John Meshad Residence
CAP Construction Completion
Action ID: SAW-2019-02248
June 11, 2021
Project Information
CreekStone, PLLC (CS, PLLC) was retained by John Meshad to complete the construction of
the associated approved CAP. CreekStone personnel completed construction oversight of
the corrective action plan prepared by others which was approved by the USACE and
NCDEQ on June 16, 2020.
CAP Construction
Construction of the off line pond and stream channel had been initiated prior to Mr. Meshad
retaining CreekStone, PLLC to complete the project. The northern pond berm and stream
channel were not located as designed. The berm was the first thing to be addressed with
relocation to ensure the implementation of proper stream buffer for the proposed stream
channel. Under CreekStone guidance, construction of the correction action plan began on
December 10th and was completed on April 29th, 2021. Field changes included installation of
an H-vane in -stream structure at the confluence of Big Norton Prong to eliminate head
cutting, installation of rootwads just upstream of the confluence to reduce active erosion and
extension the stream channels with proper curvature to tie into actual spring locations. The
site received several rain events during construction that forced two completion date
extension request which were granted by the USACE and NCDEQ. Stream channels S3 and
S4 are stable, significantly enriching the immediate hydrology and ecosystem. Additionally,
the wetland adjacent to the eastern bank of Big Norton Prong was excavated a depth 1.25' to
restore wetland hydrology. Specified livestakes are to be installed in February 2022 by
CreekStone, PLLC personnel. A monitoring period of 18 months shall begin on June 1591
2021 and continue through December 15th, 2022 at which time a monitoring report along with
a request for no further action will be submitted. Please refer the following photographs and
attached as -built survey G1:
CreekStone, PLLC — 132 Blueberry Lane - FRANKLIN, NC - 28734
(828) 200-4585, Ronnie@creekstonewnc.com
Page 2 of 14
Ronnie Dilbeck, PG
CreekStone, PLLC
Project Photographs:
Previous construction efforts of stream channel and berm
CreekStone, PLLC — 132 Blueberry Lane - FRANKLIN, NC - 28734
(828) 200-4585, Ronnie@creekstonewnc.com
Page 3 of 14
Northern berm relocation
CreekStone, PLLC — 132 Blueberry Lane - FRANKLIN, NC - 28734
(828) 200-4585, Ronnie@creekstonewnc.com
Page 4 of 14
Northern berm relocation
CreekStone, PLLC — 132 Blueberry Lane - FRANKLIN, NC - 28734
(828) 200-4585, Ronnie@creekstonewnc.com
Page 5 of 14
Rough grading of S4 channel
CreekStone, PLLC — 132 Blueberry Lane - FRANKLIN, NC - 28734
(828) 200-4585, Ronnie@creekstonewnc.com
Page 6 of 14
Bank sloping and stabilization of S4
CreekStone, PLLC — 132 Blueberry Lane - FRANKLIN, NC - 28734
(828) 200-4585, Ronnie@creekstonewnc.com
Page 7 of 14
Constructed riffle — S4
CreekStone, PLLC — 132 Blueberry Lane - FRANKLIN, NC - 28734
(828) 200-4585, Ronnie@creekstonewnc.com
Page 8 of 14
S3 completion (both streams live)
CreekStone, PLLC — 132 Blueberry Lane - FRANKLIN, NC - 28734
(828) 200-4585, Ronnie@creekstonewnc.com
Page 9 of 14
S4 and Big Norton Prong confluence — H-vane and rootwads
CreekStone, PLLC — 132 Blueberry Lane - FRANKLIN, NC - 28734
(828) 200-4585, Ronnie@creekstonewnc.com
Page 10 of 14
H-vane and associated pool
CreekStone, PLLC — 132 Blueberry Lane - FRANKLIN, NC - 28734
(828) 200-4585, Ronnie@creekstonewnc.com
Page 11 of 14
S3 and S4 confluence
CreekStone, PLLC — 132 Blueberry Lane - FRANKLIN, NC - 28734
(828) 200-4585, Ronnie@creekstonewnc.com
Page 12 of 14
Overview of S3 and S4 completion
CreekStone, PLLC — 132 Blueberry Lane - FRANKLIN, NC - 28734
(828) 200-4585, Ronnie@creekstonewnc.com
Page 13 of 14
Restored wetland area adjacent to Big Norton Prong
CreekStone, PLLC — 132 Blueberry Lane - FRANKLIN, NC - 28734
(828) 200-4585, Ronnie@creekstonewnc.com
Page 14 of 14
Restored wetland area adjacent to Big Norton Prong (Prior to seeding)
CreekStone, PLLC — 132 Blueberry Lane - FRANKLIN, NC - 28734
(828) 200-4585, Ronnie@creekstonewnc.com
SPRING
BACKFILL
BENCH CUT
EDGE OF
ATER
ROOT WAD
PLAN VIEW
ROOTWAD (HARDWOOD)
24" - 36" DIAMETER
ROOT WAD
SECTION
SPRING
7 ROOTWAD (HARDWOOD)
24" - 36" DIAMETER
LEGEND
EDGE OF WATER
CONSTRUCTED RIFFLE
H-VANE
ROOTWAD
STREAM FLOW DIRECTION
0
1/3 1/3 1/3
FILL GAPS
WITH COBBLES
20°- 30°
H -VAN E
PLAN VIEW
m
G))
20°- 30° m
m
7J
RESTORATION REACH /Cr
UNNAMED TRIBUTARY OF BIG NORTON PRONG
APPROXIMATELY 535 LINEAR FEET
BACKFILL WITH
RIFFLE MATERIAL
TO EDGE OF WATER
SCALE 1" = 10'
5 0
10
H-VANE
````0 ,11111►1///,,,�
�N CA R0 /
i
• A•
_ -..
- - • —_
° 2250 I/
• -
- •• -
.
1/ V .
%,16:®LOG
'•.• �' .��..•°°C,��� 6/ 11 /21
�, •..°
10/01111111\o`
MESHAD - CAP
STREAM RESTORATION PLAN
AS -BUILT
ROOTWADS
/4
Ji
Creelditon
Environmental and Geological Services
132 BLUEBERRY LANE
FRANKLIN, NC 28734
(828) 200-4585
creekstonewnc@gmail.com
JOHN MESHAD - CAP
STREAM RESTORATION AS -BUILT
MACON COUNTY, NC
DATE: 6 / 11 / 2021
G1