HomeMy WebLinkAboutNC0036269_WWTP Phased Expansion_20210617fyi
From: VonCannon, Chad [mailto:CVonCannon@wsacc.org]
Sent: Thursday, June 17, 2021 9:58 AM
To: Pitner, Andrew <andrew.pitner@ncdenr.gov>
Cc: Hahn, Thomas <T.hahn@wsacc.org>
Subject: [External] FW: Follow-Up on Flow Acceptance Conversation/Questions
CAUTION: External email. Do not click links or open attachments unless you verify. Send all suspicious email as an attachment to Report Spam. <mailto:report.spam@nc.gov>
Andrew,
Below is the original email sent back on 6/7/21 to Corey. We appreciate you taking a look at this and helping us out. We are simply attempting to make sure we provide information
to the State in an efficient and correct manor.
Chad VonCannon, PE
Engineering Director
Water & Sewer Authority of Cabarrus County
704-786-1783 x224
980-521-8164 (cell)
From: Hahn, Thomas
Sent: Monday, June 07, 2021 4:44 PM
To: corey.basinger@ncdenr.gov <mailto:corey.basinger@ncdenr.gov>
Cc: VonCannon, Chad <CVonCannon@wsacc.org <mailto:CVonCannon@wsacc.org> >
Subject: Follow-Up on Flow Acceptance Conversation/Questions
Mr. Basinger,
Thank you for your time on the phone last week. As we discussed, and following up on our call in February, WSACC is moving forward with a phased expansion of the Rocky River Regional
WWTP (RRRWWTP), with the first phase of the expansion from 26.5 MGD to 30 MGD, and the second phase of the expansion from 30 MGD to 34 MGD. We and our engineering consultant (Brown
and Caldwell) have discussed this approach in detail with Mike Montebello and Min Xiao, and we provided a formal request for an intermediate flow tier (for 30 MGD) to DEQ for review.
Brown and Caldwell is working towards completion of the Preliminary Engineering Report (PER) for the RRRWWTP Expansion later this summer. Completion of the initial expansion (to 30
MGD) is currently anticipated on or before May 2025. WSACC plans to move forward with a progressive design-build approach for the project following completion of the PER. With the
progressive design-build approach, WSACC’s goal is to streamline the time required for the project overall, with a goal of having the 30 MGD expansion online in mid-2024. WSACC also
completed a Wastewater Flow Rate Evaluation with Willis Engineers, and submitted it and the corresponding requests for wastewater design flow rate adjustment to DEQ for consideration
on April 23.
In combination with this approach, WSACC has worked with Charlotte Water to delay construction of the Back Creek Sewer Improvements / Extension to correspond with completion of the initial
expansion to 30 MGD. This delay will result in a 1.1 MGD reduction of the current estimate for flow allocated but not yet tributary to the RRRWWTP. Additionally, WSACC staff have been
working with the four jurisdictions within Cabarrus County and with Charlotte Water to update estimated flows for other projects with flow allocated but not yet tributary, and we expect
to submit an update which will recognize that adjustment soon. As we discussed, we have a few questions on those adjustments with regards to the flow acceptance process:
1. To recognize the delay for the Back Creek Sewer Improvements / Extension project, we currently plan to submit an FTSE form and cover letter to DEQ to document the removal of
the associated 1.1 MGD from the estimated flow currently allocated but not yet tributary. As we know more about the finalized timing for the RRRWWTP Expansion to 30 MGD and the associated
timing for the Back Creek efforts, we would submit an additional FTSE form later to document the anticipated addition of that flow following the completion of the initial RRRWWTP Expansion
to 30 MGD. Please let us know if this approach is acceptable.
2. Following up on our call in February, we currently plan to submit an FTSE form and cover letter to DEQ to document adjustment of the current estimate of other flow allocated
but not yet tributary. This submittal will follow completion of the ongoing status updates for projects within the four Cabarrus County jurisdictions and Charlotte Water. Based on
the efforts completed so far, we do not currently expect that to be a large adjustment relative to the overall estimate of flow allocated but not yet tributary. Please let us know if
this approach is acceptable.
3. As we anticipate completing the RRRWWTP Expansion to 30 MGD within the next few years, we understand that some larger projects may have phases which will be completed under the
26.5 MGD permit and other phases which will be completed following the initial expansion to 30 MGD. We have requested that, to the extent practical, jurisdictions requesting flow allocations
for each project do so in phases to reflect the associated flow allocation for the near future. However, other projects (such as larger industrial or commercial efforts) may request
a larger flow allocation as part of a single flow acceptance request, but also identify phases and anticipated completion dates within that overall project which may occur on either
“side” of the initial expansion to 30 MGD. We would appreciate any guidance on documenting flow for phased projects with early phases falling under the current 26.5 MGD permit/facility
and later phases falling under the 30 MGD permit/facility.
We appreciate your guidance, and please let us know if you have any questions.
Thank you,
Thomas Hahn, PE
Assistant Engineering Director
Water & Sewer Authority of Cabarrus County
232 Davidson Highway
Concord, NC 28027
704.786.1783 ext. 228 Office
704.985.0403 Mobile
704.795.1564 Fax
t.hahn@wsacc.org <mailto:t.hahn@wsacc.org>
"Pursuant to the Freedom of Information-Privacy Acts (FOIPA) and North Carolina General Statutes Chapter 132, Public Records, this electronic mail message and any attachments hereto,
as well as any electronic mail message(s) sent in response to it may be considered public record and as such subject to request and review by anyone at any time."