HomeMy WebLinkAboutNC0068888_Correspondence_20210628Mayor
Rick Coleman
Aldermen
Jerry Cearley
Allen Huggins
Darlene Morrow
Hoyle Withers
Town Manager
Maria Struope
Town Clerk
Shannon Whittle
Town Attorney
Thomas Hunn
Public Works
Bill Trudnak
Electrical
J. Doug Huffman
Police Chief
Robert Walls
Planning
David Kahler
Fire Chief
Earl Withers
Recreation
Brandon Whitener
Town of Dallas
210 N. Holland St.
Dallas, NC 28034
Phone:
704-922-3176
Fax:
704-922-4701
Web Page:
www.dallasnc.ne
Public ."
�. 4
Ihe C'ro3srca s o 6aston Cou
June 22, 2021
Ori Tuvia
Mooresville Regional Office
610 East Center Ave.
Mooresville, N.C. 28115
Received: NOTICE OF VIOLATION
Tracking Number: NOV-2021-LV-0449
Permit No. NC0068888
Dallas WWTP
Gaston County
RECEIVEDINCDEQIDWR
JUN 2 8
WORDS
MOORESVILLE REGIONAL OFFICE
Sir,
On February 13th, 2021, through February 15th the Dallas Waste Water Treatment Plant experienced
a total of 3 3/4 inches of rain. The heaviest of which was on February 15th, a total of 2 3/4 inches within
an hour. It led to these limit violations.
SAMPLE LOCATION Date LIMIT SAMPLE VAULE VIOLATION
001 Effluent BOD
001 Effluent TSS
001 Effluent TSS
2/20/21
2/20/21
2/28/21
39 68.37 Weekly Average Exceeded
45 86.98 Weekly Average Exceeded
30 30.05 Monthly Average Exceeded
During the rain event I made the effort to try and hold the WW'1'P within permit limits and prevent
it from hydraulic overloading by turning RAS fully open on East Basin and West Basin and had waste
valves open at same time. Filling both digesters up during rain event. Which would give proper time for
treatment by taking some of the high flow. I Also shut blower one off to help keep solids down during
high flow The flow rate just exceeded the system's designed flow rate. Effectively causing these
violations of our permit. We regret going non -compliant that corresponding week and for the month.
We thrive to stay within permit limits and meet all guidelines. New measures are currently under
construction to take some of the flow off the plant. There is an interconnect being constructed to take
150,000 gallons a day and reroute it to Gastonia's Long Creek WWTP. Which will give our plant a much
needed break until we can upgrade. The interconnect is under construction now and scheduled to be
complete December 2021.
Any questions concerning this non -compliant event are welcome.
Thank You,
Michael Stafford/ORC