point B Post -Development Hydrograph type = SCS Runoff Peak discharge = 17.71 cfs Storm frequency = 1 yrs Time to peak = 716 min Time interval = 2 min Hyd. volume = 37,780 cuft Drainage area = 4.630 ac Curve number = 93* Basin Slope = 0.0 % Hydraulic length = 0 ft Tc method = User Time of conc. (Tc) = 5.00 min Total precip. = 3.15 in Distribution = Type II Storm duration = 24 hrs Shape factor = 484 Composite (Area/CN) _ [(0.870 x 74) + (3.760 x 98)] / 4.630 Q (cfs) 18.00 15.00 12.00 •M .M 3.00 e 120 240 Hyd No. 6 Analysis Point B Post -Development Hyd. No. 6 -- 1 Year 360 480 600 Q (cfs) 18.00 15.00 12.00 M M 3.00 0.00 720 840 960 1080 1200 Time (min) Hydrograph Report 9 MOV Expansion Hydraflow Hydrographs Extension for AUtodeskS Civil 3DO 2019 by Autodesk, Inc. v2019.2 Wednesday, 07 / 14 / 2021 Hyd. No. 7 Wet Pond 2 Hydrograph type = Reservoir Peak discharge = 2.804 cfs Storm frequency = 1 yrs Time to peak = 726 min Time interval = 2 min Hyd. volume = 36,035 cuft Inflow hyd. No. = 6 - Analysis Point B Post-Develdp3nOibvation = 1212.82 ft Reservoir name = Wet Pond B Max. Storage = 20,707 cuft Storage Indication method used. Q (cfs) 18.00 15.00 12.00 M M 3.00 600 Hyd No. 7 Wet Pond 2 Hyd. No. 7 -- 1 Year Q (cfs) 18.00 15.00 12.00 3.00 0.00 1200 1800 2400 3000 3600 4200 4800 5400 6000 Time (min) — Hyd No. 6 ® Total storage used = 20,707 cult Hydrograph Report 10 MOV Expansion Hydraflow Hydrographs Extension for AUtodeskS Civil 3DO 2019 by Autodesk, Inc. v2019.2 Wednesday, 07 / 14 / 2021 Hyd. No. 8 MOV Pre Development Hydrograph type = SCS Runoff Peak discharge = 44.16 cfs Storm frequency = 1 yrs Time to peak = 724 min Time interval = 2 min Hyd. volume = 140,081 cuft Drainage area = 28.300 ac Curve number = 80* Basin Slope = 0.0 % Hydraulic length = 0 ft Tc method = User Time of conc. (Tc) = 19.30 min Total precip. = 3.15 in Distribution = Type II Storm duration = 24 hrs Shape factor = 484 Composite (Area/CN) = [(27.350 x 79) + (0.950 x 98)] / 28.300 MOV Pre Development Q (cfs) Hyd. No. 8 -- 1 Year Q (cfs) 50.00 50.00 40.00 40.00 30.00 30.00 20.00 20.00 10.00 10.00 0.00 0.00 0 120 240 360 480 600 720 840 960 1080 1200 1320 1440 1560 — Hyd No. 8 Time (min) Hydrograph Report 11 MOV Expansion Hydraflow Hydrographs Extension for AUtodeskS Civil 3DO 2019 by Autodesk, Inc. v2019.2 Wednesday, 07 / 14 / 2021 Hyd. No. 9 MOV Bypass Hydrograph type = SCS Runoff Peak discharge = 40.80 cfs Storm frequency = 1 yrs Time to peak = 724 min Time interval = 2 min Hyd. volume = 129,438 cuft Drainage area = 26.150 ac Curve number = 80* Basin Slope = 0.0 % Hydraulic length = 0 ft Tc method = TR55 Time of conc. (Tc) = 19.30 min Total precip. = 3.15 in Distribution = Type II Storm duration = 24 hrs Shape factor = 484 Composite (Area/CN) = [(25.410 x 79) + (0.740 x 98)] / 26.150 MOV Bypass Q (cfs) Hyd. No. 9 -- 1 Year Q (cfs) 50.00 50.00 40.00 40.00 30.00 30.00 20.00 20.00 10.00 10.00 0.00 0.00 0 120 240 360 480 600 720 840 960 1080 1200 1320 1440 1560 — Hyd No. 9 Time (min) Hydrograph Report 12 MOV Expansion Hydraflow Hydrographs Extension for AUtodeskS Civil 3DO 2019 by Autodesk, Inc. v2019.2 Hyd. No. 10 MOV COMBINED Hydrograph type = Combine Peak discharge Storm frequency = 1 yrs Time to peak Time interval = 2 min Hyd. volume Inflow hyds. = 7, 9 Contrib. drain. area MOV COMBINED Wednesday, 07 / 14 / 2021 = 43.56 cfs = 724 min = 165,473 cuft = 26.150 ac Q (cfs) Hyd. No. 10 -- 1 Year Q (cfs) 50.00 50.00 40.00 40.00 30.00 30.00 20.00 20.00 10.00 10.00 0.00 - 0.00 0 120 240 360 480 600 720 840 960 1080 1200 1320 1440 1560 Time (min) — Hyd No. 10 Hyd No. 7 Hyd No. 9 Hydrograph Report 13 MOV Expansion Hydraflow Hydrographs Extension for AUtodeskS Civil 3DO 2019 by Autodesk, Inc. v2019.2 Wednesday, 07 / 14 / 2021 Hyd. No. 1 Pre Development Hydrograph type = SCS Runoff Peak discharge = 101.42 cfs Storm frequency = 2 yrs Time to peak = 716 min Time interval = 2 min Hyd. volume = 207,061 cuft Drainage area = 26.380 ac Curve number = 85* Basin Slope = 0.0 % Hydraulic length = 0 ft Tc method = User Time of conc. (Tc) = 5.00 min Total precip. = 3.83 in Distribution = Type II Storm duration = 24 hrs Shape factor = 484 Composite (Area/CN) _ [(8.300 x 98) + (18.080 x 79)] / 26.380 Q (cfs) 120.00 100.00 40.00 rIt ee Pre Development Hyd. No. 1 -- 2 Year Q (cfs) 120.00 100.00 40.00 20.00 0.00 0.00 0 120 240 360 480 600 720 840 960 1080 1200 1320 1440 — Hyd No. 1 Time (min) Hydrograph Report 14 MOV Expansion Hydraflow Hydrographs Extension for AUtodeskS Civil 3DO 2019 by Autodesk, Inc. v2019.2 Wednesday, 07 / 14 / 2021 Hyd. No. 2 Post Development -Bypass Hydrograph type = SCS Runoff Peak discharge = 45.51 cfs Storm frequency = 2 yrs Time to peak = 716 min Time interval = 2 min Hyd. volume = 91,915 cuft Drainage area = 14.200 ac Curve number = 80* Basin Slope = 0.0 % Hydraulic length = 0 ft Tc method = User Time of conc. (Tc) = 5.00 min Total precip. = 3.83 in Distribution = Type II Storm duration = 24 hrs Shape factor = 484 Composite (Area/CN) _ [(3.840 x 98) + (10.360 x 74)] / 14.200 Post Development -Bypass Q (cfs) Hyd. No. 2 -- 2 Year Q (cfs) 50.00 50.00 40.00 40.00 30.00 30.00 20.00 20.00 10.00 10.00 0.00 - 0.00 0 120 240 360 480 600 720 840 960 1080 1200 1320 1440 1560 — Hyd No. 2 Time (min) 15 Hydrograph Report MOV Expansion Hydraflow Hydrographs Extension for AUtodeskS Civil 3DO 2019 by Autodesk, Inc. v2019.2 Wednesday, 07 / 14 / 2021 Hyd. No. 3 Post Development-BMP Hydrograph type = SCS Runoff Peak discharge = 80.39 cfs Storm frequency = 2 yrs Time to peak = 716 min Time interval = 2 min Hyd. volume = 172,182 cuft Drainage area = 17.130 ac Curve number = 92* Basin Slope = 0.0 % Hydraulic length = 0 ft Tc method = User Time of conc. (Tc) = 5.00 min Total precip. = 3.83 in Distribution = Type II Storm duration = 24 hrs Shape factor = 484 Composite (Area/CN) _ [(13.090 x 98) + (4.040 x 74)] / 17.130 Post Development-BMP Q (cfs) Hyd. No. 3 -- 2 Year Q (cfs) 90.00 90.00 80.00 80.00 70.00 70.00 60.00 60.00 50.00 50.00 40.00 40.00 30.00 30.00 20.00 20.00 10.00 10.00 0.00 0.00 0 120 240 360 480 600 720 840 960 1080 1200 — Hyd No. 3 Time (min) Hydrograph Report 16 MOV Expansion Hydraflow Hydrographs Extension for AUtodeskS Civil 3DO 2019 by Autodesk, Inc. v2019.2 Wednesday, 07 / 14 / 2021 Hyd. No. 4 BMP Routing Hydrograph type = Reservoir Peak discharge = 38.82 cfs Storm frequency = 2 yrs Time to peak = 722 min Time interval = 2 min Hyd. volume = 169,689 cuft Inflow hyd. No. = 3 - Post Development-BMP Max. Elevation = 1204.02 ft Reservoir name = Wet Pond Max. Storage = 78,103 cuft Storage Indication method used. Q (cfs) 90.00 80.00 70.00 60.00 50.00 40.00 30.00 20.00 BMP Routing Hyd. No. 4 -- 2 Year 1 1 �1 .1 �:1 .11 1 :�1 •.1 1:1 11 1 ��1 .1 Q (cfs) 90.00 80.00 70.00 60.00 50.00 40.00 30.00 20.00 Hydrograph Report 17 MOV Expansion Hydraflow Hydrographs Extension for AUtodeskS Civil 3DO 2019 by Autodesk, Inc. v2019.2 Wednesday, 07 / 14 / 2021 Hyd. No. 5 Post Development -Total Hydrograph type = Combine Peak discharge = 80.91 cfs Storm frequency = 2 yrs Time to peak = 718 min Time interval = 2 min Hyd. volume = 261,604 cuft Inflow hyds. = 2, 4 Contrib. drain. area = 14.200 ac Q (cfs) 90.00 80.00 70.00 60.00 50.00 40.00 30.00 20.00 Post Development -Total Hyd. No. 5 -- 2 Year Q (cfs) 90.00 80.00 70.00 60.00 50.00 40.00 30.00 20.00 10.00 1 moll is I I I I I I 110.00 0.00 - - 0.00 0 120 240 360 480 600 720 840 960 1080 1200 1320 1440 1560 — Hyd No. 5 — Hyd No. 2 Hyd No. 4 Time (min) 18 Hydrograph Report MOV Expansion Hydraflow Hydrographs Extension for AUtodeskS Civil 3DO 2019 by Autodesk, Inc. v2019.2 Wednesday, 07 / 14 / 2021 Hyd. No. 6 Analysis Point B Post -Development Hydrograph type = SCS Runoff Peak discharge = 22.22 cfs Storm frequency = 2 yrs Time to peak = 716 min Time interval = 2 min Hyd. volume = 48,130 cuft Drainage area = 4.630 ac Curve number = 93* Basin Slope = 0.0 % Hydraulic length = 0 ft Tc method = User Time of conc. (Tc) = 5.00 min Total precip. = 3.83 in Distribution = Type II Storm duration = 24 hrs Shape factor = 484 Composite (Area/CN) _ [(0.870 x 74) + (3.760 x 98)] / 4.630 Analysis Point B Post -Development Q (cfs) Hyd. No. 6 -- 2 Year Q (cfs) 24.00 24.00 20.00 20.00 16.00 16.00 12.00 12.00 8.00 8.00 4.00 4.00 0.00 0.00 0 120 240 360 480 600 720 840 960 1080 1200 — Hyd No. 6 Time (min) Hydrograph Report 19 MOV Expansion Hydraflow Hydrographs Extension for AUtodeskS Civil 3DO 2019 by Autodesk, Inc. v2019.2 Wednesday, 07 / 14 / 2021 Hyd. No. 7 Wet Pond 2 Hydrograph type = Reservoir Peak discharge = 4.367 cfs Storm frequency = 2 yrs Time to peak = 726 min Time interval = 2 min Hyd. volume = 46,368 cuft Inflow hyd. No. = 6 - Analysis Point B Post-Develdp3nOibvation = 1213.29 ft Reservoir name = Wet Pond B Max. Storage = 25,786 cuft Storage Indication method used. Wet Pond 2 Q (cfs) Hyd. No. 7 -- 2 Year Q (cfs) 24.00 24.00 20.00 20.00 16.00 16.00 12.00 12.00 8.00 8.00 4.00 4.00 0.00 - 0.00 0 480 960 1440 1920 2400 2880 3360 3840 4320 4800 Time (min) — Hyd No. 7 — Hyd No. 6 ® Total storage used = 25,786 cult Hydrograph Report 20 MOV Expansion Hydraflow Hydrographs Extension for AUtodeskS Civil 3DO 2019 by Autodesk, Inc. v2019.2 Wednesday, 07 / 14 / 2021 Hyd. No. 8 MOV Pre Development Hydrograph type = SCS Runoff Peak discharge = 62.28 cfs Storm frequency = 2 yrs Time to peak = 724 min Time interval = 2 min Hyd. volume = 195,395 cuft Drainage area = 28.300 ac Curve number = 80* Basin Slope = 0.0 % Hydraulic length = 0 ft Tc method = User Time of conc. (Tc) = 19.30 min Total precip. = 3.83 in Distribution = Type II Storm duration = 24 hrs Shape factor = 484 Composite (Area/CN) _ [(27.350 x 79) + (0.950 x 98)] / 28.300 Q (cfs) 70.00 50.00 40.00 30.00 10.00 Q (cfs) 70.00 •• •• 50.00 40.00 30.00 20.00 10.00 0.00 0.00 0 120 240 360 480 600 720 840 960 1080 1200 1320 1440 1560 — Hyd No. 8 Time (min) Hydrograph Report 21 MOV Expansion Hydraflow Hydrographs Extension for AUtodeskS Civil 3DO 2019 by Autodesk, Inc. v2019.2 Wednesday, 07 / 14 / 2021 Hyd. No. 9 MOV Bypass Hydrograph type = SCS Runoff Peak discharge = 57.55 cfs Storm frequency = 2 yrs Time to peak = 724 min Time interval = 2 min Hyd. volume = 180,550 cuft Drainage area = 26.150 ac Curve number = 80* Basin Slope = 0.0 % Hydraulic length = 0 ft Tc method = TR55 Time of conc. (Tc) = 19.30 min Total precip. = 3.83 in Distribution = Type II Storm duration = 24 hrs Shape factor = 484 Composite (Area/CN) _ [(25.410 x 79) + (0.740 x 98)] / 26.150 MOV Bypass Q (cfs) Hyd. No. 9 -- 2 Year Q (cfs) 60.00 60.00 50.00 50.00 40.00 40.00 30.00 30.00 20.00 20.00 10.00 10.00 0.00 0.00 0 120 240 360 480 600 720 840 960 1080 1200 1320 1440 1560 — Hyd No. 9 Time (min) Hydrograph Report 22 MOV Expansion Hydraflow Hydrographs Extension for AUtodeskS Civil 3DO 2019 by Autodesk, Inc. v2019.2 Wednesday, 07 / 14 / 2021 Hyd. No. 10 MOV COMBINED Hydrograph type = Combine Peak discharge = 61.91 cfs Storm frequency = 2 yrs Time to peak = 724 min Time interval = 2 min Hyd. volume = 226,918 cuft Inflow hyds. = 7, 9 Contrib. drain. area = 26.150 ac Q (cfs) 70.00 50.00 40.00 30.00 10.00 Q (cfs) 70.00 *1 01 50.00 40.00 30.00 20.00 10.00 0.00 0.00 0 120 240 360 480 600 720 840 960 1080 1200 1320 1440 1560 Time (min) — Hyd No. 10 Hyd No. 7 — Hyd No. 9 23 Hydrograph Report MOV Expansion Hydraflow Hydrographs Extension for AUtodeskS Civil 3DO 2019 by Autodesk, Inc. v2019.2 Wednesday, 07 / 14 / 2021 Hyd. No. 1 Pre Development Hydrograph type = SCS Runoff Peak discharge = 171.35 cfs Storm frequency = 10 yrs Time to peak = 716 min Time interval = 2 min Hyd. volume = 358,388 cuft Drainage area = 26.380 ac Curve number = 85* Basin Slope = 0.0 % Hydraulic length = 0 ft Tc method = User Time of conc. (Tc) = 5.00 min Total precip. = 5.67 in Distribution = Type II Storm duration = 24 hrs Shape factor = 484 Composite (Area/CN) _ [(8.300 x 98) + (18.080 x 79)] / 26.380 Q (cfs) 180.00 160.00 140.00 120.00 100.00 80.00 60.00 40.00 Q (cfs) 180.00 160.00 140.00 120.00 100.00 80.00 60.00 40.00 20.00 20.00 0.00 0.00 0 120 240 360 480 600 720 840 960 1080 1200 1320 — Hyd No. 1 Time (min) 24 Hydrograph Report MOV Expansion Hydraflow Hydrographs Extension for AUtodeskS Civil 3DO 2019 by Autodesk, Inc. v2019.2 Wednesday, 07 / 14 / 2021 Hyd. No. 2 Post Development -Bypass Hydrograph type = SCS Runoff Peak discharge = 82.30 cfs Storm frequency = 10 yrs Time to peak = 716 min Time interval = 2 min Hyd. volume = 168,404 cuft Drainage area = 14.200 ac Curve number = 80* Basin Slope = 0.0 % Hydraulic length = 0 ft Tc method = User Time of conc. (Tc) = 5.00 min Total precip. = 5.67 in Distribution = Type II Storm duration = 24 hrs Shape factor = 484 Composite (Area/CN) _ [(3.840 x 98) + (10.360 x 74)] / 14.200 Q (cfs) 90.00 80.00 70.00 60.00 50.00 40.00 30.00 20.00 Post Development -Bypass Hyd. No. 2 -- 10 Year Q (cfs) 90.00 80.00 70.00 60.00 50.00 40.00 30.00 20.00 0 120 240 360 480 600 720 840 960 1080 1200 1320 — Hyd No. 2 Time (min) 25 Hydrograph Report MOV Expansion Hydraflow Hydrographs Extension for AUtodeskS Civil 3DO 2019 by Autodesk, Inc. v2019.2 Wednesday, 07 / 14 / 2021 Hyd. No. 3 Post Development-BMP Hydrograph type = SCS Runoff Peak discharge = 125.26 cfs Storm frequency = 10 yrs Time to peak = 716 min Time interval = 2 min Hyd. volume = 276,630 cuft Drainage area = 17.130 ac Curve number = 92* Basin Slope = 0.0 % Hydraulic length = 0 ft Tc method = User Time of conc. (Tc) = 5.00 min Total precip. = 5.67 in Distribution = Type II Storm duration = 24 hrs Shape factor = 484 Composite (Area/CN) _ [(13.090 x 98) + (4.040 x 74)] / 17.130 Post Development-BMP Q (cfs) Hyd. No. 3 -- 10 Year Q (cfs) 140.00 140.00 120.00 120.00 100.00 100.00 80.00 80.00 60.00 60.00 40.00 40.00 20.00 20.00 0.00 0.00 0 120 240 360 480 600 720 840 960 1080 1200 — Hyd No. 3 Time (min) Hydrograph Report 26 MOV Expansion Hydraflow Hydrographs Extension for AUtodeskS Civil 3DO 2019 by Autodesk, Inc. v2019.2 Wednesday, 07 / 14 / 2021 Hyd. No. 4 BMP Routing Hydrograph type = Reservoir Peak discharge = 42.85 cfs Storm frequency = 10 yrs Time to peak = 724 min Time interval = 2 min Hyd. volume = 274,122 cuft Inflow hyd. No. = 3 - Post Development-BMP Max. Elevation = 1205.10 ft Reservoir name = Wet Pond Max. Storage = 116,964 cuft Storage Indication method used. Q (cfs) 140.00 120.00 100.00 40.00 Q (cfs) 140.00 120.00 100.00 •• •• 40.00 20.00 0.00 0.00 0 120 240 360 480 600 720 840 960 1080 1200 1320 1440 1560 Time (min) — Hyd No. 4 Hyd No. 3 ® Total storage used = 116,964 cult Hydrograph Report 27 MOV Expansion Hydraflow Hydrographs Extension for AUtodeskS Civil 3DO 2019 by Autodesk, Inc. v2019.2 Wednesday, 07 / 14 / 2021 Hyd. No. 5 Post Development -Total Hydrograph type = Combine Peak discharge = 123.31 cfs Storm frequency = 10 yrs Time to peak = 716 min Time interval = 2 min Hyd. volume = 442,526 cuft Inflow hyds. = 2, 4 Contrib. drain. area = 14.200 ac Q (cfs) 140.00 120.00 100.00 40.00 Q (cfs) 140.00 120.00 100.00 •• •• 40.00 20.00 0.00 0.00 0 120 240 360 480 600 720 840 960 1080 1200 1320 1440 1560 Time (min) — Hyd No. 5 Hyd No. 2 Hyd No. 4 28 Hydrograph Report MOV Expansion Hydraflow Hydrographs Extension for AUtodeskS Civil 3DO 2019 by Autodesk, Inc. v2019.2 Wednesday, 07 / 14 / 2021 Hyd. No. 6 Analysis Point B Post -Development Hydrograph type = SCS Runoff Peak discharge = 34.28 cfs Storm frequency = 10 yrs Time to peak = 716 min Time interval = 2 min Hyd. volume = 76,531 cuft Drainage area = 4.630 ac Curve number = 93* Basin Slope = 0.0 % Hydraulic length = 0 ft Tc method = User Time of conc. (Tc) = 5.00 min Total precip. = 5.67 in Distribution = Type II Storm duration = 24 hrs Shape factor = 484 Composite (Area/CN) _ [(0.870 x 74) + (3.760 x 98)] / 4.630 Analysis Point B Post -Development Q (cfs) Hyd. No. 6 -- 10 Year Q (cfs) 35.00 35.00 30.00 30.00 25.00 25.00 20.00 20.00 15.00 15.00 10.00 10.00 5.00 5.00 0.00 0.00 0 120 240 360 480 600 720 840 960 1080 1200 — Hyd No. 6 Time (min) Hydrograph Report 29 MOV Expansion Hydraflow Hydrographs Extension for AUtodeskS Civil 3DO 2019 by Autodesk, Inc. v2019.2 Wednesday, 07 / 14 / 2021 Hyd. No. 7 Wet Pond 2 Hydrograph type = Reservoir Peak discharge = 6.876 cfs Storm frequency = 10 yrs Time to peak = 726 min Time interval = 2 min Hyd. volume = 74,738 cuft Inflow hyd. No. = 6 - Analysis Point B Post-Develdp3nOibvation = 1214.48 ft Reservoir name = Wet Pond B Max. Storage = 39,928 cuft Storage Indication method used. Wet Pond 2 Hydrograph Report 30 MOV Expansion Hydraflow Hydrographs Extension for AUtodeskS Civil 3DO 2019 by Autodesk, Inc. v2019.2 Wednesday, 07 / 14 / 2021 Hyd. No. 8 MOV Pre Development Hydrograph type = SCS Runoff Peak discharge = 114.30 cfs Storm frequency = 10 yrs Time to peak = 724 min Time interval = 2 min Hyd. volume = 357,996 cuft Drainage area = 28.300 ac Curve number = 80* Basin Slope = 0.0 % Hydraulic length = 0 ft Tc method = User Time of conc. (Tc) = 19.30 min Total precip. = 5.67 in Distribution = Type II Storm duration = 24 hrs Shape factor = 484 Composite (Area/CN) _ [(27.350 x 79) + (0.950 x 98)] / 28.300 MOV Pre Development Q (cfs) Hyd. No. 8 -- 10 Year Q (cfs) 120.00 120.00 100.00 100.00 80.00 80.00 60.00 60.00 40.00 40.00 20.00 20.00 0.00 0.00 0 120 240 360 480 600 720 840 960 1080 1200 1320 1440 1560 — Hyd No. 8 Time (min) Hydrograph Report 31 MOV Expansion Hydraflow Hydrographs Extension for AUtodeskS Civil 3DO 2019 by Autodesk, Inc. v2019.2 Wednesday, 07 / 14 / 2021 Hyd. No. 9 MOV Bypass Hydrograph type = SCS Runoff Peak discharge = 105.62 cfs Storm frequency = 10 yrs Time to peak = 724 min Time interval = 2 min Hyd. volume = 330,799 cuft Drainage area = 26.150 ac Curve number = 80* Basin Slope = 0.0 % Hydraulic length = 0 ft Tc method = TR55 Time of conc. (Tc) = 19.30 min Total precip. = 5.67 in Distribution = Type II Storm duration = 24 hrs Shape factor = 484 Composite (Area/CN) _ [(25.410 x 79) + (0.740 x 98)] / 26.150 MOV Bypass Q (cfs) Hyd. No. 9 -- 10 Year Q (cfs) 120.00 120.00 100.00 100.00 80.00 80.00 60.00 60.00 40.00 40.00 20.00 20.00 0.00 0.00 0 120 240 360 480 600 720 840 960 1080 1200 1320 1440 1560 — Hyd No. 9 Time (min) Hydrograph Report 32 MOV Expansion Hydraflow Hydrographs Extension for AUtodeskS Civil 3DO 2019 by Autodesk, Inc. v2019.2 Hyd. No. 10 MOV COMBINED Hydrograph type = Combine Peak discharge Storm frequency = 10 yrs Time to peak Time interval = 2 min Hyd. volume Inflow hyds. = 7, 9 Contrib. drain. area Q (cfs) 120.00 100.00 40.00 rIt ee Wednesday, 07 / 14 / 2021 = 112.49 cfs = 724 min = 405,537 cuft = 26.150 ac Q (cfs) 120.00 100.00 40.00 20.00 rIraa 840 960 1080 1200 1320 1440 1560 Time (min) Hyd No. 9 33 Hydrograph Report MOV Expansion Hydraflow Hydrographs Extension for AUtodeskS Civil 3DO 2019 by Autodesk, Inc. v2019.2 Wednesday, 07 / 14 / 2021 Hyd. No. 1 Pre Development Hydrograph type = SCS Runoff Peak discharge = 283.62 cfs Storm frequency = 100 yrs Time to peak = 716 min Time interval = 2 min Hyd. volume = 612,484 cuft Drainage area = 26.380 ac Curve number = 85* Basin Slope = 0.0 % Hydraulic length = 0 ft Tc method = User Time of conc. (Tc) = 5.00 min Total precip. = 8.63 in Distribution = Type II Storm duration = 24 hrs Shape factor = 484 Composite (Area/CN) _ [(8.300 x 98) + (18.080 x 79)] / 26.380 Pre Development Q (cfs) Hyd. No. 1 -- 100 Year Q (cfs) 320.00 280.00 240.00 200.00 160.00 120.00 80.00 40.00 0 00 320.00 280.00 240.00 200.00 160.00 120.00 80.00 40.00 0 00 0 120 240 360 480 600 720 840 960 1080 1200 — Hyd No. 1 Time (min) Hydrograph Report MOV E3 pansion MOV Expansion Hydraflow Hydrographs Extension for AUtodeskS Civil 3DO 2019 by Autodesk, Inc. v2019.2 Wednesday, 07 / 14 / 2021 Hyd. No. 2 Post Development -Bypass Hydrograph type = SCS Runoff Peak discharge = 142.92 cfs Storm frequency = 100 yrs Time to peak = 716 min Time interval = 2 min Hyd. volume = 300,479 cuft Drainage area = 14.200 ac Curve number = 80* Basin Slope = 0.0 % Hydraulic length = 0 ft Tc method = User Time of conc. (Tc) = 5.00 min Total precip. = 8.63 in Distribution = Type II Storm duration = 24 hrs Shape factor = 484 Composite (Area/CN) _ [(3.840 x 98) + (10.360 x 74)] / 14.200 Q (cfs) 160.00 140.00 120.00 100.00 40.00 Q (cfs) 160.00 140.00 120.00 100.00 40.00 20.00 0.00 0.00 0 120 240 360 480 600 720 840 960 1080 1200 1320 — Hyd No. 2 Time (min) 35 Hydrograph Report MOV Expansion Hydraflow Hydrographs Extension for AUtodeskS Civil 3DO 2019 by Autodesk, Inc. v2019.2 Wednesday, 07 / 14 / 2021 Hyd. No. 3 Post Development-BMP Hydrograph type = SCS Runoff Peak discharge = 196.39 cfs Storm frequency = 100 yrs Time to peak = 716 min Time interval = 2 min Hyd. volume = 446,987 cuft Drainage area = 17.130 ac Curve number = 92* Basin Slope = 0.0 % Hydraulic length = 0 ft Tc method = User Time of conc. (Tc) = 5.00 min Total precip. = 8.63 in Distribution = Type II Storm duration = 24 hrs Shape factor = 484 Composite (Area/CN) _ [(13.090 x 98) + (4.040 x 74)] / 17.130 Post Development-BMP Q (cfs) Hyd. No. 3 -- 100 Year Q (cfs) 210.00 210.00 180.00 180.00 150.00 150.00 120.00 120.00 90.00 90.00 60.00 60.00 30.00 30.00 0.00 0.00 0 120 240 360 480 600 720 840 960 1080 1200 — Hyd No. 3 Time (min) Hydrograph Report 36 MOV Expansion Hydraflow Hydrographs Extension for AUtodeskS Civil 3DO 2019 by Autodesk, Inc. v2019.2 Wednesday, 07 / 14 / 2021 Hyd. No. 4 BMP Routing Hydrograph type = Reservoir Peak discharge = 47.56 cfs Storm frequency = 100 yrs Time to peak = 724 min Time interval = 2 min Hyd. volume = 444,463 cuft Inflow hyd. No. = 3 - Post Development-BMP Max. Elevation = 1206.60 ft Reservoir name = Wet Pond Max. Storage = 177,689 cuft Storage Indication method used. Q (cfs) 210.00 180.00 150.00 120.00 •• •• 30.00 Q (cfs) 210.00 180.00 150.00 120.00 •• •• 30.00 0.00 - 0.00 0 120 240 360 480 600 720 840 960 1080 1200 1320 1440 1560 Time (min) — Hyd No. 4 Hyd No. 3 ® Total storage used = 177,689 cult Hydrograph Report 37 MOV Expansion Hydraflow Hydrographs Extension for AUtodeskS Civil 3DO 2019 by Autodesk, Inc. v2019.2 Wednesday, 07 / 14 / 2021 Hyd. No. 5 Post Development -Total Hydrograph type = Combine Peak discharge = 186.95 cfs Storm frequency = 100 yrs Time to peak = 716 min Time interval = 2 min Hyd. volume = 744,941 cuft Inflow hyds. = 2, 4 Contrib. drain. area = 14.200 ac Q (cfs) 210.00 180.00 150.00 120.00 •• •• 30.00 Q (cfs) 210.00 180.00 150.00 120.00 •• •• 30.00 0.00 - 0.00 0 120 240 360 480 600 720 840 960 1080 1200 1320 1440 1560 Time (min) — Hyd No. 5 Hyd No. 2 Hyd No. 4 38 Hydrograph Report MOV Expansion Hydraflow Hydrographs Extension for AUtodeskS Civil 3DO 2019 by Autodesk, Inc. v2019.2 Wednesday, 07 / 14 / 2021 Hyd. No. 6 Analysis Point B Post -Development Hydrograph type = SCS Runoff Peak discharge = 53.42 cfs Storm frequency = 100 yrs Time to peak = 716 min Time interval = 2 min Hyd. volume = 122,714 cuft Drainage area = 4.630 ac Curve number = 93* Basin Slope = 0.0 % Hydraulic length = 0 ft Tc method = User Time of conc. (Tc) = 5.00 min Total precip. = 8.63 in Distribution = Type II Storm duration = 24 hrs Shape factor = 484 Composite (Area/CN) _ [(0.870 x 74) + (3.760 x 98)] / 4.630 Q (cfs) 60.00 50.00 40.00 30.00 10.00 0.00 ' 0 120 240 — Hyd No. 6 Analysis Point B Post -Development Hyd. No. 6 -- 100 Year 360 480 600 Q (cfs) 60.00 50.00 40.00 30.00 20.00 10.00 0.00 720 840 960 1080 1200 Time (min) Hydrograph Report 39 MOV Expansion Hydraflow Hydrographs Extension for AUtodeskS Civil 3DO 2019 by Autodesk, Inc. v2019.2 Wednesday, 07 / 14 / 2021 Hyd. No. 7 Wet Pond 2 Hydrograph type = Reservoir Peak discharge = 32.44 cfs Storm frequency = 100 yrs Time to peak = 720 min Time interval = 2 min Hyd. volume = 120,888 cuft Inflow hyd. No. = 6 - Analysis Point B Post-Develdp3nOibvation = 1215.28 ft Reservoir name = Wet Pond B Max. Storage = 50,197 cuft Storage Indication method used Wet Pond 2 Q (cfs) Hyd. No. 7 -- 100 Year Q (cfs) 60.00 60.00 50.00 50.00 40.00 40.00 30.00 30.00 20.00 20.00 10.00 10.00 0.00 0.00 0 120 240 360 480 600 720 840 960 1080 1200 1320 1440 1560 Time (min) — Hyd No. 7 Hyd No. 6 ® Total storage used = 50,197 cult Hydrograph Report 40 MOV Expansion Hydraflow Hydrographs Extension for AUtodeskS Civil 3DO 2019 by Autodesk, Inc. v2019.2 Wednesday, 07 / 14 / 2021 Hyd. No. 8 MOV Pre Development Hydrograph type = SCS Runoff Peak discharge = 200.77 cfs Storm frequency = 100 yrs Time to peak = 724 min Time interval = 2 min Hyd. volume = 638,765 cuft Drainage area = 28.300 ac Curve number = 80* Basin Slope = 0.0 % Hydraulic length = 0 ft Tc method = User Time of conc. (Tc) = 19.30 min Total precip. = 8.63 in Distribution = Type II Storm duration = 24 hrs Shape factor = 484 Composite (Area/CN) _ [(27.350 x 79) + (0.950 x 98)] / 28.300 Q (cfs) 210.00 180.00 150.00 120.00 •• •• 30.00 Q (cfs) 210.00 180.00 150.00 120.00 •• •• 30.00 0.00 1 1 1 1 1 Ink 0.00 0 120 240 360 480 600 720 840 960 1080 1200 1320 1440 1560 — Hyd No. 8 Time (min) Hydrograph Report 41 MOV Expansion Hydraflow Hydrographs Extension for AUtodeskS Civil 3DO 2019 by Autodesk, Inc. v2019.2 Wednesday, 07 / 14 / 2021 Hyd. No. 9 MOV Bypass Hydrograph type = SCS Runoff Peak discharge = 185.52 cfs Storm frequency = 100 yrs Time to peak = 724 min Time interval = 2 min Hyd. volume = 590,237 cuft Drainage area = 26.150 ac Curve number = 80* Basin Slope = 0.0 % Hydraulic length = 0 ft Tc method = TR55 Time of conc. (Tc) = 19.30 min Total precip. = 8.63 in Distribution = Type II Storm duration = 24 hrs Shape factor = 484 Composite (Area/CN) _ [(25.410 x 79) + (0.740 x 98)] / 26.150 Q (cfs) 210.00 180.00 150.00 120.00 •• •• 30.00 Q (cfs) 210.00 180.00 150.00 120.00 •• •• 30.00 0.00 0.00 0 120 240 360 480 600 720 840 960 1080 1200 1320 1440 1560 — Hyd No. 9 Time (min) Hydrograph Report 42 MOV Expansion Hydraflow Hydrographs Extension for AUtodeskS Civil 3DO 2019 by Autodesk, Inc. v2019.2 Wednesday, 07 / 14 / 2021 Hyd. No. 10 MOV COMBINED Hydrograph type = Combine Peak discharge = 215.84 cfs Storm frequency = 100 yrs Time to peak = 724 min Time interval = 2 min Hyd. volume = 711,125 cuft Inflow hyds. = 7, 9 Contrib. drain. area = 26.150 ac Q (cfs) 240.00 210.00 180.00 150.00 120.00 30.00 Q (cfs) 240.00 210.00 180.00 150.00 120.00 30.00 0.00 0.00 0 120 240 360 480 600 720 840 960 1080 1200 1320 1440 1560 Time (min) — Hyd No. 10 Hyd No. 7 Hyd No. 9 Hydraflow Rainfall Report 43 MOV Expansion Hydraflow Hydrographs Extension for Autodeskg Civil 3DO 2019 by Autodesk, Inc. v2019.2 Wednesday, 07 / 14 / 2021 Return Period Intensity -Duration -Frequency Equation Coefficients (FHA) (Yrs) B D E (NIA) 1 52.0631 11.7000 0.8619 -------- 2 66.4941 12.6000 0.8713 -------- 3 0.0000 0.0000 0.0000 -------- 5 0.0000 0.0000 0.0000 -------- 10 71.9699 12.4000 0.8031 -------- 25 66.3798 11.3000 0.7470 -------- 50 59.6913 10.1000 0.6967 -------- 100 55.6813 9.2000 0.6564 -------- File name: Morganton.IDF Intensity = B / (Tc + D)^E Return Period Intensity Values (in/hr) (Yrs) 5 min 10 15 20 25 30 35 40 45 50 55 60 1 4.60 3.67 3.07 2.65 2.33 2.09 1.90 1.74 1.60 1.49 1.39 1.31 2 5.47 4.40 3.69 3.19 2.82 2.53 2.30 2.11 1.95 1.81 1.69 1.59 3 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 5 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 10 7.26 5.93 5.04 4.41 3.93 3.55 3.25 2.99 2.78 2.60 2.45 2.31 25 8.25 6.76 5.77 5.07 4.54 4.12 3.78 3.50 3.27 3.07 2.89 2.74 50 9.01 7.38 6.32 5.57 5.00 4.56 4.20 3.90 3.65 3.44 3.25 3.09 100 9.76 8.00 6.88 6.08 5.48 5.01 4.63 4.32 4.05 3.82 3.62 3.45 Tc = time in minutes. Values may exceed 60. Precip. file name: R:\333\39004-NCNG MORGANTON RRC\Calcs\Stormwater\Morganton.pcp Storm Rainfall Precipitation Table (in) Distribution 1-yr 2-yr 3-yr 5-yr 10-yr 25-yr 50-yr 100-yr SCS 24-hour 3.15 3.83 0.00 4.43 5.67 6.79 7.70 8.63 SCS 6-Hr 2.06 2.48 0.00 3.11 3.60 4.35 4.98 5.66 Huff-1 st 0.00 0.00 0.00 2.75 0.00 0.00 0.00 0.00 Huff-2nd 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Huff-3rd 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Huff-4th 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Huff-Indy 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Custom 0.00 0.00 0.00 2.80 0.00 0.00 0.00 0.00 Hydraflow Storm Sewers Extension for Autodesk® Civil 3D® Plan Original Permit Outfall 41 Outfall • 43 42 X Outfall \45 Project File: StormPH2.stm Number of lines: 45 40 39 Outfall Date: 1 /28/2020 Storm Sewers v2019.20 Storm Sewer Summary Report Original Permit Pagel Line Line ID Flow Line Line Line Invert Invert Line HGL HGL Minor HGL Dns Junction No. rate Size shape length EL Dn EL Up Slope Down Up loss Junct Line Type (cfs) (in) (ft) (ft) (ft) N (ft) (ft) (ft) (ft) No. 1 B1-C1 (1) 56.84 42 Cir 55.149 1197.00 1197.91 1.650 1205.01" 1205.19" 0.54 1205.72 End Manhole 2 B1-C1 44.06 36 Cir 119.735 1198.41 1200.38 1.645 1205.72" 1206.25" 0.59 1206.84 1 Manhole 3 132-131 39.88 30 Cir 65.695 1200.88 1202.14 1.918 1206.84" 1207.46" 0.51 1207.97 2 Grate 4 133-132 35.57 30 Cir 137.277 1206.62 1210.02 2.477 1207.97 1212.04 1.32 1212.04 3 Combination 5 134-133 35.40 30 Cir 98.074 1210.12 1211.11 1.009 1212.04 1213.13 1.57 1213.13 4 Combination 6 135-134 33.83 30 Cir 105.326 1211.21 1212.26 0.997 1213.13 1214.24 0.86 1214.24 5 Combination 7 136-135 32.43 30 Cir 84.283 1212.36 1213.22 1.020 1214.24 1215.16 n/a 1215.16 6 Combination 8 137-136 32.53 30 Cir 119.192 1213.32 1214.53 1.015 1215.16 1216.47 n/a 1216.47 7 Grate 9 138-137 31.10 30 Cir 123.666 1214.63 1215.86 0.995 1216.47 1217.76 n/a 1217.76 8 Grate 10 1314-138 2.17 15 Cir 84.964 1220.39 1221.24 1.000 1220.89 1221.83 0.21 1221.83 9 Grate 11 1315-1314 1.10 15 Cir 56.434 1221.44 1222.00 0.992 1221.83 1222.41 0.15 1222.41 10 Grate 12 1313-138 4.08 15 Cir 67.720 1220.98 1222.33 1.993 1221.57 1223.15 0.36 1223.15 9 Grate 13 A2-132 17.50 24 Cir 78.709 1202.89 1206.53 4.625 1205.72 1208.04 n/a 1208.04 j 1 Combination 14 A3-A2 15.02 18 Cir 200.862 1206.73 1209.79 1.523 1208.23" 1212.34" 1.63 1213.97 13 Combination 15 A4-A3 8.96 18 Cir 161.016 1209.89 1213.89 2.484 1213.97 1215.05 0.78 1215.83 14 Combination 16 A5-A4 3.53 15 Cir 165.314 1214.14 1217.46 2.008 1215.83 1218.22 n/a 1218.22 j 15 Combination 17 A6-A5 1.92 15 Cir 182.318 1217.66 1220.76 1.700 1218.22 1221.31 n/a 1221.31 j 16 Grate 18 A7-A6 1.37 15 Cir 37.003 1220.96 1221.59 1.703 1221.31 1222.05 0.17 1222.05 17 Grate 19 139-138 21.25 24 Cir 161.626 1216.36 1217.98 1.002 1217.90 1219.63 0.91 1219.63 9 Manhole 20 1316-139 5.55 18 Cir 218.522 1218.73 1220.04 0.600 1219.64 1220.95 0.38 1221.33 19 Manhole 21 B16A-B16 3.24 18 Cir 43.797 1220.24 1220.56 0.731 1221.33 1221.25 n/a 1221.25 20 Grate 22 A8-A3 5.43 15 Cir 138.707 1210.04 1214.18 2.984 1213.97 1215.12 n/a 1215.12 j 14 Combination 23 A9-A8 5.12 15 Cir 59.174 1214.38 1215.45 1.808 1215.12 1216.37 0.43 1216.37 22 Combination 24 A10-A9 3.98 15 Cir 69.290 1215.65 1216.90 1.804 1216.37 1217.71 n/a 1217.71 23 Combination Project File: StormPH2.stm Number of lines: 45 Run Date: 1/28/2020 NOTES: Return period = 10 Yrs. ; "Surcharged (HGL above crown). ; j - Line contains hyd. jump. Storm Sewers v2019.20 Storm Sewer Summary Report Original Permit Page Line Line ID Flow Line Line Line Invert Invert Line HGL HGL Minor HGL Dns Junction No. rate Size shape length EL Dn EL Up Slope Down Up loss Junct Line Type (cfs) (in) (ft) (ft) (ft) N (ft) (ft) (ft) (ft) No. 25 C2-131 14.78 24 Cir 30.940 1201.38 1202.38 3.232 1206.84" 1206.97" 0.17 1207.14 2 Grate 26 C3-C2 14.68 24 Cir 64.033 1202.48 1203.60 1.749 1207.14" 1207.41" 0.17 1207.58 25 Combination 27 C4-C3 13.75 24 Cir 41.479 1204.10 1205.14 2.507 1207.58" 1207.74" 0.15 1207.88 26 Combination 28 C5-C4 12.65 24 Cir 49.694 1205.34 1206.53 2.395 1207.88 1207.81 0.81 1208.62 27 Grate 29 C6-05 12.48 24 Cir 102.922 1206.63 1209.16 2.458 1208.62 1210.43 n/a 1210.43 j 28 Combination 30 C7-C6 12.00 18 Cir 73.750 1209.26 1211.10 2.495 1210.43 1212.41 n/a 1212.41 29 Combination 31 C8-C7 11.75 18 Cir 54.652 1211.20 1212.57 2.507 1212.41 1213.87 n/a 1213.87 30 Combination 32 C9-C8 9.67 18 Cir 125.915 1212.67 1215.19 2.001 1213.87 1216.39 n/a 1216.39 j 31 Combination 33 C10-C9 12.59 18 Cir 148.048 1215.29 1218.25 1.999 1216.39 1219.59 0.45 1219.59 32 Combination 34 C11-C10 12.15 18 Cir 249.163 1218.35 1221.34 1.200 1219.68 1222.83 0.74 1223.57 33 Grate 35 B16 17.10 24 Cir 172.495 1218.08 1219.80 0.997 1219.63 1221.29 n/a 1221.29 j 19 Grate 36 1312-134 0.69 15 Cir 97.111 1217.97 1219.89 1.977 1218.20 1220.21 n/a 1220.21 5 Combination 37 C12-C9 0.15 15 Cir 86.000 1215.29 1217.26 2.291 1216.39 1217.41 n/a 1217.41 j 32 Grate 38 1311-133 0.33 15 Cir 22.706 1211.17 1211.40 1.013 1212.04 1211.62 n/a 1211.62 4 Grate 39 D2-D1 4.43 15 Cir 134.551 1200.46 1210.18 7.224 1200.89 1211.03 0.34 1211.03 End Grate 40 D3-D2 0.48 15 Cir 244.058 1213.16 1219.43 2.569 1213.34 1219.70 n/a 1219.70 39 Grate 41 E2-E1 4.74 15 Cir 86.454 1204.23 1209.62 6.235 1204.70 1210.50 n/a 1210.50 End Grate 42 E3-E2 0.66 15 Cir 225.333 1213.28 1218.62 2.370 1213.50 1218.94 n/a 1218.94 41 Grate 43 F2-F1 4.92 15 Cir 45.656 1215.00 1215.46 1.007 1215.81 1216.36 n/a 1216.36 End Grate 44 F3-F2 2.10 15 Cir 89.085 1215.56 1216.45 0.999 1216.36 1217.03 n/a 1217.03 j 43 Grate 45 G2-G1 3.31 15 Cir 78.428 1214.86 1215.59 0.931 1215.51 1216.32 n/a 1216.32 End Grate Project File: StormPH2.stm Number of lines: 45 Run Date: 1/28/2020 NOTES: Return period = 10 Yrs. ; "Surcharged (HGL above crown). ; j - Line contains hyd. jump. Storm Sewers v2019.20 Storm Sewer Tabulation Original Permit Pagel Station Len Drng Area Rnoff Area x C Tc Rain Total Cap Vel Pipe Invert Elev HGL Elev Grnd / Rim Elev Line ID coeff (1) flow full Line To Incr Total Incr Total Inlet Syst Size Slope Dn Up Dn Up Dn Up Line (ft) (ac) (ac) (C) (min) (min) (in/hr) (cfs) (cfs) (ft/s) (in) (%) (ft) (ft) (ft) (ft) (ft) (ft) 1 End 55.149 0.00 14.41 0.00 0.00 12.50 5.0 18.7 4.5 56.84 129.2 5.91 42 1.65 1197.00 1197.91 1205.01 1205.19 0.00 1208.71 B1-C1 (1) 2 1 119.735 0.00 11.10 0.00 0.00 9.62 5.0 18.5 4.6 44.06 85.55 6.23 36 1.65 1198.41 1200.38 1205.72 1206.25 1208.71 1210.37 B1-C1 3 2 65.695 0.89 7.31 0.86 0.77 6.40 5.0 8.7 6.2 39.88 56.80 8.13 30 1.92 1200.88 1202.14 1206.84 1207.46 1210.37 1209.88 B2-B1 4 3 137.277 0.05 6.42 0.71 0.04 5.64 5.0 8.3 6.3 35.57 64.54 10.74 30 2.48 1206.62 1210.02 1207.97 1212.04 1209.88 1218.35 133-132 5 4 98.074 0.25 6.24 0.83 0.21 5.56 5.0 8.1 6.4 35.40 41.20 8.54 30 1.01 1210.12 1211.11 1212.04 1213.13 1218.35 1223.24 134-133 6 5 105.326 0.29 5.89 0.90 0.26 5.25 5.0 7.8 6.4 33.83 40.95 8.25 30 1.00 1211.21 1212.26 1213.13 1214.24 1223.24 1224.24 135-134 7 6 84.283 0.05 5.60 0.95 0.05 4.99 5.0 7.6 6.5 32.43 41.43 8.08 30 1.02 1212.36 1213.22 1214.24 1215.16 1224.24 1224.25 136-135 8 7 119.192 0.51 5.55 0.55 0.28 4.95 5.0 7.3 6.6 32.53 41.32 8.19 30 1.02 1213.32 1214.53 1215.16 1216.47 1224.25 1224.00 137-136 9 8 123.666 0.69 5.04 0.95 0.66 4.67 5.0 6.9 6.7 31.10 40.90 7.90 30 0.99 1214.63 1215.86 1216.47 1217.76 1224.00 1225.75 138-137 10 9 84.964 0.17 0.33 0.95 0.16 0.31 5.0 6.0 6.9 2.17 6.46 4.29 15 1.00 1220.39 1221.24 1220.89 1221.83 1225.75 1226.00 1314-138 11 10 56.434 0.16 0.16 0.95 0.15 0.15 5.0 5.0 7.3 1.10 6.43 3.26 15 0.99 1221.44 1222.00 1221.83 1222.41 1226.00 1226.00 1315-1314 12 9 67.720 0.72 0.72 0.78 0.56 0.56 5.0 5.0 7.3 4.08 9.12 6.01 15 1.99 1220.98 1222.33 1221.57 1223.15 1225.75 1225.00 1313-138 13 1 78.709 0.52 3.31 0.85 0.44 2.87 5.0 9.3 6.1 17.50 48.64 6.23 24 4.62 1202.89 1206.53 1205.72 1208.04 1208.71 1208.95 A2-B2 14 13 200.862 0.28 2.79 0.86 0.24 2.43 5.0 8.9 6.2 15.02 12.96 8.50 18 1.52 1206.73 1209.79 1208.23 1212.34 1208.95 1217.58 A3-A2 15 14 161.016 0.97 1.60 0.91 0.88 1.42 5.0 8.4 6.3 8.96 16.55 5.59 18 2.48 1209.89 1213.89 1213.97 1215.05 1217.58 1220.04 A4-A3 16 15 165.314 0.29 0.63 0.93 0.27 0.54 5.0 7.5 6.5 3.53 9.15 3.71 15 2.01 1214.14 1217.46 1215.83 1218.22 1220.04 1222.56 A5-A4 17 16 182.318 0.11 0.34 0.75 0.08 0.27 5.0 5.6 7.1 1.92 8.42 3.65 15 1.70 1217.66 1220.76 1218.22 1221.31 1222.56 1224.50 A6-A5 18 17 37.003 0.23 0.23 0.82 0.19 0.19 5.0 5.0 7.3 1.37 8.43 4.08 15 1.70 1220.96 1221.59 1221.31 1222.05 1224.50 1225.20 A7-A6 19 9 161.626 0.00 3.30 0.00 0.00 3.14 5.0 6.5 6.8 21.25 22.64 7.93 24 1.00 1216.36 1217.98 1217.90 1219.63 1225.75 1226.43 139-138 20 19 218.522 0.35 0.82 0.95 0.33 0.78 5.0 5.4 7.1 5.55 8.13 4.95 18 0.60 1218.73 1220.04 1219.64 1220.95 1226.43 1226.66 1316-139 21 20 43.797 0.47 0.47 0.95 0.45 0.45 5.0 5.0 7.3 3.24 8.98 3.24 18 0.73 1220.24 1220.56 1221.33 1221.25 1226.66 1225.05 B16A-B16 22 14 138.707 0.06 0.91 0.85 0.05 0.77 5.0 5.6 7.1 5.43 11.15 4.94 15 2.98 1210.04 1214.18 1213.97 1215.12 1217.58 1222.85 A8-A3 Project File: StormPH2.stm Number of lines: 45 Run Date: 1/28/2020 NOTES:Intensity = 71.97 / (Inlet time + 12.40) ^ 0.80; Return period =Yrs. 10 ; c = cir e = ellip b = box Storm Sewers v2019.20 Storm Sewer Tabulation Original Permit Page Station Len Drng Area Rnoff Area x C Tc Rain Total Cap Vel Pipe Invert Elev HGL Elev Grnd / Rim Elev Line ID coeff (1) flow full Line To Incr Total Incr Total Inlet Syst Size Slope Dn Up Dn Up Dn Up Line (ft) (ac) (ac) (C) (min) (min) (in/hr) (cfs) (cfs) (ft/s) (in) (%) (ft) (ft) (ft) (ft) (ft) (ft) 23 22 59.174 0.19 0.85 0.89 0.17 0.72 5.0 5.4 7.1 5.12 8.68 6.02 15 1.81 1214.38 1215.45 1215.12 1216.37 1222.85 1224.33 A9-A8 24 23 69.290 0.66 0.66 0.83 0.55 0.55 5.0 5.0 7.3 3.98 8.67 5.11 15 1.80 1215.65 1216.90 1216.37 1217.71 1224.33 1225.80 A10-A9 25 2 30.940 0.10 3.79 0.35 0.04 3.22 5.0 18.4 4.6 14.78 40.66 4.70 24 3.23 1201.38 1202.38 1206.84 1206.97 1210.37 1209.50 C2-131 26 25 64.033 0.25 3.69 0.85 0.21 3.19 5.0 18.2 4.6 14.68 29.91 4.67 24 1.75 1202.48 1203.60 1207.14 1207.41 1209.50 1211.01 C3-C2 27 26 41.479 0.32 3.44 0.78 0.25 2.97 5.0 18.1 4.6 13.75 35.81 4.38 24 2.51 1204.10 1205.14 1207.58 1207.74 1211.01 1211.94 C4-C3 28 27 49.694 0.17 3.12 0.35 0.06 2.72 5.0 18.0 4.6 12.65 35.00 4.98 24 2.39 1205.34 1206.53 1207.88 1207.81 1211.94 1211.50 C5-C4 29 28 102.922 0.13 2.95 0.86 0.11 2.66 5.0 17.6 4.7 12.48 35.46 4.95 24 2.46 1206.63 1209.16 1208.62 1210.43 1211.50 1215.80 C6-05 30 29 73.750 0.08 2.82 0.73 0.06 2.55 5.0 17.5 4.7 12.00 16.59 7.72 18 2.49 1209.26 1211.10 1210.43 1212.41 1215.80 1218.33 C7-C6 31 30 54.652 0.52 2.74 0.88 0.46 2.49 5.0 17.4 4.7 11.75 16.63 7.44 18 2.51 1211.20 1212.57 1212.41 1213.87 1218.33 1219.26 C8-C7 32 31 125.915 0.26 2.22 0.90 0.23 2.04 5.0 17.1 4.7 9.67 14.86 6.37 18 2.00 1212.67 1215.19 1213.87 1216.39 1219.26 1221.66 C9-C8 33 32 148.048 0.12 1.92 0.90 0.11 1.78 5.0 5.6 7.1 12.59 14.85 8.32 18 2.00 1215.29 1218.25 1216.39 1219.59 1221.66 1224.47 C10-C9 34 33 249.163 1.80 1.80 0.93 1.67 1.67 5.0 5.0 7.3 12.15 11.50 7.12 18 1.20 1218.35 1221.34 1219.68 1222.83 1224.47 1225.20 C11-C10 35 19 172.495 2.48 2.48 0.95 2.36 2.36 5.0 5.0 7.3 17.10 22.59 6.68 24 1.00 1218.08 1219.80 1219.63 1221.29 1226.43 1224.00 B16 36 5 97.111 0.10 0.10 0.95 0.10 0.10 5.0 5.0 7.3 0.69 9.08 3.54 15 1.98 1217.97 1219.89 1218.20 1220.21 1223.24 1224.21 B12-134 37 32 86.000 0.04 0.04 0.50 0.02 0.02 5.0 5.0 7.3 0.15 9.77 0.96 15 2.29 1215.29 1217.26 1216.39 1217.41 1221.66 1221.50 C12-C9 38 4 22.706 0.13 0.13 0.35 0.05 0.05 5.0 5.0 7.3 0.33 6.50 1.30 15 1.01 1211.17 1211.40 1212.04 1211.62 1218.35 1217.50 1311-133 39 End 134.551 1.91 2.10 0.43 0.82 0.89 5.0 15.3 5.0 4.43 17.36 8.39 15 7.22 1200.46 1210.18 1200.89 1211.03 1201.90 1220.25 D2-D1 40 39 244.058 0.19 0.19 0.35 0.07 0.07 5.0 5.0 7.3 0.48 10.35 3.39 15 2.57 1213.16 1219.43 1213.34 1219.70 1220.25 1226.00 D3-D2 41 End 86.454 1.78 2.04 0.43 0.77 0.86 5.0 12.0 5.5 4.74 16.12 8.18 15 6.23 1204.23 1209.62 1204.70 1210.50 1205.67 1221.00 E2-El 42 41 225.333 0.26 0.26 0.35 0.09 0.09 5.0 5.0 7.3 0.66 9.94 3.64 15 2.37 1213.28 1218.62 1213.50 1218.94 1221.00 1226.00 E3-E2 43 End 45.656 0.67 1.05 0.62 0.42 0.70 5.0 5.9 7.0 4.92 6.48 5.51 15 1.01 1215.00 1215.46 1215.81 1216.36 1216.44 1218.33 F2-F1 44 43 89.085 0.38 0.38 0.76 0.29 0.29 5.0 5.0 7.3 2.10 6.45 3.16 15 1.00 1215.56 1216.45 1216.36 1217.03 1218.33 1218.25 F3-F2 Project File: StormPH2.stm Number of lines: 45 Run Date: 1/28/2020 NOTES:Intensity = 71.97 / (Inlet time + 12.40) ^ 0.80; Return period =Yrs. 10 c = cir e = ellip b = box Storm Sewers v2019.20 Storm Sewer Tabulation Original Permit Page Station Len (ft) Drng Area Rnoff coeff (C) Area x C Tc Rain (1) (in/hr) Total flow (cfs) Cap full (cfs) Vel (ft/s) Pipe Invert Elev HGL Elev Grnd / Rim Elev Line ID Line To Line Incr (ac) Total (ac) Incr Total Inlet (min) Syst (min) Size (in) Slope (%) Dn (ft) Up (ft) Dn (ft) Up (ft) Dn (ft) Up (ft) 45 End 78.428 0.99 0.99 0.46 0.46 0.46 5.0 5.0 7.3 3.31 6.23 4.78 15 0.93 1214.86 1215.59 1215.51 1216.32 1216.29 1217.50 G2-G1 Project File: StormPH2.stm Number of lines: 45 Run Date: 1/28/2020 NOTES:Intensity = 71.97 / (Inlet time + 12.40) ^ 0.80; Return period =Yrs. 10 ; c = cir e = ellip b = box Storm Sewers v2019.20 Hydraflow Storm Sewers Extension for Autodesk® Civil 3D® Plan MOV Expansion 4 3 2 6 5 1 Outfall Project File: D&E.stm Number of lines: 6 Date: 7/14/2021 Storm Sewers v2019.20 Storm Sewer Inventory Report MOV Expansion Pagel Line Alignment Flow Data Physical Data Line ID No. Dnstr Line Defl Junc Known Drng Runoff Inlet Invert Line Invert Line Line N J-Loss Inlet[ Line Length angle Type Q Area Coeff Time El Dn Slope El Up Size Shape Value Coeff Rim El No. (ft) (deg) (cfs) (ac) (C) (min) (ft) M (ft) (in) (n) (K) (ft) 1 End 68.274 -123.30 DrGrt 0.00 0.96 0.95 5.0 1206.50 1.05 1207.22 24 Cir 0.013 1.50 1224.00 D2-D1 2 1 191.420 -4.843 DrGrt 0.00 0.14 0.95 5.0 1207.32 1.00 1209.23 24 Cir 0.013 0.50 1227.26 D3-D2 3 2 336.130 0.001 DrGrt 0.00 0.20 0.95 5.0 1209.33 1.00 1212.70 24 Cir 0.013 0.50 1224.58 D4-D3 4 3 209.103 0.000 DrGrt 0.00 1.58 0.95 5.0 1213.20 1.00 1215.30 18 Cir 0.013 1.00 1220.53 D5-D4 5 1 50.585 88.259 DrGrt 0.00 0.22 0.57 5.0 1207.97 5.00 1210.50 15 Cir 0.013 1.00 1223.00 E2-D2 6 1 204.820 -49.546 DrGrt 2.30 0.24 0.95 5.0 1207.97 6.00 1220.25 15 Cir 0.013 1.00 1226.74 El-D2 Project File: D&E.stm Number of lines: 6 Date: 7/14/2021 Storm Sewers v2019.20 Structure Report MOV Expansion Pagel Struct Structure ID Junction Rim Structure Line Out Line In No. Type Elev Shape Length Width Size Shape Invert Size Shape Invert (ft) (ft) (ft) (in) (ft) (in) (ft) 1 D2 DropGrate 1224.00 Rect 2.00 2.00 24 Cir 1207.22 24 Cir 1207.32 15 Cir 1207.97 15 Cir 1207.97 2 D3 DropGrate 1227.26 Rect 2.00 2.00 24 Cir 1209.23 24 Cir 1209.33 3 D4 DropGrate 1224.58 Rect 2.00 2.00 24 Cir 1212.70 18 Cir 1213.20 4 D5 DropGrate 1220.53 Rect 2.00 2.00 18 Cir 1215.30 5 E2 DropGrate 1223.00 Rect 2.00 2.00 15 Cir 1210.50 6 E1 DropGrate 1226.74 Rect 2.00 2.00 15 Cir 1220.25 Project File: D&E.stm Number of Structures: 6 Run Date: 7/14/2021 Storm Sewers v2019.20 Storm Sewer Summary Report MOV Expansion Page 1 Line Line ID Flow Line Line Line Invert Invert Line HGL HGL Minor HGL Dns Junction No. rate Size shape length EL Dn EL Up Slope Down Up loss Junct Line Type (cfs) (in) (ft) (ft) (ft) M (ft) (ft) (ft) (ft) No. 1 D2-D1 22.08 24 Cir 68.274 1206.50 1207.22 1.055 1208.10 1208.90 1.44 1208.90 End DropGrate 2 D3-D2 12.09 24 Cir 191.420 1207.32 1209.23 0.998 1208.90 1210.48 n/a 1210.48 j 1 DropGrate 3 D4-D3 11.96 24 Cir 336.130 1209.33 1212.70 1.003 1210.48 1213.94 n/a 1213.94 2 DropGrate 4 D5-D4 10.90 18 Cir 209.103 1213.20 1215.30 1.004 1214.48 1216.58 0.71 1217.30 3 DropGrate 5 E2-D2 0.91 15 Cir 50.585 1207.97 1210.50 5.000 1208.90 1210.87 n/a 1210.87 j 1 DropGrate 6 El-D2 3.95 15 Cir 204.820 1207.97 1220.25 5.996 1208.90 1221.05 n/a 1221.05 j 1 DropGrate Project File: D&E.stm Number of lines: 6 Run Date: 7/14/2021 NOTES: Return period = 10 Yrs. ; j - Line contains hyd. jump. Storm Sewers v2019.20 Inlet Report MOV Expansion Pagel Line Inlet ID Q = Q Q Q June Curb Inlet Grate Inlet Gutter Inlet Byp No CIA carry capt Byp Type Line Ht L Area L W So W SW Sx n Depth Spread Depth Spread Depr No (cfs) (cfs) (cfs) (cfs) (in) (ft) (sgft) (ft) (ft) (ft/ft) (ft) (ft/ft) (ft/ft) (ft) (ft) (ft) (ft) (in) 1 D2 6.62 0.00 6.62 0.00 DrGrt 0.0 0.00 4.00 2.00 2.00 Sag 2.17 0.020 0.020 0.013 0.42 44.53 0.42 44.53 0.0 Off 2 D3 0.97 0.00 0.97 0.00 DrGrt 0.0 0.00 4.00 2.00 2.00 Sag 2.17 0.020 0.020 0.013 0.12 13.90 0.12 13.90 0.0 Off 3 D4 1.38 0.00 1.38 0.00 DrGrt 0.0 0.00 4.00 2.00 2.00 Sag 2.17 0.020 0.020 0.013 0.15 17.05 0.15 17.05 0.0 Off 4 D5 10.90 0.00 10.90 0.00 DrGrt 0.0 0.00 4.00 2.00 2.00 Sag 2.17 0.020 0.020 0.013 0.59 61.22 0.59 61.22 0.0 Off 5 E2 0.91 0.00 0.91 0.00 DrGrt 0.0 0.00 4.00 2.00 2.00 Sag 2.17 0.020 0.020 0.013 0.11 13.45 0.11 13.45 0.0 Off 6 E1 3.95* 0.00 3.95 0.00 DrGrt 0.0 0.00 4.00 2.00 2.00 Sag 2.17 0.020 0.020 0.013 0.30 32.19 0.30 32.19 0.0 Off Project File: D&E.stm TNumber of lines: 6 Run Date: 7/14/2021 NOTES: Inlet N-Values = 0.016; Intensity = 71.97 / (Inlet time + 12.40) ^ 0.80; Return period = 10 Yrs. ; * Indicates Known Q added. All curb inlets are throat. Storm Sewers v2019.20 Hydraulic Grade Line Computations MOV Expansion Pagel Line Size Q Downstream Len Upstream Check JL Minor coeff loss Invert HGL Depth Area Vel Vel EGL Sf Invert HGL Depth Area Vel Vel EGL Sf Ave Enrgy elev elev head elev elev elev head elev Sf loss (in) (cfs) (ft) (ft) (ft) (sqft) (ft/s) (ft) (ft) (%) (ft) (ft) (ft) (ft) (sgft) (ft/s) (ft) (ft) (%) (%) (ft) (K) (ft) (1) (2) (3) (4) (5) (6) (7) (8) (9) (10) (11) (12) (13) (14) (15) (16) (17) (18) (19) (20) (21) (22) (23) (24) 1 24 22.08 1206.50 1208.10 1.60 2.69 8.20 0.96 1209.06 0.000 68.274 1207.22 1208.90 1.68** 2.81 7.85 0.96 1209.86 0.000 0.000 n/a 1.50 1.44 2 24 12.09 1207.32 1208.90 1.58 2.06 4.55 0.53 1209.43 0.000 191.42 1209.23 1210.48 j 1.25** 2.06 5.86 0.53 1211.01 0.000 0.000 n/a 0.50 0.27 3 24 11.96 1209.33 1210.48 1.15 1.87 6.41 0.53 1211.01 0.000 336.13 1212.70 1213.94 1.24** 2.05 5.84 0.53 1214.47 0.000 0.000 n/a 0.50 n/a 4 18 10.90 1213.20 1214.48 1.28* 1.61 6.77 0.71 1215.20 1.004 209.10 1215.30 1216.58 1.28 1.61 6.77 0.71 1217.30 1.005 1.005 2.100 1.00 0.71 5 15 0.91 1207.97 1208.90 0.93 0.31 0.93 0.14 1209.03 0.000 50.585 1210.50 1210.87 j 0.37** 0.31 2.95 0.14 1211.01 0.000 0.000 n/a 1.00 0.14 6 15 3.95 1207.97 1208.90 0.93 0.83 4.05 0.35 1209.25 0.000 204.82 1220.25 1221.05 j 0.80** 0.83 4.74 0.35 1221.40 0.000 0.000 n/a 1.00 n/a Project File: D&E.stm Number of lines: 6 Run Date: 7/14/2021 Notes: * depth assumed; ** Critical depth.; j-Line contains hyd. jump c = cir e = ellip b = box Storm Sewers v2019.20 Hydraflow HGL Computation Procedure MOV Expansion Pagel General Procedure: Hydraflow computes the HGL using the Bernoulli energy equation. Manning's equation is used to determine energy losses due to pipe friction. In a standard step, iterative procedure, Hydraflow assumes upstream HGLs until the energy equation balances. If the energy equation cannot balance, supercritical flow exists and critical depth is temporarily assumed at the upstream end. A supercritical flow Profile is then computed using the same procedure in a downstream direction using momentum principles. Col. 1 The line number being computed. Calculations begin at Line 1 and proceed upstream. Col. 2 The line size. In the case of non -circular pipes, the line rise is printed above the span. Col. 3 Total flow rate in the line. Col. 4 The elevation of the downstream invert. Col. 5 Elevation of the hydraulic grade line at the downstream end. This is computed as the upstream HGL + Minor loss of this line's downstream line. Col. 6 The downstream depth of flow inside the pipe (HGL - Invert elevation) but not greater than the line size. Col. 7 Cross -sectional area of the flow at the downstream end. Col. 8 The velocity of the flow at the downstream end, (Col. 3 / Col. 7). Col. 9 Velocity head (Velocity squared / 2g). Col. 10 The elevation of the energy grade line at the downstream end, HGL + Velocity head, (Col. 5 + Col. 9). Col. 11 The friction slope at the downstream end (the S or Slope term in Manning's equation). Col. 12 The line length. Col. 13 The elevation of the upstream invert. Col. 14 Elevation of the hydraulic grade line at the upstream end. Col. 15 The upstream depth of flow inside the pipe (HGL - Invert elevation) but not greater than the line size. Col. 16 Cross -sectional area of the flow at the upstream end. Col. 17 The velocity of the flow at the upstream end, (Col. 3 / Col. 16). Col. 18 Velocity head (Velocity squared / 2g). Col. 19 The elevation of the energy grade line at the upstream end, HGL + Velocity head, (Col. 14 + Col. 18) . Col. 20 The friction slope at the upstream end (the S or Slope term in Manning's equation). Col. 21 The average of the downstream and upstream friction slopes. Col. 22 Energy loss. Average Sf/100 x Line Length (Col. 21 /100 x Col. 12). Equals (EGL upstream - EGL downstream) +/- tolerance. Col. 23 The junction loss coefficient (K). Col. 24 Minor loss. (Col. 23 x Col. 18). Is added to upstream HGL and used as the starting HGL for the next upstream line(s). Rip Rap Calcs- PH2 4/6/2020 Page 1 of 1 Rip Rap Calcs- PH2 1/29/2020 Page 2 of 8 Rip Rap Calcs- PH2 1/29/2020 Page 3 of 8 Rip Rap Calcs- PH2 1/29/2020 Page 4 of 8 Rip Rap Calcs- PH2 1/29/2020 Page 5 of 8 Rip Rap Calcs- PH2 7/14/2021 Page 7 of 15 Rip Rap Calcs- PH2 7/14/2021 Page 8 of 15 FDRn�sLOAnE❑ DJECT INFORMATION 1 Project Name NCNG Morganton Regional Readiness Center 2 Project Area ac 34.4 3 Coastal Wetland Area ac 0 4 Surface Water Area ac 0.6 S Is this pro'ect High or Low Density? High 3 Does this project use an off -site SCM? No MPLIANCE WITH 021-11.100 tt' 7 Width of vegetated setbacks provided feet 50 3 Will the vegetated setback remain vegetated? Yes 3 Is BUA other that as listed in .1003(4)(c-dl out of the setback? No j Is streambank stabilization proposed on this project? No MBER AND TYPE OF SCMs: 1 Infiltration System 0 2 Bioretention Cell 0 3 Wet Pond 1 4 Stormwater Wetland 0 5 Permeable Pavement 0 5 Sand Filter 0 7 Rainwater Harvesting RWH 0 3 Green Roof 0 L Level Spreader -Filter Strip (IS-FS 0 3 Disconnected Impervious Surface. DIS 0 1 Treatment Swale 0 2 Dry Pond 0 3 StormFilter 0 4 Silva Cell 0 5 Bayfilter 0 3 J Filterra 0 FORMS LOADED 31GNER CERTIFICATION 7 1 Name and Title: a I Street address: 1 5410 Trinity Road. Suite 102 1 7 F'none numbers : 919 866-4505 2 Email: frank.slinskYC�timmons.com Certification Statement: I certify, under penalty of law that this Supplement-EZ form and all supporting information were prepared under my direction or supervision; that the information provided in the form is, to the best of my knowledge and belief, true, accurate, and complete; and that the engineering plans, specifications, operation and maintenance agreements and other supporting information are consistent wlth the information provided here. 1ill;; CAiq��•,ff� 2• DFf,S8/ . .q SEAL r; : 033612 Sigrmtur4 of Designer Date -51rg/2-02.0 Original Permit DRAINAGE AREAS 1 Is this a high density project? Yes 2 If so, number of drainage areas/SCMs 1 3 Is all/part of this project subject to previous rule versions? No FORMS LOADED Original Permit DRAINAGE AREA INFORMATION Entire Site 1 4 T pe of SCM Wet Pond 5 Total BUA in project (sq ft 700010 sf 570010 sf 6permitting) New BUA on subdivided lots (subject to s ft 7permitting) New BUA outside of subdivided lots (subject to s 700010 sf 570010 sf 8 Offsite - total area (sq ft 9 Offsite BUA (sq ft 10 Breakdown of new BUA outside subdivided lots: Parking (sq ft 530612 sf 465306 sf Sidewalk (sq ft 33389 sf 33389 sf Roof (sq ft 64267 sf 64267 sf Roadway s ft 10194 sf Future (sq ft 61548 sf 7048 sf Other, please specify in the comment box below (sq ft 11 New infiltrating permeable pavement on subdivided lots (sq ft 12 New infiltrating permeable pavement outside of subdivided lots (sq ft 13permitting) Exisitng BUA that will remain (not subject to s ft 14 Existina BUA that is already permitted (sq ft 15 Existing BUA that will be removed (sq ft 16 Percent BUA 47% 76% 17 Design storm inches 1 in 18 Design volume of SCM cu ft 45874 cf 19 Calculation method for design volume Simple Method ADDITIONAL INFORMATION 20 Please use this space to provide any additional information about the drainage area(s): WET POND 1 Drainage area number A2 21 Design volume of SCM (cu ft) 45874 cf GENERAL 31 MDC FROM 02H .1050 Is the SCM sized to treat the SW from all surfaces at build -out? Yes 4 Is the SCM located away from contaminated soils? Yes 5 What are the side slopes of the SCM (H:V)? 3:1 6 Does the SCM have retaining walls, gabion walls or other engineered side slopes? No 7 Are the inlets, outlets, and receiving stream protected from erosion (10-year storm)? Yes 8 Is there an overflow or bypass for inflow volume in excess of the design volume? Yes 9 What is the method for dewatering the SCM for maintenance? Drawdown Orifice 10 If applicable, will the SCM be cleaned out after construction? Yes 11 Does the maintenance access comply with General MDC (8)? Yes 12 Does the drainage easement comply with General MDC (9)? 13 If the SCM is on a single family lot, does (will?) the plat comply with General MDC (10)? 14 Is there an O&M Agreement that complies with General MDC (11)? Yes 15 Is there an O&M Plan that complies with General MDC (12)? Yes 16 Does the SCM follow the device specific MDC? Yes 17 Was the SCM designed by an NC licensed professional? Yes hAXT PC)Nr) nnr)r PRC)nn n9N 18 Method used SA/DA 19 Has a stage/storage table been provided in the calculations? Yes 20 Elevation of the excavated main pool depth (bottom of sediment removal) (fmsl) 1196.00 21 Elevation of the main pool bottom -(top of sediment removal) (fmsl) 1197.00 221 Elevation of the bottom of the vegetated shelf (fmsl) 1201.00 23 Elevation of the permanent pool (fmsl) 1201.50 24 Elevation of the top of the vegetated shelf (fmsl) 1202.00 25 Elevation of the temporary pool (fmsl) 1203.10 26 Surface area of the main permanent pool (square feet) 21548.00 27 Volume of the main permanent pool (cubic feet) 71664 cf 28 Average depth of the main pool (feet) 3.33 ft 29 Average depth equation used Equation 2 30 If using equation 3, main pool perimeter (feet) 31 If using equation 3, width of submerged veg. shelf (feet) 32 Volume of the forebay (cubic feet) 11876 cf 33 Is this 15-20% of the volume in the main pool? Yes 34 Clean -out depth for forebay (inches) 54 in 35 Design volume of SCM (cu ft) 45874 cf 361 Is the outlet an orifice or a weir? Orifice 37 If orifice, orifice diameter (inches) 3.5 in 38 If weir, weir height (inches) 39 If weir, weir length (inches) 40 Drawdown time for the temporary pool (days) 2.4 41 Are the inlet(s) and outlet located in a manner that avoids short- circuiting? Yes 42 Are berms or baffles provided to improve the flow path? No 43 Depth of forebay at entrance (inches) 66 in 44 Depth of forebay at exit (inches) 60 in 45 Does water flow out of the forebay in a non -erosive manner? Yes 46 Width of the vegetated shelf (feet) 6 ft 47 Slope of vegetated shelf (H:V) 6:1 481 Does the orifice drawdown from below the top surface of the permanent pool? Yes 49 Does the pond minimize impacts to the receiving channel from the 1- yr, 24-hr storm? Yes 50 Are fountains proposed? (If Y, please provide documentation that MDC(9) is met.) No 51 Is a trash rack or other device provided to protect the outlet system? Yes 52 Are the dam and embankment planted in non -clumping turf grass? Yes 53 Species of turf that will be used on the dam and embankment Bermuda b4l Has a planting plan been provided for the vegetated shelf? Yes ADDITIONAL INFORMATION 55 Please use this space to provide any additional information about the wet pond(s): Parcel is state owned land, therefore no drainage easement is required. Original Permit Wet Pond 3 3:52 PM 5/18/2020 SUPPLEMENT-EZ COVER PAGE FORMS LOADED :OJECT INFORMATION 1 Project Name 2 Project Area ac 3 Coastal Wetland Area 4 Surface Water Area ac 5 Is this project High or Low Density? 6 Does this project use an off -site SCM? NCNG 34.4 0.6 H No MOV Expansion Readiness Center COMPLIANCE WITH 02H .1003(4) 7 Width of vegetated setbacks provided (feet) 50 8 Will the vegetated setback remain vegetated? Yes 9 Is BUA other that as listed in .1003 4 c-d out of the setback? No 10 Is streambank stabilization proposed on this project? No NUMBER AND TYPE OF SCMs: 11 Infiltration System 0 12 Bioretention Cell 0 13 Wet Pond 2 14 Stormwater Wetland 0 15 Permeable Pavement 0 16 Sand Filter 0 17 Rainwater Harvesting RWH 0 18 Green Roof 0 19 Level Spreader -Filter Strip LS-FS 0 20 Disconnected Impervious Surface (DIS) 0 21 Treatment Swale 0 22 Dry Pond 0 23 StormFilter 0 24 Silva Cell 0 25 Ba filter 0 26 Filterra 0 FORMS LOADED DESIGNER CERTIFICATION 27 Name and Title: Frank Slinsky, P.E., Senior Project Manager 28 Organization: Timmons Group 29 Street address: 5410 Trinity Road, Suite 102 30 City, State, Zip: Raleigh, NC, 27607 31 Phone numbers : 919 866-4505 32 1 Email: frank.slinsky@timmons.com Certification Statement: I certify, under penalty of law that this Supplement-EZ form and all supporting information were prepared under my direction or supervision, that the information provided in the form is, to the best of my knowledge and belief, true, accurate, and complete, and that the engineering plans, specifications, operation and maintenance agreements and other supporting information are consistent with the information provided here. Signature of Designer Date DRAINAGE AREAS 1 Is this a high density project? Yes 2 If so, number of drainage areas/SCMs 2 3 Is all/part of this project subject to previous rule versions? No FORMS LOADED DRAINAGE AREA INFORMATION Entire Site 1 2 4 Type of SCM Wet Pond Wet Pond 5 Total BUA in project (sq ft 727160 sf 593666 sf 163786 sf 6 New BUA on subdivided lots (subject to permitting) (sq ft 7permitting) New BUA outside of subdivided lots (subject to s 727160 sf 593666 sf 163786 sf 8 Offsite - total area (sq ft 9 Offsite BUA (sq ft 10 Breakdown of new BUA outside subdivided lots: Parking (sq ft 520349 sf 458962 sf 61657 sf Sidewalk (sq ft 33389 sf 33389 sf -- Roof (sq ft 66486 sf 64267 sf 2219 sf Roadway s ft 5045 sf -- 5045 sf Future (sq ft 131891 sf 37048 sf 94865 sf Other, please specify in the comment box below (sq ft 11 New infiltrating permeable pavement on subdivided lots (sq ft 12 New infiltrating permeable pavement outside of subdivided lots (sq ft 13 Exisitng BUA that will remain (not subject to ermitting) (sq ft 14 Existing BUA that is already permitted (sq ft 15 Existing BUA that will be removed (sq ft 16 Percent BUA 77% 80% 81% 17 Design storm inches 1 in 1 in 18 Design volume of SCM cu ft 45874 cf 13132 cf 19 Calculation method for design volume Simple Method Simple Method ADDITIONAL INFORMATION 20 Please use this space to provide any additional information about the drainage area(s): MOV Expansion WET POND F----l]Drainage area number ERAL MDC FROM 02H .1050 A2 I B1 _ I MOV Expansion 31 Is the SCM sized to treat the SW from all surfaces at build -out? Yes Yes 4 Is the SCM located away from contaminated soils? Yes Yes 5 What are the side slopes of the SCM (H:V)? 3:1 3:1 6 Does the SCM have retaining walls, gabion walls or other engineered side slopes? No No 7 Are the inlets, outlets, and receiving stream protected from erosion (10-year storm)? Yes Yes 8 Is there an overflow or bypass for inflow volume in excess of the design volume? What is the method for dewatering the SCM for maintenance? Yes Yes 9 Drawdown Orifice Drawdown Orifice 10 If applicable, will the SCM be cleaned out after construction? Yes Yes 11 Does the maintenance access comply with General MDC (8)? Yes Yes 12 Does the drainage easement comply with General MDC (9)? 13 If the SCM is on a single family lot, does (will?) the plat comply with General MDC (10)? 141 Is there an O&M Agreement that complies with General MDC (11)? Yes Yes 15 Is there an O&M Plan that complies with General MDC (12)? 1 Yes Yes 16 Does the SCM follow the device specific MDC? Yes Yes 17 WET Was the SCM designed by an NC licensed professional? ND MDC FROM 02H .1053 Yes SA/DA Yes SA/DA 18 Method used 19 Has a stage/storage table been provided in the calculations? Yes Yes 201 Elevation of the excavated main pool depth (bottom of sediment removal) (fmsl) 1196.00 1206.00 21 Elevation of the main pool bottom -(top of sediment removal) (fmsl) 1197.00 1207.00 22 Elevation of the bottom of the vegetated shelf (fmsl) 1201.00 1210.00 23 Elevation of the permanent pool (fmsl) 1201.50 1210.50 24 Elevation of the top of the vegetated shelf (fmsl) 1202.00 1211.00 25 Elevation of the temporary pool (fmsl) 1203.10 1206.25 26 Surface area of the main permanent pool (square feet) 21548.00 5502.00 27 Volume of the main permanent pool (cubic feet) 71664 cf 19358 cf 28 Average depth of the main pool (feet) 3.33 ft 3.52 ft 29 Average depth equation used Equation 2 Equation 2 30 If using equation 3, main pool perimeter (feet) 31 If using equation 3, width of submerged veg. shelf (feet) 32 Volume of the forebay (cubic feet) 11876 cf 2968 cf 33 Is this 15-20% of the volume in the main pool? Yes Yes 34 Clean -out depth for forebay (inches) 54 in 54 in 35 Design volume of SCM (cu ft) 45874 cf 13132 cf 36 Is the outlet an orifice or a weir? Orifice Orifice 37 If orifice, orifice diameter (inches) 3.5 in 1.5 in 38 If weir, weir height (inches) 39 If weir, weir length (inches) 40 Drawdown time for the temporary pool (days) 2.4 3.6 41 Are the inlet(s) and outlet located in a manner that avoids short- circuiting? Yes Yes 42 Are berms or baffles provided to improve the flow path? No No 43 Depth of forebay at entrance (inches) 66 in 60 in 44 Depth of forebay at exit (inches) 60 in 51 in 45 Does water flow out of the forebay in a non -erosive manner? Yes Yes 46 Width of the vegetated shelf (feet) 6 ft 6 ft 47 Slope of vegetated shelf (H:V) 6:1 6:1 48 Does the orifice drawdown from below the top surface of the permanent pool? Yes Yes 49 Does the pond minimize impacts to the receiving channel from the 1- yr, 24-hr storm? Yes Yes 50 Are fountains proposed? (If Y, please provide documentation that MDC(9) is met.) No No 51 Is a trash rack or other device provided to protect the outlet system? Yes Yes 52 Are the dam and embankment planted in non -clumping turf grass? Yes Yes 53 Species of turf that will be used on the dam and embankment Bermuda Bermuda 54 Has a planting plan been provided for the vegetated shelf? Yes No ADDITIONAL INFORMATION 55 Please use this space to provide any additional information about the wet pond(s): Parcel is state owned land, therefore no drainage easement is required. Wet Pond 3 12:05 PM 7/15/2021 Operation & Maintenance Agreement Project Name: Project Location: NCNG Morganton Regional Readiness Center Phase 2 5155 Western Avenue, Morganton, NC 28655 Original Permit Cover Page Maintenance records shall be kept on the following BMP(s). This maintenance record shall be kept in a log in a known set location. Any deficient BMP elements noted in the inspection will be corrected, repaired, or replaced immediately. These deficiencies can affect the integrity of structures, safety of the public, and the pollutant removal efficiency of the BMP(s). The BMP(s) on this project include (check all that apply & cc Bioretention Cell Quantity: Dry Detention Basin Grassed Swale Green Roof Infiltration Basin Infiltration Trench Level Spreader/VFS Permeable Pavement Proprietary System Rainwater Harvesting Sand Filter Stormwater Wetland Wet Detention Basin Disconnected Impervious Area User Defined BMP Quantity: Quantity: Quantity: Quantity: Quantity: Quantity: Quantity: Quantity: Quantity: Quantity: Quantity: Quantity: Present: Present: ng O&M tables wil Location(s): Location(s): Location(s): Location(s): Location(s): Location(s): Location(s): Location(s): Location(s): Location(s): Location(s): Location(s): Location(s): Location(s): Location(s): De aciclecl auto I Northwest of the site I I acknowledge and agree by my signature below that I am responsible for the performance of the maintenance procedures listed for each BMP above, and attached O&M tables. I agree to notify NCDENR of any problems with the system or prior to any changes to the system or responsible party. * Responsible Party: Title & Organization: Street address: City, state, zip: Phone number(s): Email: Signature: County of personally appeared before me this Rodney D. Newton Facility Management Officer North Carolina National Guard 1636 Gold Star Drive, Suite 2600 Raleigh, NC, 27607 919-345-6137 rodney.d.newton.mil@mail.mil , a Notary Public for the State of , do hearby certify that day of acknowledge the due execution of the Operations and Maintenance Agreement . Witness my hand and official seal, Date: and STO,RZ Version 1.4 My commission expires 12/13/2019 Page 1 of 5 STORM-EZ 12/13/2019 Version 1.4 O&M Manual Page 2 of 5 Wet Detention Pond Maintenance Requirements The wet detention basin system is defined as the wet detention basin, pretreatment including forebays and the vegetated filter if one is provided. Important maintenance procedures: Immediately after the wet detention basin is established, the plants on the vegetated shelf and perimeter of the basin should be watered twice weekly if needed, until the plants become established (commonly six weeks). No portion of the wet detention pond should be fertilized after the first initial fertilization that is required to establish the plants on the vegetated shelf. Stable groundcover should be maintained in the drainage area to reduce the sediment load to the wet detention basin. If the basin must be drained for an emergency or to perform maintenance, the flushing of sediment through the emergency drain should be minimized to the maximum extent practical. - Once a year, a dam safety expert should inspect the embankment. After the wet detention pond is established, it should be inspected once a month and within 24 hours after every storm event greater than 1.0 inches (or 1.5 inches if in a Coastal County). Records of operation and maintenance should be kept in a known set location and must be available upon request. Inspection activities shall be performed as follows. Any problems that are found shall be repaired immediately. BMP element: Potential problem: How I will remediate the problem: The entire BMP Trash/debris is present. Remove the trash/debris. The perimeter of the BMP Areas of bare soil and/or Regrade the soil if necessary to remove the gully, and then plant a erosive gullies have formed. ground cover and water until it is established. Provide lime and a one- time fertilizer application. Vegetation is too short or too Maintain vegetation at a height of approximately six inches. long. The inlet device The pipe is clogged. Unclog the pipe. Dispose of the sediment off -site. The pipe is cracked or Replace the pipe. otherwise damaged. Erosion is occurring in the Regrade the swale if necessary to smooth it over and provide erosion swale. control devices such as reinforced turf matting or riprap to avoid future problems with erosion. Stone verge is clogged or Remove sediment and replace with clean stone. covered in sediment (if applicable). The forebay Sediment has accumulated to Search for the source of the sediment and remedy the problem if a depth greater than the possible. Remove the sediment and dispose of it in a location where it original design depth for will not cause impacts to streams or the BMP. sediment storage. Erosion has occurred. Provide additional erosion protection such as reinforced turf matting or riprap if needed to prevent future erosion problems. Weeds are present. Remove the weeds, preferably by hand. If pesticide is used, wipe it on the plants rather than spraying. The vegetated shelf Best professional practices Prune according to best professional practices show that pruning is needed to maintain optimal plant health. Plants are dead, diseased or Determine the source of the problem: soils, hydrology, disease, etc. dying. Remedy the problem and replace plants. Provide a one-time fertilizer application to establish the ground cover if a soil test indicates it is necessary. Weeds are present. Remove the weeds, preferably by hand. If pesticide is used, wipe it on the plants rather than spraying. STORM-EZ 12/13/2019 Version 1.4 O&M Manual Page 3 of 5 Wet Detention Pond Maintenance Requirements (Continued) The main treatment area Sediment has accumulated to Search for the source of the sediment and remedy the problem if a depth greater than the possible. Remove the sediment and dispose of it in a location where it original design sediment will not cause impacts to streams or the BMP. storage depth. Algal growth covers over 50% Consult a professional to remove and control the algal growth. of the area. Cattails, phragmites or other Remove the plants by wiping them with pesticide (do not spray). invasive plants cover 50% of the basin surface. The embankment Shrubs have started to grow Remove shrubs immediately. on the embankment. Evidence of muskrat or Use traps to remove muskrats and consult a professional to remove beaver activity is present. beavers. A tree has started to grow on Consult a dam safety specialist to remove the tree. the embankment. An annual inspection by an Make all needed repairs. appropriate professional shows that the embankment needs repair. (if applicable) The outlet device Clogging has occurred. Clean out the outlet device. Dispose of the sediment off -site. The outlet device is damaged Repair or replace the outlet device. The receiving water Erosion or other signs of Contact the local NC Department of Environment and Natural damage have occurred at the Resources Regional Office. outlet. The measuring device used to determine the sediment elevation shall be such that it will give an accurate depth reading and not readily penetrate into accumulated sediments. STORM-EZ 12/13/2019 Version 1.4 O&M Manual Page 4 of 5 Wet Detention Pond Design Summary )riginal Permit Wet Pond Diamiam WET POND ID FOREBAY MAIN POND 1 Permanent Pool El. 1201.5 Permanent Pool El. 1201.5 Temporary Pool El: 1203.1 Temporary Pool El: 1203.1 Pretreatment other No Clean Out Depth: 4.5 Clean Out Depth: 4.5 than forebay? Sediment Removal El: 1197 Sediment Removal El: 1197 Has Veg. Filter? Yes Bottom Elevation: 1196 Bottom Elevation: 1196 STORM-EZ 12/13/2019 Version 1.4 O&M Manual Page 5 of 5 Operation & Maintenance Agreement Project Name: Project Location: NCNG Morganton Regional Readiness Center Phase 2 5155 Western Avenue, Morganton, NC 28655 MOV Expansion Cover Page Maintenance records shall be kept on the following BMP(s). This maintenance record shall be kept in a log in a known set location. Any deficient BMP elements noted in the inspection will be corrected, repaired, or replaced immediately. These deficiencies can affect the integrity of structures, safety of the public, and the pollutant removal efficiency of the BMP(s). The BMP(s) on this project include (check all that apply & cc Bioretention Cell Quantity: Dry Detention Basin Grassed Swale Green Roof Infiltration Basin Infiltration Trench Level Spreader/VFS Permeable Pavement Proprietary System Rainwater Harvesting Sand Filter Stormwater Wetland Wet Detention Basin Disconnected Impervious Area User Defined BMP Quantity: Quantity: Quantity: Quantity: Quantity: Quantity: Quantity: Quantity: Quantity: Quantity: Quantity: Quantity: Present: Present: ig O&M tables will Location(s): Location(s): Location(s): Location(s): Location(s): Location(s): Location(s): Location(s): Location(s): Location(s): Location(s): Location(s): Location(s): Location(s): Location(s): oe aaaea automatical I Northwest of the site. East of the site I I acknowledge and agree by my signature below that I am responsible for the performance of the maintenance procedures listed for each BMP above, and attached O&M tables. I agree to notify NCDENR of any problems with the system or prior to any changes to the system or responsible party. * Responsible Party: Title & Organization: Street address: City, state, zip: Phone number(s): Email: Signature: County of personally appeared before me this Rodney D. Newton Facility Management Officer North Carolina National Guard 1636 Gold Star Drive, Suite 2600 Raleigh, NC, 27607 919-345-6137 rodney.d.newton.mil@mail.mil , a Notary Public for the State of , do hearby certify that day of acknowledge the due execution of the Operations and Maintenance Agreement . Witness my hand and official seal, O&M Manual Date: and 7/14/2021 Page 1 of 5 Seal My commission expires STORM-EZ 7/14/2021 Version 1.4 O&M Manual Page 2 of 5 Wet Detention Pond Maintenance Requirements The wet detention basin system is defined as the wet detention basin, pretreatment including forebays and the vegetated filter if one is provided. Important maintenance procedures: Immediately after the wet detention basin is established, the plants on the vegetated shelf and perimeter of the basin should be watered twice weekly if needed, until the plants become established (commonly six weeks). No portion of the wet detention pond should be fertilized after the first initial fertilization that is required to establish the plants on the vegetated shelf. Stable groundcover should be maintained in the drainage area to reduce the sediment load to the wet detention basin. If the basin must be drained for an emergency or to perform maintenance, the flushing of sediment through the emergency drain should be minimized to the maximum extent practical. - Once a year, a dam safety expert should inspect the embankment. After the wet detention pond is established, it should be inspected once a month and within 24 hours after every storm event greater than 1.0 inches (or 1.5 inches if in a Coastal County). Records of operation and maintenance should be kept in a known set location and must be available upon request. Inspection activities shall be performed as follows. Any problems that are found shall be repaired immediately. BMP element: Potential problem: How I will remediate the problem: The entire BMP Trash/debris is present. Remove the trash/debris. The perimeter of the BMP Areas of bare soil and/or Regrade the soil if necessary to remove the gully, and then plant a erosive gullies have formed. ground cover and water until it is established. Provide lime and a one- time fertilizer application. Vegetation is too short or too Maintain vegetation at a height of approximately six inches. long. The inlet device The pipe is clogged. Unclog the pipe. Dispose of the sediment off -site. The pipe is cracked or Replace the pipe. otherwise damaged. Erosion is occurring in the Regrade the swale if necessary to smooth it over and provide erosion swale. control devices such as reinforced turf matting or riprap to avoid future problems with erosion. Stone verge is clogged or Remove sediment and replace with clean stone. covered in sediment (if applicable). The forebay Sediment has accumulated to Search for the source of the sediment and remedy the problem if a depth greater than the possible. Remove the sediment and dispose of it in a location where it original design depth for will not cause impacts to streams or the BMP. sediment storage. Erosion has occurred. Provide additional erosion protection such as reinforced turf matting or riprap if needed to prevent future erosion problems. Weeds are present. Remove the weeds, preferably by hand. If pesticide is used, wipe it on the plants rather than spraying. The vegetated shelf Best professional practices Prune according to best professional practices show that pruning is needed to maintain optimal plant health. Plants are dead, diseased or Determine the source of the problem: soils, hydrology, disease, etc. dying. Remedy the problem and replace plants. Provide a one-time fertilizer application to establish the ground cover if a soil test indicates it is necessary. Weeds are present. Remove the weeds, preferably by hand. If pesticide is used, wipe it on the plants rather than spraying. STORM-EZ 7/14/2021 Version 1.4 O&M Manual Page 3 of 5 Wet Detention Pond Maintenance Requirements (Continued) The main treatment area Sediment has accumulated to Search for the source of the sediment and remedy the problem if a depth greater than the possible. Remove the sediment and dispose of it in a location where it original design sediment will not cause impacts to streams or the BMP. storage depth. Algal growth covers over 50% Consult a professional to remove and control the algal growth. of the area. Cattails, phragmites or other Remove the plants by wiping them with pesticide (do not spray). invasive plants cover 50% of the basin surface. The embankment Shrubs have started to grow Remove shrubs immediately. on the embankment. Evidence of muskrat or Use traps to remove muskrats and consult a professional to remove beaver activity is present. beavers. A tree has started to grow on Consult a dam safety specialist to remove the tree. the embankment. An annual inspection by an Make all needed repairs. appropriate professional shows that the embankment needs repair. (if applicable) The outlet device Clogging has occurred. Clean out the outlet device. Dispose of the sediment off -site. The outlet device is damaged Repair or replace the outlet device. The receiving water Erosion or other signs of Contact the local NC Department of Environment and Natural damage have occurred at the Resources Regional Office. outlet. The measuring device used to determine the sediment elevation shall be such that it will give an accurate depth reading and not readily penetrate into accumulated sediments. STORM-EZ 7/14/2021 Version 1.4 O&M Manual Page 4 of 5 Wet Detention Pond Design Summary WET POND ID FOREBAY MAIN POND 1 Permanent Pool El. 1201.5 Permanent Pool El. 1201.5 Temporary Pool El: 1203.1 Temporary Pool El: 1203.1 Pretreatment other No Clean Out Depth: 4.5 Clean Out Depth: 4.5 than forebay? Sediment Removal El: 1197 Sediment Removal El: 1197 Has Veg. Filter? Yes Bottom Elevation: 1196 Bottom Elevation: 1196 WET POND ID FOREBAY MAIN POND B Permanent Pool El. 1210.5 Permanent Pool El. 1210.5 Temporary Pool El: 1212.02 Temporary Pool El: 1212.02 Pretreatment other No Clean Out Depth: 3.5 Clean Out Depth: 3.5 than forebay? Sediment Removal El: 1207 Sediment Removal El: 1207 Has Veg. Filter? Yes Bottom Elevation: 1206 Bottom Elevation: 1206 STORM-EZ 7/14/2021 Version 1.4 O&M Manual Page 5 of 5