May 3, 2021
SEDIMENT AND EROSION CONTROL & CONSTRUCTION STORMWATER
INSPECTION REPORT
Virginia Electric and Power Company d/b/a Dominion Energy North Carolina
Attn: Mr. Mark Allen, Director, ET Project Development & Execution
10900 Nuckols Road, 4th Floor
Glen Allen, VA 23060
RE: TL 182 Removal Phase 1 (Pitt-2020-011)
Dear Sir,
Attached is a copy of the inspection report prepared following an onsite inspection of the project
referenced on the report. This report is intended to inform you of the project's compliance with
the North Carolina Sedimentation Pollution Control Act of 1973 and Construction NPDES
Stormwater General Permit.
Please review this report carefully as it may contain corrective actions needed and/or comments
which will assist you in meeting the required performance standards.
It is our desire that any and all possible problems be discussed and resolved at the earliest
possible time. To facilitate this effort, please contact me at the address/phone number below
should you have any questions.
Sincerely,
J. Randall Jones, Jr., PE
Environmental Engineer
(252) 946-6481
Enclosure: Sediment/Construction Stormwater Inspection Report
e:-�eD E1A
5oy"xnmenS aE Cnv�ienmvnwi quaa�
North Carolina Department ofEnvironmental nvironmental Quality I Division of Energy. Mincra[ and Land Resources
Washington Regional office : 943 Washington Square Nial[ Washington, North Carolina 27889
252 3-}b.b 18i
Sediiiieiitatioii/CojistrLICtiOlI Stormwater Inspection Report
North Carolina Department of Environmental Quality
Land Resources: 943 Washington Square Mall, Washington, NC 27889 (252) 946-6481
County: Pitt Project: TL I82 Removal Phase 1
Person financially responsible: Virginia Electric and Power Company - Mark
Allen, Director of Engineering
Address: 10900 Nuckols Rd 4th Floor, Glen Allen, VA 23060
1. Project Location: Various, Greenville
Pictures: No
2. Weather and soil conditions: Sunny, warm, dry
3. Is site currently under notice of violation? No
4. Is the site in compliance with S.P.C.A. and rules? Yes
5. Violations:
River basin: Tar -Pamlico
Project #: PITT-2020-011
Initial inspection: No
If no, check violations below:
6. Is the site in compliance with NPDES Permit NCG010000 Construction Stormwater requirements?
Describe:
7. Has sedimentation damage occurred since last inspection? No If Yes, where? (check all that apply)
Degree of damage:
8. Contact made with (name):
Inspection report: Sent Report
9. Corrective action needed: NIA
Title:
Date given/sent: May 03, 2021
10. Comments: Permanent ground cover sufficient to restrain erosion has been established. No additional self -
monitoring or self -inspections are required. Project is in compliance and released under the
SPCA. Termination of coverage under the NPDES General Stormwater Permit for
Construction Activities (NCGO 1) must be requested by the permittee via a Notice of
Termination (NOT). The NOT is available at: https://edoes.deq.nc.gov/FormsNCGO I -
Termination. Please note that this correspondence must be uploaded as part of completing the
NOT process.
Reported by: Randall Jones
Date of inspection: April 28, 2021
cc:
Others present:
Time arriving on site: 2:00 PM Time leaving site: 4:00 PM
Yes