HomeMy WebLinkAboutSW6201202_Plan (Misc. Detail)_20210325it
VARIES _I' 6'
(SWALE) (SHOULDER)
1
U
a .5' CARRY BASE COURSE 6"
BEYOND SURFACE COURSE
0 8%
N
\\2\\\/qj\/
1 � \
3
�1
3
50' PUBLIC R/W
20'
COMPACTED
SUBGRADE
GEOTECHNICAL ENGINEER SHOULD BE
CONSULTED TO DETERMINE DEPTH OF ABC
NEEDED TO MEET NCDOT REQUIREMENTS
ROADWAY TYPICAL SECTION (WITH DITCH)
TEMPORARY SEEDING/MULCHING SPECIFICATIONS (FOR LATE WINTER AND EARLY SPRING)
SEEDING MIXTURE:
SPECIES RATE (LB./ACRE)
RYE (GRAIN) 120
SWITCHGRASS 50
SEEDING DATES:
JANUARY 1 - MAY 1
SOIL AMENDMENTS:
FOLLOW RECOMMENDATIONS OF SOIL TESTS OR APPLY 2,000 LBJACRE GROUND AGRICULTURAL LIMESTONE AND 750
LB./ACRE 10-10-10 FERTILIZER.
MULCH:
APPLY 4,000 LB./ACRE STRAW. ANCHOR STRAW BY TACKING WITH ASPHALT, NETTING, OR A MULCH ANCHORING TOOL.
A DISK WITH BLADES SET NEARLY STRAIGHT CAN BE USED AS A MULCH ANCHORING TOOL.
MAINTENANCE:
REFERTILIZE IF GROWTH IS NOT FULLY ADEQUATE. RESEED, REFERTILIZE AND MULCH IMMEDIATELY FOLLOWING
EROSION OR OTHER DAMAGE.
TEMPORARY SEEDING/MULCHING SPECIFICATIONS (FOR SUMMER)
SEEDING MIXTURE:
SPECIES RATE (LB./ACRE)
GERMAN MILLET 40
A SMALL -STEMMED SUDANGRASS MAY BE SUBSTITUTED AT A RATE OF 50 LBJACRE.
SEEDING DATES:
MAY 1- AUGUST 15
SOIL AMENDMENTS:
FOLLOW RECOMMENDATIONS OF SOIL TESTS OR APPLY 2,000 LBJACRE GROUND AGRICULTURAL LIMESTONE AND 750
LB./ACRE 10-10-10 FERTILIZER.
MULCH:
APPLY 4,000 LBJACRE STRAW. ANCHOR STRAW BY TACKING WITH ASPHALT, NETTING, OR A MULCH ANCHORING TOOL.
A DISK WITH BLADES SET NEARLY STRAIGHT CAN BE USED AS A MULCH ANCHORING TOOL.
MAINTENANCE:
REFERTILIZE IF GROWTH IS NOT FULLY ADEQUATE. RESEED, REFERTILIZE AND MULCH IMMEDIATELY FOLLOWING
EROSION OR OTHER DAMAGE.
TEMPORARY SEEDING/MULCHING SPECIFICATIONS (FOR FALL)
SEEDING MIXTURE:
SPECIES RATE (LB./ACRE)
RYE (GRAIN) 120
SEEDING DATES:
AUGUST 15 - DECEMBER 30
SOIL AMENDMENTS:
FOLLOW RECOMMENDATIONS OF SOIL TESTS OR APPLY 2,000 LBJACRE GROUND AGRICULTURAL LIMESTONE AND
1,000 LB./ACRE 10-10-10 FERTILIZER.
MULCH:
APPLY 4,000 LBJACRE STRAW. ANCHOR STRAW BY TACKING WITH ASPHALT, NETTING, OR A MULCH ANCHORING TOOL.
A DISK WITH BLADES SET NEARLY STRAIGHT CAN BE USED AS A MULCH ANCHORING TOOL.
MAINTENANCE:
REPAIR AND REFERTILIZE DAMAGED AREAS IMMEDIATELY. TOP DRESS WITH 50 LB./ACRE OF NITROGEN IN MARCH. IF
IT IS NECESSARY TO EXTEND TEMPORARY COVER BEYOND JUNE 15, OVERSEED WITH 50 LBJACRE KOBE LESPEDEZA
IN LATE OR EARLY MARCH.
SEEDING SPECIFICATIONS
SEEDING MIXTURES
SPECIES RATE (LBS./ACRE
PENSACOLA BAHIAGRASS 50
INDIAN WOODOATS 2.5
VIRGINIA WILD RYE 6
EASTERN BOTTLEBRUSH GRASS 2.5
WHEAT 30
6'
(SHOULDER)
5'
8%
1
3
THIS IS FOR
FILL SECTION
USE 3:1 CUT SLOPES IN CUT SECTIONS
SEEDING NOTES:
1. FROM SEPT. 1 TO MAR. 1 USE UNSCARIFIED SERICEA SEED.
2. ON POORLY DRAINED SITES OMIT SERICEA AND INCREASE KOBE TO 30 LB./ACRE.
3. WHERE A NEAT APPEARANCE IS DESIRED, OMIT SERICEA AND INCREASE KOBE TO 40 LB./ACRE.
NURSE PLANTS:
BETWEEN APRIL 15 AND AUG. 15, ADD 10 LB./ACRE OF GERMAN MILLET OR 15 LB./ACRE SUDANGRASS. PRIOR TO MAY 1
OR AFTER AUG. 15, ADD 25 LB./ACRE RYE (GRAIN).
SEEDING DATES:
BEST POSSIBLE
EARLY SPRING: FEB. 15 - MAR. 20 FEB. 15 - APR. 30
FALL: SEPT. 1 - SEPT. 30 SEPT. 1 - OCT. 31
SOIL AMENDMENTS:
APPLY LIME AND FERTILIZER ACCORDING TO SOIL TEST, OR APPLY 3,000 - 5,000 LB./ACRE GROUND AGRICULTURAL
LIMESTONE (USE THE LOWER RATE ON SANDY SOILS) AND 1,000 LB./ACRE 10-10-10 FERTILIZER.
MULCH:
APPLY 4,000 LB./ACRE GRAIN STRAW OR EQUIVALENT COVER OF ANOTHER SUITABLE MULCH. ANCHOR STRAW BY
TACKING WITH ASPHALT, NETTING, OR ROVING OR BY CRIMPING WITH A MULCH ANCHORING TOOL. A DISK WITH
BLADES SET NEARLY STRAIGHT CAN BE USED AS A MULCH ANCHORING TOOL.
MAINTENANCE:
IF GROWTH IS LESS THAN FULLY ADEQUATE, REFERTILIZE IN THE SECOND YEAR, ACCORDING TO THE SOIL TESTS OR
RESEED, FERTILIZE, AND MULCH DAMAGED AREAS IMMEDIATELY.
SEEDING SPECIFICATIONS
SEEDING MIXTURE:
SPECIES RATE (LB./ACRE)
LITTLE BLUESTEM 7
SWEET WOODREED 2.5
BROWNTOP MILLET 10
RICE CUTGRASS 6
SEEDING DATES:
COASTAL PLAIN: APR. - JULY
SOIL AMENDMENTS:
APPLY LIME AND FERTILIZER ACCORDING TO SOIL TEST, OR APPLY 3,000 LB./ACRE GROUND AGRICULTURAL LIMESTONE
AND 500 LB./ACRE 10-10-10 FERTILIZER.
MULCH:
USE JUTE, EXCELSIOR MATTING, OR OTHER EFFECTIVE CHANNEL LINING MATERIAL TO COVER THE BOTTOM OF
CHANNELS AND DITCHES. THE LINING SHOULD EXTEND ABOVE THE HIGHEST CALCULATED DEPTH OF FLOW. ON
CHANNEL SIDE SLOPES ABOVE THIS HEIGHT, AND IN DRAINAGES NOT REQUIRING TEMPORARY LININGS, APPLY 4,000
LB./ACRE GRAIN STRAW AND ANCHOR STRAW BY STAPLING NETTING OVER THE TOP.
MULCH AND ANCHORING MATERIALS MUST NOT BE ALLOWED TO WASH DOWN SLOPES WHERE THEY CAN CLOG
DRAINAGE DEVICES.
MAINTENANCE:
A MINIMUM OF 3 WEEKS IS REQUIRED FOR ESTABLISHMENT. INSPECTION AND REPAIR MULCH FREQUENTLY.
REFERTILIZE THE FOLLOWING APR. WITH 50 LB./ACRE NITROGEN.
NTS
3 TEMPORARY
SEEDING
SPECIFICATIONS
4 PERMANENT SEEDING
SPECIFICATIONS
DESIGN CRITERIA
AGGREGATE SIZE - USE 2-3 INCH WASHED STONE
DIMENSION OF GRAVEL PAD
GRAVEL ENTRANCE SHALL FEET
IN LENGTH AND 12 FEET IN WIDTH
THICKNESS - 6 INCHES MINIMUM
GROUND
STABILIZATION CHART
WITH 2O FOOT RADIUS AT EXISTING
WIDTH- 12 FT. MINIMUM OR FULL WIDTH AT ACCESS
ROADWAY
POINTS OF THE VEHICULAR ENTRANCE AND EXIT
36-0" MIN 4'-0" 10'-0"
AREA, WHICHEVER IS GREATER
SITE AREA
STABILIZATION
STABILIZATION TIME
s"�
LENGTH- 50 FT. MINIMUM.
DESCRIPTION
TIME FRAME
FRAME EXCEPTIONS
LOCATION - LOCATE CONSTRUCTION ENTRANCES AND
EXITS TO LIMIT SEDIMENT FROM LEAVING THE SITE
AND TO PROVIDE FOR MAXIMUM UTILITY BY ALL
PERIMETER DIKES,
FILTER FABRIC
2-3" WASHED STONE
CONSTRUCTION VEHICLES. AVOID STEEP GRADES
AND ENTRANCES AT CURVES IN PUBLIC ROADS.
SWALES, DITCHES
7 DAYS
NONE
AND SLOPES
GRAVEL CONSTRUCTION ENTRANCE
CONTRACTOR SHALL INSTALL ADDITIONAL GRAVEL
CONSTRUCTION ENTRANCES NOT INDICATED ON THE PLANS
REQUIRED FOR STAGING AND/OR BORROW AREAS AND
HIGH QUALITY
MAINTAIN AT NO ADDITIONAL EXPENSE TO THE OWNER.
WATER (HQW)
7 DAYS
NONE
CONTRACTOR SHALL SUPPLEMENT AND MAINTAIN GRAVEL
CONSTRUCTION ENTRANCES AT HIS EXPENSE UNTIL FINAL
ZONES
ACCEPTANCE.
GP
Q /IF
SLOPES ARE 10' OR
SLOPES STEEPER
LESS IN LENGTH AND ARE
G
Z,,&O
MAINTENANCE
7 DAYS
THAN 3:1
NOT STEEPER THAN 2: 1 ,
MAINTAIN THE GRAVEL PAD INBA CONDITION TO PREVENT MUD OR
14 DAYS ARE ALLOWED
/
SEDIMENT FROM LEAVING THE CONSTRUCTION SITE. THIS MAY
50,
REQUIRE PERIODIC TOPDRESSING WITH 2-INCH STONE. AFTER EACH
RAINFALL, INSPECT ANY STRUCTURE USED TO TRAP SEDIMENT AND
SLOPES 3:1 OR
7-DAYS FOR SLOPES
CLEAN IT OUT AS NECESSARY. IMMEDIATELY REMOVE ALL
14 DAYS
GREATER THAN 50 FEET
/
OBJECTIONABLE MATERIALS SPILLED, WASHED OR TRACKED ONTO
FLATTER
IN LENGTH
PUBLIC ROADWAYS.
NONE
O
ALL OTHER AREAS
(EXCEPT FOR
WITH SLOPES FLATTER
14 DAYS
PERIMETERS AND
��•
THAN 4:1
HQW ZONES)
AGGREGATE_
GROUND STABILIZATION CHART
NTS NTS
9 TEMPORARY GRAVEL CONSTRUCTION ENTRANCE
COMPACTED
SUBGRADE
CARRY BASE COURSE 6"
BEYOND SURFACE COURSE
AT LOCATIONS WITHOUT
CURB AND GUTTER
2 ASPHALT PAVEMENT
1. UNLESS OTHERWISE INDICATED, ALL VEGETATIVE AND
STRUCTURAL EROSION AND SEDIMENT CONTROL MEASURES SHALL
BE CONSTRUCTED AND MAINTAINED IN ACCORDANCE WITH THE
MINIMUM STANDARDS AND SPECIFICATIONS OF THE NORTH
CAROLINA EROSION AND SEDIMENT CONTROL HANDBOOK.
2. THE CONTRACTOR SHALL NOTIFY PLAN APPROVING AUTHORITY
ONE WEEK PRIOR TO THE PRECONSTRUCTION CONFERENCE, ONE
WEEK PRIOR TO THE COMMENCEMENT OF LAND DISTURBING
ACTIVITY, AND ONE WEEK PRIOR TO FINAL INSPECTION.
3. IF POSSIBLE ALL EROSION AND SEDIMENT CONTROL MEASURES
ARE TO BE PLACED PRIOR TO CLEARING AND/OR LAND DISTURBANCE
4. A COPY OF THE APPROVED EROSION AND SEDIMENT CONTROL
PLAN AND PERMIT SHALL BE MAINTAINED ON THE SITE AT ALL TIMES.
5. PRIOR TO COMMENCING LAND DISTURBING ACTIVITIES IN AREAS
OTHER THAN INDICATED ON THESE PLANS (INCLUDING, BUT NOT
LIMITED TO OFF -SITE BORROW OR WASTE AREAS, STAGING OR
STORAGE AREAS), THE CONTRACTOR SHALL PREPARE AND SUBMIT
A SUPPLEMENTARY EROSION CONTROL PLAN TO THE OWNER FOR
REVIEW AND TO NCDENR REGIONAL OFFICE FOR APPROVAL.
CONTRACTOR SHALL PAY ALL FEES REQUIRED AND SHALL INSTALL
NECESSARY MEASURES AT NO SEPARATE PAYMENT. THE
CONTRACTOR SHALL PROVIDE THE OWNER AND THE ENGINEER A
COPY OF THE AMENDED PERMIT.
6. THE CONTRACTOR IS RESPONSIBLE FOR INSTALLATION OF ANY
ADDITIONAL EROSION CONTROL MEASURES NECESSARY TO PREVENT
EROSION AND SEDIMENTATION AS DETERMINED BY EITHER NCDENR
OR THE ENGINEER.
cV
00
COMPACTED
C
NTS
7. ALL DISTURBED AREAS ARE TO DRAIN TO APPROVED SEDIMENT
CONTROL MEASURES AT ALL TIMES DURING LAND DISTURBING
ACTIVITIES AND DURING SITE DEVELOPMENT UNTIL FINAL
STABILIZATION IS ACHIEVED.
8. ALL AREAS DISTURBED BY CONSTRUCTION UNLESS OTHERWISE
IMPROVED SHALL BE SODDED OR SEEDED AS INDICATED AND
STABILIZED.
9. DURING DEWATERING OPERATIONS, WATER SHALL BE PUMPED
INTO AN APPROVED FILTERING DEVICE PRIOR TO DISCHARGE TO
RECEIVING OUTLET.
10. THE CONTRACTOR SHALL INSPECT ALL EROSION CONTROL
MEASURES WEEKLY AND AFTER EACH RUNOFF -PRODUCING EVENT
ANY NECESSARY REPAIRS OR CLEANUP TO MAINTAIN THE
EFFECTIVENESS OF THE EROSION CONTROL DEVICES SHALL BE
MADE IMMEDIATELY.
11. ALL TEMPORARY EROSION CONTROL MEASURES SHALL BE
REMOVED BY CONTRACTOR ONCE STABILIZATION OR A SUFFICIENT
GROUND COVER HAS BEEN ESTABLISHED OR AS DIRECTED BY THE
ENGINEER. NCDENR'S FINAL APPROVAL IS REQUIRED.
12. TEMPORARY GRAVEL CONSTRUCTION ENTRANCE SHALL BE
REQUIRED AT ALL CONSTRUCTION STAGING AREA ENTRANCES AND
ALL CONSTRUCTION ACCESS LOCATIONS INTO NON -PAVED AREA.
13. WHEN CROSSING CREEK OR DRAINAGE -WAY, THE CONTRACTOR
SHALL RIP -RAP WITH FABRIC DISTURBED BANKS AND CHANNEL AND
RESTORE SLOPES TO ORIGINAL CONTOURS, BUT NOT STEEPER THAN
2:1 MAXIMUM. DISTURBED CREEK AREA SHALL BE STABILIZED
IMMEDIATELY.
PLAN VIEW
INFLOW
STRUCTURE
SKIMMER
DEWATERING
DEVICE
ON STONE
BEDDING
MIN 8"
BAFFLES
INFLOW
EMERGENCY
SPILLWAY
EMBANKMENT
1' FREEBOARD
DEWATERING
ZONEE
FILTER FABRIC/ STONE BEDDING
SEDIMENT
STORAGE ZONE
CONSTRUCTION SPECIFICATIONS
1. CLEAR, GRUB & STRIP TOPSOIL FROM AREAS UNDER THE EMBANKMENT TO
REMOVE TREES, VEGETATION, ROOTS AND OTHER OBJECTIONABLE MATERIAL.
PLACE TEMPORARY SEDIMENT CONTROLS BELOW THE BASIN AS NEEDED.
2. ENSURE THAT FILL MATERIAL FOR THE EMBANKMENT IS FREE OF ROOTS,
WOOD VEGETATION, ORGANIC MATTER AND OTHER OBJECTIONABLE MATERIAL
PLACE THE FILL IN LIFTS NOT TO EXCEED 9 INCHES AND MACHINE COMPACT IT.
OVER FILL THE EMBANKMENT 6 INCHES TO ALLOW FOR SETTLEMENT.
3. SHAPE THE BASIN TO THE SPECIFIED DIMENSIONS. PREVENT THE SKIMMING
DEVICE FROM SETTLING INTO THE MUD BY EXCAVATING A SHALLOW PIT UNDER
THE SKIMMER OR PROVIDING A LOW SUPPORT UNDER THE SKIMMER OF STONE
OR TIMBER.
4. PLACE THE BARREL ON A FIRM, SMOOTH FOUNDATION OF IMPERVIOUS SOIL.
PLACE THE FILL MATERIAL AROUND THE PIPE SPILLWAY IN 4 INCH LAYERS AND
COMPACT IT UNDER AND AROUND THE PIPE TO AT LEAST THE SAME DENSITY AS
THE ADJACENT EMBANKMENT. PLACE A MINIMUM OF 2 FEET OF COMPACTED
BACKFILL OVER THE PIPE SPILLWAY BEFORE CROSSING IT WITH CONSTRUCTION
EQUIPMENT.
5. ASSEMBLE THE SKIMMER FOLLOWING THE MANUFACTURER'S INSTRUCTIONS
6. LAY THE ASSEMBLED SKIMMER ON THE BOTTOM OF THE BASIN WITH THE
FLEXIBLE JOINT AT THE INLET OF THE BARREL PIPE. ATTACHED THE FLEXIBLE
JOINT TO THE BARREL PIPE AND POSITION THE SKIMMER OVER THE EXCAVATED
PIT. ATTACH A ROPE TO THE SKIMMER AND ANCHOR IT TO THE SIDE OF THE
BASIN.
7. INSTALL THE SPILLWAY IN UNDISTURBED SOIL TO THE GREATEST EXTEND
POSSIBLE. THE SPILLWAY SHOULD BE LINED WITH LAMINATED PLASTIC OR
IMPERMEABLE GEOTEXTILE FABRIC. THE FABRIC MUST BE WIDE AND LONG
ENOUGH TO COVER THE BOTTOM AND SIDES AND EXTEND ONTO THE TOP OF
THE DAM FOR ANCHORING IN A TRENCH. THE EDGES MAY BE SECURED WITH 8
INCH STAPLES. THE FABRIC MUST BE LONG ENOUGH TO EXTEND DOWN THE
SLOPE AND EXIT ONTO STABLE GROUND. THE WIDTH OF THE FABRIC MUST BE
ONE PIECE. IF MULTIPLE SECTIONS AREA REQUIRED, THE UPPER SECTION
SHOULD OVERLAP THE LOWER SECTION SO THAT WATER CANNOT FLOW UNDER
THE FABRIC.
8. DISCHARGE WATER INTO THE BASIN TO PREVENT EROSION. USE TEMPORARY
SLOPE DRAINS OR DIVERSIONS WITH OUTLET PROTECTION TO DIVERT SEDIMENT
LADEN WATER TO THE UPPER END OF THE POOL AREA TO IMPROVE BASIN TRAP
EFFICIENCY.
9. CONSTRUCT THE STRUCTURE SO THAT THE DISTURBED AREA IS MINIMIZED.
DIVERT SURFACE WATER AWAY FROM BARE AREAS. COMPLETE THE
EMBANKMENT BEFORE THE AREA IS CLEARED.
10. INSTALL POROUS BAFFLES AS SPECIFIED.
11. AFTER ALL SEDIMENT PRODUCING AREAS HAVE BEEN STABILIZED, REMOVE
THE STRUCTURE AND ALL THE UNSTABLE SEDIMENT. SMOOTH THE AREA TO
BLEND WITH THE ADJOINING AREAS AND STABILIZE PROPERLY.
EMERGENCY SPILLWAY
EMERGENC'
6" MIN. INVE T ELEVATION OF
SPILLWAY
I
SCH 40 PVC **SKIMMER CAN BE PURCHASED FROM J.W. FAIRCLOTH & SON INC.
PIPE SKIMMER CHOSEN SHALL BE EQUAL TO THE FAIRCLOTH SKIMMER.
SKIMMER
MAINTENANCE
INSPECT SKIMMER SEDIMENT BASINS WEEKLY AND AFTER EACH PERIOD OF
SIGNIFICANT RAINFALL. REMOVE SEDIMENT AND RESTORE TRAP TO ITS ORIGINAL
DIMENSIONS WHEN THE SEDIMENT HAS ACCUMULATED TO ONE-HALF THE HEIGHT
OF THE FIRST BAFFLE. EXCAVATE SEDIMENT FROM THE ENTIRE BASIN. MAKE SURE
VEGETATION GROWING IN THE BOTTOM OF THE BASIN DOES NOT HOLD DOWN THE
SKIMMER. PLACE THE SEDIMENT THAT IS REMOVED IN AN AREA WITH SEDIMENT
CONTROLS.
REPAIR THE BAFFLES IF THEY ARE DAMAGED. RE -ANCHOR THE BAFFLES IF WATER
IS FLOWING UNDERNEATH OR AROUND THEM.
UNCLOGGED THE SKIMMER AS NEEDED. CHECK TO MAKE SURE ORIFICE INSIDE OF
THE SKIMMER IS NOT CLOGGED; IF SO, REMOVE THE DEBRIS. IF SKIMMER ARM OR
BARREL IS CLOGGED, REMOVE THE ORIFICE AND CLEAR THE DEBRIS.
CHECK THE FABRIC LINED SPILLWAY FOR DAMAGE AND MAKE ANY REQUIRED
REPAIRS WITH FABRIC THAT SPANS THE FULL WIDTH OF THE SPILLWAY. CHECK
THE EMBANKMENT, SPILLWAYS AND OUTLET FOR EROSION DAMAGE. MAKE ALL
NECESSARY REPAIRS IMMEDIATELY. REMOVE TRASH AND DEBRIS FROM THE
SKIMMER AND POOL AREAS.
5
GENERAL EROSION AND SEDIMENT CONTROL NOTES
I 6
TEMPORARY SKIMMER BASIN
NOTES:
1. GRADE THE BASIN SUCH THAT THE BOTTOM IS LEVEL
DRIVE POSTS 24" INTO THE GROUND
ATTACH WIRE FENCE TO POSTS AND EXTEND
2. INSTALL THE BAFFLES AS SHOWN ON THE GRADING PLAN.
MAXIMUM 4' O.C. AND EXCAVATE A 4" X 8"
THE BOTTOM OF THE FENCE 8" INTO THE
BAFFLES SHALL EXTEND THE FULL WIDTH OF THE BASIN.
TRENCH UPHILL ALONG THE LINE OF
EXCAVATED TRENCH AND TURNED OUT 4" IN
POSTS.
THE TRENCH. SUPPORT WIRE OR
3. DO NOT SPLICE THE FABRIC, USE A CONTINUOUS PIECE
ROPE
ACCROSS THE BASIN OR TRAP.
STEEL POSTS
4. POSTS FOR THE BAFFLES SHALL BE 4' OC.
STEEL POST
EARTH BERM F�OV
MAINTENANCE
1. INSPECT THE BAFFLES EACH ACTIVE DAY ON SITE BUT IN
NO CASE LESS THAN ONCE PER WEEK AND AFTER EACH
RAINFALL EVENT. MAKE ANY REPAIRS IMMEDIATELY.
BOTTOM ANCHORED
WITH STAPLES
2. REMOVE SEDIMENT DEPOSITS WHEN THE MEASURE
REACHES HALF FULL. TAKE CARE TO AVOID DAMAGING THE
BAFFLES WHEN THE SEDIMENT IS REMOVED.
3. TEMPORARY MEASURE SHALL NOT BE REMOVED BY THE
5
CONTRACTOR UNTIL THIS ACTION IS APPROVED BY AN
NCDENR REPRESENTATIVE. THE ACTION WILL BE
APPROVED WHEN THE CONTRIBUTING DRAINAGE AREA IS
INLET ZONE
STEP 1
STEE2
STABLE.
35% OF SURFACE AREA
4. PLACEMENT OF BAFFLES:
ATTACH THE JUTE NETTING OR OTHER FABRIC
BACKFILL THE TRENCH AND COMPACT THE SOIL
INLET ZONE- 35% OF LENGTH FROM ENTRY POINT
APPROVED BY THE ENGINEER TO THE STAY WIRE
FIRMLY TO ANCHOR THE BOTTOM OF THE SILT
FIRST CELL - 25% OF LENGTH FROM INLET ZONE
FIRST CHAMBER
AND POSTS, EXTEND THE BOTTOM OF THE FABRIC
FENCE. BURIED FABRIC SHALL NOT BE VISIBLE.
SECOND CELL - 25% OF LENGTH FROM FIRST CELL
25% OF SURFACE AREA
8" INTO THE TRENCH AND TURNED OUT 4" IN THE
THE TOP OF THE FABRIC SHALL BE 6" HIGHER
OUTLET ZONE - 15 % OF LENGTH FROM SECOND CELL
TRENCH OR USE 8" EROSION CONTROL MATTING
THAN THE WEIR.
SECOND CHAMBER
STAPLES.
25% OF SURFACE AREA
POSTS MAX 4' O.C.
TOP STAY WIRE OR ROPE
OUTLET ZONE
15% OF SURFACE AREA
A
- JUTE NETTING OR EQUIVILENT
IQ
x OF FABRIC BURIED 8"
a IN EXCAVATED TRENCH &
= TURNED OUT 4" IN THE
PERSPECTIVE VIEW
FBOTTOM
Q TRENCH, OR PINNED WITH 8"
w EROSION CONTROL MATTING
4A24"
STAPLES.
FLOW
STEEL POST DRIVEN
INTO GROUND
STEP 3
STEP 4
SECTION A -A
NTS
NTS
7
POROUS BAFFLES
DRIVE STEEL POSTS 18" INTO THE GROUND
ATTACH WIRE FENCE TO POSTS AND EXTEND
NOTES:
MAXIMUM 8' O.C. AND EXCAVATE A 4" X 8"
THE BOTTOM OF THE FENCE 8" INTO THE
TRENCH UPHILL ALONG THE LINE OF
POSTS.
EXCAVATED TRENCH AND TURNED OUT
4" IN THE TRENCH
1. WIRE SHALL BE A MINIMUM OF 32 INCHES IN WIDTH AND
L = THE DISTANCE SUCH THAT POINTS
A AND B ARE OF EQUAL ELEVATION
CENTER OF THE DAM IS
TO BE 9" LOWER THAN
THE EDGES (MIN)
1.5'
TO FORM A WEIR A MIN.
9" MIN.
FILTER FABRIC J
CHANNEL OR DITCH CLA/ %
SS A OR B EROSION
APPLICATION CONTROL STONE
A
MAINTENANCE
1. INSPECT THE CHECK DAMS AFTER EACH RAINFALL BUT IN NO
CENTER OF THE DAM IS
TO BE 9" LOWER THAN
THE EDGES (MIN)
TO FORM A WEIR
(-�ty� 24" MAX.
J AT CENTER
CASE LESS THAN ONCE PER WEEK FILTER FABRIC
3. REMOVE SEDIMENT DEPOSITS AS NECESSARY TO PROVIDE
ADEQUATE STORAGE VOLUME FOR THE NEXT RAIN. TAKE CARE SECTION A -A
TO AVOID UNDERMINING THE DAM DURING CLEANOUT.
3. CLEAN OR REPLACE THE STONE WHEN IT SHOWS SIGNS OF
CLOGGING OR OTHERWISE DOES NOT PERFORM CORRECTLY
4. WEIR SECTION MUST BE 9" LOWER THAN ABUTMENTS
5. DOWNSTREAM APRON LENGTH SHOULD BE 3 TIMES THE
HEIGHT OF THE WEIR.
10 CHECK DAM WITH WEIR
NTS
TOP & BOTTOM STRAND SHALL HAVE A MINIMUM OF 6 WIRES WITH 12" STAY SPACING.
MIN. 10 GA. WIRE
2. FILTER FABRIC SHALL BE A MINIMUM OF 36" IN WIDTH AND
STAY WIRES SHALL BE FASTENED ADEQUATELY TO THE WIRE WITH #9 WIRE
MIN. 12-1/2 GA STAPLES 1-1/2" LONG. FABRIC THAT DETERIORATES TO SUCH
LINE WIRES EXTENT THAT ITS EFFECTIVENESS IS REDUCED SHALL BE
MIN. 12-1/2 GA. REPLACED BY CONTRACTOR AT CONTRACTOR'S EXPENSE.
3. STEEL POSTS SHALL BE A MIN. OF 5' HEIGHT AND SHALL BE
THE SELF FASTENER ANGLE STEEL TYPE.
4. CONTRACTOR SHALL REVIEW SILT FENCE ONCE PER WEEK
AND AFTER EACH RAINFALL OCCURRENCE. ANY NECESSARY
_ REPAIRS OR CLEAN-UP TO MAINTAIN THE EFFECTIVENESS OF
THE DEVICE SHALL BE MADE IMMEDIATELY.
ICI 5. REMOVE DEPOSITED SEDIMENT ALONG THE FENCE TO
PROVIDE ADEQUATE STORAGE VOLUME AND TO REDUCE
PRESSURE ON THE FENCE AS NEEDED.
STEP 1 STEP 2 0 5. TEMPORARY MEASURE SHALL NOT BE REMOVED BY THE
CONTRACTOR UNTIL THIS ACTION IS APPROVED BY AN NCDENR
ATTACH THE FILTER FABRIC TO THE WIRE FENCE, BACKFILL THE TRENCH AND COMPACT THE SOIL REPRESENTATIVE. THE ACTION WILL BE APPROVED WHEN THE
EXTEND THE BOTTOM OF THE FABRIC 8" INTO THE FIRMLY TO ANCHOR THE BOTTOM OF THE SILT CONTRIBUTING DRAINAGE AREA IS STABLE.
TRENCH AND TURNED OUT 4" IN THE TRENCH. FENCE. BURIED FABRIC SHALL NOT BE VISIBLE.
POSTS MAX 8' O.C.
WIRE FENCE "HOG WIRE"
A FILTER FABRIC
x #9 WIRE STAPLES 1-112" LONG
Q
BOTTOM OF WIRE FENCE AND
111J��� FILTER FABRIC BURIED 8" IN
`I w EXCAVATED TRENCH & TURNED
x OUT 4" IN THE TRENCH
_FLOW
STEEL POST DRIVEN
24" INTO GROUND
A
STEP 3 STEP 4 � SECTION A -A
MAINTENANCE
1. INSPECT SEDIMENT FENCES AT LEAST ONCE A WEEK AND AFTER EACH RAINFALL. MAKE ANY REQUIRED REPAIRS IMMEDIATELY.
2. SHOULD THE FABRIC OF A SEDIMENT FENCE COLLAPSE, TEAR, DECOMPOSE OR BECOME INEFFECTIVE, REPLACE IT PROMPTLY.
3. REMOVE SEDIMENT DEPOSITS AS NECESSARY TO PROVIDE ADEQUATE STORAGE VOLUME FOR THE NEXT RAIN AND TO REDUCE
PRESSURE ON THE FENCE. TAKE CARE TO AVOID UNDERMINING THE FENCE DURING CLEANOUT. ■ T /�
4. REMOVE ALL FENCING MATERIALS AND UNSTABLE SEDIMENT DEPOSITS AND BRING THE AREA TO GRADE AND STABILIZE AFTER NTS
THE CONTRIBUTING DRAINAGE AREA HAS BEEN PROPERLY STABILIZED AND NCDENR APPROVES REMOVAL.
SILT FENCE
4Dsite
solutions
civil engineering I land surveying
409 Chicago Drive, Suite.U2, Fayetteville, NC 28306
office 910-426-6777 fax 1910-426-5777 license number I C-2354
www.4Dsitesotutions.com
``�Y`IICARO,�
```
�� i O` O es ^ '�•�L
SEA
02
G I IN .•: `�
••......
V//;, 00
v3
REVISIONS
PROJECT NAME
FAITHWILL
FARMS
SUBDIVISION
SITE & EROSION
CONTROL
DETAILS
CLIENT
0Lff
Construction
AM, Sr
409 Chicago Drive - Suite 103
Fayetteville, North Carolina 28306
Phone: (910) 779-0019
PROJECT INFORMATION
DESIGNED BY:
CALEB
DRAWN BY:
CALEB
CHECKED BY:
SCOTT
PROJECT NUMBER:
1691
DRAWING SCALE
NOT TO SCALE
DATE RELEASED
MARCH 25, 2021
SHEET NUMBER
C-600
it
PIPE OUTLE
WELL-DEFINED
PLAN
GRAVEL OR FABRIC
MAINTENANCE
1. INSPECT THE OUTLET PROTECTION
AFTER EACH RAINFALL BUT IN NO
CASE LESS THAN ONCE PER WEEK.
ANY STONES THAT THAT HAVE BEEN
DISLODGED SHOULD BE REPLACED
AND ANY EROSION AROUND THE
OUTLET SHOULD BE REPAIRED.
L
. D
FILTER LAYER
GRAVEL OR FABRIC
NOTES
1. LA IS THE LENGTH OF THE RIPRAP
APRON.(SEE EC PLAN)
2. D = 1.5 TIMES THE MAXIMUM
STONE DIAMETER BUT NOT LESS
THAN 6".
3. IN A WELL-DEFINED CHANNEL EXTEND
THE APRON THE REQUIRED 4' WIDTH
OR UP TO THE TOP OF THE CHANNEL
BANKS, WHICHEVER IS LESS.
4. A FILTER FABRIC OR BLANKET SHOULD BE
INSTALLED BETWEEN THE RIPRAP
AND SOIL FOUNDATION.
NTS
TYPICAL RIP RAP APRON
GRASSED OR RIP RAP LINED SWALE
NOTE: THIS CROSS SECTION IS TO BE USED FOR THE
ENTIRE LENGTH OF THE SWALE.
SEE PLAN FOR WIDTH
GRASS COVER TO CONSIST OF SEE PLAN �
MIXTURE OF THE FOLLOWING: FOR DEPTH,\
TALL FESCUE �'`" 1
PENSACOLA BAHIAGRASS SEE PLAN SEE PLAN
SERICEA LESPEDEZA
KOBE LESPEDEZA
2
3
MAINTENANCE
GROUND
CONSTRUCTION SPECIFICATIONS:
1. REMOVE ALL TREES, BRUSH, STUMPS, AND OTHER
COMPACTED OBJECTIONABLE MATERIAL FROM THE FOUNDATION AREA.
SUBGRADE 2. EXCAVATE THE CHANNEL AND SHAPE IT TO NEAT LINES
AND DIMENSIONS SHOWN ON THE PLANS PLUS 0.2 FT
OVERCUT AROUND THE CHANNEL PERIMETER TO ALLOW
FOR BULKING DURING SEEDBED PREPARATIONS AND SOD
BUILDUP.
3. REMOVE AND PROPERLY DISPOSE OF ALL EXCESS SOIL
SO THAT SURFACE WATER MAY ENTER THE CHANNEL
FREELY.
4. ESTABLISH GRASS IN THE CHANNEL IMMEDIATELY.
MAINTENANCE & CONSTRUCTION
1. INSPECT THE SWALE FOR EROSION ONCE A WEEK AND AFTER EVERY RAINFALL.
2. IMMEDIATELY REPAIR AND/OR REPLACE ANY DAMAGED AREAS.
3. MAINTAIN PROPER CROSS SECTION UNTIL THE SWALE IS STABLE.
4. KEEP THE GRASS IN A HEALTHY, VIGOROUS CONDITION AT ALL TIMES.
TYPICAL SWALE CROSS SECTION
3
0
LASS 1 RIP RAP
(SEE SECTION THRU BASIN BELOW)
LASS 1 RIP RAP HEADWALL
57 WASHED STONE
\\ 1' THICKX THIGH MIN.
/ \ SEDIMENT STORAGE AREA
PERSPECTIVE VIEW
NOT TO SCALE
FLOO
STORAGE NATURAL GROUND
ZONE 1'I 2' I RIP RAP HEADWALL
SEDIMENT ....
STORAGE 1.5 _ _ FL01N
'FL0�=1.5' ,;,r;;�,;y IPEINVERT
#57 FILTER FABRIC
MAX SEDIMENT DEPT WASHED LASS 1 RIP -RAP CONSTRUCTION SPECIFICATIONS
(CLEAN OUT POINT) STONE
SECTION THRU BASIN FILTER & CULVERT PIPE
NOT TO SCALE
INSPECT ROCK PIPE INLET PROTECTION AT LEAST WEEKLY AND AFTER
EACH SIGNIFICANT (1/2" OR GREATER) RAINFALL EVENT AND REPAIR
IMMEDIATELY. REMOVE SEDIMENT AND RESTORE THE SEDIMENT
STORAGE AREA TO ITS ORIGINAL DIMENSIONS WHEN THE SEDIMENT HAS
ACCUMULATED TO 1/2 THE DESIGN DEPTH OF THE TRAP. PLACE THE
SEDIMENT THAT IS REMOVED IN THE DESIGNATED DISPOSAL AREA AND
REPLACE THE CONTAMINATED PART OF THE GRAVEL FACING.
CHECK THE STRUCTURE FOR DAMAGE. ANY RIPRAP DISPLACED FROM
THE STONE HORSESHOE MUST BE REPLACED IMMEDIATELY.
NTS
1. CLEAR THE AREA OF ALL DEBRIS.
2. INSTALL THE CLASS B OR CLASS I RIPRAP IN A SEMI -CIRCLE AROUND
THE PIPE INLET.
3. A 1 FOOT THICK LAYER OF NCDOT #5 OR #57 STONE SHOULD BE
PLACED ON THE OUTSIDE SLOPE OF THE RIPRAP.
4. SEDIMENT STORAGE AREA SHOULD BE EXCAVATED AROUND THE
OUTSIDE OF THE STONE HORSESHOE 18" BELOW NATURAL GRADE.
5. WHEN THE CONTRIBUTING DRAINAGE AREA HAS BEEN STABILIZED, FILL
DEPRESSION AND ESTABLISH FINAL GRADING ELEVATIONS, COMPACT,
AND STABILIZE WITH GROUND COVER.
ROCK PIPE INLET PROTECTION
BAG TO BE PLACED r HIGH STRENGTH SEWN IN SPOUT
ON AGGREGATED BASE - / DOUBLE STITCHED F
/ 'J" TYPE SEAMS
HIGH STRENGTH
STRAPPING FOR
HOLDING HOSE
IN PLACE
PUP DISCHARGE
HOSE
NOTES:
1. USE NO 5 OR NO 57 STONE FOR SEDIMENT CONTROL STONE.
2. PROVIDE STABILIZED OUTLET TO STREAM BANK.
3. WOOD PALLETS MAY BE USED IN LIEU OF STONE AND GEOTEXTILE AS DIRECTED. A
SUFFICIENT NUMBER OF PALLETS MUST BE PROVIDED TO ELEVATE THE ENTIRE SPECIAL
STILLING BASIN ABOVE NATURAL GROUND.
4. THE SIZE AND NUMBER OF SILT BAGS SHOULD BE BASED ON THE DEWATERING PUMP AND
MANUFACTURER RECOMMENDATIONS.
5. TIGHTLY SECURE THE PUMP DISCHARGE TO THE SILT BAG SLEEVE WITH A STRAP OR
SIMILAR DEVICE TO PREVENT WATER/SEDIMENT FROM LEAKING WITHOUT TREATMENT.
6. CONTROL PUMPING RATE TO PREVENT EXCESSIVE PRESSURE WITHIN THE SILT BAG IN
ACCORDANCE WITH THE MANUFACTURER RECOMMENDATIONS, AS THE BAG FILLS WTHIN
SEDIMENT, REDUCE PUMP RATE.
7. REPLACE THE SILT BAG WHEN ONE HALF (2) FULL OF SEDIMENT.
8. SILT BAG DEVICE MUST BE GREATER THAN OR EQUAL TO 50 FT FROM THE TOP OF THE
STREAM BANK AND WATER MUST BE DISCHARGED IN A DIFFUSE MANNER.
NTS
NTS
GROUND STABILIZATION AND MATERIALS HANDLING PRACTICES FOR COMPLIANCE WITH
THE NCGO1 CONSTRUCTION GENERAL PERMIT
Implementing the details and specifications on this plan sheet will result in the construction
activity being considered compliant with the Ground Stabilization and Materials Handling
sections of the NCGO1 Construction General Permit (Sections E and F, respectively). The
permittee shall comply with the Erosion and Sediment Control plan approved by the
delegated authority having jurisdiction. All details and specifications shown on this sheet
may not apply depending on site conditions and the delegated authority having jurisdiction.
SECTION E: GROUND STABILIZATION
Required Ground Stabilization
Timeframes
Stabilize within this
Site Area Description
many calendar
Timeframe variations
days after ceasing
land disturbance
(a) Perimeter dikes,
swales, ditches, and
7
None
perimeter slopes
(b) High Quality Water
7
None
(HQW) Zones
(c) Slopes steeper than
If slopes are 10' or less in length and are
3:1
7
not steeper than 2:1, 14 days are
allowed
-7 days for slopes greater than 50' in
length and with slopes steeper than 4:1
-7 days for perimeter dikes, swales,
(d) Slopes 3:1 to 4:1
14
ditches, perimeter slopes and HQW
Zones
-10 days for Falls Lake Watershed
-7 days for perimeter dikes, swales,
(e) Areas with slopes
ditches, perimeter slopes and HQW Zones
flatter than 4:1
14
-10 days for Falls Lake Watershed unless
there is zero slope
Note: After the permanent cessation of construction activities, any areas with temporary
ground stabilization shall be converted to permanent ground stabilization as soon as
practicable but in no case longer than 90 calendar days after the last land disturbing
activity. Temporary ground stabilization shall be maintained in a manner to render the
surface stable against accelerated erosion until permanent ground stabilization is achieved.
GROUND STABILIZATION SPECIFICATION
Stabilize the ground sufficiently so that rain will not dislodge the soil. Use one of the
techniques in the table below:
Temporary Stabilization
Permanent Stabilization
• Temporary grass seed covered with straw or
• Permanent grass seed covered with straw or
other mulches and tackifiers
other mulches and tackifiers
• Hydroseeding
• Geotextile fabrics such as permanent soil
• Rolled erosion control products with or
reinforcement matting
without temporary grass seed
• Hydroseeding
• Appropriately applied straw or other mulch
• Shrubs or other permanent plantings covered
• Plastic sheeting
with mulch
• Uniform and evenly distributed ground cover
sufficient to restrain erosion
• Structural methods such as concrete, asphalt or
retaining walls
• Rolled erosion control products with grass seed
POLYACRYLAMIDES (PAMS) AND FLOCCULANTS
1. Select flocculants that are appropriate for the soils being exposed during
construction, selecting from the NC DWR List of Approved PAMS/Flocculants.
2. Apply I flocculants at or before the inlets to Erosion and Sediment Control Measures.
3. Apply flocculants at the concentrations specified in the NC DWR List of Approved
PAMS/Flocculants and in accordance with the manufacturer's instructions.
4. Provide ponding area for containment of treated Stormwater before discharging
offsite.
5. Store flocculants in leak -proof containers that are kept under storm -resistant cover
or surrounded by secondary containment structures.
EQUIPMENT AND VEHICLE MAINTENANCE
1. Maintain vehicles and equipment to prevent discharge of fluids.
2. Provide drip pans under any stored equipment.
3. Identify leaks and repair as soon as feasible, or remove leaking equipment from the
project.
4. Collect all spent fluids, store in separate containers and properly dispose as
hazardous waste (recycle when possible).
5. Remove leaking vehicles and construction equipment from service until the problem
has been corrected.
6. Bring used fuels, lubricants, coolants, hydraulic fluids and other petroleum products
to a recycling or disposal center that handles these materials.
LITTER, BUILDING MATERIAL AND LAND CLEARING WASTE
1. Never bury or burn waste. Place litter and debris in approved waste containers.
2. Provide a sufficient number and size of waste containers (e.g dumpster, trash
receptacle) on site to contain construction and domestic wastes.
3. Locate waste containers at least 50 feet away from storm drain inlets and surface
waters unless no other alternatives are reasonably available.
4. Locate waste containers on areas that do not receive substantial amounts of runoff
from upland areas and does not drain directly to a storm drain, stream or wetland.
5. Cover waste containers at the end of each workday and before storm events or
provide secondary containment. Repair or replace damaged waste containers.
6. Anchor all lightweight items in waste containers during times of high winds.
7. Empty waste containers as needed to prevent overflow. Clean up immediately if
containers overflow.
8. Dispose waste off -site at an approved disposal facility.
9. On business days, clean up and dispose of waste in designated waste containers.
PAINT AND OTHER LIQUID WASTE
1. Do not dump paint and other liquid waste into storm drains, streams or wetlands.
2. Locate paint washouts at least 50 feet away from storm drain inlets and surface
waters unless no other alternatives are reasonably available.
3. Contain liquid wastes in a controlled area.
4. Containment must be labeled, sized and placed appropriately for the needs of site.
5. Prevent the discharge of soaps, solvents, detergents and other liquid wastes from
construction sites.
PORTABLE TOILETS
1. Install portable toilets on level ground, at least 50 feet away from storm drains,
streams or wetlands unless there is no alternative reasonably available. If 50 foot
offset is not attainable, provide relocation of portable toilet behind silt fence or place
on a gravel pad and surround with sand bags.
2. Provide staking or anchoring of portable toilets during periods of high winds or in high
foot traffic areas.
3. Monitor portable toilets for leaking and properly dispose of any leaked material.
Utilize a licensed sanitary waste hauler to remove leaking portable toilets and replace
with properly operating unit.
EARTHEN STOCKPILE MANAGEMENT
1. Show stockpile locations on plans. Locate earthen -material stockpile areas at least
50 feet away from storm drain inlets, sediment basins, perimeter sediment controls
and surface waters unless it can be shown no other alternatives are reasonably
available.
2. Protect stockpile with silt fence installed along toe of slope with a minimum offset of
five feet from the toe of stockpile.
3. Provide stable stone access point when feasible.
4. Stabilize stockpile within the timeframes provided on this sheet and in accordance
with the approved plan and any additional requirements. Soil stabilization is defined
as vegetative, physical or chemical coverage techniques that will restrain accelerated
erosion on disturbed soils for temporary or permanent control needs.
,
i NO C: ROU N
• / , I 1WAA3 • • • , • • • •
PART III
SELF -INSPECTION, RECORDKEEPING AND REPORTING
SECTION A: SELF -INSPECTION
Self -inspections are required during normal business hours in accordance with the table
below. When adverse weather or site conditions would cause the safety of the inspection
personnel to be in jeopardy, the inspection may be delayed until the next business day on
which it is safe to perform the inspection. In addition, when a storm event of equal to or
greater than 1.0 inch occurs outside of normal business hours, the self -inspection shall be
performed upon the commencement of the next business day. Any time when inspections
were delayed shall be noted in the Inspection Record.
Frequency
Inspect
(during normal
Inspection records must include:
business hours)
(1) Rain gauge
Daily
Daily rainfall amounts.
maintained in
If no daily rain gauge observations are made during weekend or
good working
holiday periods, and no individual -day rainfall information is
order
available, record the cumulative rain measurement for those un-
attended days (and this will determine it a site inspection is
needed). Days on which no rainfall occurred shall be recorded as
"zero." The permittee may use another rain -monitoring device
approved bythe Division,
(2) E&SC
At least once per
1. Identification of the measures inspected,
Measures
7 calendar days
2. Date and time of the inspection,
and within 24
3. Name of the person performing the inspection,
hours of a rain
4. Indication of whether the measures were operating
event > 1.0 inch in
properly,
24 hours
5. Description of maintenance needs for the measure,
6. Description, evidence, and date of corrective actions taken.
(3) Stormwater
At least once per
1. Identification of the discharge outfalls inspected,
discharge
7 calendar days
2. Date and time of the inspection,
outfalls (SDOS)
and within 24
3. Name of the person performing the inspection,
hours of a rain
4. Evidence of indicators of Stormwater pollution such as oil
event> 1.0 inch in
sheen, floating or suspended solids or discoloration,
24 hours
5. Indication of visible sediment leaving the site,
6. Description, evidence, and date of corrective actions taken.
(4) Perimeter of
At least once per
If visible sedimentation is found outside site limits, then a record
site
7 calendar days
of the following shall be made:
and within 24
1. Actions taken to clean up or stabilize the sediment that has left
hours of a rain
the site limits,
event> 1.0 inch in
2. Description, evidence, and date of corrective actions taken, and
24 hours
3. An explanation as to the actions taken to control future
releases.
(5) Streams or
At least once per
If the stream or wetland has increased visible sedimentation or a
wetlands onsite
7 calendar days
stream has visible increased turbidity from the construction
or offsite
and within 24
activity, then a record of the following shall be made:
(where
hours of a rain
1. Description, evidence and date of corrective actions taken, and
accessible)
event> 1.0 inch in
2. Records of the required reports to the appropriate Division
24 hours
Regional Office per Part III, Section C, Item (2)(a) of this permit
of this permit.
(6) Ground
After each phase
1. The phase of grading (installation of perimeter E&SC
stabilization
of grading
measures, clearing and grubbing, installation of storm
measures
drainage facilities, completion of all land -disturbing
activity, construction or redevelopment, permanent
ground cover).
2. Documentation that the required ground stabilization
measures have been provided within the required
timeframe or an assurance that they will be provided as
soon as possible.
NOTE: The rain inspection resets the required 7 calendar day inspection requirement.
o ka ,) NORTH V CA OLINA
Envifronm en tat Quality
PART III
SELF -INSPECTION, RECORDKEEPING AND REPORTING
SECTION B: RECORDKEEPING
1. E&SC Plan Documentation
The approved E&SC plan as well as any approved deviation shall be kept on the site. The
approved E&SC plan must be kept up-to-date throughout the coverage under this permit.
The following items pertaining to the E&SC plan shall be documented in the manner
described:
Item to Document
Documentation Requirements
(a) Each E&SC Measure has been installed
Initial and date each E&SC Measure on a copy
and does not significantly deviate from the
of the approved E&SC Plan or complete, date
locations, dimensions and relative elevations
and sign an inspection report that lists each
shown on the approved E&SC Plan.
E&SC Measure shown on the approved E&SC
Plan. This documentation is required upon the
initial installation of the E&SC Measures or if
the E&SC Measures are modified after initial
installation.
(b) A phase ofgrading has been completed.
Initial and date a copy of the approved E&SC
Plan or complete, date and sign an inspection
report to indicate completion of the
construction phase.
c Ground cover is located and installed
()
Initial and date a co of the a roved E&SC
PY PP
in accordance with the approved E&SC
Plan or complete, date and sign an inspection
Plan.
report to indicate compliance with approved
ground cover specifications.
(d) The maintenance and repair
Complete, date and sign an inspection report.
requirements for all E&SC Measures
have been performed.
(e) Corrective actions have been taken
Initial and date a copy of the approved E&SC
to E&SC Measures.
Plan or complete, date and sign an inspection
report to indicate the completion of the
corrective action.
2. Additional Documentation
In addition to the E&SC Plan documents above, the following items shall be kept on the
site
and available for agency inspectors at all times during normal business hours, unless the
Division provides a site -specific exemption based on unique site conditions that make this
requirement not practical:
(a) This general permit as well as the certificate of coverage, after it is received.
(b) Records of inspections made during the previous 30 days. The permittee shall record
the required observations on the Inspection Record Form provided by the Division Or
a similar inspection form that includes all the required elements. Use of
electronically -available records in lieu of the required paper copies will be allowed if
shown to provide equal access and utility as the hard -copy records.
(c) All data used to complete the Notice of Intent and older inspection records shall be
maintained for a period of three years after project completion and made available
upon request. [40 CFR 122.41]
CONCRETE WASHOUTS
1. Do not discharge concrete or cement slurry from the site.
2. � or recycle Dispose of settled hardened concrete residue in accordance with local
p
and state solid waste regulations and at an approved facility.
3. Manage washout from mortar mixers in accordance with the above item and in
addition place the mixer and associated materials on impervious barrier and within
lot perimeter silt fence.
4. Install temporary concrete washouts per local requirements, where applicable. If an
alternate method or product is to be used, contact your approval authority for
review and approval. If local standard details are not available, use one of the two
types of temporary concrete washouts provided on this detail.
5. Do not use concrete washouts for dewatering or storing defective curb or sidewalk
sections. Stormwater accumulated within the washout may not be pumped into or
discharged to the storm drain system or receiving surface waters. Liquid waste must
be pumped out and removed from project.
6. Locate washouts at least 50 feet from storm drain inlets and surface waters unless it
can be shown that no other alternatives are reasonably available. At a minimum,
install protection of storm drain inlet(s) closest to the washout which could receive
spills or overflow.
7. Locate washouts in an easily accessible area, on level ground and install a stone
entrance pad in front of the washout. Additional controls may be required by the
approving authority.
8. Install at least one sign directing concrete trucks to the washout within the project
limits. Post signage on the washout itself to identify this location.
9. Remove leavings from the washout when at approximately 75% capacity to limit
overflow events. Replace the tarp, sand bags or other temporary structural
components when no longer functional. When utilizing alternative or proprietary
products, follow manufacturer's instructions.
10. At the completion of the concrete work, remove remaining leavings and dispose of
in an approved disposal facility. Fill pit, if applicable, and stabilize any disturbance
caused by removal of washout.
HERBICIDES, PESTICIDES AND RODENTICIDES
1. Store and apply herbicides, pesticides and rodenticides in accordance with label
restrictions.
2. Store herbicides, pesticides and rodenticides in their original containers with the
label, which lists directions for use, ingredients and first aid steps in case of
accidental poisoning.
3. Do not store herbicides, pesticides and rodenticides in areas where flooding is
possible or where they may spill or leak into wells, stormwater drains, ground water
or surface water. If a spill occurs, clean area immediately.
4. Do not stockpile these materials onsite.
IAZARDOUS AND TOXIC WASTE
1. Create designated hazardous waste collection areas on -site.
2. Place hazardous waste containers under cover or in secondary containment.
3. Do not store hazardous chemicals, drums or bagged materials directly on the ground
EFFECTIVE: 04/01 / 19
SELF -INSPECTION, RECORDKEEPING AND REPORTING
SECTION C: REPORTING
1. Occurrences that must be reported
Permittees shall report the following occurrences:
(a) Visible sediment deposition in a stream or wetland.
(b) Oil spills if:
• They are 25 gallons or more,
• They are less than 25 gallons but cannot be cleaned up within 24 hours,
• They cause sheen on surface waters (regardless of volume), or
• They are within 100 feet of surface waters (regardless of volume).
a Releases of hazardous substances in excess of reportable quantities under Section 311
() p
of the Clean Water Act (Ref: 40 CFR 110.3 and 40 CFR 117.3) or Section 102 of CERCLA
(Ref: 40 CFR 302.4) or G.S. 143-215.85.
(b) Anticipated bypasses and unanticipated bypasses.
(c) Noncompliance with the conditions of this permit that may endanger health or the
environment.
2. Reporting Timeframes and Other Requirements
After a permittee becomes aware of an occurrence that must be reported, he shall contact
the appropriate Division regional office within the timeframes and in accordance with the
other requirements listed below. Occurrences outside normal business hours may also be
reported to the Division's Emergency Response personnel at (800) 662-7956, (800)
858-0368 or (919) 733-3300.
Occurrence
Reporting Timeframes (After Discovery) and Other Requirements
(a) Visible sediment
• Within 24 hours, an oral or electronic notification.
deposition in a
• Within 7 calendar days, a report that contains a description of the
stream or wetland
sediment and actions taken to address the cause of the deposition.
Division staff may waive the requirement for a written report on a
case -by -case basis.
• If the stream is named on the NC 303(d) list as impaired for sediment -
related causes, the permittee may be required to perform additional
monitoring, inspections or apply more stringent practices if staff
determine that additional requirements are needed to assure compliance
with the federal or state impaired waters conditions.
(b) Oil spills and
• Within 24 hours, an oral or electronic notification. The notification
release of
shall include information about the date, time, nature, volume and
hazardous
location of the spill or release.
substances per Item
1(b)-(c) above
(c) Anticipated
A report at least ten days before the date of the bypass, if possible.
bypasses [40 CFR
The report shall include an evaluation of the anticipated quality and
122.41(m)(3)]
effect of the bypass.
(d) Unanticipated
• Within 24 hours, an oral or electronic notification.
bypasses [40 CFR
• Within 7calendar days, a report that includes an evaluation of the
122.41(m)(3)]
quality and effect of the bypass.
(e) Noncompliance
. Within 24 hours, an oral or electronic notification.
with the conditions
• Within 7 calendar days, a report that contains a description of the
of this permit that
noncompliance, and its causes; the period of noncompliance,
may endanger
including exact dates and times, and if the noncompliance has not
health or the
been corrected, the anticipated time noncompliance is expected to
environrnent[40
continue; and steps taken or planned to reduce, eliminate, and
CFR 122.41(1)(7)]
prevent reoccurrence of the noncompliance. [40 CFR 122.41(I)(6).
• Division staff may waive the requirement for a written report on a
case -by -case basis.
EFFECTIVE: 04/01/19
■
411,,',D
■
aolutuonat%
Civil( engineering I land surveying
409 Chicago Drive, Suite 112, Fayetteville, NC 28306
office 910-426-6777 fax 1910-426-5777 license number I C-2354
wwwAD site solutions.com
•% `9 i
4� SEA
0274
•• G I NE ••°����
REVISIONS
PROJECT NAME
FAITHWILL
FARMS
SUBDIVISION
EROSION
CONTROL
DETAILS
CLIENT
409 Chicago Drive - Suite 103
Fayetteville, North Carolina 28306
Phone: (910) 779-0019
PROJECT INFORMATION
DESIGNED BY:
CALEB
DRAWN BY:
CALEB
CHECKED BY:
SCOTT
PROJECT NUMBER:
1691
DRAWING SCALE
NOT TO SCALE
DATE RELEASED
MARCH 25, 2021
SHEET NUMBER
2
SILT BAG INSTALLATION
C-6m 1