HomeMy WebLinkAboutNCC202907_NOT Closeout Documents_20210505North Carolina Department of Environmental Quality
Land Resources: 1628 Mail Service Center, Raleigh, NC 27699 (919) 791-4200
County: Edgecombe Project: Harts Mill Solar Connector River basin: Tar -Pamlico
Person financially responsible: VEPCO dba Dominion Energy NC - Mark Allen, Project #: EDGEC-2020-003
Director ET Project Development & Erecti
Address: 10900 Nuckols Road, 4th Floor, Glen Allen, VA 23060
1. Project Location: NCSR 1208, Tarboro
Pictures: Yes - Digital
2. Weather and soil conditions: Sunny, dry, workable Initial inspection: No
3. Is site currently under notice of violation? No
4. Is the site in compliance with S.P.C.A. and rules? Yes If no, check violations below:
5. Violations:
6. Is the site in compliance with NPDES Permit NCG010000 Construction Stormwater requirements? Yes
Describe:
7. Has sedimentation damage occurred since last inspection? No If Yes, where? (check all that apply)
Degree of damage:
8. Contact made with (name): John Fowler
Inspection report: Sent Report
9. Corrective action needed:
Title: Dominion Energy
Date given/sent: April 28, 2021
10. Comments: Project work is complete. Permanent ground cover sufficient to restrain erosion has been
established. No additional self -monitoring or self -inspections are required. Project is in
compliance and released under the SPCA. Termination of coverage under the NPDES General
Stormwater Permit for Construction Activities (NCGO1) must be requested by the permittee
via a Notice of Termination (NOT). The NOT is available at:
https://edocs.deq.nc.gov/Fonns/NCGOI-Termination. Please note that this correspondence
must be uploaded as part of completing the NOT process.
Reported by: Lauren Garcia Others present:
Date of inspection: April 28, 2021 Time arriving on site: 10:30 AM Time leaving site: 10:45 AM
cc: