Loading...
HomeMy WebLinkAbout20070744 Ver 1_More Info Received_20070613~~ ~~ _ __ Soil & Environmental Consultants, PA 11010 Raven Ridge Road Raleigh, North Carolina 27614 Phone: (919) 846-5900 Fax: (919) 846-9467 www.SandEC.com June 13, 2007 S&EC Project # 4605.W2 To: US Army Corps of Engineers NC Division of Water Quality Raleigh Regulatory Field Office 401 Oversight and Express Permits Unit Attn: Monte Matthews Attn: Cyndi Karoly 6508 Falls of the Neuse Rd, Suite 120 2321 Crabtree Boulevard, Suite 250 Raleigh, N.C. 27615 Raleigh, NC 27604-2260 t,:~~ ~" From: Debbie Edwards --,+~ Soil & Environmental Consultants, P.A. ~.--® 11010 Raven Ridge Road ~ 3 Raleigh, NC 27614 2 0 0 7 0 7 4 4 ~~"~`~ ;~~ ~ , _ ~ a~ Re: Watson Tract .`t.r~ Knigtdale, Wake County, NC f 4` yf ~~h ~ \~ ~~(e41 d "TLA~3R;>~,'L` is.~,~'~'`°'~~~~i`{'ifbAhlGN On behalf of the owners, Carter Development (Attn: Mr. A. Trent Germano), ase fend attached a complete, revised application and information requested in a meeting with the North Carolina Division of Water Quality (NCDWQ) on May 25, 2007, again requesting written concurrence from the U.S. Army Corps of Engineers (USAGE) and the NCDWQ that the activities proposed below may precede utilizing Nationwide Permits 3, 12 & 39. In addition, written authorization from the NC-DWQ is again requested for activities proposed to impact Neuse River Buffers. Please contact me at (919) 846-5900 if you have any questions or require additional information. PRrI IG('T cl Inenenw Pro~ect Name Watson Tract Pro~ect T e Commercial/Institutional Develo ment Owner / A licant Carter Develo ment Count Wake Nearest Town Kni htdale Waterbod Name Milburnie Creek Basin /Sub-basin 03-04-02 Index Number 27-31 Class C; NSW II IRICIII(`TI(l~lAl InA~er~T ci inenenov Stream Impact (acres): Permanent-0.223 Tem orar -0.012 Wetland Impact (acres): Permanent-0.235 Temporary-0.023 Open Water Impact (acres): Permanent-0.016 Total Impact to Waters of the U.S. (acres): Permanent-0.474 Tem orar -0.035 Total Stream Impact (linear feet): Permanent-445 Temporary-20 Total Riparian Buffer Impacts (square feet): 87,404 Charlotte Office: 236 LePhillip Court, Suite C Concord, NC 28025 Phone: (704) 720-9405 Fax: (704)720-9406 Greensboro Office: 3817-E Lawndale Drive Greensboro, NC 27455 Phone: (336) 540-8234 Fax: (336) 540-8235 S&EC Project No. 4605.W2 Page 2 of 2 Attachments: Revised Pre-construction Notification (PCN) Application Form Revised Impact Maps-sheets 1-11 (11x17) Revised Overall Wetland Impact Map-24x36 (DWQ only) Revised Schematic Land Use Plan-24x36 (DWQ only) Revised Justification General Statement-Priest, Craven & Associates, Inc. (dated June 8, 2007) Office Use Only: Fonn Versiorrn~~ March OS 2 Lf u 1 V 7 USACE Action ID No. DWQ No. (If any particular item is not applicable to this project, please enter "Not Applicable" or "N/A".) Processing '' 1. Check all of the approval(s) requested for this project: ® Section 404 Permit ® Riparian or Watershed Buffer Rules ^ Section 10 Permit ^ Isolated Wetland Permit from DWQ ® 401 Water Quality Certification ^ Express 401 Water Quality Certification 2. Nationwide, Regional or General Permit Number(s) Requested: NWP 3. 12 & 39 3. If this notification is solely a courtesy copy because written approval for the 401 Certification is not required, check here: ^ 4. If payment into the North Carolina Ecosystem Enhancement Program (NCEEP) is proposed for mitigation of impacts, attach the acceptance letter from NCEEP, complete section VIII, and check here: 5. If your project is located in any of North Carolina's twenty coastal counties (listed on page 4), and the project is within a North Carolina Division of Coastal Management Area of Environmental Concern (see the top of page 2 for further details), check here: ^ ~~ ~,~ s _ II. Applicant Information ~sc~ l~~ JU~'~ ~ ~ ZUC% 1. Owner/Applicant Information r~ ;~~ - ~~~,ar~-r~ c~a~~: r ~, Name: Carter Development (Attn~ A Trent Gerrrr~a~~•,1~,,,,,,,,,,. Mailing Address: 171 17th Street. Suite 1200 ~~ Atlanta, GA 30363 Telephone Number: (404) 888-3156 Fax Number: N/A E-mail Address: 2. Agent/Consultant Information (A signed and dated copy of the Agent Authorization letter must be attached if the Agent has signatory authority for the owner/applicant.) Name: Debbie Edwards Company Affiliation: Soil & Environmental Consultants. PA Mailing Address:__ 11010 Raven Ridge Road Raleigh NC 27614 Telephone Number: (919) 846-5900 Fax Number: (919) 846-9467 E-mail Address: dedwardsCc~sandec.com Page 1 of 13 III. Project Information 2 Attach a vicinity map clearly showing the location of the property with respect to local landmarks such as towns, rivers, and roads. Also provide a detailed site plan showing property boundaries and development plans in relation to surrounding properties. Both the vicinity map and site plan must include a scale and north arrow. The specific footprints of all buildings, impervious surfaces, or other facilities must be included. If possible, the maps and plans should include the appropriate USGS Topographic Quad Map and NRCS Soil Survey with the property boundaries outlined. Plan drawings, or other maps may be included at the applicant's discretion, so long as the property is clearly defined. For administrative and distribution purposes, the USACE requires information to be submitted on sheets no larger than 11 by 17-inch format; however, DWQ may accept paperwork of any size. DWQ prefers full-size construction drawings rather than a sequential sheet version of the full-size plans. If full-size plans are reduced to a small scale such that the final version is illegible, the applicant will be informed that the project has been placed on hold until decipherable maps are provided. 1. Name of project: Watson Tract T.I.P. Project Number or State Project Number (NCDOT Only): N/A 3. Property Identification Number (Tax PIN): 1744-37-2735 4. Location County: Wake Nearest Town: Knightdale Subdivision name (include phase/lot number): N/A Directions to site (include road numbers/names, landmarks, etc.): The site is located in the northwest quadrant of the intersection of Interstate 540 and Highway 64 (business). Site coordinates (For linear projects, such as a road or utility line, attach a sheet that separately lists the coordinates for each crossing of a distinct waterbody.) Decimal Degrees (6 digits minimum): 35.8061 °N 78.5178 °W 6. Property size (acres): ± 184 acres 7. Name of nearest receiving body of water: Milburnie Creek and UT to Milburnie Creek: 27-31; C:NSW 8. River Basin: Neuse (03-04-02) HUC 03020201 (Note -this must be one of North Carolina's seventeen designated major river basins. The River Basin map is available at http://h2o.enr.state.nc.us/admin/maps/.) 9. Describe the existing conditions on the site and general land use in the vicinity of the project at the time of this application: The site is currently an agricultural farm with some area forested There is a single family residence within the property boundaries The general land use in the vicinity is in the process of being highly developed with Interstate 540 just being completed Page 2 of 13 on the eastern side of the property_ and several residential developments and commercial developments being built up along Highway 64 business. 10. Describe the overall project in detail, including the type of equipment to be used: The final product of this project is intended to be mixed use with some commercial, some institutional and some residential development. Impacts associated with this development result from construction of an access road, utilities and pond maintenance. Heavy equipment typically used for grading and excavation will be utilized for this project. 11. Explain the purpose of the proposed work: The purpose of the proposed development is to construct a mixed use development for the existing residential area and new residential for the developing area. IV. Prior Project History If jurisdictional determinations and/or permits have been requested and/or obtained for this project (including all prior phases of the same subdivision) in the past, please explain. Include the USACE Action ID Number, DWQ Project Number, application date, and date permits and certifications were issued or withdrawn. Provide photocopies of previously issued permits, certifications or other useful information. Describe previously approved wetland, stream and buffer impacts, along with associated mitigation (where applicable). If this is a NCDOT project, list and describe permits issued for prior segments of the same T.I.P. project, along with construction schedules. Spangler Environmental, Inc. conducted the detailed delineation, Neuse River Basin Buffer Determinations and USACE/NCDWQ field verifications. A USACE jurisdictional determination was issued for the property on June 22, 2006 (AID# 200620349). On January. 24, 2006, Mr. Eric Kulz of the NC-DWQ conducted a site visit to verify Neuse River Buffers (NBRRO 06-027) and at a later date, Mr. Kevin Martin of S&EC met with Cyndi Karoly onsite to conduct an intermittent/perennial determination on feature W1 Impact #1 ). In addition, Environmental Services Incorporated identified a population of Michaux's Sumac on the property. This population was confirmed by the U.S. Fish and Wildlife Service on November 15, 2006. Since that time, S&EC has again confirmed that population onsite and has met with Dale Suiter with U.S. Fish and Wildlife Service. Additionally, the developer has consented to the U.S. Fish and Wildlife Service's recommendations and has designed a development plan that will preserve and minimize impacts to the population in the future. As per the US Department of Interior, Fish and Wildlife Service letter dated November 27, 2006 outlines and as per a meeting on April 12, 2007 with Dale Suiter, the developer has done the following: Avoided the existing population; 2~ Provided a 100' undisturbed buffer; 3) Provided additional preservation in the adjacent area that has suitable habitat; 4) Will provide fencing of area around existing population and buffer; 5) Will later provide "restrictive covenants" document to Dale Suiter for review and schedule meeting with future Page 3 of 13 Homeowners Association with Dale Suiter so he can discuss the future maintenance of the area. Dale Suiter is content with the developer moving forward in the manner outlined above and requested a copy of this application. Dale Suiter was sent a copy of this application. A meeting took place on May 25, 2007 with Cyndi Karoly Amy Chapman Annette Lucas of the NCDWQ, Jack Rhodes and Jerry Penson of Carter Development Tommy Craven and Gary Meadows of Priest, Craven & Associates Inc and Debbie Edwards and Kevin Martin of S&EC to discuss the overall site plan and stormwater mans ement plan. The outcome of this meeting included providing detailed justification for impact #1 (see attached, Priest, Craven &Associates-General Statement dated June 8 2007, the completion of section #1 of the BMP worksheets (see attached sheet 5 of 6~, designed to suite the projected land use statistics as shown on sheet 1 of 11 and a qualitative discussion on cumulative impacts with main focus being "stormwater" (see section XIV). V. Future Project Plans Are any future permit requests anticipated for this project? If so, describe the anticipated work, and provide justification for the exclusion of this work from the current application. S&EC is not aware of any future permit requests anticipated for this project VI. Proposed Impacts to Waters of the United States/Waters of the State It is the applicant's (or agent's) responsibility to determine, delineate and map all impacts to wetlands, open water, and stream channels associated with the project. Each impact must be listed separately in the tables below (e.g., culvert installation should be listed separately from riprap dissipater pads). Be sure to indicate if an impact is temporary. All proposed impacts, permanent and temporary, must be listed, and must be labeled and clearly identifiable on an accompanying site plan. All wetlands and waters, and all streams (intermittent and perennial) should be shown on a delineation map, whether or not impacts are proposed to these systems. Wetland and stream evaluation and delineation forms should be included as appropriate. Photographs may be included at the applicant's discretion. If this proposed impact is strictly for wetland or stream mitigation, list and describe the impact in Section VIII below. If additional space is needed for listing or description, please attach a separate sheet. 1. Provide a written description of the proposed impacts: Proposed permanent impacts include 295 linear feet of important/perennial stream channel for road crossings and dam repair 150 linear feet of unimportant/intermittent stream for a road crossing 0.235 acres of wetlands for a road crossing and dam repair and 0.016 acres of open water for the extension of a pipe within the footprint of the pond associated with dam repair. Proposed temporary impacts include 20 linear feet of important/perennial stream for a sanitary sewer crossing and 0 023 acres of wetlands associated with dam repair and stormwater bypasses (all fringe wetlands within fluctuating pool levels). Page 4 of 13 2. Individually list wetland impacts. Types of impacts include, but are not limited to mechanized clearing, grading, fill, excavation, flooding, ditching/drainage, etc. For dams, separately list impacts due to both structure and flooding. Wetland Impact Type of Wetland Located within Distance to Nearest ,e,~-ea of Impact Site Number Type of Impact (e.g., forested, marsh, 100-year Floodplain Stream (acres) (indicate on map) herbaceous, bog, etc.) (yes/no) (linear feet) Impact #3 Temporary-Dam Riparian No 0 0.019' (NWP 39) Repair Impact #5 (NWP 39) permanent-Fill Riparian No --110' 0.141 Impact #6 Permanent-Dam Riparian No --25 0.094 (NWP 3) Repair Impact #9 Temporary- (NWP 39) Stormwater Riparian No 0 0.004' Bypass Total Wetland Impact (acres) Permanent-0.235 ' Temporary-0.023 ` *TEMPORARY IMPACTS-FRINGE WETLANDS AT FLUCTUATING POOL LEVEL 3. List the total acreage (estimated) of all existing wetlands on the property: 13.89 acres 4. Individually list all intermittent and perennial stream impacts. Be sure to identify temporary impacts. Stream impacts include, but are not limited to placement of fill or culverts, dam construction, flooding, relocation, stabilization activities (e.g., cement walls, rip-rap, crib walls, gabions, etc.), excavation, ditching/straightening, etc. If stream relocation is proposed, plans and profiles showing the linear footprint for both the original and relocated streams must be included. To calculate acreage, multiply length X width, then divide by 43,560. Stream Impact Average Impact Number Stream Name Type of Impact Perennial or Stream Width Length A'r'ea of Impact (indicate on map) Intermittent? Before (linear feet) (acres) Im act Impact #1 UT to Milburnie Permanent- (NWP 39) Creek culvert & Intermittent -13 150 0.045 dissipater Impact #2 UT to Milburnie Permanent- ' (NWP 39) Creek culvert & Perennial -26 120 0.087 dissipater Impact #4 Permanent- (NWP 39) Milburnie Creek culvert & Perennial --21 150 0.085 dissi ater Impact #7 UT to Milburnie Temporary- "' ' ' (NWP 12) Creek Excavation Perennial -15 20 ` 0.012 ` ` Impact #13 Permanent-Dam (NWP 39) Milburnie Creek Repair & Pipe Perennial -5 25 0.006 extention Page 5 of 13 Total Stream Impact (by length and acreage) Perm-445 Perm-0.223 Temp-20** Temp-0.012** ""TEMPORARY IMPACTS-NOT INCLUDED AS PERMANENT, EXCAVATION OF CHANNEL AND THEN CHANNEL RESTORED 5. Individually list all open water impacts (including lakes, ponds, estuaries, sounds, Atlantic Ocean and any other water of the U.S.). Open water impacts include, but are not limited to fill, excavation, dredging, flooding, drainage, bulkheads, etc. Open Water Impact Name of Waterbody Type of Waterbody Area of Site Number (if applicable) Type of Impact (lake, pond, estuary, sound, bay, Impact indicate on ma ocean, etc.) acres) Dam Repair- Impact #3 (NWP 3) UT to Milburnie Creek Replacement and Extension of Pond 0.008 Existing Pipe Dam Repair- Impact #6 Milburnie Creek Replacement and Pond 0 008 (NWP 3) Extension of . Existing Pipe Total Open Water Impact (acres) 0.016 6. List the cumulative impact to all Waters of the U.S. resulting from the project: Stream Impact (acres): Permanent-0.223 Temporary-0.012** Wetland Impact (acres): Permanent-0.235 Temporary-0.023* O en Water Impact (acres): 0.016 Total Impact to Waters of the U.S. (acres) Permanent-0.474 Temporary-0.035 Total Stream Im act (linear feet): 465** *TEMPORARY IMPACTS-FRINGE WETLANDS AT FLUCTUATING POOL LEVEL **TEMPORARY IMPACTS-NOT INCLUDED AS PERMANENT, EXCAVATION OF CHANNEL AND THEN CHANNEL RESTORED 7. Isolated Waters Do any isolated waters exist on the property? ^ Yes ®No Describe all impacts to isolated waters, and include the type of water (wetland or stream) and the size of the proposed impact (acres or linear feet). Please note that this section only applies to waters that have specifically been determined to be isolated by the USACE. There are no isolated wetland onsite. Page 6 of 13 8. Pond Creation If construction of a pond is proposed, associated wetland and stream impacts should be included above in the wetland and stream impact sections. Also, the proposed pond should be described here and illustrated on any maps included with this application. Pond to be created in (check all that apply): ®uplands ^ stream ^ wetlands Describe the method of construction (e.g., dam/embankment, excavation, installation of draw-down valve or spillway, etc.): future excavation in non-jurisdictional areas Proposed use or purpose of pond (e.g., livestock watering, irrigation, aesthetic, trout pond, local stormwater requirement, etc.): future stormwater Current land use in the vicinity of the pond: agricultural & wooded Size of watershed draining to pond: Expected pond surface area: * see attached sheet 5 of 6, section #1 of BMP worksheets completed VII. Impact Justification (Avoidance and Minimization) Specifically describe measures taken to avoid the proposed impacts. It may be useful to provide information related to site constraints such as topography, building ordinances, accessibility, and financial viability of the project. The applicant may attach drawings of alternative, lower-impact site layouts, and explain why these design options were not feasible. Also discuss how impacts were minimized once the desired site plan was developed. If applicable, discuss construction techniques to be followed during construction to reduce impacts. The developer has worked diligently on designing a plan to avoid and minimize impacts to the maximum extent praticable. As outlined in the Priest, Craven & Associates, Inc. letter dated June 8, 2007, Impact #1 is necessary as access to US 64 in the area of the interchange of US 64 and I-540 is very tightly regulated by the NC Department of Tr_a_nsportation. NCDOT will not allow a driveway access closer to the interchange than the Hodge Road intersection where we currently derive access. The eastern propey line of the tract abuts the off ramp from I-540 and can not be accessed by the proposed development with either a public street or a private drive. The intensity of the proposed land uses on the property located to the east of the drainage feature warrant two points of access for emergency service vehicles and adequate traffic circulation. Given the control of access on the south and east, the only way to provide this access is with a loop road, that inevitably must cross the stream buffer and wetlands as illustrated in Impact 1. Impact #2 was selected in order to minimize the impact to the wetland channel located downstream of the dam b rLplacing the proposed roadway along the existing dam to the greatest extent possible. We are further constrained in this location in order to keep all the construction physically on this property. It should also be remembered that if the road were located outside of the buffer around the existing pond, the buffer around the pond would still have to be disturbed in order to make the necessary renovations and repairs to the dam. A four foot wide median is shown at this location in order to continue the lane separation that is in place on both sides of the crossing to the intersection located to the north of the crossing. The median is a significant safety feature given the narrowing of the road width. The Town of Knightdale street plan calls for a street designation of a boulevard, two 27.5 foot road sections with a 16 foot wide median on a 100 foot wide right of way. They have agreed to allow us to reduce the street section through the cr_ossinq to a 47 foot road section on a 74 foot right of way. Impact #3 and #6 are necessary Page 7 of 13 dam repair impacts because of development below the structure. Impact #4 is necessary to access the northern portion of the property; it has also been aligned in a way to cross at the Impact #5 location where an old farm road culvert crossing existed. Impact #7 is a sanitary sewer crossing that has been designed at a perpendicular angle. Impact #'s 8, 9, 10, 11 and 12 are all proposed stormwater bypass outlets for future designed BMP's. Impact #13 is some additional stream impact necessary for the maintenance of the dam and extension of the pipe. It is also important to note that this proposed plan includes any proposed and/or future impacts to jurisdictional waters of the US/State. The applicant has designed an infrastructure plan which includes roads, utilities and stormwater management facilities that is intended to capture all necessary impacts to jurisdictional waters of the US/State for future development on this 184 acre parcel of land. The applicant would request deed restrictions to be included within the 401 Water Quality Certification Approval to ensure that all future lot owners are aware that no additional impacts to jurisdictional waters of the US/State can take place. VIII. Mitigation DWQ - In accordance with 15A NCAC 2H .0500, mitigation may be required by the NC Division of Water Quality for projects involving greater than or equal to one acre of impacts to freshwater wetlands or greater than or equal to 150 linear feet of total impacts to perennial streams. USAGE - In accordance with the Final Notice of Issuance and Modification of Nationwide Permits, published in the Federal Register on January 15, 2002, mitigation will be required when necessary to ensure that adverse effects to the aquatic environment are minimal. Factors including size and type of proposed impact and function and relative value of the impacted aquatic resource will be considered in determining acceptability of appropriate and practicable mitigation as proposed. Examples of mitigation that maybe appropriate and practicable include, but are not limited to: reducing the size of the project; establishing and maintaining wetland and/or upland vegetated buffers to protect open waters such as streams; and replacing losses of aquatic resource functions and values by creating, restoring, enhancing, or preserving similar functions and values, preferable in the same watershed. If mitigation is required for this project, a copy of the mitigation plan must be attached in order for USAGE or DWQ to consider the application complete for processing. Any application lacking a required mitigation plan or NCEEP concurrence shall be placed on hold as incomplete. An applicant may also choose to review the current guidelines for stream restoration in DWQ's Draft Technical Guide for Stream Work in North Carolina, available at http://h2o. enr.state.nc.us/ncwetlands/strmgide.html. 1. Provide a brief description of the proposed mitigation plan. The description should provide as much information as possible, including, but not limited to: site location (attach directions and/or map, if offsite), affected stream and river basin, type and amount (acreage/linear feet) of mitigation proposed (restoration, enhancement, creation, or preservation), a plan view, preservation mechanism (e.g., deed restrictions, conservation easement, etc.), and a Page 8 of 13 description of the current site conditions and proposed method of construction. Please attach a separate sheet if more space is needed. Because permanent impacts to perennial, important streams exceed 150 linear feet, we are proposing stream mitigation for 295 linear feet of steam. In addition because permanent impacts to wetlands and waters exceed 0.10 acres, we are proposing 0.24 acres of riparian wetland mitigation. The Ecosystem Enhancement letter accepting our proposed mitigation was attached to our original application. 2. Mitigation may also be made by payment into the North Carolina Ecosystem Enhancement Program (NCEEP). Please note it is the applicant's responsibility to contact the NCEEP at (919) 715-0476 to determine availability, and written approval from the NCEEP indicating that they are will to accept payment for the mitigation must be attached to this form. For additional information regarding the application process for the NCEEP, check the NCEEP website at http://h2o.enr.state.nc.us/wrp/index.htm. If use of the NCEEP is proposed, please check the appropriate box on page five and provide the following information: Amount of stream mitigation requested (linear feet): 295 Amount of buffer mitigation requested (square feet): 0 Amount of Riparian wetland mitigation requested (acres): 0.24 Amount ofNon-riparian wetland mitigation requested (acres): 0 Amount of Coastal wetland mitigation requested (acres): 0 IX. Environmental Documentation (required by DWQ) 1. Does the project involve an expenditure of public (federal/state/local) funds or the use of public (federal/state) land? Yes ^ No 2. If yes, does the project require preparation of an environmental document pursuant to the requirements of the National or North Carolina Environmental Policy Act (NEPA/SEPA)? Note: If you are not sure whether a NEPA/SEPA document is required, call the SEPA coordinator at (919) 733-5083 to review current thresholds for environmental documentation. Yes ^ No ^ 3. If yes, has the document review been finalized by the State Clearinghouse? If so, please attach a copy of the NEPA or SEPA final approval letter. Yes ^ No ^ X. Proposed Impacts on Riparian and Watershed Buffers (required by DWQ) It is the applicant's (or agent's) responsibility to determine, delineate and map all impacts to required state and local buffers associated with the project. The applicant must also provide justification for these impacts in Section VII above. All proposed impacts must be listed herein, and must be clearly identifiable on the accompanying site plan. All buffers must be shown on a map, whether or not impacts are proposed to the buffers. Correspondence from the DWQ Regional Office may be included as appropriate. Photographs may also be included at the applicant's discretion. 1. Will the project impact protected riparian buffers identified within 15A NCAC 2B .0233 (Neusc), 15A NCAC 2B .0259 (Tar-Pamlico), 15A NCAC 02B .0243 (Catawba) 15A NCAC Page 9 of 13 2B .0250 (Randleman Rules and Water Supply Buffer Requirements), or other (please identify )? Yes ® No ^ 2. If "yes", identify the square feet and acreage of impact to each zone of the riparian buffers. If buffer mitigation is required calculate the required amount of mitigation by applying the buffer multipliers. IMPACT #1-ROAD CROSSING Zone* Impact s uare feet Multiplier Required Miti anon 1 9750 3 n/a 2 4746 1.5 n/a Total 14496 n/a IMPACT #2-ROAD CROSSING Zone* Impact s uare feet) Multiplier Required Miti anon 1 7838 3 n/a 2 4394 1.5 n/a Total 12232 n/a IMPACT #3-DAM REPAIR-"EXEMPT" Zone* Impact (s uare feet) Multiplier Required Miti anon 1 7250 3 n/a 2 4364 1.5 n/a Total 11614 n/a IMPACT #4-ROAD CROSSING Zone* Impact s uare feet Multiplier Required Miti anon 1 9354 3 n/a 2 4516 1.5 n/a Total 13870 n/a IMPACT #6-DAM REPAIR-"EXEMPT" Zone* Impact s uare feet) Multiplier Required Miti anon 1 17037 3 n/a 2 10823 1.5 n/a Total 27860 n/a IMPACT #7-SANITARY SEWER CROSSING Zone* Impact Multiplier Required (s uare feet) Miti anon 1 1228 3 n/a Page 10 of 13 2 817 1.5 n/a Total 2045 n/a IMPACT #8- STORMWATFR BYPASS Zone* Impact (s uare feet) Multiplier Required Miti anon 1 621 3 n/a 2 406 1.5 n/a Total 1027 n/a IMPACT #9- STORMWATER BYPASS Zone* Impact s uare feet) Multiplier Required Miti anon 1 604 3 n/a 2 402 1.5 n/a Total 1006 n/a IMPACT #10-STORMWATER BYPASS Zone* Impact (s uare feet Multiplier Required Miti anon 1 739 3 n/a 2 407 1.5 n/a Total 1146 n/a IMPACT #11-STORMWATER BYPASS Zone* Impact s uare feet Multiplier Required Miti anon 1 607 3 n/a 2 407 1.5 n/a Total 1014 n/a IMPACT #12-STORMWATER BYPASS Zone* Impact (s uare feet Multiplier Required Miti anon 1 643 3 n/a 2 451 1.5 n/a Total 1094 n/a * "Lone 1 extends out 30 feet perpendicular from the top of the near bank of channel; Zone 2 extends an additional 20 feet from the edge of Zone I . 3. If buffer mitigation is required, please discuss what type of mitigation is proposed (i.e., Donation of Property, Riparian Buffer Restoration /Enhancement, or Payment into the Riparian Buffer Restoration Fund). Please attach all appropriate information as identified within 15A NCAC 2B .0242 or .0244, or .0260. All activities proposed do not require riparian buffer mitigation. Page 1 I of 13 XI. Stormwater (required by DWQ) Describe impervious acreage (existing and proposed) versus total acreage on the site. Discuss Stormwater controls proposed in order to protect surface waters and wetlands downstream from the property. If percent impervious surface exceeds 20%, please provide calculations demonstrating total proposed impervious level. The. percent impervious for the site is expected to be greater than 30% therefore a stormwater management designed to meet the NCDWQ General Certification 3631 and diffuse flow is planned. However, at this time the specific use and layouts for each tract that is being created is unknown. Please see Sheet 1 of 11-Schematic Land Use Plan and the General Statement written on Priest, Craven & Associates, Inc. letterhead dated June 8. 2007. Since our original application submittal date of April 30, 2007, we met with Cyndi Karol Amy Chapman and Annette Lucas of the NCDWQ on May 25 2007. At the request of ~rndi, Amy and Annette, sheet 1 of 11-Schematic Land Use Plan now includes the proposed future BMP locations and stormwater bypass locations. In addition, sheet 5 of 6 includes section #1 of the BMP worksheets for the proposed future BMP's. The applicant would like to request that a condition be incorporated into the 401 Water Quality Certification Approval that requires future lot owners to submit a final & complete Stormwater Management Plan, on a lot by lot basis, to the 401 /Express Permittinq_Unit for review an approval as per condition #4 within Water Quality Certification 3631. XII. Sewage Disposal (required by DWQ) Clearly detail the ultimate treatment methods and disposition (non-discharge or discharge) of wastewater generated from the proposed project, or available capacity of the subject facility. The development will connect to an existing sanitary sewer system. The Town of Knightdale will ensure that this development does not exceed the available capacity of the facility. XIII. Violations (required by DWQ) Is this site in violation of DWQ Wetland Rules (15A NCAC 2H .0500) or any Buffer Rules? Yes ^ No Is this an after-the-fact permit application? Yes ^ No XIV. Cumulative Impacts (required by DWQ) Will this project (based on past and reasonably anticipated future impacts) result in additional development, which could impact nearby downstream water quality? Yes ^ No If yes, please submit a qualitative or quantitative cumulative impact analysis in accordance with the most recent North Carolina Division of Water Quality policy posted on our website at http://h2o.enr.state.nc.us/ncwetlands. If no, please provide a short narrative description: We have reviewed the "DRAFT Internal Policy Cumulative impacts and the 401 Water Quality Certification and Isolated Wetland Programs" document prepared by the NC Division of Water Quality on October 3, 2002, version 1.6. The draft states that most small commercial developments are unlikely to cause cumulative impacts. The Watson Tract does not meet any of the three criteria of private projects that can clearly Page 12 of 13 result in cumulative impacts. We anticipate that you will advise us if a qualitative or quantitative impact analysis is required. In our meeting dated May 25, 2007, it was requested to include a qualitative statement regarding stormwater for the Watson Tract. The stream classification for the proposed Watson Tract development is C; NSW. This proposed project is located within the Neuse River Basin and therefore is required to adhere to the Neuse River Basin Riparian Buffer Rules. In addition, this property is located with the ETJ of the Town of Knightdale which has been designated a Phase II stormwater Community and will have to implement a plan that includes the following: 1) Public education and outreach on stormwater impacts; 2) Public involvement/participation; 3~ Illicit discharge detection and elimination; 4) Construction site stormwater runoff control; 5) Post-construction stormwater management in new development and redevelopment: and 61 Pollution prevention/good housekeeping for municipal operations. Furthermore, the applicant is willing to accept a condition within the 401 Water Quality Certification Approval that would require the future owners of the lots to submit a final stormwater management plan to the 401/Express Permitting Unit for review an approval as per condition #4 within Water Quality Certification 3631. All three of the above will protect downstream water quality. XV. Other Circumstances (Optional): It is the applicant's responsibility to submit the application sufficiently in advance of desired construction dates to allow processing time for these permits. However, an applicant may choose to list constraints associated with construction or sequencing that may impose limits on work schedules (e.g., draw-down schedules for lakes, dates associated with Endangered and Threatened Species, accessibility problems, or other issues outside of the applicant's control). N/A j` L ~-, June 13, 2007 Applicant/Agent's Signature _ Date (Agent's signature is valid only if an authorization letter from the applicant is provided.) Page 13 of 13 PRIEST, CRAVEN & ASSOCIATES, INC. LAND USE CONSULTANTS WATSON TRACT -June 8, 2007 GENERAL STATEMENT The Watson Tract is a 184 acre tract at the intersection of US 64 and I 540 in Knightdale. The property is flexibly zoned for a variety of uses, allowing commercial, office and institutional, high density residential, medium density residential and low density residential. The Carter Company is proposing to construct the major public streets through the tract, creating parcels of 2 to 70 acres that will be sold to separate users. Each individual purchaser will then prepaze site plans for their intended use, and submit those plans to the Town of Knightdale for permitting under the Town's Unified Development Ordinance. The construction of the streets and infrastructure to serve the proposed tracts necessitate the permitting of the wetland and buffer impacts. Without the construction of these streets and infrastructure, it is impossible to mazket the property. At this time the specific use and layout for each of the tracts that aze being created is unknown. Based on the zoning and our understanding of the market conditions, we can estimate maximum impervious surfaces, but are unable to accurately or reliably differentiate between buildings, parking azeas and roadways, or illustrate the site plan or the drainage system. Based on the topography, we aze able to indicate the likely locations for BMP's and their general size and shape, but are unable to realistically design the devices. For those reasons, we are asking to illustrate the general nature of the stormwater management plan, and ask that as a condition of the permit individual devices be designed, reviewed and permitted at a later date, when there is certainty regarding the nature of the proposed development. Each site plan will comply with both the town and state mandated stonmwater requirements, including detention for both quantity and quality, diffuse flow measures, and Operation and Maintenance Manuals. STATEMENT OF JUSTIFICATION FOR IMPACT NO. I Access to US 64 in the area of the interchange of US 64 and I-540 is very tightly regulated by the NC Department of Transportation. NCDOT will not allow a driveway access closer to the interchange than the Hodge Road intersection where we currently derive access. The eastern property line of the tract abuts the off ramp from I-540 and can not be accessed by the proposed development with either a public street or a private drive. The intensity of the proposed land uses on the property located to the east of the drainage feature warrant two points of access for emergency service vehicles and adequate traffic circulation. Given the control of access on the south and east, the only way to provide this access is with a loop road, that inevitably must cross the stream buffer and wetlands as illustrated in Impact 1. PLANNERS /LANDSCAPE DESIGNERS /ENGINEERS /SURVEYORS 3803-B Computer Drive, Suite 104, Raleigh, NC 27609 Phone 919/781-0300 Fax 919/782-1288 During the presubmittal meeting with DWQ the idea of accessing this area with two cul de sacs rather that a loop road was discussed. However, in researching this approach, it became evident that Chapter 9 of the Knightdale Unified Development Ordinance prohibits this alternative. Page 9-l, Section 9-1 states that the purpose and intent of the Ordinance is to "to support the creation of a highly connected transportation system with the Town". A copy of this page of the Ordinance is attached. Page 9-3, Section C, prescribes a formula for calculating a "Connectivity Index", which attempts to quantify the desirable nature of roadway interconnections. Our current plan, approved by the Town, does not score high enough to qualify by code. The ordinance allows for some consideration on the part of the Town for unusual site constraints, and that was apparently given on this tract. But any plan, such as the dual cul de sac plan, that would further decrease the Connectivity Index, would be in direct opposition to the Town's written policy and ordinance. Also on Page 9-4, Section 9.4 E states the importance of highly connected street networks. This section of Ordinance is also included. Page 9-4, Section 9.4 D states that in the NMX and HB zoning districts, which is the zoning on this portion of the property, that cul de sacs are simply not allowed. A copy of this section of the UDO is attached as reference. A medical center is proposed to be constructed by Duke Hospital on this portion of the site. While the plans for the facility are still being prepared, the nature of the use is such that full and secondary access to the entire tract for emergency service vehicles is imperative. The dual cul de sac plan does not provide this level of access, only a public loop road can. As part of the site plan approval for the tract, stating his concern for adequate emergency access, the Fire Chief has also required that an additional emergency only access be provided to this portion of the tract from US 64. The access will be gated, with access to emergency service vehicles only, and surfaced with a reinforced turf matting, so as not to appear to be a road to routine traffic. NC DOT has agreed to this. This emergency access, in collaboration with the loop road, was necessary to provide adequate access in the Fire Chief s professional opinion. Constructing a water distribution system that provides flows and pressures adequate for fighting fires is also a requirement of the local ordinances. Dead end water lines, such as in a cul de sac, are hydraulically inferior to a continuous looping water line, which pulls water from both directions. This looping system provides increased flows, at higher pressures, along with the additional safety of two ties to the rest of the system, allowing flow to the site even if there should be a break or blockage at one of the ties. Since Raleigh Public Utility Department, which provides utility service to Knightdale, requires that water lines be located within a public street right of way and not run "cross country", this looping water distribution system can not be provided under the dual cul de sac scenario. A copy of this portion of Raleigh's Public Utility Handbook, which is incorporated by reference into Knightdale's Unified Development Ordinance, is attached for reference. The Town ordinances and NC DOT rulings require minimum street centerline radii and intersection separations that cause the alignment of the loop road to impact the buffer area. For all of these reasons the dual cul de sac option is in direct violation of the Town's Ordinances and is therefore not a viable option. STATEMENT OF JUSTIFICATION FOR IMPACT N0.4 The location of the proposed road at Impact 4 was selected in order to minimize the impact to the wetland channel located downstream of the dam by placing the proposed roadway along the existing dam to the greatest extent possible. We are fiuther constrained in this location in order to keep all the construction physically on this property. It should also be remembered that if the road were located outside of the buffer around the existing pond, the buffer around the pond would still have to be disturbed in order to make the necessary renovations and repairs to the dam. A four foot wide median is shown at this location in order to continue the lane separation that is in place on both sides of the crossing to the intersection located to the north of the crossing. The median is a significant safety feature given the narrowing of the road width. The Town of Knightdale street plan calls for a street designation of a boulevard, two 27.5 foot road sections with a 16 foot wide median on a 100 foot wide right of way. They have agreed to allow us to reduce the street section through the crossing to a 47 foot road section on a 74 foot right of way. Chapter 9. CIRCULATION AND CONNECTIVITY 9.1 Purpose and Intent The purpose of this section is to support the creation of a highly connected transportation system with the Town in order to provide choices for drivers, biryclists, and pedestrians; promote walking and birycling; connect neighborhoods to each other and to local destinations such as schools, parks, and shopping centers; reduce vehicle miles of travel and travel times; increase effectiveness of munidpal service delivery; and free up arterial capacity to better serve regional long distance travel needs. It is the intent of this Code to build streets that are integral components of community design. Streets shall be detailed to compliment neighborhoods and commercial centers and shall be pedestrian in scale. In addition to these standards, streets shall conform to the provisions of Chapter 17. In certain situations, streets are encouraged to be designed with on-street parking. 9.2 Arterial Plan The street layout in any subdivision shall conform to the arrangement, width and location of public streets indicated on the regulating Arterial Plan for the area. (See Arterial Map, Appendix A). Whenever a tract of land included within any proposed development plan embraces any part of the arterial system as designated on the Town Arterial Plan, the development shall be required to dedicate and plat the arterial right-of--way, and shall be responsible for the cost and the installation of the improvements in accordance with the Town's standards for roadways. Developments which embrace only one side of an existing or planned arterial right-of--way will only be required to dedicate and plat additional right-of--way for that portion of roadway with which the development has frontage, and shall be responsible for the cost and the installation of the improvements in accordance with the Town's standards for roadways. 9.3 Collector Street Plan The street layout in any subdivision shall conform to the arrangement, width and location of public streets indicated on the regulating Collector Street Plan for the area. (See Collector Street Map, Appendix B). Whenever a tract of land included within any proposed development plan embraces any part of the collector street system as designated on the Town Collector Street Plan, the development shall be required to dedicate and plat the collector right-of--way, and shall be responsible for the cost and the installation of the improvements in accordance with the Town's standards for roadways. Developments which embrace only one side of an existing or planned collector street right- oEway will only be required to dedicate and plat additional right-of--way, and shall be responsible for the cost and the installation of the improvements in accordance with the Town's standards for roadways. New developments will also be required to provide a collector street to the outer perimeter boundaries of the development based on the criteria below. If the street in question meets at least two of the criteria, then the street must be built to an appropriate collector street standard. RPTIGHTDALE, NC UNIFIED DEVELOPMENT ORDINANCE 9-1 CHAPTER 9: CIRCULATION & CONNECTIVITY A. The street intersects directly with an arterial street and provides access to an azea with an overall density of ten (10) dwelling units per acre, or provides access to more than 150 dwelling units. B. The street by its general configuration, in relationship to the existing development of the azea, in effect serves a collector function. C. The street extends into an undeveloped area in such a manner as to serve a future collector function. D. The street serves as primary access to a significant nonresidential, institutional, or recreational land, as well as, an access to a residential azea of 20 or more acres. 9.4 Vehicular Connectivity A. Stteet Arrangement Streets should be designed and located so that they relate to the topography, preserve natural features such as streams and tree growth and provide for adequate public safety and convenience. Vehicular connections from adjacent property (street stub-outs) must be utilized unless the Administrator deems the connection impractical due to topographic conditions, environmental constraints, property shape or property accessibility. Where a through street or a series of streets establishes a connection between two (2) public streets, such street shall be a public street. Local public and private streets may incorporate traffic calming devices. Streets should be designed so pedestrians have convenient and safe means to cross streets. Allowable treatments may include, but are not limited to, roundabouts, raised pedestrian cross walks, multi-way stops, bulb-outs, alternative pavement treatments, and sigaals at cross walks when warranted. B. Block Length Maximum block lengths inside proposed developments should be in accordance with lengths shown in the following table. Short block lengths aze strongly encouraged in order to create a better pedestrian-scaled environment. The Administrator may waive this requirement if it is determined that this requirement is impractical due to topograpMc conditions, environmental constraints, property shape or property accessibility. Block widths within neighborhoods should be sufficient to allow two tiers of lots except where single tiers of lots will facilitate nonresidential development and the separation of residential and nonresidential developments or the separation of residential developments from arterials, railroad rights-of--way, linear greenways or parks. Block Length n/a 11500 ft 1000 ft ~ 800 ft 660 ft 660 ft n/a rnt ....:........~ 9_`z KNIGHTDALE, NC UNIFIED DEVELOPMENT ORDINANCE CHAPTER 9: CIRCULATION & CONNECTIVITY C. Connectivity Index A Connectivity Index should be used to determine the adequacy of street layout design. This is calculated as the ratio of the number of street links (road sections between intersections) in the project's street layout divided by the number of street nodes (intersections and cul-de-sac heads). For comparison purposes, a perfect grid has a Connectivity Index of 2.0 or higher. The figure for a conventional cul-de-sac subdivision is often 1.0 or less. The accompanying illustradon exhibits a connectivity index of 1.2 (links aze shown as circles and nodes are shown as stars). The illustration has 11 links and 9 nodes for an index of 11 / 9 = 1.2 Any development shall be required to ~~ `~ , 1 achieve a connectivity index as shown in * ~J the following table. The Administrator may award connectivity index reductions if it is determined that more than 60 percent of any "side" of a development (4 sides total) faces impracticalities for connectivity to adjacent properties due to the presence of controlled-access highways, railroad rights-of--way, Neuse River stream buffers or existing developments that have not provided street stub-outs for connection purposes. In addition, the Administrator may ~ awazd connectivity index bonuses where pedestrian greenways are provided to link any cul-de-sac to another street or cul-de-sac within the development. Street links on existing adjacent streets that aze not part of the proposed subdivision are not included in the connectivity index calculation. Connectivity Index I n/a I 1.3 I 1.4 I 1.4 ~ 1.5 1.6 n/a /AA:«.........1 KNIGHTDALE, NC UNIFIED DEVELOPMENT ORDINANCE O_3 CHAPTER 9: CIRCULATION & CONNECTIVITY D. Cul-de-sacs In general, permanent cul-de-sac streets and dead-end streets are discouraged in the design of street network systems, and they should be used only when topography, the presence of natural features, and/or vehicular safety factors make a vehicular connection impractical Where cul-de-sacs or dead-end streets are unavoidable, developments shall incorporate provisions for future vehicular connections to adjacent, undeveloped properties, and to existing adjacent developments where existing connections are poor. No system of multiple branching cul-de-sacs from a single junction with a connected street network is permitted, unless the Administrator deems it allowable due to environmental constraints. Any permanent dead-end streets or cul-de-sac shall comply with the length limits shown in the following table, and shall be provided with a turnaround at the closed end of the street as set forth in the Town's Standard Specifuationt and Details Manual Cul-de-Sac Length I n/a 1 500 ft I 300 ft I 200 ft Not Not n/a (Maximum) Allowed Allowed E. Cross Access Traffic studies have shown that highly connected street networks provide much greater traffic throughput and mobility for a community, at less cost. A high degree of connectivity should occur not only at the level of arterials, but also on collector, local and other secondary roads. Such connectivity vastly improves a sweet network's performance. The street pattern should not force short trips of one (1) or two (2) miles onto arterials; it should be possible to make trips of this sort by using collector or other secondary streets. With a highly connected street network, cross-town trips should be possible using fairly direct secondary roads. All development in HB and MI zoning districts shall be designed to allow for cross- access to adjacent properties to encourage shared parking and shared access points on public and private streets. When cross access is deemed impractical by the Administrator on the basis of severe topography, environmental constraints or vehicular safety factors, the requirement maybe waived provided that appropriate birycle and pedestrian connections are provided between adjacent developments or land uses. Development plans should provide cross-access easement and complete the connection if completing the link can derive an immediate benefit. If no immediate benefit can be derived, development plans should provide cross access and construction easements and arrange the site design so when the adjoining property owner extends the connection to the property line, the link will be completed. If the link is to be completed in the future, the grade of the connection, parking, landscaping, and other improvements must be set to allow for extension into the adjacent property. 9-4 KNIGH'TDALE, NC UNIFIED DEVELOPMENT ORDINANCE WATER DESIGN STANDARDS Unless otherwise indicated, all standards apply to both the public and private water systems. Described in this section are the general design standards, which are to be followed by all parties in preparing subdivision, utility extension, and utility replacement plans for the City of Raleigh. These design standards will ensure that the citizens of Raleigh will continue to have quality water facilities along with an adequate fire protection system. All engineering plans for public and private water systems must meet State and City minimum design standards as indicated in the most recent amended Rules Governing Public Water Supplies by the N.C. Department of Health and Human Services and/or the Citv of Raleigh Public Utilities Handbook whichever is the more stringent. All projects must be certified by the engineer of record or the City Engineer. The engineer shall be responsible for determining the water pressure at the point of connection and adequacy for services at the highest point of the project. Water pressure zone information is available from the Public Utilities Administrative office. Plan and profile drawings shall be prepared by a registered professional engineer signed, sealed, and dated showing the various elements of the utility mains and shall include an overall utility plan layout on a single sheet with scale no smaller than 1 inch = 200 feet. The design of improvements must be based upon actual field verification by the engineer of existing utilities. The utility drawings shall be on separate sheets, free of landscaping and other details not pertinent to the utility plans. A separate landscaping plan must be submitted with the utility plan showing any proposed landscaping and all water and sewer utilities or easement. All adjacent tracts and topographic information must be shown on the landscaping plan. The water drawings and sewer drawings may be on the same sheets. Landscaping plans shall show all utility engineering drawings and shall be on paper 24 inches by 36 inches. Once installed, certified surveyed "as built" plans shall be provided to the City showing the utilities. "As built" drawings for the utilities shall be submitted to the Public Works Department prior to acceptance of the project by the City. WATER DESIGN -PUBLIC a. Location Conditions for Design 1) All mains are to be within dedicated street rights-of-way except major transmission mains not affording direct service connection. Mains within the street right-of-way shall be a minimum of 5 feet from the outside of the pipe to the edge of the right-of-way. Greater separation may be required for greater depth. Water mains as specified by the City of Raleigh will be marked as indicated on Detail W-13. 2) Water mains shall be located either in the north or east side of the street pavement. 37 Effective 8/2/05 ~~ ~ o ~ z~no ~ ~ ~~ ~ 66~6~r~-~r~-r~-m ~W QQ~ ~ v Q ~ ~ m ~ `~ N m W m mo ~_ ddddd0°ooo~d ~~~~z~~m~o.or=z~ ,~ '- =o ~~ w Z ~ w ~d v N ~Wd ~ ~ J s ~ N ~ dddddrOrv- od Z Z Z Z Z~_~~ ry Z -id J U (Y W Q ~ °oZ Q~~ ~ O O WSJ ~~~ d ~ O w ~ C~~Odddddd OOOC O ~ O ~S ~ ~ ~ ~ ~ ~ ~ O ~ z~ ,nO NNCV~- m Q w ~,(^~ V1 LL ~~J Q O~ 0 6 m 6~ d d d d d d O O O O O ~ ~ ~ ~ ~ ~ dd W w Q ~ d ~ ~ ~Nj zQ z~ Z d `~ cy In ~ m~~r NUl~~r ~ J Q d Q z ~ U m W ~Q Z W ~ ' 1 ' L~1--1 O = 2 ~ ~ ~~~~~ w~ Qom Q d d o a o o" v ;Q d d U Q U 2 LL 2 2 J~ u ~?~ V Q~ J~~~~ v v Jl JO W ww~wFO~00~w QQQ W ~ ~ ~ ~ ~ i i i i i ~ ~ if ON Q Q ~~zuzddddd'v ~ ~OWtK ~~ I I I ~ ^ ~ ~ W W° W° Z Z Z Z Z ~ l~ l~ W W W W W~ Q Z~ J lL r v ~ Q Q Q Q ~ J J~ J~ Q d~~~ H Z l ~ t1 ~ U ..~ ~ 7 ? 7 ? ~ 2' ~ ~ ~ N ~ W Z O _ ~ Z ~v~0 ~' Q v 0 0 wz ood~ 0 ~~~ ~ p(~, J~ WL< NZZZ SO- r-.n ~~ ~w~ z ~~~ N ~ OC ~_~~~ FWFW~(V ~<ary LL T ?~K~ R' W ZOWZF CWWZ~O f Y~O ~«Fm'z x~ ~`) \~ 1\.,` , 11 \~; ~~~ ~1 '' ~ 'r ~~(~? ~~ r, ---;~ `:~ - ,~lti ~ ; `r,~, i ~ ~ r l.~ !~ ~ ! / i r~ \ J __ --,l~l :`~~`l~ t ~' ' -; ~~, `~' ` / `~ - `~~_~ ;- '(I'~ I "~ ~) _ i ~'•~ ~. ~,\ ~~\; -- ~ :, it ~~ ',~%%r~~ ii ~~ , ~~~, ,~,, ,.~~ .1,, i~+ '~ ~~ ~ ,`_.. `. ~~~. I` '~~~ ,C~ ~f ~1 i I / I~QQiiII1I((I IM i I S 8 &~s ~ ~ a ~ p ~ 6 ~ a o o ~ o~PO s 0 o m o 0 3 2 ~ ~ ~, u ~ j ~~ Q °~ a ^~ ~~~ ~ ~~ ~ J ~ Q - ~ s ~ ~ m ~ g w Z ~~ Q JW UJ (K Z I- Q N 2 J U Q Q Q ~a ~ ~ ~~ ~ B p ~ ~ ~ ~ z~~y -l ~O W ~ 40 .~ ~- - ~~- ~ ~ s s s ~ ~ ~ ~ o g a o o $ o 0 ~ ~ ~ ~ ~ ~ 0 0 0 0 0 o v v z `~ iS ~ ~ ~ ~ 4 0 & ~ ~ g ~l r^~ ~, °ill ,_ i ^~ rv ~~i YW i ~N o r =~ Y~ 4= -u~ YW gN r w F = w w < _ ~ ~ ~l n ~ f ~ ~~ t ~ Q Q ~ ~ ~ i o ? U1 J i o a ~ ~ 0 0 ~ > a a z_ w w z w c~ w J ~ ® \ \ r ~ Q (n J Q ~___ ~ _~ a. r llJ W ~ g O ~ ~g W Q F- 3 w. m Z W Z ~ ~ . ~ O Z W ~ W Z II ~ /± T~ 1_~ ~ 1^ ~~n„/y/~ IIQ~ /~G ~~Itl obi j~~~ /~~~~~~'~t ' Y I/1/YII/L/f/1/17 ~l/17~/1AIJ VV v 7~/~/fs /J VOO wu~ir~uin)v~nei,]ISOU~I I~P~u ~i-N%ZIZRL!GI(~xT,i-OOf1YIxL/Glb ~u~'4.1-bOYLZ ~.)N~4~~~1r211111 '1~ny'~nuQ ~o~n~wii,~ fl'LUfii tiT17JNl!)N:1/ti210X;lA~If1S/S~J;INDISiI(I ;~Id V:)SONV'1/ti21: iNN V'ld S L'lf1tiN0:)3Sf7 (7Nt~"I LNV d9 b1Nb'Zld 2l31?Jd'~ `1A13117 (,~~~~ ~ ~ ~ LOOL bZ H'32idW °3144 ~ . . c c ~~I~I s~ 1 ~I~oss ~~n~x zs~Ix ~ 3,d41H9~N~l ~NOUd70'i 17~L NOS1 dM ,~_.~ ~a-id~s I . , ~ d ~ ~ / // // / \ / // // / / i // // / i // ~'/ / / / \ I ~ 1 ~~° / / / ~. i ~ ~~/ /" / / I ,I i / // // ~~ /~/ / Y/~//,, `~ `I i / / //~~//~/ V i~ i, i~ ~ In ~ J N a0 U~ ~ I ~%~ '~~ ~ ~ Ll 1 ~ i~~~~i~ v ~ ~ Z Z ~~ ~ ~ ~ i~~~ii; Q ~ to Z v~~ ~ ~ ~ '. ~1 ~ i~~',ii, ~ ~ - 1.1.1 .~ k ~ ~ (~/ ~` ~ ~ ~~/ / / ~ ~ ~ n°i i I ~ ~~ ii O N ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ (!~ In J (Y LL N ~, 1 \ ~ - ~`~~ ~ In Q UJ LL ~ '~'~'~ ~ ~~ x - - / ~ ,~ ~ ~ ~ ~~•~ ~ ~~ i i~ ~ iii i ~. ~~~ i ~ .~ 0 ~ ,~ ~ ~.~ f .~ i ~ , ~ iii i '' ~ `~,r, t. 1 ~ ~ I ~ ~~ i i i i i ~r,,~~, C~ ,~, ~ ~ ~,` ~ ~, '.~ ~: ~.'`~ ~, ~`, 4 ~ ' ~~ ~ ~' ,~ ~ o .-~ ~~ ~ \ .~ ~_ _ I :.. ~ \ I ~ LZ W ~ ~, ~ ~' ~ ~ `~ ~~ z W ..® ~ ~ _- ~ Q z 1 ~ `; > ~~ ~ ~ ~~ ; ~ ~ N - ~ ~~s\ ~ ~ ' [z w ~, ~, '~ ' ~ ~ ~ ~ z ~ i ~ ~ ~ `~ `~ i ' ~ ~ ~~ ~ \~ ~~ ~ ~ O z ' '` ~ ~ N '~ ~ ~ ~~ ~ ~ ~ ~ ~ ! _ ~ ~ i ~ ~ V \ \\ '^1/ ~ i ~ ~ 1 1 ~ (` \VI II ~ L W~ ~~ ~~ ~~ 1~~~ ~~ lOO'll/'LM/17 ,1/t~~/V11J ~/ 7~/~/CC~.. 1/77 w/0W0 uu~~'li'.w;n/u~~¢i,~u~u~liew~d-NHZI-ZHL/filfi xvd'(IIIEItIHC/fil6 ~u~'9d-6lN)LZ-.7'N ~4~W1~11 tnl nlinti :inu~~~.~ln~uici,l fl'EIl%E d9 ''dJ.Nd'11d '2k3121d7 °1N31~1'~ ' ~ IAOt bZ Ff~dW °3Ld4 sa3awona ; saoAaniins i saaHn~saa aav.~sarav~ i s~i~KHV~a s> KV> ~nsr~o.~ ~sn arw~ c c s~i I 1 o ~ ~~~ ~ 3NQtH9~N~l 'NOIld70~1 1~ d?~l NOS1 dM ,~_.~ ~a-~d~s ~I~n ~ ~ ss~ ~ d2I ~ is~rxd I r /I III II /, iau. '... w.. ~• au„ ~• .y ~ / ~ ~ ~ _ r. .. ,r. .. ,., .~ ~, .. .. \ / r / / --- .. ... ` .YL ~ .v . ~ ,,, yY. y' .W. ten' ~W. 'a' .YY. ~~` JIL ~' .UL ~ dW. ~` ~W. ~' dW. ~ ~ ~'' 1W. .YY. .YL "'' aIL ~' .YY. r` dW. ~'' ~W. .~~~~~~ ~/ /_• r ~ \ w At~ A6 r. AIL '~ J4 r" ai + /G ~ ti \ ~ ~ A6 . '~ Ac . JL a d. / ~\ ~ _ ~~ ~ r ~ i ~ ~ \ \~ - /~ . .. ~ .. ~~ ~. a~ ~. r~ +IL ~ y y .IG ~ ... ~y A. ~ r ~ ,y r ~. _- ~~ ~ / '~ .,, ~ ~ ~.~ . ~ ,,, ,- r~ i i i I I I I 1 Z -~ w °z ~ w ~ c~ w c~ J Z H ~_ X W ~i _ _ ~ W 3 W ~ ~~ ~ O ~ ~ m ~ C~ ~ , ~ _ _ W ~; ~/~~il=; ~ ~~ ~~ ,~ ~ ~~., ~ ~~ (Y w ~ i~ w ,, ~~ ~w~. I ~ t W219 N~id?JO ~~ 1~~~ QN~~~ t 100'110-9002 1'xJ'O?Jd wo,~,r~un~i~~o~r,~i.,~~,d pR«c.i ~ axzrcx[ i aie <c,i ~ uoetr ix[ ~ r,ia ^~~oyd - eue[z ~.rN `ya~,i~'a vui ,nag ~~~uzi „mdwo_ ? t. aixc ~ v9 burr '~~rd~ =lrem ~ ~ooz az I+~adw t3~vo saaaw~n~~ i saoA:inans i sa:3KOisaa ~av:~saHVn i sa:aHKV ia s~r~v~~nsKO.~ asn aNVn .~~ < s ~ 31Va1H91N~1 eNOUa~o-r 1~1 NOS1 dM ,a'5=.1 t~lv~s I ~~.~I~oss~ ~ ~~n~x~ .I,s~rxd ~. ~ ~~ \\ ~ ~~ / _ ~` `V ~~ ~ ° •. / ~.. ` ~ \ / \ ~ ~ / Qj2 / O \`, / / _ / I ~ • ~N ~ / V `. - ~ N Q U1 ~ ~\ ~° .. `~ ~ ~~ Z cn 2~ O \ \ ~ ~ ~ ~ LLJ 218 Z ~~ -~~ ~/ Q / ;; Y ,. ~ ~C ~ \ ~ ~ 2^ \\ .\ .` ~\\ \ Cv ,, ~, ~,~ ~ _ ~ ~~ ~ ~ ~ ~~ ,~. r \ ., ~ ~ ~ ~ -- -+ ~ ~ _ ~ ~. .„ ~ ~ j ~ f .. ,. ~ ~. ~~ • ... hr \ti - "" -- ~ _. _ ~ ~ ''1 __ - - - ~ .~- - --- --- _ _____ ' __- ------ ~~%= t ~~~~: .. ---- - ------- ~ ~ t~ ~ d: _- ~ ~ ___ ~ ~ C. ~ ~: - Z ~ ~ ~ ~ ~~ ~ ~ ~ ~ ~ - ~ ,~, ~ _ ,. N Z 0 Z Z Z ~ z 2~~ o g ~ Q o o ~~ ~ ~ ~~ ~ ~ ~n N ~ ~.. m ~ ~ ~ tY ~ z z ~. ,e o ~ Z 0 ~ ~ ~ > ~~ Q ~ ~ J W ~.~.. G ...., `~ I ~ z ~ w ~ ~ ~ '. ~ ~ I ~ 20,E ~ . ~ . W II I N N II I J ~ N _,`~ m F-F-I F~ -+-• ~ - ~ ill - Z Z ~ _ ~ c~i~ ~ cnw = w ~ _- --~~~ ~~~ ~- vi / ~ ~ ~ l z - - II ~7 7 ~_~yn q1A ~~AJ11/I Its/ /III ~rIVOLJ - y y ~I !_- _ c ~~J ' / ~w~ 71~.~' , I/1/YII/1._M/17 ,1/1T/1~IJ VV V7~/V[i iJ~ VQ0 ~uu~'y'~u')u~ne~,~ie~~~d ~iewa'gRZI-ZNL/GI(r*T:1'lNIf1YIRL(Ifi ~~~~~4J'6U4LZ ~.)'N ~4~~~IHL bUI ~l~nti'_~nu~~~~~ndwu,l fl'£OHE S21'~:~NIDN~/SNOA'dANIIS/SN'dNDIS8C79dV:~S(INV`7/SNBNNV'ld S LNV I:If1SNOJ1iSf1QNV'I d9 -did ~~-~ . J~ ~~~ ~~` r - ' ~ ,~ -~ -mod . . ~~~T~i~l~oss ~~n~x `ss~lx ~,~~-~ ~~~ld~, 1~1 NOS1 dHl ,~-.~ ~~x I ~ ~ a a ~ W ~ ~O~ w ` IN U ~ Q W p ~ ~ Q ~ W N ~ p Z (n J W W ~ W Z ~ Z Z Q W ~ J z g Ug Z ~ ° o ~_ ~ ~_ ~ = Z x ~ ~ ~ v ~ > ~ w ~ p ~ ~ I w z ~ o ~ z w z v1. - 1W. s yr., r 1~ ~- au. _ .v1. -6 .w. "- .W. --~ aW. f .vs. LL °i 1W. ~"' .Y4. a' aW. f aW. °" .YY. 'r' .1W. '"~' aW. '~' aW. "~' ~/ -~" ~- +IL r i r ~ r y, .- y. ~. ~. •r ay. ~- CIF ~ y4 /`w/••/ r. 111` ~' aW. "' 1Y. ~` .Yh. y' .YY. f 1W. '~'' aY. '"~' dl4 "r aW. '"~'~•."4. dID.. aW. '~' aW. "' dW. ~ 11Y. "' aW.~~Y-. -dW, ,1W~ _ W, /JW. w. ~y ~ v 1W. ~' aW. ~^ dW j'" ~ ~ ~ - ~ ~~ _ ~ .. ~ o .. ~ ~~~/ ~ ~ ~ v ~ ~ UJ ~ v~ Q vz ~ , ~ ~~~ ~~ ~ ~~ ~ ~• , ~ ~ ~ _; ~'~ • • ^ O ~ Q ~~v ~~Q ~ ~ , /, . /, ,~~ ~ w -~ w Q O ~ ~ z w w z ~.. X ~ ~ ~ V ~ tL l.~ Q ~ CQ ~ Q .~ ~ \ ® - ~.~ ~~ \ . ,,\ \\ _ ~ ~ ~ \ --- -,, ,; i\ ~, ~ ~~ 7V 9 W~ .~ I~YQi ~~ ~~~~ ~~~ ~W ~~~/ 7~/~/z =l~VW wu~ii'.~umlu~nn~.)i~+-~ud l~vu~~~l~%XZI-~NL/(>16x^~-Oll£(YINL'(16 ouoyd'fiU9LZ'.)-N ~49~~I^Tl bfll .'~~nti ~anuQ i.~lnJiw~.l fl-fU%E SN38NION~1 / SNOA7ANf1S / SNHNDISH(1 HdVJS(1 ' " " " vs b~nrue '~t~v~ ~~m ' woz nz ~r~avw =~vo Ntl l / SN7NNtl IJ S.LNV.L 1f1SNOJ;iSfl (1NV 1 .~~ < s~i~l~oss ~~n ~~~-~ =~~ld~, 171 NOSl dM ,~_.~ =mix I ~ ~ dx~ is~lxd / 1 ~~ i~ ~ ~ y" ~ ~~ I , ~I4,. ~ ~ ~ ,~ / ~ ~~ w \ - ~ ~ 1- ~ / ~ ~ ~ ~ ~ i~ ~ ~ ~ -~ ~ ~ ~~ ~ ~ , ~~ ,~ z ~ ~. ~. ~ ,. ~ / / - +~ ~ ~ .+ ~y~ ~ ~ ~ ~ _~ ~.~ ~ ! i ~ ~ ~ . ,~~~~, ~. .~ ~~ / dt~t .//A//A//A \, ~ ~ ~ ,~~ ~~/~A/~A/~ ~\~ / j\//j //j //\// //,MN / / ~ ~/~\/~\%\~i' ~V/~A/~~~ ~ ~ ,:~ .~ `~, ~~ ®~ ~°~ ~ s ~~ ~ ,, ~ --~ ,, I~ / ~ ~ ,~~~~ ~ ~ i /~~' / ,~ ~~~\ r. / - ~~~~/ <~~~ / . w .~ z ~, ~ ~ ~~ ~ z ~ ~o m N 1J--1 ? • • ~ ~ ~ ~ .. ~~ ~ Q ~ ~~ ~ ~` ~r 1 ~ ~ / ~ ~ ~~~~ i .~ ~ 1.~. O cn / ~ / ~ / ~ ~ I~n - _ 4J-~ V 1 Q f~ ~ ~~ / / /I ,. ,~ , r ,~ ~ ~ - ,, Z W W J ,, ~~ ~~ ~ ~ ~~ r W ~ ~N ``~ N W 2 J ~ N O Z ~ --~ W L~ Z ~ Z Z Q ~ ~i o g Q ~ m ~ ~ ~ U ~ W ~ O ~ ~ ~ I w z O ~ Z W Z U Q ~C G 00~ ~ ~ g o ~j U ~ ~ w o Q ~ ~ ~ w _~ ~ o O J W z Q U 0 J ~~~~ ~ J ~ u~ ; ~-~~~ ~ ~~~~ W 0 N m z N W z 0 m z LI..~ '~~, W z I--- ~_ X w II V1 1 3V J- 1_111L] ~ IPI \~I-J11/i l~Q'~ /~C ~rltl O~3 ~~~~ lOO`IIILM/1t ~1/1T/711J a/ T/V iJ~J VOO w~~~'L-~u;n~u~nu~J~'~ Z FIG xod'OOEO-ISiC/G16 ~uo4J'fi0~)LZ'.)~N ~4yul°21 t01 a1~n5 `hoop n. InJw~~.) fl'tiONf ~ ~~ ` V9 ''dJ.NVZIV '?~31?1V'~ °1AI31"t'~ ~ ~ l.OOt bt H'h1dW '3L'da S~ ?I~)/~~A~nS/ saaaK or~~ i s aNO~s~a ~av.~sarw~ i sv~Krw~a slrw.~~nsHO:~ asn aKV~ c c sa ~~~ ? ~ ~~~-~ ~-~ud~, l~ dZlL NOS1 dM ,~=.~ ~~x I ~~l~oss~ g ~~n~x~ is~lxd ^, ~ ,, -_. `` ` \\ ~__ ~, ~ - - ~-~ _ ~ ~ \ ~. ~ - ~ ~ . \ ~. ~ .~ ,' , w .' i i ~ ~ ~-. /~ ~ 1 ~ ~ ~ i -~ .. .. ... -- .. r 1 i ~ ~ ~,. ~ ~ ~ ~ ., ~ ~ --- ,, ~ ~ ~ ,. ~ ~ ~ --, ` ~ ~ ~ ~ / i ~ / J ~ •. Z ~~ ~ ,~ ~ ~ \ ~ ~ ,~/~,y~A/~A/~A/~A/~A/~\/ ~ ~/~A/~~ j~ '~ ~ - ~ - A~~~V//V//V//V//V//V//~ % ;':A//V~/~ 0 ~ ~- !~// ~/~//~~/V//V//V//V'.~ ~V//~\/ V~~\~. m ~ ~',~~}~~i/~~i/~/iii/~~i~~i~i/~~/~~i/~; ~ I ~~/~//~//~//~//~//~, ~ ~//~//~//~i, _ ~ W ~ ~ ~ ~'~j/i //~ //A/ ~//A/~~//A,r ~ ~. Z \/~\/~\/~ O '~ ® ~ ~ \ ` •• u~ ~'~~ ~ "" ~ ~ x \ ~ w ~ ~, v U~ ~ \ ~ ~ _ ~ ~/ ~ / ~' ~ l..l._ O ~ ~~ ,__, ~ \ ,,, _ ~ ~ II ~ i7 ~ '/~ ~~~ l~~l IW IIV TJa/~ '~~VOO wo;r'.u'~u(!?)u~nP..l ~ls~u~llew'.I~NlfZ l-ZNL/616 xe.1 WLIr IXt /61o •~u•,4a ouvt,t .~rv v•,i•.a vvi •.~•••`•..•••.~•..,.._~-... ~~ w~~ SNHBNIDNH / S210A3A21fIS / SN7NOISH4 3dtlJSONtl'1 / SN~NNtl'ld S.LNtl.I'IfISN07 9Sfl ONtl"I d9'dJ.N'd"LLd'~.L2Jd7 'J.N31"17 ,./„- Fr~~~ 1.002 bZ H'~2JdW '3144 s~l~d I ~'I~~SS~ ~ ~~11~~ 1 •~~ `5~ ~ 3-~d41H9D~d 'i~loud70'"f 1~J. 1~1OS1~dM s~~dn '3,d~s , . ., I . 1 ~/ (5~11~0?~d ~j1~4~1-d (`M•O'2k •l~ NOIl'd1~1~ QN?J9 '15X~ (~11~02~d 15) ~a'd~19 7/1 •d0?~d ('M•02! •1ZI) NOIl'd/\31~ QNZl9 •15X~ (Q310N 5"d 2}3d(1S 1~3-1/1H912~ ~Q'dZl9 7/1 'd02ld ~'i1~021d ~ '15X~ b ~ ~ ~~ ~~ W tV V N N ~ ~r ~ _ ~ b r~ ~ u n LLI V v N ~ N ~ QC ~ > 0 X I 1 ~ ~ ~ ~ ~ n ~ g ~ { ~ I I ( ~ i t ~ ~ ~ ~ ~ ~ ? ~ 4 0 3 ~ ~ ~ •~ ~ ~P N ~ 4 1 I E ~ W ~ ~ ~ ~ ~ ~ ~ ~ ~ ! ~ ~ V' Z I ~ t l c H91 ~ j ~ ~ ~ ~ J / I ~ r~ ~ ~ ~ ~r~ o _ ~ E I ~ r N~ ~ ~ - ~ ~ 1 ~ ~ i G ~ `~ ~ ~ {S ails ~ J ~ ~ ~ - ~ 1 i ~ ~ ~ ! / - ~ 3 a ~ C ~ Z ~ i ~ ~ ~ 3 z ~ 0. ~ ~ • Z 1 ~ X I 1 ~ ~ ~o ~ ~ ~~ ~ pLL( w~ 2 ~~ ' ~ I N ~3 ~ *, If119 J V ~ 3 rv ~ ~ ~ ~ = - LL O~ - ~?( I U ~ ^ U 50~~ Y 0 ~ ~ N a In ~ Q ` .J J ~ + ~tJ N p4 ~ ~ ~ !uu>i~ o n I ~ 3 ~ • ~ ~ ~ oc ~ o 7 oc ~ 0 oe ~ 7E ~ ~ z . Z f- ~ ~. ~ ~~ ~ r~ i I ~ ~ ~ ~ ~ ~ 8 ~ I ~ o ~ ~ I ~ ~ g j I ~ ~ a ~ I ~ 'I ~ OI '_w^ L~~ ~~ ~ ~ 1~~~ ~..~~ I~y~.ll~~ W ~l/~-~~/~~J /7 VaG7 wcr~'L'~um)u~ne~;~ls~ud l~awfl'HRZI-ZXL/61fi"ad ~OU£IY ISL/filfi nu~t4d'G09LZ'J~N `49~~1a21 tUl nPny `~nu4 mmdwa;) fl-f11H£ sbaaKioNa i sxoAanans i s~aN~isaa aavnsaNVV saarlKV~a s.~Nd.c~nsKOn asn aKV~ V9'V1Mf11V'213L?ld7 '1N31Y~ ~~ 1_OOL bZ Ff'~dW '3LVC[ s~I~ T I ~I~~SS ~ ~`~" n~a~ • 7~ ~S~ I , ~ , I . . . ~ ~ 11 11 _. u:w w v V ~ ~ N ~ QC _ > b ~ ~ 11 II ~ lL.1 V to N ~ ~~ ~~ ~~ W(~9 '~9 NMHCyQ S~ I'd13Q l~'ddW I QN'd~113M ~~~ ~~~-9~QZ ,lr~~rO~d woauou(n)ua+ei~lsoud l!ew'~I'88ZI-ZSL/616 xer!'OOCO-18L/616 ~~~4d'609LZ'~'N `4~NIpN b01 ~1!~S'~^P(!~~!^~w~J fl-£ONE SNH0NI7NH / SNOA9ANf1S / SN9N71SH4 3dtl7S4Ntl"1 / SNHNNtl'id SLNV L'1f1SN 7 ~Sfl ONtl 1 0 d9 ''d1N'd~l'd '21~1?JH~ ~1N~1~~ ' ' LOOZ 'bZ H~~HW '~1dQ ~ C ~ 7~ ~ ~`3n~ • S'3 1 ~1~~s ~ 1 5 `~" l~ S ~N '37'dQ1H91N~ ~NOIl'd~0~ d~l NOSl ¢M 1~ S~I?Jb'/~ `~ld~S I . . ., ~ . . d . - ~ ~ 1 0 00 ~ 3 o; ~~ a~ N ~ \~ -- - a, m w Z 0 w J O V L1J cf~ I Z Zag ~ z !!. ° ~VU ~`° V 0."i Z - J Q w timm fl ~ Z z Q zz . o-~ ~w p F- W W 13 lL Q V I ~-ZW Ul ~ Z z (Y - - J W UO m-~ J3N I=Inzz VI - J Q30 O U~ (X LLOO ~oz° i -4 W ~~~ ~ QU 3 W W IU z ~ ~ In ~Joo ~ ~-o Qzw v QQz~ (Y~ O (YOZ U) ~OF- W p W W W O I- O W ~ - Z J ~ z (Y~> I-Wln(YJLl2 2 OJT - QWWO-OWJLI~ ~-OJW~-- •f- --Q J JSWWpCOCOWZWWfYWQm f- ~32~W ~~Q Q z0>ZW ~ (Y (Y>- - ~ZUI W Ul W~~Z~JO> ~WWWIl p(Y O(Y 3z U12 OQW~ J =~>1112ZWLl-W -WTI- ZSCQU~~~pI-QJ-f-O>W IU> LL Z~ ~ V ~UWZ W~~(LU-I-WLI OC~t-- 4Ll ~ ~ f-Q3(YVQW QQ~Q W ZUIWJ~~ •W(YW Old lnClJ3fY 1f1L1W~W(Y~QWI-JO~fYJ W Q ~~W l~~l-l~-~OWfYV ILQWW(YZJWZWIn-(Y zJOrY~~11zcY~~~ -I-rSlOt-JZO=z=O -UFO- tl)~InWQ~pW -~-~0~~ ~z0 >W ~ ~ Q ~L10W3 iU ~ ~ tl)-fYU-2 _ W-pWZ4W~0 ~W W=ZZ O LL-~I-.-.WZ W(k--J UIOtY Ll~-W (YW ~U X21-LlJl- L1JJ~1-(Y IU ~ U[QJddIL(Y~ WJtIIUI QQW(YILtnZW3~Z J~ OW W~~ Wzh-~F-W --CQ JO pJ-C'Sz > IUO~~WZ-UlC'SW>(YZ~ p~CY QJ3QOWJZ -~2U zW~JW~-ZZIn- O- -J~-S~z~Ztn- Q» fY~-W> (Y3~[L~-UZ~fY- -W Z-U-z3U~(YZ QWUIL W(LW W ZW~LI Q- J W ~~~Z~O(YL1W(~WO~U(T111 Z3 z~~Ll fYW~~CY(YO-p ~p ~tZ WWU to--~JU WfY OI-LL 3 W f~ -F-pZ~dz O~- »z to W W=JWZ Ul ~Q OCaILU01- JInOLIzp(L~2~JCQQ~D~~ -W- 3Q ~Q-ZOZ-CQ~ - 2~t~ Wln .~~ ~ ~ UW~QUQfL IL3W1- OO~nz~~nL10zC'J ~U Lll~O 2 tl)tfl~ WOUWW OQ J ~~~zQWZ ~~(YI-I- ~J--~~~- J (YUl[Y(Y --ln~ WfYfY~Z~~ILC'SIn~~W .. ~111~-WW3WU~~3~WWQWO--W~U-~ W QlnlL>~O-~-WOQ»WU~LIUfY-QLI~ F- LYWZ J~JL1L1~>JWJJ(Y(YI-ZW WZ O O(YOI1_~QWOW-zW(Y»~WOOtLWW~00 z W~UOU(lp]~[YJ-CQ IUVVUI(LCQVU)[Q[Q_U~ C~ z ua J D ~~ z t LL `~ ~ ~ y ~.a_ t {~ 1 +~ ~ ~ ,, z O ~ / ~ .+1 V 1 ~ rn ~ ,\ L ~ ~ i ~~ ~~ ~ v ` ~ l.. O ~~ f~ :~ i~ ~ ~ ~ ~ -- ~ ~ ~. - ~, ~; p ~ 1 r: ~% 2 ~ w ` ~ J ~~' ~i L' ti., C1 zr UJ . ~~ ~ ~ ~' o ~ a w ~ ~, ~- ~ U ~ _~ ` °` ~~ ~ a~ d 4 S1 s~ ~ 1 ~ - _ v m m N - ~ W s c ~~ ~ c ~.!~ N ~ W ; y L ~ ~ J! P ~ a c:_ ~ ~ U ~ C _~ [G ~ a N= ~ ~J V ~' ij w ~ (( ~ ~ ~./ w Q J ~1 i) ~ - ~ tj ' y c i` : n \ ~ AP ~ ;i' ~ ~Jl . ~~t< A ~G'~ ~ ` ~ , ` ` )~ Q ~, ~ :, LL ,. cn E t_ ; ~ ~ r ~ ~ ~ ~ ,L ~ v w- W z ,~ ( , ~ ~ J _ _ ~ ; .~ .~ . n J . ;u . vI c, o ? u C O m ~ L W ~ ti: m ' ~ a: c s. `' - ~ s~ S1 ~ ._ h x ~ ~ ~; ~-. © O ~~ - - - _ - - Z