HomeMy WebLinkAboutSW5210603_Plansheet - Misc. Detail_20210622EROSION AND SEDIMENTATION CONTROL NARRATIVE PROJECT DESCRIPTION The purpose of this project is for the construction of a Gas Station. The project Is owned by Herritage, LLC. The site is currently vacant. Approximately 4.92 acres will be disturbed during construction. The pro1'ect is scheduled to begin construction in Summer 2021 with project completion and final stabilization by Winter 2021. The erosion and sediment control program for this project will include the installation of a suitable construction entrance, silt fence, inlet protection with seeding. ADJACENT PROPERTY The adjacent property is vacant. SOILS The soil at this site is a sandy clay. EROSION AND SEDIMENT CONTROL MEASURES All vegetative and structural erosion and sediment control practices shall be constructed and maintained by the contractor according to these plans and specifications and the minimum standards of the Dept. of Environmental Management, Land Quality Section and Town of Spring Hope. The contractor shall also follow any additional requirements as outlined by the Project Engineer. Structural Practices 1. Vehicle wheels shall be clean when leaving the site to prevent the tracking of mud on paved roads. 2. Construction Road Stabilization: Construction traffic shall be limited to stabilized areas. At a minimum, a temporary gravel construction entrance shall be provided as shown on this drawing. 3. Silt Fence: Silt fences shall be provided where shown and as needed on the site Ian. These barriers shall be used to contain sediment. P 4. Rip Rap/Gravel Filter Sediment Basins: Construct basin to the shape and dimensions shown in the details. The basin is to be placed below the existing ditch flow line by 2' with the berm built above as dimensioned. Vegetative Practices (Ground Stabilization) Site Area Description: Stabilization Time Frame: Stabilization Time Frame Exceptions: Perimeter dikes, swales, ditches & slopes. 7 Days None High Quality Water (HQW) Zones. 7 Days None Slope steeper than 3:1 7 Days None Slopes 3:1 or flatter. 10 Days 7 Days for slopes greater than 50 feet in length. Seeding Schedule Ongoing Activity Land left exposed shall be planted or otherwise provided with temporary ground cover, devices, or structures sufficient to restrain erosion within the applicable time period after completetion of any phase of grading or period of inactivity as follows. seven (7) days for steep slope or inclination. Ten (10) days for a moderate slope, fourteen (14) days for land with no slope or inclinination. For purposes of this section, a moderate slope means an inclined area, the inclination oif which is less than or equal to three (3) units of horizontal distance to one (1) unit of vertical distance, and a steep slope means an inclined area, the inclination of which is greater than three (3) units of horizontal distance to one (1) unit of vertical distance. No other criteria apply. Completed Activity. For any area of land -disturbing activity where grading activities have been completed, temporary or permanent ground cover sufficient to restrain erosion shall be provided as soon as practicable, but in no case later than seven (7) days after completetion of grading. Management Strategies 1. Perimeter measures are to be installed prior to grubbing or grading. 2. Tail Ditches shall be stabilized immediately following their construction. As an alternate, rock check dams may be provided at their outlets and/or the terminal downstream end of disturbance until ground cover is implemented. 3. Stockpile and/or waste areas must be maintained within the limits of the areas protected by the proposed measures and otherwise temporarily seeded if to be left stockpiled over 15 days. 4. Construction shall be planned so that grading operations can begin and end as quickly as ppossible. 5. Silt Fences shall also be installed prior to or as a first step in construction. 6. The Contractor shall be responsible for the installation and maintenance of all erosion and sediment control practices. Vegetative Ground Cover Immediately following grading, all areas shall receive either permanent or temporary seeding, as applicable, as follows: TEMPORARY SEEDING SPECIFICATIONS BETWEEN MAY 1 AND AUGUST 15, ADD 40 LB/ACRE GERMAN MILLET. PRIOR TO MAY 1 OR AFTER AUGUST 15, ADD 120 LB/ACRE RYE (GRAIN). FALL IS BEST FOR TALL FESCUE AND LATE WINTER FOR LESPEDEZAS. OVERSEEDING OF KOBE LESPEDEZAS OVER THE FALL SEEDED TALL FESCUE IS VERY EFFECTIVE. USE UNHULLED BERMUDAGRASS SEED IN FALL. SOIL AMENDMENTS APPLY LIME AND FERTILIZER ACCORDING TO TESTS, OR APPLY 2,000 LB/ACRE GROUND AGRICULTURE LIMESTONE AND 750 LB/ACRE 10-10-10 FERTILIZER MULCH APPLY 4,000 LB/ACRE GRAIN STRAW, OR EQUIVALENT COVER OF ANOTHER SUITABLE MULCHING MATERIAL. ANCHOR MULCH BY TACKING WITH ASPHALT, ROVING OR NETTING. NETTING IS THE PREFERRED ANCHORING METHOD ON STEEP SLOPES. MAINTENANCE REFERTILIZE IF GROWTH IS NOT FULLY ADEQUATE. RESEED, REFERTILIZE AND MULCH IMMEDIATELY FOLLOWING EROSION OR OTHER DAMAGE. PERMANENT SEEDING SPECIFICATIONS FESCUE - 200 Lbs./Ac. CENTIPEDE - 20 Lbs./Ac. SOIL AMENDMENTS APPLY LIME AND FERTILIZER ACCORDING TO SOIL TEST. MAINTENANCE IF GROWTH IS LESS THAN FULLY ADEQUATE, REFERTILIZE THE SECOND YEAR. ACCORDING TO SOIL TESTS OR TOPDRESS WITH 500 LB/ACRE 10-10-10 FERTILIZER. MOW AS NEEDED. REPLACE, FERTILIZE, AND MULCH DAMAGED AREAS IMMEDIATELY. Maintenance 1. Reseed and mulch bare spots larger than 9 square feet (limited to 5% maximum of site area.) 2. Maintain all seeded areas until uniform stand Is acceptable. 3. If growth is not established by final project inspection, continue specified attention until the stand is acceptable. 4. Correct and repair all undue settling and erosion within 1 year after final inspection. 5. Remove from the site, all erosion control structures after complete stabilization at end of construction period. 6. Remove silt from sediment pits and from behind check dams when silt is within half depth of the pit or spillway. Dispose of in an area where silt cannot re-enter pit / trap. Calculations The practice utilized for the proposed site did require formal calculations. Calculations have been provided. OWNER Herritage, LLC Chester Brantley, et al PO Box 277 PO Box 697 Kinston NC 28502 Spring Hoe NC 27882 > P 9 Hope, 1-800-336-9921 252-904-3429 Maintenance Notes: 1. Follow chart for timelines of when to apply temporary seeding. 2. Maintain all erosion control measures daily and reseed disturbed areas as needed. 3. Inspect all erosion control measures weekly and after each rainfall event. Repair as needed COMSTBUCT/ONENTRANCE NOT TO SCALE CONSTRUCTION SPECIFICATIONS: 1. CLEAR THE ENTRANCE AND EXIT AREA OF ALL VEGETATION ROOTS AND OTHER OBJECTIONABLE MATERIAL AND PROPERLY GRADE IT 2. PLACE THE GRAVEL TO THE SPECIFIC GRADE AND DIMENSIONS SHOWN ON THE PLANS, AND SMOOTH /T. J. PROVIDE DRAINAGE TO CARRY WATER TO A SEDIMENT TRAP OR OTHER SUITABLE OUTLET. 4. USE GEOTEXTILE FABRICS BECAUSE THEY IMPROVE STABILITY OF THE FOUNDATION IN LOCATIONS SUBJECT TO SEEPAGE OR HIGH WATER TABLE. MAINTENANCE.• MAINTAIN THE GRAVEL PAD IN A CONDITION TO PREVENT MUD OR SEDIMENT FROM LEAVING THE CONSTRUCTION SITE. THIS MAY REQUIRE PERIODIC TOPDRESSING WITH 2-INCH STONE. AFTER EACH RAINFALL, INSPECT ANY STRUCTURE USED TO TRAP SEDIMENT AND CLEAN IT OUT AS NECESSARY. IMMEDIATELY REMOVE ALL OBJECTIONABLE MATERIALS SPILLED, WASHED, OR TRACKED ONTO PUBLIC ROADWAYS. PIPE OUTLET TO FLAT AREA NO WELL-DEFINED CHANNEL n l � T � a PLAN VIEW 77 �La� a FILTER BLANKET II OR (MIRAFI 140N) SECTION A -A PIPE OUTLET TO FLAT AREA NO WELL-DEFINED CHANNEL I^ La FILTER BLANKET OR (MIRAFI 140N) SECTION A -A PIPE OUTLET TO WELL-DEFINED CHANNEL GENERAL NOTES: 1. La = THE LENGTH OF THE RIP RAP APRON. 2. d = 1.5 TIMES THE MAXIMUM STONE DIAMETER BUT NOT LESS THAN 6". J.IN A WELL-DEFINED CHANNEL EXTEND THE APRON UP THE CHANNEL BANKS TO AN ELEVATION OF 6" ABOVE THE MAXIMUM TAILWATER DEPTH OR TO THE TOP OF THE BANK, WHICHEVER IS LESS. 4. A FILTER BLANKET OR FILTER FABRIC SHOULD BE INSTALLED BETWEEN THE RIP RAP AND SOIL FOUNDATION. 5. FLARED END SECTION IS OPTIONAL. SEE PLANS FOR REQUIREMENT. 6. SEE PLAN AND PROFILES FOR ACTUAL DIMENSIONS. MAINTENANCE.• INSPECT RIP RAP OUTLET STRUCTURES WEEKLY AND AFTER SIGNIFICANT (I INCH OR GREATER) RAINFALL EVENTS TO SEE IF ANY EROSION AROUND OR BELOW THE RIP RAP HAS TAKEN PLACE, OR IF STONES HAVE BEEN DISLODGED. IMMEDIATELY MAKE ALL NEEDED REPAIRS TO PREVENT FURTHER DAMAGE. PIPE OUTLET PROTECTION SCALE: N.T.S. CONSTRUCTION SEQUENCE STAKE 10 MIL LINING STAPLE (2 PER BALE) SILT FENCE 10 MIL PLASTIC LINING STRAW BALE METAL STAKE (2 PER BALE) PLYWOOD PAINTED WHITE BLACK LETTERS 6" TALL CONCRETE WASHOUT WOOD POST T f GROUND LEVEL CONSTRUCTION SPECIFICATIONS.• 1. CONCRETE WASHOUT SIGN SHALL BE INSTALLED NO FURTHER THAN 25' FROM THE FACILITY AND SHALL BE VISIBLE TO ALL CONSTRUCTION TRAFFIC. 2. POLYETHYLENE SHEETING SHALL BE 10 MILS FREE OF HOLES, TEARS, OR LEAKS. MAINTENANCE.• FACILITY SHALL NOT BE FILLED MORE THAN 12" FROM THE TOP BEFORE DISPOSING OF CONCRETE CONCRETE SHALL BE DISPOSED OF IN THE SAME MANNER AS OTHER NON-HAZORDOUS MATERIALS FROM THE SITE OR MAY BE BROKEN UP AND USED AS FILL IN NON-STRUCTURAL AREAS. CONCRETETRf1ffW.Uff,,Wr NOT TO SCALE 0, 4hKA9,EC11%M L NOT TO SCALE CAM GENERAL NOTES: 1. NCDOT DITCH SIDE SLOPES TO BE 4:1 OR GREATER. 2. DEPTH TO BE 18" MINIMUM. SEE GRADING PLAN FOR INDIVIDUAL CHANNEL SLOPE AND DEPTH SPECIFICATIONS. 3. AFTER INSTALLING, APPLY SEED, AND TACK WITH IRS OR CRS LIQUID EMULSIFIED ASPHALT AT A RATE EQUAL TO 10 GAL. PER 1000 S.F. COVER W/EXCELSIOR MATTING. SEE EXCELSIOR MATTING DETAIL FOR SPECIFICATIONS AND MAINTENANCE REQUIREMENTS. # 57 WASHED STONE PLACED TO A HEIGHT OF 12"-18" MINIMUM ABOVE TOPOF BOX Q-.000.V% mo... 1. Schedule and hold a pre -construction conference prior to beginning any land -disturbing activities. This conference should be attended by a representative of the financially responsible party and/or the general contractor, grading sub -contractor, erosion control sub -contractor and the Engineer. 2. Erosion and Sediment Control (E&SC) permit and a Certificate of Coverage (COC) must be obtained before and land disturbing activities occur. The COC can be obtained by filling out the electronic Notice of Intent (e-NOI) form at deq.nc.gov/NCGO1. Please note, the e-NOT form may only be filled out once the plans have been approved. A copy of the E&SC permit, the COC, and a hard copy of the plan must be kept on site, preferably in a permits box, and accessible during inspection. J. Per NPDES requirements, a rain gauge, self -inspections records, permit, Certificate of Coverage, and S&E plan are required to be maintained on site and accessible during inspection. It is recommended that these items be placed in a permits box at the beginning or entrance of project. 4. The contractor shall conduct self -inspections of the erosion and sedimentation control measures and compete the following combined self -inspection form found on the DEMLR website https: Llfiles.nc.gov ncdecl Energy72OMineral720and72OLand720Resources/StormwaterZ NPDES72OGenerol72OPermits/DEMLR-CSW-Monitoring-Form-Rev-August-8-2019.pdf . Twelve months of complete inspection forms shall be kept on -site and available for inspection at all times. It is recommended a copy be kept in a permits box. 5. Self -inspections for erosion and sedimentation control measures are to be performed at least once every seven calendar days and within 24 hours of every rain event of greater than 1 inch. Any needed repairs shall be made immediately to maintain measures as designed. All ESC measures shall be maintained as specified in the construction details on this plan. A rain gauge shall be installed at the project site for monitoring. 6. Contact the DEMLR Raleigh Regional Office at least 48 hours prior to commencing the land disturbing activity. The DEMLR Raleigh Regional Office can be reached at (919) 791-4200. 7. Install construction egress/exit, silt fencing with outlets, skimmer sediment basins, and other initial erosion control measures as specified in the plan. Remove only trees and ground cover necessary to install these devices. 8. Notify the NC DEQ site inspector after measures have been installed and project has started. 9. Begin demolition, clearing, grubbing and grading of site in accordance with the approved S&E control plan. Install temporary diversions with excelsior matting. 10. Provide all disturbed areas with round cover as per round stabilization table or after completion of an phase of clearing, grubbing or 9 P 9 P y P 9� 9 9 grading. The seeding, seedbed preparation, mulch and/or rolled erosion control product installation must be in accordance with the seeding schedule provided in this S&E plan. Per the NPDES Permit, ground stabilization will be applied within 14 calendar days from last land disturbing activity. For steep slopes, that area must be stabilized within 7 calendar days. 11. Start installation of storm drain system beginning with outlet pipe and working uphill toward DI #3. Install inlet and outlet protections for storm drain system immediately after pipe installation. 12. At the conclusion of grading or if land -disturbing activity is stopped temporary or permanent vegetative cover shall be installed in accordance with ground stabilization table. Include excelsior matting as shown on plan. Permanent groundcover shall be established in 90 calendar days. However, NPDES groundcover requirements take precedence. 13. Perimeter measures must be left in place until all upland areas are permanently stabilized. After site is permanently stabilized, remove all temporary erosion control measures and provide permanent seeding where temporary measures have been removed and ground cover is not adequate. Sediment basins may not be removed or converted to permanent BMPs until all upland areas are permanently stabilized. 14. When DEMLR has approved removal of E&SC measures, remove sediment basins using dewatering silt bag. (See Detail) 15. When the project is complete, the permittee shall contact DEMLR to close out the E&SC Plan. After DEMLR informs the permittee of the project close out, via inspection report, the permittee shall visit deq.nc.gov/NCGO1 to submit an electronic Notice of Termination (e-NOT). A $'100 annual general permit fee will be charged until the e-NOT has been filled out. 16. Remaining measures must be removed and resulting bare areas stabilized before permit can be closed. 17. Remove all erosion control measures after the NC DEQ office approval of permanent stabilization. GENERAL NOTES: 1. All Stockpile areas shall be a minimum of 100' away from surface waters and inside the perimeter EC Measures. 2. All Concrete Washout areas shall be a minimum of 100' away from surface waters and inside the perimeter EC Measures. 3. If an offsite soil spoil or borrow site is utilized, then the disturbed area for the spoil/borrow site must be included in the land -disturbance plan and permit unless the spoil/borrow site already has a land -disturbance permit. S1VrFAF&CF NOT TO SCALE MIRAFI 10OX OR TREWRA S1115 1 r 11-1 11��� III 11° S/L rFENCE OUTLET NOT TO SCALE 12" OF #57 SILT FENCE WASHED STONE STANDARD METAL POSTS 2'-0" IN GROUND GALVANIZED HARDWARE WIRE EXTENDS TO TOP OF BOX CONS TRUC PON SPECIFI CA TIONS: 1. CONSTRUCT THE SEDIMENT BARRIER OF STANDARD OR EXTRA STRENGTH SYNTHETIC FILTER FABRICS. 2. ENSURE THAT THE HEIGHT OF THE SEDIMENT FENCE DOES NOT EXCEED 24 INCHES ABOVE GROUND SURFACE. (HIGHER FENCES MAY IMPOUND VOLUMES OF WATER SUFFICIENT TO CAUSE FAILURE OF THE STRUCTURE). J. CONSTRUCT THE FILTER FABRIC FROM A CONTINUOUS ROLL CUT TO THE LENGTH OF THE BARRIER TO AVOID JOINTS. WHEN JOINTS ARE NECESSARY, SECURELY FASTEN THE FILTER CLOTH ONLY AT A SUPPORT POST WITH 4 FEET MINIMUM OVERLAP TO THE NEXT POST. 4. SUPPORT STANDARD FILTER FABRIC BY WIRE MESH FASTENED SECURELY TO THE UPSLOPE SIDE OF THE POSTS. EXTEND THE WIRE MESH SUPPORT TO THE BOTTOM OF THE TRENCH. FASTEN THE WIRE REINFORCEMENT, THEN FABRIC ON THE UPSLOPE SIDE OF THE FENCE POST. WIRE OR PLAS77C ZIP 77ES SHOULD HAVE MINIMUM 50 POUND TENSILE STRENGTH. 5. WHEN A WIRE MESH SUPPORT FENCE IS USED, SPACE POSTS A MAXIMUM OF 8 FEET APART. SUPPORT POSTS SHOULD BE DRIVEN SECURELY INTO THE GROUND A MINIMUM OF 24 INCHES. 6. EXTRA STRENGTH FILTER FABRIC WITH 6 FEET POST SPACING DOES NOT REQUIRE WIRE MESH SUPPORT FENCE. SECURELY FASTEN 7HE FILTER FABRIC DIREC7ZY TO POSTS. WIRE OR PLASTIC ZIP TIES SHOULD HAVE MINIMUM 50 POUND ]ENSILE STRENGTH. Z EXCAVATE A TRENCH APPROXIMA TEL Y 4 INCHES WIDE AND 8 INCHES DEEP ALONG THE PROPOSED LINE OF POSTS AND UPSLOPE FROM 7HE BARRIER. 8. PLACE 12 INCHES OF 7HE FABRIC ALONG 7HE BOTTOM AND SIDE OF THE TRENCH. 9. BACKFILL 7HE TRENCH WIN SOIL PLACED OVER 7HE FILTER FABRIC AND COMPACT. THOROUGH COMPACTION OF 7HE BACKFILL IS CRI77CAL TO SILT FENCE PERFORMANCE. 10. DO NOT ATTACH FILTER FABRIC TO EXIS77NG TREES "'Rir' MAIN TENANCE: INSPECT SEDIMENT FENCES AT LEAST ONCE A WEEK AND AFTER EACH RAINFALL. - m MAKE ANY REQUIRED REPAIRS IMMEDIATELY. SHOULD 7HE FABRIC OF A SEDIMENT FENCE COLLAPSE, TEAR, DECOMPOSE OR BECOME INEFFECTIVE, REPLACE IT PROMP7ZY. REMOVE SEDIMENT DEPOSITS AS NECESSARY TO PROVIDE ADEQUA7E STORAGE VOLUME FOR THE NEXT RAIN AND TO REDUCE PRESSURE ON THE FENCE. TAKE CARE TO AVOID UNDERMINING 7HE FENCE DURING CLEANOUT. REMOVE ALL FENCING MATERIALS AND UNSTABLE SEDIMENT DEPOSITS AND BRING 7HE AREA TO GRADE AND STABILIZE IT AFTER THE CONTRIBUTING DRAINAGE AREA HAS BEEN PROPERLY STABILIZED. 1'-8" MIN. SEE PLAN CLASS B EROSION CONTROL STONE 2:1 �I 2' MIN. f s FILTER ` FABRIC SILT FENCE SILT FENCE r� CROSS SECT ION TOP VIEW F RONT V IE% CONS TRUC TION SPECS: 1. CLEAR & GRUB THE AREA AROUND THE SILT FENCE OUTLET AND PROPERLY DISPOSE OF DEBRIS. 2. PLACE GRAVEL TO THE SPECIFIC GRADE AS SHOWN PER THE DETAIL. J. PROPERLY OVERLAP STONE BEYOND EDGES OF SILT FENCE OPENING. MAIN TENANCE.' INSPECT OUTLETS WEEKLY AND AFTER EACH RAIN EVENT. IMMEDIATELY REMOVE SEDIMENT FROM THE FLOW AREA AND REPAIR AS NEEDED. CAREFULLY CHECK OUTLETS FOR EROSION AND REPAIR IMMEDIA TEL Y. ENSURE THERE IS NO SCOURING APPARENT DOWNSTREAM OF OUTLET IMMEDIA TEL Y STABILIZE ANY AREAS THAT NEED REPAIR. MAINTENANCE.- 6' TYP. DIMENSIONS OF TEMPORARY DIVERSION (GRASSED) INSPECT THE BARRIER AFTER EACH RAIN AND MAKE REPAIRS AS NEEDED. REMOVE SEDIMENT AS NECESSRY TO PROVIDE ADEQUATE STORAGE VOLUME FOR SIDE SLOPES = 2:1 SUBSEQUENT RAINS WHEN THE CONTRIBUTING DRAINAGE AREA HAS BEEN DEPTH = 2' ADEQUATELY STABILIZED, REMOVE ALL MATERIALS AND ANY UNSTABLE SOIL, AND EITHER SALVAGE OR DISPOSE OF IT PROPERLY. BRING THE DISTURBED AREA TO SLOPE = 0.50% MIN. (SPECIFIED BY GRADE) PROPER GRADE, THEN SMOOTH AND COMPACT IT. APPROPRIATELY STABILIZE ALL �O(i BARE AREAS AROUND THE INLETo H14,AO 4/RECLOT/f/& CONSTRUCTION SPECIFICATIONS: o 1 REMOVE AND PROPERLY DISPOSE OF ALL TREES, BRUSH, STUMPS, AND OTHER ORA!/EL /NLETPROTECT/ON OBJECTIONABLE MATERIAL. 2. ENSURE THAT THE MINIMUM CONSTRUCTED CROSS SECTION MEETS ALL DESIGN NOT TO SCALE REQUIREMENTS. 3. ENSURE THAT THE TOP OF THE DIKE IS NOT LOWER AT ANY POINT THAN THE DESIGN ELEVATION PLUS THE SPECIFIED SETTLEMENT. 4. PROVIDE SUFFICIENT ROOM AROUND DIVERSIONS TO PERMIT MACHINE REGRADING AND CLEANOUT. 5. VEGETATE THE RIDGE IMMEDIATELY AFTER CONSTRUCTION, UNLESS IT WILL REMAIN IN PLACE LESS THAN 30 WORKING DAYS. MAINTENANCE: INSPECT TEMPORARY DIVERSIONS ONCE A WEEK AND AFTER EVERY RAINFALL. IMMEDIATELY REMOVE SEDIMENT FROM THE FLOW AREA AND REPAIR THE DIVERSION RIDGE. CAREFULLY CHECK OUTLETS AND MAKE TIMELY REPAIRS AS NEEDED. WHEN THE AREA PROTECTED IS PERMANENTLY STABILIZED, REMOVE THE RIDGE AND THE CHANNEL TO BLEND WITH THE NATURAL GROUND LEVEL AND APPROPRIATELY STABILIZE IT. TE/19POWYAMERS/01 Installation and Use: 1. Place Dewatering Bag on the ground or on a trailer over a relatively level, stabilized area. 2. Insert discharge pipe a minimum of 5ft. inside dewatering bag and secure with a rope wrapped 6 times around the snout over a 6 inch width of the bag. 3. Replace Dewatering Bag when half full of sediment or when the sediment has reduced the flow rate of the pump discharge to an impractical amount. Maintenance and Disposal: 1. Remove and dispose of accumulated sediment away from waterways or environmentally sensitive areas. Slit open Sediment Bag and remove accumulated sediment. Dispose of bag at an appropriate recycling or solid waste facility. OR; as directed by engineer or inspector. LET ME GET YOU SOMETHING TO EAT, SO YOU CAN BE REFRESHED AND THEN GO ON YOUR WAY...... GENESIS 18:5 DEWATERING BAG SCALE: N.T.S. NOT TO SCALE ExcE1sioAAarriac NOT TO SCALE 0 0 FLOW TURNDOWN NETTING MINIMUM BURY 6" AND STAPLE EVERY 1 FT, JUST BELOW ANCHOR SLOT. FLOW OVERLAP NETTING - MINIMUM OVERLAP 18" �oI AND STAPLING EVERY 18" 1 FT THROUGH BOTH LAYERS. A L STAPLE USE �6 GAUGE WIRE USE o I • �00 xl O m lt oN . N LO W N w Z O D- 0 0 cj Z_ D- w W z_ Zz w U) Y 0 O W WV z u7 0 00 Z N = U 3::z Z�w U) J Ww= SV) 000 z BLN=C-1874 N Iec J ' n� O �..i/ ■ L v 06 O L / Z vLJJ V v C AR O Q l SEAL 19843 CNAEL - 6 3 - 21 GENERAL NOTES. EROSION 1. Apply seed, and tack with rs or crs liquid emulsified asphalt at o CONTROL DETAILS rate equal to 10 gal. per 1000 s. f. Cover w/excelsior matting. 2. Staple every 24" along perimeter edges and overlaps. Staple every REVISIONS 36" to 48" randomly to secure netting. J. Roll out netting in the direction of water flow. Do not stretch. MAINTENANCE.' 1. Inspect rolled Excelsior matting at least weekly and after each significant (�" or greater) rain fall event and repair immediately. 2. Good contact with the ground must be maintained, and erosion must not occur beneath the matting. J. Any areas of the matting that are damaged or not in close contact with the ground shall be repaired and stapled. FILE No. 2021-o1s 4. if erosion occurs due to poorly controlled drainage, the problem HORZ. SCALE: 1" = 50' shall be fixed and the eroded area protected. VERT. SCALE: 1" = 5' 5. Monitor and repair the matting as necessary until groundcover is established. D-01