August 20, 2020
Subject: Compliance Evaluation Inspection — Non -Compliance Status
State Stormwater Management Permit SW6120306
Dollar General Store - Buffalo Lake Road
Harnett County
Dear Mr. Clodfelter:
On August 18, 2020, a Compliance Evaluation Inspection was conducted at the Dollar General Store - Buffalo Lake Road
facility located at 55 Buffalo Lake Road in Harnett County, North Carolina. Mr. Tim O'Connell, Lead Project Manager with
Rhetson Companies, Inc. was also present during the inspection and his time and assistance is greatly appreciated. The
purpose of the inspection was to ensure compliance with State Stormwater Management Permit SW6120306 that was
issued on April 12, 2012. A copy of the Compliance Inspection Report is enclosed for your review. As a result of the
inspection and subsequent file review, it has been determined that the facility is not in compliance with the conditions of
the subject permit and approved plans.
The required actions that are necessary to bring this site into compliance are noted under the Inspection Summary and
Comments sections of the report. You are asked to provide this office a written/typed response within 30 calendar days
from receipt of this letter. Your response should specify actions that will be undertaken and the time frame that will be
required to correct the deficiencies. Failure to provide the requested information may constitute the issuance of a
Notice of Violation, which is subject to the assessment of a civil penalty of up to $25,000 per day, per violation. If
you have any questions.or this office can be of any assistance, please contact me at (910) 433-9934 or by e-mail at
mike.lawyer@ncdenr.gov.
Sincerely,
� v
Michael Lawyer, CPSWQ
Environmental Program Consultant
DEMLR
Enclosure: Compliance Inspection Report
ec: Tim O'Connell, Lead Project Manager — Rhetson Companies, Inc.
Jennifer Wincklhofer — Rhetson Companies, Inc.
cc: FRO — DEMLR, State Stormwater Files, SW6120306
CJ--�,,,., 11
North Carolina Department of Environmental Quality (t}lvision of Energy. Mineral Land Resources
Fayetteville Regional Office 1 225 Green Street, Suite 7141 Fayetteville. North Carolina 2830t
NOar: a CAR,MI
UWp d..M of Fnukomme W quaEm /"""'� 910.433,3300
Compliance Inspection Report
Permit: SW6120306 Effective:04/12/12 Expiration: 04/12/20
Project: Dollar General Store Buffalo Lake Rd
Owner: Par 5 Development Group LLC
County: Harnett
Region: Fayetteville
Contact Person: Brian R Clodfelter
Directions to Project:
Type of Project: State Stormwater - HD - Infiltration
Drain Areas: 001 - (Barbeque Creek) (03-06-13 ) ( C)
On -Site Representative(s):
On -site representative Tim O'Connell
Related Permits:
Adress: 55 Buffalo Lk Rd
City/State/Zip: Sanford NC 27332
Title: Phone: 910-944-0881
910-944-0881
Inspection Date: 08/18/2020 Entry Time 02:18PM
Primary Inspector: Mike Lawyer Apt
Secondary Inspector(s):
Reason for Inspection: Routine
Permit Inspection Type: State Stormwater
Facility Status: ❑ Compliant Not Compliant
Question Areas:
State Stormwater
(See attachment summary)
Exit Time: 02:47PM
Phone: 910-433-3394
Inspection Type: Compliance Evaluation
page 1
Permit: SW6120306 Owner - Project: Par 5 Development Group LLC
Inspection Date: 08/18/2020 Inspection Type Compliance Evaluation Reason for Visit: Routine
Inspection Summary:
At the time of inspection, it appeared that the associated built -upon area and stormwater control measure (infiltration
basin) had been initially constructed per the stormwater management permit and approved plans. However, it was
apparent that the infiltration basin has not been properly maintained. Vegetative growth and standing water was obsen
throughout the main treatment area, which should be 12" of clean sand. Large trees and shrubs are growing within a
significant portion of the infiltration basin and around the rip rap dissipator receiving bypass flows from the storm drain
splitter box. Due to the standing water and abundance of vegetative growth throughout the infiltration basin, other aspe
of the permitted system such as the forebay and grass filter strip could not be thoroughly evaluated. An area of erosior
at the southern end of the infiltration basin was also observed. Records of inspection and maintenance activities could
not be provided for review upon request.
Appropriate maintenance must be conducted on all parts of the permitted stormwater management system in order to
meet approved design criteria. Upon completion of necessary maintenance, a follow-up inspection will be conducted.
Please note that Stormwater Management Permit SW6120306 expired on April 12, 2020 and must be renewed.
page 2
Permit: SW6120306 Owner - Project: Par 5 Development Group LLC
Inspection Date: 08/18/2020 Inspection Type Compliance Evaluation Reason for Visit: Routine
File Review Yes No NA NE
Is the permit active? ❑ 0 ❑ ❑
Signed copy of the Engineer's certification is in the file? E ❑ ❑ ❑
Signed copy of the Operation & Maintenance Agreement is in the file? 0 ❑ ❑ ❑
Copy of the recorded deed restrictions is in the file? ❑ ❑ E ❑
Comment: Permit expired on April 12, 2020. A permit renewal application will need to be submitted.
Built Upon Area
Is the site BUA constructed as per the permit and approval plans?
Is the drainage area as per the permit and approved plans?
Is the BUA (as permitted) graded such that the runoff drains to the system?
Comment:
SW Measures
Are the SW measures constructed as per the approved plans?
Are the inlets located per the approved plans?
Are the outlet structures located per the approved plans?
Comment:
Operation and Maintenance
Are the SW measures being maintained and operated as per the permit requirements?
Yes No NA NE
■ ❑❑❑
❑ ❑ ❑
■ ❑❑❑
Yes No NA NE
■ ❑❑❑
■ ❑❑❑
■ ❑❑❑
Yes No NA NE
❑ N ❑ ❑
Are the SW BMP inspection and maintenance records complete and available for review or provided to ❑ E ❑ ❑
DWQ upon request?
Comment: The stormwater control measure (infiltration basin) has not been properly maintained. See inspection
summary for details.
Inspection and maintenance records could not be provided for review.
Other Permit Conditions Yes No NA NE
Is the site compliant with other conditions of the permit? 0 ❑ ❑ ❑
Comment:
Other WQ Issues Yes No NA NE
Is the site compliant with other water quality issues as noted during the inspection? ❑ ❑ ❑
Comment:
page 3