HomeMy WebLinkAbout12_Inspection Reports for SCM at Goldsboro Fire DepartmentCity of Goldsboro Control Number: Operation, Maintenance, and Management Inspection Checklist For Ponds INSPECTION FORMS FOR STORMWATER MANAGEMENT SYSTEMS Inspector Name: John Heath BMP1 Dry Detention Pond Inspection Date: Dec. 16, 2019 Owner/Operator: City of Goldsboro Date BMP Put Into Service: Jan. 20, 2011 Address: 200 N. Center St Site Plan: Harris St FD Goldsboro NC Location:1300 Harris St Phone #: Items inspected Checked Maintenance Needed Remarks Yes No Yes No I. Pond components A. Embankment and emergency spillway 1. Vegetation and ground cover adequate X X 2. Embankment erosion X X 3. Animal burrows X X 4. Unauthorized plantings X X 5. Cracking, bulging, or sliding of dam RP RP a. Upstream face X X b. Downstream face X X c. At or beyond toe Upstream X X Downstream X X d. Emergency spillway X X 6. Pond, toe & chimney drains clear and functioning X X 7. Seeps/leaks on downstream face X X 8. Slope protection or riprap failures X X 9. Vertical and horizontal alignment of top of dam as per "As -Built" plans X X 10. Emergency spillway clear of obstructions and debris X X 1/4 City of Goldsboro Control Number: Items inspected Checked Maintenance Needed Remarks Yes No Yes No 11. Other (specify) N/A B. Riser and principal spillway Type: Reinforced concrete _ Corrugated pipe X Masonry _ _ N/A 1. Low flow orifice obstructed " 2. Low flow trash rack a. Debris removal necessary " b. Corrosion control " 3. Weir trash rack maintenance a. Debris removal necessary " b. Corrosion control " 4. Excessive sediment accumulation inside riser " 5. Concrete/Masonry condition Riser and barrels a. Cracks or displacement " b. Minor spalling (<1") " c. Major spalling (rebars exposed) " d. Joint failures " e. Water tightness " 6. Metal pipe condition N/A 7. Control valve N/A a. Operational/exercised " b. Chained and locked " 8. Pond drain valve N/A a. Operational/exercised " b. Chained and locked " 9. Outfall channels functioning " 10. Other (specify) " cc C. Permanent pool (wet ponds) N/A 1. Undesirable vegetative growth " 2. Floating or floatable debris removal required " 3. Visible pollution " 4. Shoreline problems " 5. Other (specify) " 2/4 City of Goldsboro Control Number: Items inspected Checked Maintenance Needed Remarks Yes No Yes No D. Sediment forebays N/A 1. Sedimentation noted " 2. Sediment cleanout when depth < 50% design depth " E. Dry pond areas 1. Vegetation adequate X X 2. Undesirable vegetative growth X X Cut all unwanted vegetation 3. Undesirable woody vegetation X X 4. Low flow channels clear of obstructions X X 5. Standing water or wet spots X X 6. Sediment and/or trash accumulation X X Remove all debris 7. Other (specify) X X X X F. Condition of outfalls into pond 1. Riprap failures X X 2. Slope erosion X X 3. Storm drain pipes X X 4. Endwalls/headwalls X X 5. Other (specify) G. Other 1. Encroachments on pond or easement area X X 2. Complaints from residents (describe on back) X X 3. Aesthetics a. grass mowing required X X b. graffiti removal needed N/A c. Other (specify) X X 4. Any public hazards (specify) X X 5. Maintenance access X X X X H. Constructed wetland areas N/A 1. Vegetation healthy and growing " 2. Evidence of invasive species " 3. Excessive sedimentation in wetland area " 3/4 City of Goldsboro Control Number: II. Summary 1. Inspector's Remarks: Tall weeds need to be cut and removed and all debris that was previously cut needs to be removed as it can cause drainage problems at the drainage box. Pond should be cut on a regular basis as weather permits to prevent above issue 2. Overall condition of Facility (Check one) _ Acceptable, Performing as Designed X Needs Some Maintenance, Performing as Designed/May Fail Before Next Inspection Unacceptable, Not Performing as Designed 3. Action to be taken: If the overall condition of the facility is Unacceptable, a time frame shall be established for correction or repair. No action necessary. Continue routine inspections (initials) Correct noted deficiencies before next inspection JH (initials) Correct noted facility deficiencies by (date/initials) 4. Facility repairs were completed. Site is ready for re -inspection to verify corrections. Date Signature of Owner/Operator Name of Owner/Operator Initials Site reinspection accomplished on: Site reinspection was satisfactory. Month of December 2020 Next routine inspection is scheduled for: John Heath Signature of Inspector Marty Anderson Signature of City Engineer 4/4 City of Goldsboro Control Number: Operation, Maintenance, and Management Inspection Checklist For Ponds INSPECTION FORMS FOR STORMWATER MANAGEMENT SYSTEMS Inspector Name: David Ratliff BMP1 Dry Detention Pond Inspection Date: Aug. 26, 2017 Owner/Operator: City of Goldsboro Date BMP Put Into Service: Jan. 20, 2011 Address: 200 N. Center St Site Plan: Harris St FD Goldsboro NC Location:1300 Harris St Phone #: Items inspected Checked Maintenance Needed Remarks Yes No Yes No I. Pond components A. Embankment and emergency spillway 1. Vegetation and ground cover adequate X X 2. Embankment erosion X X 3. Animal burrows X X 4. Unauthorized plantings X X 5. Cracking, bulging, or sliding of dam RP RP a. Upstream face X X b. Downstream face X X c. At or beyond toe Upstream X X Downstream X X d. Emergency spillway X X 6. Pond, toe & chimney drains clear and functioning X X 7. Seeps/leaks on downstream face X X 8. Slope protection or riprap failures X X 9. Vertical and horizontal alignment of top of dam as per "As -Built" plans X X 10. Emergency spillway clear of obstructions and debris X X 1/4 City of Goldsboro Control Number: Items inspected Checked Maintenance Needed Remarks Yes No Yes No 11. Other (specify) N/A B. Riser and principal spillway Type: Reinforced concrete _ Corrugated pipe X Masonry _ _ N/A 1. Low flow orifice obstructed " 2. Low flow trash rack a. Debris removal necessary " b. Corrosion control " 3. Weir trash rack maintenance a. Debris removal necessary " b. Corrosion control " 4. Excessive sediment accumulation inside riser " 5. Concrete/Masonry condition Riser and barrels a. Cracks or displacement " b. Minor spalling (<1") " c. Major spalling (rebars exposed) " d. Joint failures " e. Water tightness " 6. Metal pipe condition N/A 7. Control valve N/A a. Operational/exercised " b. Chained and locked " 8. Pond drain valve N/A a. Operational/exercised " b. Chained and locked " 9. Outfall channels functioning " 10. Other (specify) " cc C. Permanent pool (wet ponds) N/A 1. Undesirable vegetative growth " 2. Floating or floatable debris removal required " 3. Visible pollution " 4. Shoreline problems " 5. Other (specify) " 2/4 City of Goldsboro Control Number: Items inspected Checked Maintenance Needed Remarks Yes No Yes No D. Sediment forebays N/A 1. Sedimentation noted " 2. Sediment cleanout when depth < 50% design depth " E. Dry pond areas 1. Vegetation adequate X X 2. Undesirable vegetative growth X X Cut all unwanted vegetation 3. Undesirable woody vegetation X X Cut down all trees not per plans 4. Low flow channels clear of obstructions X X 5. Standing water or wet spots X X 6. Sediment and/or trash accumulation X X 7. Other (specify) X X X X F. Condition of outfalls into pond 1. Riprap failures X X 2. Slope erosion X X 3. Storm drain pipes X X 4. Endwalls/headwalls X X 5. Other (specify) G. Other 1. Encroachments on pond or easement area X X 2. Complaints from residents (describe on back) X X 3. Aesthetics a. grass mowing required X X b. graffiti removal needed N/A c. Other (specify) X X 4. Any public hazards (specify) X X 5. Maintenance access X X X X H. Constructed wetland areas N/A 1. Vegetation healthy and growing " 2. Evidence of invasive species " 3. Excessive sedimentation in wetland area " 3/4 City of Goldsboro Control Number: II. Summary 1. Inspector's Remarks: Cut all vegetation woody and unwanted. Cannot inspect due to overgrown vegetation 2. Overall condition of Facility (Check one) _ Acceptable, Performing as Designed X Needs Some Maintenance, Performing as Designed/May Fail Before Next Inspection Unacceptable, Not Performing as Designed 3. Action to be taken: If the overall condition of the facility is Unacceptable, a time frame shall be established for correction or repair. No action necessary. Continue routine inspections (initials) Correct noted deficiencies before next inspection DR (initials) Correct noted facility deficiencies by (date/initials) jrl Facility repairs were completed. Site is ready for re -inspection to verify corrections. Date Signature of Owner/Operator Name of Owner/Operator Initials Site reinspection accomplished on: Site reinspection was satisfactory. Month of August 2018 Next routine inspection is scheduled for: David Ratliff Signature of Inspector Marty Anderson Signature of City Engineer 4/4 City of Goldsboro Control Number: Operation, Maintenance, and Management Inspection Checklist For Ponds INSPECTION FORMS FOR STORMWATER MANAGEMENT SYSTEMS Inspector Name: David Ratliff BMP1 Dry Detention Pond Inspection Date: Aug. 26, 2016 Owner/Operator: City of Goldsboro Date BMP Put Into Service: Jan. 20, 2011 Address: 200 N. Center St Site Plan: Harris St FD Goldsboro NC Location:1300 Harris St Phone #: Items inspected Checked Maintenance Needed Remarks Yes No Yes No I. Pond components A. Embankment and emergency spillway 1. Vegetation and ground cover adequate X X 2. Embankment erosion X X 3. Animal burrows X X 4. Unauthorized plantings X X 5. Cracking, bulging, or sliding of dam a. Upstream face X X b. Downstream face X X c. At or beyond toe Upstream X X Downstream X X d. Emergency spillway X X 6. Pond, toe & chimney drains clear and functioning X X 7. Seeps/leaks on downstream face X X 8. Slope protection or riprap failures X X 9. Vertical and horizontal alignment of top of dam as per "As -Built" plans X X 10. Emergency spillway clear of obstructions and debris X X 1/4 b/Z „ (Alioads) j9gl0 -5 n swelga awlajogS -t, n uoilnpo elgisin -g paiin ai IenowaJ sugep algeleoll jo 6upo13 -Z n g1Moj 9nlle1969n elgejisepun - i d/N spuo lam) lood luauewJad -O „ (Alioads) jagl0 -o l n uiuoilounj slauuego llegn0 '6 n peNool pue pauieUO -q n pasioiaxa/leuoileja O -e b/N amen UleJp puod -g „ palloOl pue pauieg0 -q „ pasioiaxe/leuolleja O -e y/N amen IaIUOO -L d/N uolllpuoo edid IelaW -g „ ssaulg Il JaleM -a sajnliei luiof -p „ paso xa siegai) 6uilleds jofeW -o n ,l> Mlle sjouilN -q n luawaoel sip jo sNoejo -e slajjeq pue aasia UOilipuoo AJUosew/alajouoO -g „ jasp episui uoilelnwnooe luawlpas anlss93x3 't, „ Ialuoo uoisajo0 -q „ essaoau lenowaJ sugaa -e aoueualulew Now gseil ilem -g n Ioiluoo UOiSOJJOO -q „ essaoau Ienowai sugaa -e Now gseJl Moll MOI 'Z n palonjlsgo 9311po MOIl Mot - y/N UOseW X adid p9le6njjoO — alaJouoo paoJOJUiaa :8dAl AeMlllds lediouud pue jasia 'e d/N (Alioads) j9gl0 sNjewa» ON sa'k ON sa'k pepadsui swab papaaN aoueualupvy palloagO :sagwnN ioluoD ojogspioJ 3o Si!D City of Goldsboro Control Number: Items inspected Checked Maintenance Needed Remarks Yes No Yes No D. Sediment foreba s N/A 1. Sedimentation noted " 2. Sediment cleanout when depth < 50% design depth " E. Dry pond areas 1. Vegetation adequate X X 2. Undesirable vegetative growth X X Cut all unwanted vegetation 3. Undesirable woody vegetation X X Cut down all trees not per plans 4. Low flow channels clear of obstructions X X 5. Standing water or wet spots X X 6. Sediment and/or trash accumulation X X 7.Other (specify) X X X X F. Condition of outfalls into and 1. Riprap failures X X 2. Slope erosion X X 3. Storm drain pipes X X 4. Endwalls/headwalls X X 5. Other (specify) G. Other 1. Encroachments on pond or easement area X X 2. Complaints from residents (describe on back X X 3. Aesthetics a. grass mowing required X X b. graffiti removal needed N/A c.Other (specify) X X 4. Any public hazards (specify) X X 5. Maintenance access X X X X H. Constructed wetland areas N/A 1. Vegetation healthy and growing 2. Evidence of invasive species " 3. Excessive sedimentation in wetland area " 3/4 tl/t, aaaulbq A4!0 to aan u6!S aoloodsul to ainleubis i}!Ile» p!nea LLOZ isnbny to ylu`oVy :aol palnpayos si uolloa su! oulina VON -tioloelslles sane uolloodsulai al!S :uo pays!l w000e uolloa sulai al!S (sleiliup aoleiadO/aaumo to OWEN aoleaadO/jaunno to ainleubiS GIB(] 'suolloaaaoo Aluan of uo!loadsu!-aj jol Apeai sl al!S -pololduwoo aiann si!adaa A4!1!ou=l .,v (slall!u!/alep) Aq saloualollap A4!1!oel palou loaJaoo (slelilu!) Ind uo!loodsul Vou ajolaq sa!oualo!lap polou loaaaoo (slelllu!) suolloadsu! oupoi anulluoo 'tiessaoau uolloe ON -ima ai ao uolloaajoo aol pays!lgalsa aq Ileys awejl auwli a `olgeld000eun s! i(i!l!oal ayl to uo!i!puoo pe�ano ayl 11 :uaNel aq of uolloy 'E pau6lsaa se 6u!wJolJad ION `olgald000aun — uolloodsul VON aaola8 I1ed ALVglpaublsad se 6u!wJolaad `aoueualulelnl awoS spaaN X pau6ls90 se 6u!wJolJad `algeldaooy — (quo Moayo) Al!Iloed to uoli!puoo IleaanO 'Z uollela an unnoa aano of anp loa su! louueo -poluennun pue WPOOM uollela an Ile inO :sNjuwaH s,ioloadsul ' L tiewwnS 'll :.zoquznN losluoo osogsploJ jo Alio