HomeMy WebLinkAboutNCC203485_NOT Closeout Documents_20210708North Carolina Department of Environmental Quality
Land Resources: 943 Washington Square Mall, Washington, NC 27889 (252) 946-6481
County: Beaufort Project: Line I82 Removal Wharton Washington River basin: Tar -Pamlico
Person financialy responsible: Virginia Electric and Power Company- Kevin J Project #: BEAUF-2021-001
Fields, Authorized Representative
Address: 10900 Nuckols Rd 4th Floor, Richmond, VA 23060
1. Project Location: Multiple, Washington
Pictures: No
2. Weather and soil conditions: 90 degrees, sunny, dry Initial inspection: No
3. Is site currently under notice of violation? No
4. Is the site in compliance with S.P.C.A. and rules? Yes If no, check violations below:
5. Violations:
6. Is the site in compliance with NPDES Permit NCG010000 Construction Stormwaterrequirements? Yes
Describe:
7. Has sedimentation damage occurred since last inspection? No If Yes, where? (check all that apply)
Degree of damage:
8. Contact made with (name): No contact was made. Title:
Inspection report: Sent Report Date given/sent: July 07, 2021
9. Corrective action needed:
10. Comments: Permanent ground cover sufficient to restrain erosion has been established. No additional self -monitoring
or self -inspections are required. The project is in compliance and released under the SPCA. The permittee must request
termination of coverage under the NPDES General Stormwater Permit for Construction Activities (NCGO 1) via a Notice of
Termination (NOT). The NOT is available at https://edocs.deq.nc.gov/Forms/NCGOI-Termination. Please note that this
correspondence must be uploaded as part of completing the NOT process.
Reportedby: ScottGraboski Others present:
Date of inspection: July 06, 2021 Time arriving on site: 12:00 PM Time leaving site: 12:10 PM