PUBLIC NOTICE SAW- 2001 - 21125- PLANS -File
2
Issue Date: May 24, 2013
Comment Deadline: June 24, 2013
Corps Action ID #: SAW - 2001 -21125
The Wilmington District, Corps of Engineers (Corps) has received an application from The North Carolina
Department of Transportation (NCDOT), seeking Department of the Army (DA) authorization to permanently
impact 7,717 linear feet of jurisdictional stream channel, temporarily impact 438 linear feet of jurisdictional
stream channel, permanently impact 6.13 acres of adjacent wetlands and temporary impact 0.80 acre of
adjacent wetlands. There will also be 4.3 acres of wetland impacts due the hand clearing. These impacts are
associated with the proposed construction of a section of the Greensboro Western Loop from north of SR
2176 (Bryan Boulevard) to SR 2303 (Lawndale Drive) in Greensboro, Guilford County, North Carolina. The
project is proposed to be a six -lane divided facility on new location and totals 4.8 miles in length. This project
is referred to as Transportation Improvement Project (TIP) U- 2524CD. Section C of this project begins
immediately north of SR 2176 (Bryan Boulevard) and terminates immediately east of US220 (Battleground
Avenue) and Section D begins immediately east of Battleground Avenue and ends at SR 2303 (Lawndale
Drive). Permit Drawings of the proposed project have been prepared based on final design for U -2524C and
preliminary design for U- 2524D.
Specific plans and location information are described below and shown on the attached plans. This Public
Notice and all attached plans are also available on the Wilmington District Web Site
at http://www.saw.usace.ar ' / / .
Applicant: North Carolina Department of Transportation
Attn: Ms. Elizabeth Lusk
Project Development and Environmental Analysis
Natural Environment Section
1598 Mail Service Center
Raleigh, North Carolina 27699 -1598
Authority
The Corps will evaluate this application and a decide whether to issue, conditionally issue, or deny the
1 of 4 5/28/2013 10:13 AM
http: / /www.saw.usace. army. mil/ DesldopModules /DigArticle /Print.aspx?P...
proposed work pursuant to the applicable procedures of Section 404 of the Clean Water Act.
Location
The proposed project (U- 2524CD) is located from north of SR 2176 (Bryan Boulevard) to SR 2303
(Lawndale Drive) in Greensboro, Guilford County, North Carolina. Within the proposed construction
footprint there are approximately 24 stream channels, and 19 wetland sites. The project is proposed to impact
a portion of the Horsepen Creek, fifteen (15) unnamed tributaries to Horsepen Creek, a portion of Richland
Creels, five (5) unnamed tributaries to Richland Creels, and fifteen (15) adjacent wetland areas in the Cape
Fear River Basin (8 -Digit Cataloging Unit 03030002). Coordinates (in decimal degrees) for the approximate
center of the site are 36.1377 °N, - 79.8616 0W (NAD83 /WGS84). See attached project location map and
USGS topographic map.
Existing Site Conditions
The project lies within the Piedmont Physiographic Province in the Cape Fear River Basin [Hydrologic Unit
Code (HUC) 03030002]. The project corridor is located in the northwestern portion of Guilford County. The
proposed corridor is mostly undeveloped with a combination of the following land use classifications: single
family, multi- family, open, agricultural, forest and recreational. The extreme western portion of the project is
located within Guilford County and the remainder of the project is located within the City of Greensboro.
Applicant's Stated Purpose
As stated by the applicant, the primary purposes of the project are to: 1) provide an efficient connection for
major thoroughfares such as 1-85,140, High Point Road, West Market Street, and US 220; 2) improve service
for local north -south traffic; and 3) improve access to the Piedmont Triad International Airport and the major
employers in the western section of Greensboro from the north and south.
Project Description
The following description of the work is taken from data provided by the applicant. Plans submitted with the
application show the placement of fill material permanently impacting 7,717 linear feet of jurisdictional
stream channel, temporarily impacting 43 8 linear feet of jurisdictional stream channel, permanently impacting
6.13 acres of adjacent wetlands and temporary impacting 0.80 acre of adjacent wetlands within the Cape Fear
River basin (Hydrologic Categorical Unit 03030002). The proposed 4.8 -mile project consists of constructing a
six -lane divided facility on new location.
The project will involve impacts at twenty -six (26) stream sites, and fifteen (15) adjacent riparian wetland
sites as shown on the attached plans. U2524C will impact 14 unnamed tributaries to Horsepen Creek, a
segment of Horsepen Creek, and 15 adjacent riparian wetland sites. U2524D will impact 1 unnamed tributary
to Horsepen Creek, a segment of Richland Creek and 5 unnamed tributaries to Richland Creek. Impacts at the
U2524C section include 3,113 linear feet of permanent impacts, 3 5 8 linear feet of temporary impacts, 6.13
acres of permanent wetland impacts and 0.80 acre of temporary wetland impacts. These impact totals for
Section U -2524C include 0.52 acre of permanent and 0.79 acre of temporary wetland impacts associated with
utility line relocations. Permanent impacts associated with the utility line relocation are due to mechanized
land clearing and the temporary wetland impacts will involve excavating and side casting the wetland soil to
remove the existing lines and then replacing the side cast soil back into the excavated area. Impacts at the
U2524D section include 4,604 linear feet of permanent stream impacts and 80 linear feet of temporary
impacts.
The applicant proposes compensatory mitigation of impacts which result in a permanent loss of stream
channels with important aquatic function, by providing payment into the North Carolina Ecosystem
Enhancement Program (NCEEP) for 14,758 Warm Stream Mitigation Units. Impacts include 2,775 linear feet
2 of 4 5/28/2013 10:13 AM
http: / /www.saw.usace. army. mil/ DesldopModules /DigArticle /Print.aspx?P...
associated with U -2524C and 4,604 linear feet associated with U- 2524D. Compensatory mitigation for these
stream impacts will all be at a 2:1 ratio and will be purchased within the Cape Fear River Basin (Cataloging
Unit 03030002). The applicant also proposes compensatory mitigation of impacts to adjacent wetlands by
providing payment to the NCEEP for 10.53 riparian wetland credits. NCDOT proposes to provide
compensatory mitigation for 4.40 acres at a 2:1 ratio and for 1.73 acres at a 1:1 ratio. All mitigation units will
be purchased within the Cape Fear River Basin (03030002). In addition to the proposed payment to the
NCEEP, the applicant has avoided and minimized impacts by the proposed use of the following measures:
• Utilization NCDOT's Best Management Practices (BMPs) for the protection of surface waters;
• Use of Design Standards in Sensitive Watersheds throughout the project;
• Minimization of wetland and stream impacts through the proposed construction of 2:1 slopes where
practicable;
• Design of ditches with diffuse flow and velocity reducing discharge points where they drain directly into
wetlands;
• Use of pre-formed scour holes at four (4) locations;
• Use of a hazardous spill basin at five sites where the receiving waters are classified as Critical Area;
• Use of a 1.5:1 fill slope with rock plating at Permit Site 8 to avoid stream impacts.
Other Required Authorizations
This notice and all applicable application materials are being forwarded to the appropriate State agencies for
review. The Corps will generally not make a final permit decision until the North Carolina Division of Water
Quality (NCDWQ) issues, denies, or waives State certification required by Section 401 of the Clean Water
Act (PL 92 -500). The receipt of the application and this public notice in the NCDWQ Central Office in
Raleigh serves as application to the NCDWQ for certification. A waiver will be deemed to occur if the
NCDWQ fails to act on this request for certification within sixty days of the date of the receipt of this notice
in the NCDWQ Central Office. Additional information regarding the Clean Water Act certification may be
reviewed at the NCDWQ Central Office, 401 Oversight and Express Permits Unit, 2321 Crabtree Boulevard,
Raleigh, North Carolina 27604 -2260. All persons desiring to make comments regarding the application for
certification under Section 401 of the Clean Water Act should do so in writing delivered to the North Carolina
Division of Water Quality (NCDWQ), 1650 Mail Service Center, Raleigh, North Carolina 27699 -1650,
Attention: Mrs. Jennifer Burdette by June 13, 2013.
Essential Fish Habitat
This notice initiates the Essential Fish Habitat (EFE) consultation requirements of the Magnuson- Stevens
Fishery Conservation and Management Act. The Corps' initial determination is that the proposed project will
not adversely impact EFH or associated fisheries managed by the South Atlantic or Mid Atlantic Fishery
Management Councils or the National Marine Fisheries Service.
Cultural Resources
The Corps has consulted the latest published version of the National Register of Historic Places and is not
aware that any registered properties, or properties listed as being eligible for inclusion therein will be affected
by the proposed work. The NCDOT, Human Environment Section, Historic Architecture Group has provided
information also indicating that no registered properties, or properties listed as being eligible for inclusion
therein will be affected by the proposed work. Presently, unknown archeological, scientific, prehistoric, or
3 of 4 5/28/2013 10:13 AM
http: / /www.saw.usace. army. mil/ DesldopModules /DigArticle /Print.aspx?P...
historical data may be located within the project area and /or could be affected by the proposed work.
Endangered Species
The Corps has reviewed the project area, examined all information provided by the applicant and consulted
the latest North Carolina Natural Heritage Database. Based on available information, the Corps is not aware
of the presence of species listed as threatened or endangered or their critical habitat formally designated
pursuant to the Endangered Species Act of 1973 (ESA) within the project area. A final determination on the
effects of the proposed project will be made upon additional review of the project and completion of any
necessary biological assessment and /or consultation with the U.S. Fish and Wildlife Service.
Evaluation
The decision whether to issue a permit will be based on an evaluation of the probable impacts, including
cumulative impacts, of the proposed activity on the public interest. That decision will reflect the national
concern for both protection and utilization of important resources. The benefit which reasonably may be
expected to accrue from the proposal must be balanced against its reasonably foreseeable detriments. All
factors which may be relevant to the proposal will be considered including the cumulative effects thereof;
among those are conservation, economics, aesthetics, general environmental concerns, wetlands, historic
properties, fish and wildlife values, flood hazards, flood plain values (in accordance with Executive Order 1
1988), land use, navigation, shoreline erosion and accretion, recreation, water supply and conservation, water
quality, energy needs, safety, food and fiber production, mineral needs, considerations of property ownership,
and, in general, the needs and welfare of the people. For activities involving the discharge of dredged or fill
materials in waters of the United States, the evaluation of the impact of the activity on the public interest will
include application of the Environmental Protection Agency's 404(b)(1)guidelines.
Commenting Information
The Corps is soliciting comments from the public; Federal, State and local agencies and officials, including
any consolidate State Viewpoint or written position of the Governor; Indian Tribes and other interested parties
in order to consider and evaluate the impacts of this proposed activity. Any comments received will be
considered by the Corps to determine whether to issue, modify, condition or deny a permit for this proposal.
To make this decision, comments are used to assess impacts on endangered species, historic properties, water
quality, general environmental effects and the other public interest factors listed above. Comments are used in
the preparation of an Environmental Assessment (EA) and /or an Environmental Impact Statement (EIS)
pursuant to the National Environmental Policy Act (NEPA). Comments are also used to determine the need
for a public hearing and to determine the overall public interest of the proposed activity.
Any person may request, in writing, within the comment period specified in this notice that a public hearing
be held to consider the application. Requests for public hearings shall state, within particularity, the reasons
for holding a public hearing. Requests for a public hearing shall be granted, unless the District Engineer
determines that the issues raised are insubstantial or there is otherwise no valid interest to be served by a
hearing.
Written comments pertinent to the proposed work, as outlined above, will be received by the Corps of
Engineers, Wilmington District, until 5pm, June 24, 2013. Comments should be submitted to Andrew