HomeMy WebLinkAbout20130259 Ver 1_Approval Letter_20130318A �
Station
Permanent Fill in
Open Waters ac
Temporary Fill in
O en Waters ac
HCU R
I
North Carolina Department of Environment and Natural Resources
Division of Water Quality
<0.001
Pat McCrory Charles Wakild, P. E.
John E. Skvarla, III
Governor Director
Secretary
0.002
March I8, 2013
Onslow County
NCDWQ Project No. 13 -0259
Intersection of NC 210 & NC 172
WBS No, 43518
APPROVAL of 401 WATER QUALITY CERTIFICATION, with ADDITIONAL CONDITIONS
Ms. Karen Fussell, P.E., Division Engineer
NCDOT, Division 3
5501 Barbados Blvd.
Castle Hayne, N.C. 28429
Dear Ms. Fussell:
You have our approval, in accordance with the conditions listed below, for the following impacts associated with the
improvements at the intersection of NC 210 and NC 172 in Onslow County:
Open Water (Tributar) Impacts in the White Oak River Basin
Site
Station
Permanent Fill in
Open Waters ac
Temporary Fill in
O en Waters ac
Total Fill in Open
Waters ac
I
- YI -Sta. 16 +84 LT
<0.001
<0.001
0.002
TOTAL
<0.00101
<0.001(2)
0.002
Total Open Water Impact for Project: 0.002 acres.
(1)32 sq ft of permanent impact. (2)40 sq ft of temporary impact for dewatering.
The project shall be constructed in accordance with your application dated received March 11, 2013. After
reviewing your application, we have decided that these impacts are covered by General Water Quality Certification
Number 3886. This certification corresponds to the Nationwide Permit 3 issued by the Corps of Engineers. In
addition, you should acquire any other federal, state or local permits before you proceed with your project including
(but not limited to) Sediment and Erosion Control, Non- Discharge and Water Supply Watershed regulations. This
approval will expire with the accompanying 404 permit.
This approval is valid solely for the purpose and design described in your application (unless modified below).
Should your project change, you must notify the NCDWQ and submit a new application. If the property is sold, the
new owner must be given a copy of this Certification and approval letter, and is thereby responsible for complying
with all the conditions. If total wetland fills for this project (now or in the future) exceed one acre, or of total
impacts to streams (now or in the future) exceed 150 linear feet, compensatory mitigation may be required as
described in 15A NCAC 2H .0506 (h) (6) and (7). For this approval to remain valid, you must adhere to the
conditions listed in the attached certification and any additional conditions listed below.
Condition(s) of Certification:
Project Specific Conditions
225 Green St , Suite 714. Fayetteville, NC 28301 -5095
Phone: 910 - 433 -3300 4 FAX. 910 - 486 -0707
Internet: www,ncwaterguahN.org
An Equal Opportumty l Affirmative Action Employer- 50% Recycled - 10 10 Post Consumer Paper
One
NorthCai-ol i na
Agtumilr,
I . For the 10 linear feet of tributary being impacted due to site dewatering activities, the site shall be graded to
its preconstruction contours and re- vegetated with appropriate native species.
2. For projects impacting waters classified by the NC Environmental Management Commission as Trout Jr),
High Quality Waters (HQW), or Water Supply I or II (WSI, WS11) stormwater shall be directed to vegetated
buffer areas, grass -lined ditches or other means appropriate to the site for the purpose of pre- treating storm
water runoff prior to discharging directly into streams. Mowing of existing vegetated buffers is strongly
discouraged.
3. NCDOT shall be in compliance with the NCS00250 issued to the NCDOT, including the applicable
requirements of the NCGO 1 provided to NCDOT in the guidance memo dated November 17, 2011.
Please note the extra protections for sensitive watersheds which include HQW and 303(d) watersheds
which are within the project limits.
4. Tall fescue shall not be used in the establishment of temporary or permanent groundcover within riparian
areas. For the establishment of permanent herbaceous cover, erosion control matting shall be used in
conjunction with an appropriate native seed mix on disturbed soils within the riparian area and on disturbed
steep slopes with the following exception. Erosion control matting is not necessary if the area is contained
by perimeter erosion control devices such as silt fence, temporary sediment ditches, basins, etc. Matting
should be secured in place with staples, stakes, or wherever possible, live stakes of native trees. Erosion
control matting placed in riparian areas shall not contain a nylon mesh grid, which can impinge and entrap
small animals. For the establishment of temporary groundcover within riparian areas, hydroseeding along
with wood or cellulose based hydro mulch applied from a fertilizer- and limestone -free tank is allowable at
the appropriate rate in conjunction with the erosion control measures. Discharging hydroseed mixtures and
wood or cellulose mulch into surface waters in prohibited. Riparian areas are defined as a distance 25 feet
landward from top of stream bank.
General Conditions
5. Unless otherwise approved in this certification, placement of culverts and other structures in open waters and
streams shall be placed below the elevation of the streambed by one foot for all culverts with a diameter
greater than 48 inches, and 20 percent of the culvert diameter for culverts having a diameter less than 48
inches, to allow low flow passage of water and aquatic life. Design and placement of culverts and other
structures including temporary erosion control measures shall not be conducted in a manner that may result in
dis- equilibrium of wetlands or streambeds or banks, adjacent to or upstream and downstream of the above
structures, The applicant is required to provide evidence that the equilibrium is being maintained if requested
in writing by NCDWQ. If this condition is unable to be met due to bedrock or other limiting features
encountered during construction, please contact NCDWQ for guidance on how to proceed and to determine
whether or not a permit modification will be required.
6. If concrete is used during construction, a dry work area shall be maintained to prevent direct contact
between curing concrete and stream water. Water that inadvertently contacts uncured concrete shall not be
discharged to surface waters due to the potential for elevated pH and possible aquatic life and fish kills.
7. During the construction of the project, no staging of equipment of any kind is permitted in waters of the
U.S., or protected riparian buffers.
8. The dimension, pattern and profile of the stream above and below the crossing shall not be modified,
Disturbed floodplains and streams shall be restored to natural geomorphic conditions.
9. The use of rip -rap above the Normal High Water Mark shall be minimized. Any rip -tap placed for stream
stabilization shall be placed in stream channels in such a manner that it does not impede aquatic life
passage.
10. The Permittee shall ensure that the final design drawings adhere to the permit and to the permit drawings
submitted for approval.
11. All work in or adjacent to stream waters shall be conducted in a dry work area. Approved BMP measures
from the most current version of NCDOT Construction and Maintenance Activities manual such as
sandbags, rock berms, cofferdams and other diversion structures shall be used to prevent excavation in
flowing water.
12. Heavy equipment shall be operated from the banks rather than in the stream channel in order to minimize
sedimentation and reduce the introduction of other pollutants into the stream.
13. All mechanized equipment operated near surface waters must be regularly inspected and maintained to
prevent contamination of stream waters from fuels, lubricants, hydraulic fluids, or other toxic materials.
14. No rock, sand or other materials shall be dredged from the stream channel except where authorized by this
certification.
15. Discharging hydroseed mixtures and washing out hydroseeders and other equipment in or adjacent to surface
waters is prohibited.
16. The permittee and its authorized agents shall conduct its activities in a manner consistent with State water
quality standards (including any requirements resulting from compliance with §303(d) of the Clean Water
Act) and any other appropriate requirements of State and Federal law. If NCDWQ determines that such
standards or laws are not being met (including the failure to sustain a designated or achieved use) or that State
or federal law is being violated, or that further conditions are necessary to assure compliance, NCDWQ may
reevaluate and modify this certification.
17. All fill slopes located in jurisdictional wetlands shall be placed at slopes no flatter than 3: I, unless otherwise
authorized by this certification..
18. A copy of this Water Quality Certification shall be maintained on the construction site at all times. In
addition, the Water Quality Certification and all subsequent modifications, if any, shall be maintained with
the Division Engineer and the on -site project manager.
19. The outside buffer, wetland or water boundary located within the construction corridor approved by this
authorization shall be clearly marked by highly visible fencing prior to any land disturbing activities. Impacts
to areas within the fencing are prohibited unless otherwise authorized by this certification.
20. The issuance of this certification does not exempt the Permittee from complying with any and all statutes,
rules, regulations, or ordinances that may be imposed by other government agencies (i.e. local, state, and
federal) having jurisdiction, including but not limited to applicable buffer rules, stormwater management
rules, soil erosion and sedimentation control requirements, etc.
21. The Permittee shall report any violations of this certification to the Division of Water Quality within 24 hours
of discovery.
22. Upon completion of the project (including any impacts at associated borrow or waste sites), the NCDOT
Division Engineer shall complete and return the enclosed "Certification of Completion Form" to notify
NCDWQ when all work included in the 401 Certification has been completed.
23. Native riparian vegetation must be reestablished in the riparian areas within the construction limits of the
project by the end of the growing season following completion of construction.
24. There shall be no excavation from, or waste disposal into, jurisdictional wetlands or waters associated with
this permit without appropriate modification. Should waste or borrow sites, or access roads to waste or
borrow sites, be located in wetlands or streams, compensatory mitigation will be required since that is a direct
impact from road construction activities.
25. Erosion and sediment control practices must be in full compliance with all specifications governing the
proper design, installation and operation and maintenance of such Best Management Practices in order to
protect surface waters standards:
a. The erosion and sediment control measures for the project must be designed, installed, operated, and
maintained in accordance with the most recent version of the North Carolina Sediment and Erosion
Control Planning and Design Manual.
b. The design, installation, operation, and maintenance of the sediment and erosion control measures
must be such that they equal, or exceed, the requirements specified in the most recent version of the
North Carolina Sediment and Erosion Control Manual. The devices shall be maintained on all
construction sites, borrow sites, and waste pile (spoil) projects, including contractor -owned or leased
borrow pits associated with the project.
C. For borrow pit sites, the erosion and sediment control measures must be designed, installed, operated,
and maintained in accordance with the most recent version of the North Carolina Surface Mining
Manual.
d. The reclamation measures and implementation must comply with the reclamation in accordance with
the requirements of the Sedimentation Pollution Control Act.
26. Sediment and erosion control measures shall not be placed in wetlands or waters unless otherwise approved
by this Certification.
If you wish to contest any statement in the attached Certification you must file a petition for an administrative
hearing. You may obtain the petition form from the office of Administrative hearings. You must file the petition
with the office of Administrative Hearings within sixty (60) days of receipt of this notice. A petition is considered
filed when it is received in the office of Administrative Hearings during normal office hours. The Office of
Administrative Hearings accepts filings Monday through Friday between the hours of 8:00am and 5:00pm, except
for official state holidays. The original and one (1) copy of the petition must be filed with the Office of
Administrative Hearings.
The petition may be faxed - provided the original and one copy of the document is received by the Office of
Administrative Hearings within five (5) business days following the faxed transmission.
The mailing address for the Office of Administrative Hearings is:
Office of Administrative Hearings
6714 Mail Service Center
Raleigh, NC 27699 -6714
Telephone: (919) -431 ,3000, Facsimile: (919)- 431 -3100
A copy of the petition must also be served on DENR as follows:
Mr. Lacy Presnell, General Counsel
Department of Environment and Natural Resources
1601 Mail Service Center
Raleigh, NC 27699 -1601
This letter completes the review of the Division of Water Quality under Section 401 of the Clean Water Act. If you
have any questions, please contact Mason Herndon at (910) 308 -4021 or mason.herndon @ncdenr.gov.
Sincerely,
&44j�o J ` �
Charles Wakild
Director
ec: Brad Shaver, US Army Corps of Engineers, Wilmington Field Office
Stoney Mathis, Division 3 Environmental Officer
Chris Militscher, Environmental Protection Agency
Gary Jordan, US Fish and Wildlife Service
Travis Wilson, NC Wildlife Resources Commission
Sonia Carrillo, NCDWQ Central Office
File Copy