HomeMy WebLinkAbout20201692 Ver 1_DCM Permit_20210324Permit Class
NEW
Permit Number
32-21
STATE OF NORTH CAROLINA
Department of Environmental Quality
and
Coastal Resources Commission
etmit
for
X Major Development in an Area of Environmental Concern
pursuant to NCGS 113A-118
X Excavation and/or filling pursuant to NCGS 113-229
Issued to Oyster Harbour Homeowner's Association, Inc., 2182 Clambake Court SW, Supply, NC 28462
Authorizing development in Brunswick County at adj. to the AIWW, at 3483 Windy Point Rd.
SW, in Supply , as requested in the permittee's application dated 8/7/20,
including attached workplan drawings (6), Sheets P1-P6 of 6 all dated 8/3/20.
This permit, issued on March 24, 2021 , is subject to compliance with the application (where
consistent with the permit), all applicable regulations, special conditions and notes set forth below. Any violation
of these terms may be subject to fines, imprisonment or civil action; or may cause the permit to be null and void.
Boat Ramp Replacement
1) This permit authorizes only the elevated boat ramp, and other structures and uses located in or over
the water that are expressly and specifically set forth in the permit application. No other structure,
whether floating or stationary, shall become a permanent part of this boat ramp and associated
facility without permit modification. No non -water dependent uses of structures shall be conducted
on, in or over Public Trust waters without permit modification.
2) The boat ramp shall either be poured at an upland location and pushed into place once hardened, or
poured entirely within a watertight containment structure. Live concrete shall not be allowed to
contact waters of the State or waters that will enter waters of the State.
(See attached sheets for Additional Conditions)
This permit action may be appealed by the permittee or other
qualified persons within twenty (20) days of the issuing date.
This permit must be accessible on -site to Department
personnel when the project is inspected for compliance.
Any maintenance work or project modification not covered
hereunder requires further Division approval.
All work must cease when the permit expires on
December 31, 2024
In issuing this permit, the State of North Carolina agrees that
your project is consistent with the North Carolina Coastal
Management Program.
Signed by the authority of the Secretary of DEQ and the Chair
of the Coastal Resources Commission.
For Braxton C. Davis, Director
Division of Coastal Management
This permit and its conditions are hereby accepted.
Signature of Permittee
Oyster Harbour Homeowner's Association, Inc. Permit No. 32-21
Page 2 of 3
ADDITIONAL CONDITIONS
No fill material shall be placed below the normal high water line outside of the areas indicated on the
attached workplan drawings.
Excavation and ground disturbing activities, associated with the placement of the boat ramp, above and
below the normal high water line shall be limited to that absolutely necessary to establish adequate ramp
slope and provide a ramp no greater in size than specified in the attached permit application and
workplan drawings.
If the crossing of wetlands with mechanized construction equipment is necessary, temporary
construction mats shall be utilized for the areas to be crossed. The temporary mats shall be removed
immediately upon completion of construction.
The authorized structures and associated activity shall not cause an unacceptable interference with
navigation and shall not exceed the dimensions shown on the attached permit drawings.
No attempt shall be made by the permittee to prevent the full and free use by the public of all navigable
waters at or adjacent to the authorized work.
The permittee shall install and maintain at his expense any signal lights or signals prescribed by the U.S.
Coast Guard, through regulation or otherwise, on the authorized facilities. At minimum, permanent
reflectors shall be attached to the structure in order to make it more visible during hours of darkness or
inclement weather.
The temporary placement or double handling of excavated or fill materials within waters or vegetated
wetlands is not authorized.
10) No excavated or fill material shall be placed at any time in any vegetated wetlands/marsh or surrounding
waters outside of the alignment of the fill area indicated on the workplan drawing(s).
Sediment and Erosion Control
11) Appropriate sedimentation and erosion control devices, measures or structures shall be implemented to
ensure that eroded materials do not enter adjacent wetlands, watercourses and property.
12) A ground cover sufficient to restrain erosion shall be provided within 30 calendar days of completion of
any phase of grading on cut or filled slopes.
General
13) This permit does not eliminate the need to obtain any additional state, federal or local permits, approvals
or authorizations that may be required, including but not limited to any authorizations required from the
U.S. Army Corps of Engineers.
14) The permittee shall maintain the authorized work in good condition and in conformance with the terms
and conditions of this permit. The permittee is not relieved of this requirement if he or she abandons the
permitted activity without having it transferred to a third party.
Oyster Harbour Homeowner's Association, Inc. Permit No. 32-21
Page 2 of 3
ADDITIONAL CONDITIONS
15) The permittee and/or his or her contractor shall meet with a representative of the Division prior to
project initiation.
16) All debris associated with the removal or construction of the permitted development shall be contained
within the authorized project area and removed to an appropriate upland location.
NOTE: This permit does not eliminate the need to obtain any additional state, federal or local permits,
approvals or authorizations that may be required, including but not limited to any authorizations
required from the U.S. Army Corps of Engineers.
NOTE: The N.C. Division of Water Resources authorized the proposed project by way of General Water
Quality Certification 4175 and assigned the project DWR Project No. 2002-1530v3.
NOTE: Future development of the permittee's property may require a modification of this permit.
Contact a representative of the Division at (910) 796-7215 prior to the commencement of any
such activity for this determination. The permittee is further advised that many non -water
dependent activities are not authorized within 30 feet of the normal high water line.
NOTE: An application processing fee of $400 was received by DCM for this project. This fee also
satisfied the Section 401 application processing fee requirements of the Division of Water
Resources.