HomeMy WebLinkAbout20070870 Ver 1_Approval Letter_20070604of WRQ
Ca~°
,o~ ~~
~~ ~~
> '`r
_ t ,~ --;
fl ~ ~
Michael F. Easley, Governor
William G. Ross Jr., Secretary
North Carolina Department of Environment and Natural Resources
Alan W. Klimek, P.E. Director
Division of Water Quality
1u1ay 30, 2007
Mitchell County
DWQ Project hto. 070870
US Highway 19E Spot Safety Project
APPROVAL of 401 Water Quality Certification with Additional Conditions
~G f'~,
Mr. J. J. Swain Jr., P.E. ~~~" ~:~'
~1~
Division Engineer
N C Department of Transportation /~~ ''v ~~
Post Office Box 3279 ~<,~~~ ~;,p ® ~1~~
Asheville, North Carolina 28802 l~S~~~~.,~~F~ ~~0~~ ~~
Dear Mr. Swain: ~'~" q~~'~"~-,,..
R,~~~
You have our approval, in accordance with the attached conditions and those listed below, for the following impacts~4n
an unnamed tributary to Biggerstaff Branch, for the purpose of making safety improvements to US Highway 19E in
Mitchell County:
Stream Impacts in the French Broad River Basin
Site Permanent Fill in Temporary Fill in Permanent Fill in Temporary Total Stream Stream
Intermittent Intermittent Stream Perennial Stream Dewatering in Impact Impacts
Stream (linear ft) (linear ft) (linear ft) Perennial Stream (linear ft) Requiring
(linear ft) 1VIitigation
(linear ft)
Site 1 10 20 30 0
Total 10 20 30 0
Total Stream Permanent Impact for Project: 10 linear feet. Temporary Impact for Project: 20 linear feet.
The project should be constructed in accordance with your application dated May 17, 2007 (received May 21, 2007),
including the environmental commitments made in the application letter. After reviewing your application, we have
decided that these impacts are covered by General Water Quality Certification Nos. 3627 and 3634, corresponding to the
U.S. Army Corps of Engineers Nationwide Permit Numbers 14 and 33. In addition, you should acquire any other
federal, state or local permits before you proceed with your project including (but not limited to) Sediment and Erosion
Control, Non-Discharge and Water Supply Watershed regulations. This approval will expire with the accompanying 404
Permit.
This approval is valid solely for the purpose and design described in your application (unless modified below). Should
your project change, you must notify the DWQ and submit a new application. If the property is sold, the new owner
must be given a copy of this Certification and approval letter, and is thereby responsible for complying with all
conditions. If total wetland fills for this project (now or in the future) exceed one acre, or if total impacts to streams (now
or in the future) exceed 150 linear feet, compensatory mitigation may be required as described in 15A NCAC 2H .0506
(h) (6) and (7). For this approval to be valid, you must follow the conditions listed in the attached certification and any
additional conditions listed below.
NonhCarolina
~atrrra!!y
North Carolina Division of Water Quality 2090 U.S. Highway 70 Swannanoa, NC 28778 Phone (828) 296-4500 Customer Service
lntemet: www.ncwaterquality.org FAX (828) 299-7043 1-877-623-6748
An Equal Opportunity/Affirmative Action Employer
i
Mr. J. J. Swain Jr., P.E.
May 30, 2007
Page Two
Erosion and sediment control practices must be in full compliance with all specifications g~werning the proper
design, installation and operation and maintenance of such Best Management Practices in order to protect surface
waters standards:
a. The erosion and sediment control measures for the project must be designed, installed, operated, and
maintained in accordance with the most recent version of the North Carolina Sedimer..' and Erosion Control
Planning and Design ~Llanual.
b. The design, installation, operation, and maintenance of the sediment and erosion control measures must be
such that they equal, or exceed, the requirements specified in the most recent version of the Nortla Caroli~aa
Sediment and Erosion Control ~Llanual. The devices shall be maintained on all construction sites, borrow
sites, and waste pile (spoil) projects, including contractor-owned or leased borrow pits associated with the
project.
c. For borrow pit sites, the erosion and sediment control measures must be designed, installed, operated,
and maintained in accordance with the most recent version of the North Carolina Surface Mining Manual.
d. The reclamation measures and implementation must comply with the reclamation in accordance with the
requirements of the Sedimentation Pollution Control Act.
2. There shall be no excavation from or waste disposal into, jurisdictional wetlands or waters associated with this
permit without appropriate modification. Should waste or borrow sites be located in wetlands or streams,
compensatory mitigation will be required since that is a direct impact from road construction activities.
3. Sediment and erosion control measures shall not be placed in wetlands or waters unless otherwise approved by this
Certification. If placement of sediment and erosion control devices in wetlands and waters is unavoidable, they shall
be removed and the natural grade restored upon completion of the project.
4. Placement of culverts and other structures in waters, streams and wetlands, shall be placed below the elevation of the
streambed by one foot for all culverts with a diameter greater than 48-inches, and 20 percent of the culvert diameter
for culverts having a diameter less than 48-inches, to allow low flow passage of water and aquatic life. Design and
placement of culverts and other structures including temporary erosion control measures shall not be conducted in a
manner that may result in dis-equilibrium of wetlands, streambeds or banks, adjacent to, or upstream and down
stream of the above structures. The applicant is required to provide evidence that equilibrium is being maintained, if
requested in writing by DWQ. If this condition is unable to be met due to bedrock or other limiting features
encountered during construction, please contact the NC DWQ for guidance on how to proceed and to determine
whether or not a permit modification will be required.
5. Adequate sedimentation and erosion control measures must be installed and maintained on the project site to
minimize sediment transport to downstream aquatic resources. Temporary cover (wheat, millet or similar annual
grain) or permanent herbaceous cover should be planted on all bare soil within fifteen (15) days of ground disturbing
activities to provide long-term erosion control. Erosion control mating should be used in conjunction with
appropriate seeding on disturbed soils in steep slope and riparian areas. Matting should be secured in place with
staples or wherever possible, live stakes of native trees. Straw mulch and tall fescue should not be used in riparian
areas.
6. If multiple pipes or barrels are required, they shall be designed to mimic the natural stream cross section as closely as
possible including pipes or barrels at flood plain elevation and/or sills where appropriate. Widening the stream
should be avoided. Stream channel widening at the inlet or outlet end of structures typically decreases water velocity
causing sediment deposition that requires increased maintenance and disrupts aquatic life passage.
7. For projects impacting waters classified by the NC Environmental Management Conunission as Trout (Tr), High
Quality Waters (HQW) or Water Supply I or II (WS-I, WS-II), stormwater shall be directed to vegetated buffer
areas, grass-lined ditches or other means appropriate to the site for the purpose of pre-treating stormwater runoff
prior to discharging directly into streams. Mowing of existing vegetated buffer areas is strongly discouraged.
8. The dimension, pattern and profile of the stream, above and below the crossing, shall not be modified. Disturbed
floodplains and streams shall be restored to natural geomorphic conditions.
9. Any riprap placed for bank stabilization should be limited to the streambank below the high water mark, and
vegetation should be used for stabilization above the high water elevation.
10. Riprap shall not be placed in the active thalweg channel or placed in the streambed in a manner that precludes
aquatic life passage. Bioengineering boulders or structures should be properly designed, sized and installed.
Mr. J. J. Swain Jr., P.E.
May 30, 2007
Page Three
11. Heavy equipment should 'oe operated from the banks rather than in the stream channels in order to minimize
sedimentation and reduce the introduction of other pollutants into the stream.
L. All mechanized equipment operated near surface waters must be regularly inspected daily and maintained to prevent
contamination of stream waters from fuels, lubricants, hydraulic fluids, or other toxic materials.
13. Rock check dams at culvert outlets should be removed at project completion to avoid impeding aquatic life
movement.
14. All work in or adjacent to stream eaters shall be conducted in a dry work area. Approved BMP measures from the
most current version of NCDOT Construction and Maintenance Activities manual such as sandbags, rock berms,
cofferdams and other diversion structures should be used to prevent excavation in flowing water.
15. Discharging hydrosee:i mixtures and washing out hydroseeders and other equipment in or adjacent to surface waters
is prohibited.
16. If concrete is used during construction (e.g., headwalls), a dry work area shall be maintained to prevent direct contact
between curing concrete and stream water. Water that inadvertently contacts uncured concrete shall not be
discharged to surface waters due to the potential for elevated pH and possible aquatic life and fish kills.
17. No rock, sand or other materials shall be dredged from the stream channel, except where authorized by this
certification. _
18. A copy of this Water Quality Certification shall be maintained on the construction site at all times. In addition, the
Water Quality Certification and all subsequent modifications, if any, shall be maintained with the Division Engineer
and the on-site project manager.
19. The permittee and its authorized agents shall conduct its activities in a manner consistent with State water quality
standards (including any requirements resulting from compliance with §303(d) of the Clean Water Act) and any
other appropriate requirements of State or Federal law. If DWQ determines that such standards or laws are not being
met (including failure to sustain a designated achieved use) or that State of Federal law if being violated, or that
further conditions are necessary to assure compliance, DWQ may reevaluate and modify this certification.
20. This certification does not authorize the discharge of waste rock and dirt into the stream or riparian zone except for
permitted areas associated with the bank stabilization work.
21. During the construction of the project, no staging of equipment of any kind is permitted in waters of the U.S. or
protected riparian buffers.
22. Upon completion of the project, the NCDOT Division Engineer, shall complete and return the enclosed "Certificate
of Completion Form" to notify NCDWQ when all work included in the §401 Certification has been completed. This
form shall be returned to the Transportation Permitting Unit of the NC Division of Water Quality, 2321 Crabtree
Blvd., Suite 250, Raleigh, North Carolina 27604.
If you do not accept any of the conditions of this certification, you may ask for an adjudicatory hearing. You must act
within 60 days of the date that you receive this letter. To ask for a hearing, send a written petition, which conforms to
Chapter 150B of the North Carolina General Statutes to the Office of Administrative Hearings, 6714 Mail Service
Center, Raleigh, N.C. 27699-6714. This certification and its conditions are final and binding unless you ask for a
hearing.
This letter completes the review of the Division of Water Quality under Section 401 of the Clean Water Act. If you have
any questions, please telephone Mr. Mike Parker of the Asheville Regional Office at 828.296.4500.
Sincerely,
,~ ~-_,..--- a
r
,J,c~~~ Alan W. Klimek, P.E., Director
~~ Division of Water Quality
cc: Roger Bryan, Division 13, DEO
Ed Ingle, Roadside Environmental
David Baker, USACE Asheville Field Office
Transportation Permitting Unit
Mike Parker, Asheville Regional Office